This is a Request for Bids (RFB) document issued by the City of Weslaco for the construction of a new FBO (Fixed Base Operator) Hangar at Mid-Valley International Airport in Weslaco, Texas. The project, designated RFB #2025-26-09 with KSA Project No. 102423, solicits bids for building construction work at the airport facility. A non-mandatory pre-bid conference is scheduled for September 10, 2026, at 10:00 AM via Zoom, and a mandatory site visit will be held on September 11, 2026, at 10:00 AM at the terminal building located at 1909 Joe Stephens Avenue, Weslaco, Texas 78596. Bids must be submitted electronically through the BIDNET portal at https://www.bidnetdirect.com/texas/cityofweslaco, with a deadline of 10:00 AM on October 8, 2026, at which time bids will be opened and read aloud via Zoom. The contract documents specify that contract times for substantial completion and final payment readiness will be established in the Agreement; specific completion timeframes are not detailed in this introductory section but are to be provided in the bid form.
Bids must be accompanied by bid security equal to 5 percent of the bidder's maximum bid price (base bid plus all alternates), submitted as either a certified check, bank money order, or bid bond. The City of Weslaco reserves the right to reject any or all bids and to award based on best value considerations under Local Government Code 252.043. As a state-funded construction project, the contract is subject to Historically Underutilized Business (HUB) participation requirements with an established goal of 21.1 percent HUB participation, and all bidders must submit an up-to-date HUB Subcontracting Plan with their proposals. The project is also subject to prevailing wage requirements per Davis-Bacon Act wage determinations for Hidalgo County, Texas, with wages established for various construction trades. Bidders must comply with all federal and state requirements, including debarment certifications, Buy American provisions for FAA contracts, and certification of non-segregated facilities.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFB #2025-26-09
CITY OF WESLACO
CITY FBO HANGAR AT MID-VALLEY INTERNATIONAL AIRPORT
BID FORM, CONTRACT DOCUMENTS, AND TECHNICAL SPECIFICATIONS
MID-VALLEY INTERNATIONAL AIRPORT
WESLACO, TEXAS
CITY FBO HANGAR PROJECT
Weslaco Project Bid No. 2025-26-09 KSA Project No. 102423
August 2026
Prepared by:
2107 CityWest Boulevard Third Floor
Houston, Texas 77042 281.494.3252 www.ksaeng.com TBPE Firm Registration No. F-1356 http://www.ksaeng.com/
Page Intentionally Left Blank
TABLE OF CONTENTS
INTRODUCTORY INFORMATION
Bid Advertisement and Invitation for Bids Instructions to Bidders Historically Underutilized Business (HUB) Participation Prevailing Wage Rates
BIDDING DOCUMENTS
Bid Form Qualifications Statement Bid Bond Child Support Statement Certificate of Interested Parties HB1295 State of Texas – House Bill 89 Verification Certification Regarding Lobbying Special Instruction to Bidders Regarding EEO Required Language in Proposals for AIP Contracts Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion Buy American Certification Certification of Non-Segregated Facilities
CONTRACT DOCUMENTS
Notice of Award Standard Form of Agreement Performance Bond Payment Bond Certificate of Insurance Notice to Proceed FAA & State Aviation Construction Contract General Provisions FAA & State Aviation Project Special Provisions to General Provisions Contractors Payment Application Certificate of Substantial Completion Change Order
TECHNICAL SPECIFICATIONS
PAGE INTENTIONALLY LEFT BLANK
INTRODUCTORY INFORMATION
Bid Advertisement and Invitation for Bids
RFB NO.: 2025-26-09
City of Weslaco FBO Hangar Project at Mid-Valley International Airport
(KSA NO. 102423)
Electronic submissions of bids addressed to Homer Rhodes, Purchasing Agent, will be accepted via BIDNET. RFB deadline 10:00 AM on October 8, 2026, at which time they will be opened and read aloud via ZOOM meeting (Zoom link provided in RFP document).
Potential respondents are advised that documents related to the solicitation of bids can be downloaded from the City of Weslaco web page address:
https://www.bidnetdirect.com/texas/cityofweslaco, Be advised that the BIDNET portal/website is the primary source of all bid documents. BIDNET portal/website must be monitored regularly for addendums and/or bid notices. Respondents are responsible for obtaining all the necessary information required for a compliant bid.
A non-mandatory but recommended pre-bid conference will be held on September 10, 2026 at 10:00 AM via ZOOM (link provided in RFB document).
A site visit will be held on September 11, 2026, at 10:00 AM. To attend the site visit, please meet at the Mid-Valley International Airport Terminal Building located at 1909 Joe Stephens Avenue, Weslaco, Texas 78596.
The City of Weslaco reserves the right to accept or reject any or all bids, to waive any informalities, and to accept the bid to be the best value and most advantageous (as allowed in Local Government Code 252.043) to the City and to hold bids for a period of sixty (30) days without taking action, for the purpose of reviewing and investigation of respondent’s qualifications prior to award. Bids must be submitted electronically through BIDNET, no other form of submission will be accepted.
City of Weslaco /s/ Homer Rhodes Purchasing Agent
956-447-2240 hrhodes@weslacotx.gov https://www.bidnetdirect.com/texas/cityofweslaco
Instructions to Bidders
EJCDC® C-200, Instructions to Bidders for Construction Contracts.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
This document has important legal consequences; consultation with an attorney is encouraged with respect to its use or modification. This document should be adapted to the particular circumstances of the contemplated Project and the controlling Laws and Regulations.
INSTRUCTIONS TO BIDDERS
FOR CONSTRUCTION CONTRACTS
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Copyright © 2013:
National Society of Professional Engineers
1420 King Street, Alexandria, VA 22314-2794
(703) 684-2882 www.nspe.org
American Council of Engineering Companies
1015 15th Street N.W., Washington, DC 20005
(202) 347-7474 www.acec.org
American Society of Civil Engineers
1801 Alexander Bell Drive, Reston, VA 20191-4400
(800) 548-2723 www.asce.org
The copyright for this EJCDC document is owned jointly by the three sponsoring organizations listed above. The National Society of Professional Engineers is the Copyright Administrator for the EJCDC documents; please direct all inquiries regarding EJCDC copyrights to NSPE.
NOTE: EJCDC publications may be purchased at www.ejcdc.org, or from any of the sponsoring organizations above.
http://www.nspe.org/ http://www.acec.org/ http://www.asce.org/ http://www.ejcdc.org/
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i
SUGGESTED INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
Page Article 1 – Defined Terms
Article 2 – Copies of Bidding Documents
Article 3 – Qualifications of Bidders
Article 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 5 – Bidder’s Representations
Article 6 – Pre-Bid Conference
Article 7 – Interpretations and Addenda
Article 8 – Bid Security
Article 9 – Contract Times
Article 10 – Liquidated Damages
Article 11 – Substitute and “Or-Equal” Items
Article 12 – Subcontractors, Suppliers, and Others
Article 13 – Preparation of Bid
Article 14 – Basis of Bid
Article 15 – Submittal of Bid
Article 16 – Modification and Withdrawal of Bid
Article 17 – Opening of Bids
Article 18 – Bids to Remain Subject to Acceptance
Article 19 – Evaluation of Bids and Award of Contract
Article 20 – Bonds and Insurance
Article 21 – Signing of Agreement
Article 22 – Sales and Use Taxes
EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
KSA - a Pape-Dawson Company
2107 City West Blvd., 3rd Floor
Houston, TX 77042
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Contract Documents may be viewed and downloaded free of charge (With the option to purchase hard copies) at www.bidnetdirect.com.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor
Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall submit with its Bid previous experience in the completion of similar work. For each similar project the bidder shall submit the name of the project, project owner, construction dates, and the cost of construction.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
4.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
4.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2
1. The Supplementary Conditions identify:
a. those reports, if any, known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.
b. those drawings, if any, known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).
c. reports and drawings, if any, known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.
4.03 Site Visit and Testing by Bidders
A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.
B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3
D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
4.04 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.
4.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 5 – BIDDER’S REPRESENTATIONS
5.01 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;
B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;
E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4
F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;
and
J. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
ARTICLE 6 – PRE-BID CONFERENCE
6.01 A pre-Bid conference may be held at a time and location stated in the invitation or advertisement to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer via the Q & A portal on www.bidnetdirect.com. Interpretations or clarifications considered necessary by the Engineer in response to such questions will be issued by Addenda. All Addenda issued for this project will only be posted on www.bidnetdirect.com. Questions received less than 72 hours prior to the opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of _5%_ percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and
6.02 of the General Conditions.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5
Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 – LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 Except as provided in Paragraph 11.02, the Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
11.02 In some cases, the Engineer will specify that substitutes for certain materials and equipment must be approved by Addendum prior to the bid date. The Contract for the Work, as awarded, will then be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer at least 10 days prior to the date for receipt of Bids. Each such request shall comply with the requirements of Paragraphs 7.04 and 7.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.
11.03 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6
ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.
12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of the major Subcontractors or Suppliers proposed for the following portions of the Work.
If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.
ARTICLE 13 – PREPARATION OF BID
13.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.
Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each Bid item, alternate, adjustment unit price item, and unit price item listed therein.
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
C. If Bidder elects not to submit a price for one or more sections, then Bidder should enter the words "No Bid" for those items.
13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7
13.03 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
13.04 A Bid by an individual shall show the Bidder’s name and official address.
13.05 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.
13.06 All names shall be printed in ink below the signatures.
13.07 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.08 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.
13.09 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
ARTICLE 14 – BASIS OF BID
14.01 The Bid shall be based upon one of the following methods as provided for in the Bid Form.
A. Lump Sum
1. Bidders shall submit a Bid on a lump sum basis as set forth in the Bid Form.
B. Base Bid with Alternates
1. Bidders shall submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.
2. In the comparison of Bids, alternates will be applied in the order that best serves the Owner's interests.
C. Sectional Bids
1. Bidders may submit a Bid on any individual section or any combination of sections, as set forth in the Bid Form.
2. Submission of a Bid on any section signifies Bidder’s willingness to enter into a Contract for that section alone at the price offered.
3. If Bidder submits Bids on individual sections and a Bid based on a combination of those sections, such combined Bid need not be the sum of the Bids on the individual sections.
4. Bidders offering a Bid on one or more sections shall be capable of completing the Work covered by those sections within the time period stated in the Agreement.
D. Unit Price
1. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 8
2. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph
13.03 of the General Conditions.
3. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of words.
14.02 Allowances
A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
ARTICLE 15 – SUBMITTAL OF BID
15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.
15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed to via BIDNET https://www.bidnetdirect.com/texas/cityofweslaco.
15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.
ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.
16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 9 and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.
ARTICLE 17 – OPENING OF BIDS
17.01 1.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – VALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.
19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.
19.03 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
B. In the comparison of Bids, alternates will be applied in the manner that best serves the Owner's interests. To determine the Bid prices for purposes of comparison, Owner shall announce to all bidders a “Base Bid plus alternates” budget after receiving all Bids, but prior to opening them. For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its additive alternate Bids for which Owner determines funds will be available at the time of award.
C. For determination of the apparent low Bidder(s) when sectional bids are submitted, Bids will be compared on the basis of the aggregate of the Bids for each separate section. and the Bids for combined sections that result in the lowest total amount for all of the Work.
D. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 10
19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 20 – BONDS AND INSURANCE
20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by required bonds and insurance documentation.
ARTICLE 21 – SIGNING OF AGREEMENT
21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
ARTICLE 22 – SALES AND USE TAXES
22.01 Owner is not exempt from state sales and use taxes on materials and equipment to be incorporated in the Work. Refer to Paragraph SC-7.09 of the Supplementary Conditions for additional information.
Historically Underutilized Business (HUB) Participation
HISTORICALLY UNDERUTILIZED BUSINESS
IN STATE FUNDED CONSTRUCTION
Historically Underutilized Business Participation
In accordance with Texas Government Code §2161.252, a bid that does not contain an up-to-date HUB Subcontracting Plan (HSP) is non-responsive and will be rejected without further evaluation. In addition, if the Agent’s HUB Specialist determines that the HSP was not developed in good faith, the bid will be rejected for failing to comply with material specifications based on the Notice to Bid (NTB).
1.3.1 Introduction
The Agent is committed to promoting full and equal business opportunities for businesses in state contracting in accordance with the goals specified in the State of Texas Disparity Study. The Agent encourages the use of Historically Underutilized Business es (HUBs) through race, ethnic and gender-neutral means.
Pursuant to Texas Government Code §2161.181 and §2161.182, and the Agent’s HUB policy and rules, the Agent is required to make a good faith effort to increase HUB participation in its contracts. The Agent may accomplish the goal of increased HUB participation by contracting directly with HUBs or indirectly through subcontracting opportunities.
1.3.2 Agent’s Administrative Rules
The Agent has adopted the CPA’s HUB rules as its own. The Agent’s HUB rules are located in Title 43, Part 1, Chapter 9, Subchapter L of the Texas Administrative Code, and the CPA rules are located in Title 34, Part 1, Chapter 20, Subchapter D, Division 1 .
If there are any discrepancies between the Agent’s administrative rules and this Notice to Bidders (NTB), the rules shall take priority.
1.3.3 HUB Participation Goal
The CPA has established statewide HUB participation goals for different categories of contracts in 34 T.A.C. §20.284. In order to meet or exceed the HUB participation goals, the Agent encourages outreach to certified HUBs. Contractors shall make a good faith effort to include certified HUBs in the procurement process.
This contract is classified as a Building Construction contract under the CPA rule, and therefore has a HUB Annual Procurement Utilization Goal of 21.1 % per fiscal year.
http://www.statutes.legis.state.tx.us/Docs/GV/htm/GV.2161.htm https://comptroller.texas.gov/purchasing/vendor/hub/forms.php http://www.statutes.legis.state.tx.us/Docs/GV/htm/GV.2161.htm http://www.statutes.legis.state.tx.us/Docs/GV/htm/GV.2161.htm http://texreg.sos.state.tx.us/public/readtac%24ext.ViewTAC?tac_view=5&ti=43&pt=1&ch=9&sch=L&rl=Y http://texreg.sos.state.tx.us/public/readtac%24ext.ViewTAC?tac_view=5&ti=34&pt=1&ch=20&sch=D&div=1&rl=Y http://texreg.sos.state.tx.us/public/readtac%24ext.TacPage?sl=R&app=9&p_dir&p_rloc&p_tloc&p_ploc&pg=1&p_tac&ti=34&pt=1&ch=20&rl=284
1.3.4 Required HUB Subcontracting Plan
In accordance with Government Code, Chapter 2161, Subchapter F, each state agency that considers entering into a contract with an expected value of $100,000 or more over the life of the contract (including any renewals) shall, before the agency solicits bids, proposals, offers, or other applicable expressions of interest, determine whether subcontracting opportunities are probable under the contract.
In accordance with 34 T.A.C. §20.285(a),(1),(C) of the HUB Rules. State agencies may determine that subcontracting is probable for only a subset of the work expected to be performed or the funds to be expended under the contract. If an agency determines that subcontracting is probable on only a portion of a contract, it shall document its reasons in writing for the procurement file.
The Agent has determined that subcontracting opportunities are probable f or this NTB.
As a result, the respondent must submit an HSP with its proposal. The HSP is required whether a respondent intends to subcontract or not.
In the HSP, a respondent must indicate whether it is a Texas certified HUB. Being a certified HUB does not exempt a respondent from completing the HSP requirement.
The Agent shall review the documentation submitted by the respondent to determine if a good faith effort has been made, in accordance with solicitation and HSP requirements.
During the good faith effort evaluation, The Agent may, at its discretion, allow clarifications or enhancements to information submitted with the HSP.
If the Agent determines that the respondent’s HSP was not developed in good f aith, the HSP will be considered non-responsive and will be rejected as a material failure to comply with the advertised specifications. The reasons for rejection shall be recorded in the procurement file.
1.3.5 CPA Centralized Master Bidder’s List
Respondents may search for HUB subcontractors in the CPA’s Centralized Master Bidders List (CMBL)/HUB Directory. For this procurement, the Agent has identified the following class and item codes for potential subcontracting opportunities:
NIGP Class/Item Code:
909-25, 913-10
Respondents are not required to use, nor limited to using, the class and item codes identified above, and may identify other areas for subcontracting.
The Agent does not endorse, recommend nor attest to the capabilities of any company or individual listed on the CPA’s CMBL. The list of certified HUBs is subject to change, so http://texreg.sos.state.tx.us/public/readtac%24ext.TacPage?sl=R&app=9&p_dir&p_rloc&p_tloc&p_ploc&pg=1&p_tac&ti=34&pt=1&ch=20&rl=285 https://mycpa.cpa.state.tx.us/tpasscmblsearch/index.jsp https://mycpa.cpa.state.tx.us/tpasscmblsearch/index.jsp respondents are encouraged to refer to the CMBL often to find the most current listing of HUBs.
1.3.6 HUB Subcontracting Procedures – If a Respondent Intends to Subcontract
An HSP must demonstrate that the respondent made a good faith effort to comply with the Agent’s HUB policies and procedures. The following subparts outline the items that the Agent will review in determining whether an HSP meets the good faith effort standard. A respondent that intends to subcontract must complete the HSP to document its good faith efforts.
1.3.6.1 Identify Subcontracting Areas and Divide Them into Reasonable Lots
A respondent should first identify each area of the contract work it intends to subcontract. Then, to maximize HUB participation, it should divide the contract work into reasonable lots or portions, to the extent consistent with prudent industry practices.
1.3.6.2 Notify Potential HUB Subcontractors
The HSP must demonstrate that the respondent made a good faith effort to subcontract with HUBs that have an active HUB certification. The respondent’s good faith efforts shall be shown through utilization of all methods in conformance with the development and submission of the HSP and by complying with the following steps:
1.3.6.2.1 Divide the contract work into reasonable lots or portions to the extent consistent with prudent industry practices. The respondent must determine which portions of work, including goods and services, will be subcontracted.
1.3.6.2.2 Use the appropriate method(s) to demonstrate good faith effort. The respondent can use either method(s) 1, 2, or 3:
1.3.6.3 Method 1: Respondent Intends to Subcontract with only HUBs:
The respondent must identify in the HSP the HUBs, with an active HUB certification, that will be utilized and submit written documentation that confirms 100% of all available subcontracting opportunities will be performed by one or more HUBs;
1.3.6.4 Method 2: Respondent Intends to Subcontract with HUBs and Non-HUBs
(Meet or Exceed the Goal):
The respondent must identify in the HSP and submit written documentation that one or more HUBs, with an active HUB certification, will be utilized; and that the aggregate expected percentage of subcontracts with HUBs will meet or exceed the goal specified in this solicitation. Only HUB subcontractors that have an existing contract with the respondent for less than five years may be used to comply with the good faith effort requirements under this method.
When the aggregate expected percentage of subcontracts with HUBs meets or exceeds the goal specified in this solicitation, respondents may also use non-HUB subcontractors; or,
1.3.6.6 Method 3: Respondent Intends to Subcontract with HUBs and Non-HUBs (Does Not Meet or Exceed the Goal):
The respondent must identify in the HSP and submit documentation regarding both of the following requirements:
• Written notification to minority or women trade organizations or development centers to assist in identifying potential HUBs, with an active HUB certification, of the subcontracting opportunities the respondent intends to subcontract.
Respondents must give minority or women trade organizations or development centers at least seven (7) working days prior to submission of the respondent's response for dissemination of the subcontracting opportunities to their members. A list of minority and women trade organizations is located on the CPA’s website under the Minority and Women Organization link.
• Written notification to at least three (3) HUB businesses, with an active HUB certification, of the subcontracting opportunities that the respondent intends to subcontract. The written notice must be sent to potential HUB subcontractors prior to submitting proposals and must include:
a description of the scope of work to be subcontracted, information regarding the location to review project plans or specifications, information about bonding and insurance requirements, required qualifications and other contract requirements, and a description of how the subcontractor can contact the respondent.
Respondents must give potential HUB subcontractors a reasonable amount of time to respond to the notice, at least seven (7) working days prior to submission of the respondent's response unless circumstances require a different time period, which is determined by the agency and documented in the contract file;
Respondents must also use the CMBL, the HUB Directory, and Internet resources when searching for HUB subcontractors. Respondents may rely on https://www.comptroller.texas.gov/purchasing/vendor/hub/resources.php the services of contractor groups; local, state and federal business assistance offices; and other organizations that provide assistance in identifying qualified applicants for the HUB program.
1.3.6.7 Written Justification of the Selection Process
The Agent will make a determination if a good faith effort was made by the respondent in the development of the required HSP. One or more of the methods identified in the previous sections may be applicable to the respondent’s good faith efforts in developing and submission of the HSP. The Agent may require the respondent to submit additional documentation explaining how the respondent made a good faith effort in accordance with the solicitation.
A respondent must provide written justification of its selection process if it chooses a non-HUB subcontractor. The justification should demonstrate that the respondent negotiated in good faith with qualified HUB bidders, and did not reject qualified HUBs, with an active HUB certification, who were the best value responsive bidders.
1.3.7 Method 4: Respondent Does Not Intend to Subcontract
When the respondent plans to complete all contract requirements with its own equipment, supplies, materials and/or employees, it is still required to complete an HSP.
The respondent must complete the “Self-Performance Justification” portion of the HSP, and attest that it does not intend to subcontract for any goods or services, including the class and item codes identified in Section I.3.5. In addition, the respondent must identify the sections of the proposal that describe how it will complete the Scope of Work using its own resources or provide a statement explaining how it will complete the Scope of Work using its own resources. The respondent must agree to comply with the following if requested by the Agent:
• Provide evidence of sufficient respondent staffing to meet the NTB requirements,
• Provide monthly payroll records showing the respondent staff fully dedicated to the contract,
• Allow the Agent to conduct an onsite review of company headquarters or work site where services are to be performed, and,
• Provide documentation proving employment of qualified personnel holding the necessary licenses and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .