This is an Invitation to Bid (ITB) document issued by Monroe County Commissioners for a new supply well construction project located in Hamilton Township, Monroe County, Pennsylvania. The project involves drilling a six-inch diameter well with related erosion and sedimentation control measures and site restoration. The work will be performed under a single general construction contract. The project engineer is Read and Associates, LLC. Sealed bids will be received online through the PennBid Program until 10:00 a.m. local time on December 5, 2025, with bid opening and summary review occurring at 10:30 a.m. on the same date at the Monroe County Administrative Center. Questions from prospective bidders must be submitted through PennBid by 4:00 p.m. on November 24, 2025. Bidding documents are available online at https://pennbid.bonfirehub.com without charge. The apparent low bidder must submit original bidding documents to the engineer within two business days of bid opening. The successful bidder will be selected at a later date following bid evaluation. Bids shall remain open for 60 days from the opening date, or 120 days if award is delayed by governmental approval, bond sale, or grant award requirements.

The contract is subject to Pennsylvania prevailing wage requirements as determined by the Department of Labor and Industry. Each bid must be accompanied by bid security of 10 percent of the bid total in the form of a certified check, bank check, irrevocable letter of credit, or bid bond. The successful bidder must provide 100 percent performance bond, 100 percent payment bond, and 10 percent maintenance bond within 15 days after notice of intent to award, with bonds issued by a corporate surety listed in U.S. Treasury Department Circular 570 and authorized by the Pennsylvania Department of Insurance. The successful bidder must demonstrate a minimum of five years of documented experience in well drilling and must perform at least 50 percent of the work using its own workforce rather than subcontractors. All workers must be lawfully permitted to work in the United States and Pennsylvania, and successful bidders must provide confirmation of compliance with the Public Works Employment Verification Act (Act 127 of 2012). Payment is based on actual quantities and materials used according to unit rates provided in the bid schedule, with typical payment occurring 60 to 90 days after invoice submission. The well is anticipated to reach 400 feet in depth, with a 10-inch outer casing to approximately 160 feet and a 6-inch inner casing completing the installation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID

The Monroe County Commissioners will receive sealed Bids online via the PennBid Program (www.PennBid.net) for the following Contract for work located within Monroe County, Hamilton Township:

Project: New Supply Well: The project generally consists of drilling a well, related erosion and sedimentation control, and restoration of areas disturbed within and outside of the project limits by construction operations.

The Work will be performed under one Contract as follows:

GENERAL CONSTRUCTION

Owner: Monroe County

One Quaker Plaza, Suite 201 Stroudsburg PA, 18360

Engineer: Read and Associates, LLC.

10 Field Stone Drive Mechanicsburg, PA 17050

Bid proposals will be received online until 10:00 a.m. local prevailing time on December 5, 2025, via the PennBid Program (www.PennBid.net). Bids will be opened online. The bids summary will be reviewed by the county in the Commissioners’ Public Meeting Room, Monroe County Administrative Center, One Quaker Plaza, Room 203, Stroudsburg, PA 18360 at 10:30 a.m. on Friday, December 5, 2025. After bid opening, the results will be available for viewing at the PennBid website. Successful bidder will be selected by Owner at a later date.

Questions will be accepted until 4:00 P.M., prevailing time, on November 24, 2025; All questions must be submitted through PennBid.

Bidding Documents and solicitation details are available online without charge, at https://pennbid.bonfirehub.com.

The apparent low bidder must submit to the Engineer, originals of the Bidding Documents within two (2) business days from the date of the bid opening.

Reproduction of the Bidding Documents and placement on websites other than PennBid, is not permitted. Bids may be modified or withdrawn at any time prior to the opening of Bids. After the Bid opening, Bids may be withdrawn only by complying with Commonwealth of Pennsylvania laws and regulations. Bids shall remain open for a period of 60 days from the date of Bid opening unless award is delayed by a required approval from a governmental agency, the sale of bonds, or the award of a grant or grants, in which event the Bids shall remain open for a period of 120 days from the date of Bid opening.

The Contract will be subject to the Prevailing Minimum Wage Determination established by the Commonwealth of Pennsylvania, Department of Labor and Industry. The contract documents contain requirements addressing prevailing labor wage rates, labor standards, and nondiscrimination in hiring practices. Attention is also called to the fact that a Non-Collusion Affidavit is required to be submitted as part of each bid.

http://www.pennbid.net/ http://www.pennbid.net/ https://pennbid.procureware.com/home

Each Bid must be accompanied by Bid security in the form of a certified check, bank check, payable to the order of Monroe County, irrevocable letter of credit, or Bid bond for 10% of the Bid total. If providing a Bid Bond, Bidders shall upload a scanned copy of fully executed bond as part of online sealed bid submission. After Bid Opening and upon request by Owner, Bidder(s) shall provide original hard copy of Bid Bond. If providing security in the form of a certified check or bank money order, security must be delivered to Owner prior to Bid Opening date and time.

The successful low bidder will be required to provide a 100% performance bond, 100% payment bond, and 10% maintenance bond, within 15 days after the Notice of Intent to Award is issued. Each bond shall be issued by a corporate surety listed in the latest issue of the U.S. Treasury Department Circular 570 listings and authorized by the PA Department of Insurance to do business in Pennsylvania. The successful bidder shall be required to submit evidence of insurance coverage with an insurance company having an A.M. Best rating of “A-: Class VII” or better in accordance with the specifications

It is a requirement of this Contract that at least 50% of the Work be performed by prime Bidder’s own work force, not by subcontractor(s).

It is a requirement of this Contract that Bidder shall have a minimum five (5) years of project documented experience in the type of Work required by this Project.

Bidders, subcontractors, their workers and any persons providing labor and products to the Project shall be persons lawfully permitted to work in the United States and the Commonwealth of Pennsylvania.

As a precondition of being awarded a Contract, Successful Bidder, and its subcontractor(s) are required, to provide confirmation of compliance with Act 127 of 2012, the “Public Works Employment Verification Act”.

The OWNER hereby reserves the right, which is understood and agreed to by all Bidders, to reject any or all Bids and to waive any omissions, errors, irregularities or technicalities in bidding in any Bid, and to award a contract in the best interests of the County of Monroe.

MONROE COUNTY BOARD OF COMMISSIONERS

Robert J. Gress, Chief Clerk/Administrator

LEGAL ADVERTISING: Publish:

Two (2) times; 11/17/25 and 11/21/25

PROOF OF PUBLICATION REQUIRED

1 Monroe County Well Installation Specifications

MONROE COUNTY, PENNSYLVANIA

1.0 Introduction

Monroe County (the County) proposes to develop a new source of public water supply to provide source redundancy with the existing source (Well 1) operated by the County (PWS ID 2450105). The well will be developed on the same 96-acre parcel (Parcel ID 07.9.2.40) with Well 1 on land owned by the County, located at 4230 Manor Drive in Hamilton Township, Monroe County, Pennsylvania. The purpose of the new source is to meet long-term water demand. A topographic map showing the proposed test well location on the northern portion of the property is included as Figure 1. The successful driller will contract directly with Monroe County.

To allow collection of bids from contractors for drilling services, Read and Associates, LLC (RAL) has prepared this detailed technical specification describing the anticipated well construction work to be completed as part of the project. The technical specifications, an itemized bid schedule covering all anticipated drilling work, and a hydrogeologic characterization of the target aquifer, are presented in the following sections of this document. Please note that payment is determined by the actual quantities/materials used based on the unit rates for such as provided by the successful bidder. In addition, please be aware that payment for drilling services is typically 60 to 90 days.

Hamilton Township, Monroe County Pennsylvania

PWSID# 2450105

New Supply Well Project

Characterization of Hydrogeologic Conditions and Detailed Technical Specifications for Well Construction

Monroe County, Pennsylvania

Prepared by:

Read and Associates, LLC

2 Monroe County Well Installation Specifications

2.0 Project Background, Hydrogeologic Setting and Drilling Conditions

According to the USGS 7.5-minute Saylorsburg Quadrangle (Figure 1), the proposed test well location is situated at an approximate elevation of 490 feet in a broad valley within the Blue Mountain Section of the

Ridge and Valley Physiographic Province. Surface topography at the proposed test well location slopes gently to the east and northeast. McMichael Creek borders the County parcel to the east and flows to the northeast.

According to publications of the Pennsylvania Bureau of Topographic and Geologic Survey, the bedrock geology at the proposed well is mapped as the Marcellus Formation, which consists of medium gray impure limestone with black graphitic shale partings. The proposed well is located near the mapped contact of the Marcellus Formation and the Buttermilk Falls Limestone on the southeast side of the

County-owned parcels. It is noted that these formations exist under a surface cover of alluvial and glacial deposits, as described below. A description of the target formations is as follows:

Marcellus Formation: Devonian Aged, alternating thinly bedded grey to black shale, locally may contain limestone.

Buttermilk Falls Limestone: Devonian aged, Gray fossiliferous limestone with siliceous limestone and some sandstone.

Surficial geology at the proposed test well is mapped as alluvium and undifferentiated glacial deposits.

The alluvial deposits occur as silt, sand, and gravel in riverbed and floodplain deposits of streams with thicknesses from six feet to 30 feet in some of the larger river valleys. Glacial till and outwash deposits cover most of the area at the proposed test well site and is more than 100 feet thick in place and could be up to 150 feet thick and contains boulders and sand.

An existing well, located approximately 850 feet southwest of the new well location, encountered sand and gravel and boulders to about 120 feet and weathered limestone from 120 feet to 140 feet with competent limestone below that to the total depth of the well at 200 feet. This well was constructed as a double-cased well with 8” diameter casing to 147 feet and 6” diameter casing to 150 feet. The well was completed as an open borehole well below that depth.

3.0 Site Access and Drill Rig Discharge Controls

Following site improvements as needed, the well site should be drive in accessible. A cuttings pit will be needed and will be installed by others. All cuttings and rig discharge water management will adhere to

3 Monroe County Well Installation Specifications

PADEP’s “Erosion and Sediment Control Best Management Practices for Water Well Drilling” (3800-FS-

DEP2685). Please see the attached Monroe Conty Conservation District Erosion and Sediment Control

Plan Template. This plan should include disposal of any sediment bag(s) used.

The drilling contractor shall be responsible for directing the discharge from the drilling operation to the cutting pit(s), and for providing a 200 gpm (minimum) suction pump and sediment bag(s). The suction pump shall be used to continuously dewater the cuttings pit during the drilling, if needed. The suction pump shall be discharged through a sediment bag (Interstate Products, Inc. #9727-OS, 15 feet x 15 feet or equivalent).

4.0 Six-inch Diameter Well Construction and Logging

The well will be constructed as a double cased, 6” open borehole well utilizing an air percussion drill rig supplied by an air compressor having a capacity of at least 900 cfm at 300 psi. The actual drilling depths and casing lengths will be determined by the drilling conditions and the RAL geologist. The construction of the well shall proceed in the following manner:

a) Drilling shall begin using a casing advancement drilling system with a minimum 10-inch diameter bit to advance a borehole and casing simultaneously to the competent bedrock surface, assumed to be at 130 feet, and install 10-inch diameter casing with a minimum wall thickness of 0.250 inches and driveshoe.

b) A nominal 10-inch diameter bit will be used to advance the borehole below the 10” casing to a depth of 160 feet, assuming competent rock is encountered at 130 feet.

c) Install 6-inch diameter steel casing that meets AWWA specifications and 0.280-inch wall thickness with welded casing joints, appropriately spaced centralizing tabs, and a welded drive shoe to the depth of the 10” borehole at 160 feet and inside of the previously installed 10” casing.

d) Seal annular space between 6” and 10” casing at bottom with 1 bag of bentonite hole plug. Install nominal 1-inch diameter tremie line from bentonite seal at casing bottom to grade for later grouting, and seal annular space at grade to prevent entry of any cuttings/drilling water.

e) Drilling will then progress with a 6-inch nominal diameter bit, and stabilizer, having a length of at least 10 feet, to be run behind the 6-inch diameter bit to the final test well depth of 400 feet.

f) After the well is advanced to its total depth, it shall be developed with air surging and air-lift pumping until the rig discharge is sediment free. RAL will be on-site during the drilling, and to prepare a continuous geologic log. This log will include a description of the lithology penetrated

4 Monroe County Well Installation Specifications by the well and identification of the depth, blown yield, pH, and specific conductance of all water-bearing horizons. Grab samples of the rig discharge water will also be collected by RAL as drilling progresses, which may require periods of air lifting at the end of a drill rod for 15 to 20 minutes to minimize sediment in the sample.

g) After confirming an adequate yield, the annular space between the 10” borehole and casing and the 6-inch casing shall be grouted with Type I/II Portland cement grout with up to 5% bentonite by weight using a tremie pipe, starting at the casing bottom and filling to grade. All grout used in the construction of the well shall be composed of one bag (94 lbs.) of API Class G cement

(or Class B similar to ASTM C-150 Type II) added to no more than five gallons of clean water. A grout sample shall be provided to RAL.

NOTE: Since the 10” casing will be left in place after advancement without a grouted annular space outside of the 10” casing, leaving the 10” casing in place will need to be approved by the PADEP. RAL will discuss this with PADEP to obtain approval.

5.0 Well Construction Contingencies

Given the uncertainty with the depth of overburden and weathered rock interval, temporary surface casing may be needed. The bid schedule includes a line item for per foot costs to drill and install 14-inch surface casing to be removed during final well construction.

6.0 Contingency for Test Well Abandonment

If the well does not produce sufficient yield or adequate water quality, the drilling contractor shall abandon the well with high solids bentonite. The abandonment shall be carried out as follows:

• One-inch diameter tremie line shall be installed to within 5 feet of the bottom of the well.

• The entire length of the wells shall be plugged with high solids bentonite applied through the tremie pipe.

• The tremie pipes and 6-inch well casings shall be removed from the well as the grouting proceeds. It is assumed the 10” casing will not be removable, and will be cut off +/- 2 feet below grade, and the site backfilled to grade..

• Driller assumes that these abandonments are performed during a separate mobilization.

5 Monroe County Well Installation Specifications

7.0 Project Schedule and Submission of Quotes for the Well Construction Work

Monroe County would like to complete this project during before the end of 2025. Drilling contractors interested in performing the well installation work should fill out the attached Bid Schedule and return it to RAL. A statement of availability to start the well installation work should also be returned with the Bid Schedule.

8.0 Basis of Payment for the Well Construction Work

Payment for the work performed in this project shall be based upon the Unit Prices on the Bid

Schedule. Quantities for the Unit Price items will be determined by RAL’s field measurements.

9.0 9.0 Bid Information

The county requires a bid bond, certified check or cashier’s check in the amount of 10% of the proposed contract amount. Bids may not be withdrawn for 60 days after they are opened and announced except as may be otherwise provided by law. Upon written notice from the County that it intends to accept the

Bidder’s proposal, the successful Bidder will be required to furnish to the County, in accordance with the

Instructions to Bidders all insurance certificates, a Performance Bond and a Payment Bond, each Bond in the amount of one hundred percent (100 %) of the Bid.

Separate bids may be required for the prime contractors depending on the work.

The Pennsylvania Prevailing Wage Act shall apply to the project.

Project Name: Monroe Well

General Description: Construct a test well.

Project Locality Hamilton Township

Awarding Agency: Robert Gress

Contract Award Date: 11/30/2025

Serial Number: 25-09818

Project Classification: Highway

Determination Date: 11/6/2025

Assigned Field Office: Scranton

Field Office Phone Number: (570)963-4577

Toll Free Phone Number: (877)214-3962

Project County: Monroe County

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Commonwealth of Pennsylvania Department of Labor & Industry Report Date: 11/6/2025 Page 1 of 7

Project: 25-09818 - Building Effective Date

Expiration Date

Hourly Rate Fringe Benefits

Total

Asbestos & Insulation Workers 7/1/2025 $37.08 $28.17 $65.25

Boilermaker (Commercial, Institutional, and Minor Repair Work)

3/1/2024 $36.71 $19.13 $55.84

Boilermakers 1/1/2024 $52.10 $35.72 $87.82

Bricklayers, Stone Masons, Pointers, Caulkers, Cleaners

5/4/2025 $40.14 $22.07 $62.21

Bricklayers, Stone Masons, Pointers, Caulkers, Cleaners

5/3/2026 $41.99 $22.07 $64.06

Carpenters - Piledriver/Welder 1/1/2025 $43.38 $22.72 $66.10

Carpenters - Piledriver/Welder 1/1/2026 $44.63 $23.47 $68.10

Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers

5/1/2025 $36.57 $20.29 $56.86

Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers

5/1/2026 $36.57 $22.29 $58.86

Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers

5/1/2027 $36.57 $24.29 $60.86

Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers

5/1/2028 $36.57 $26.29 $62.86

Cement Finishers & Plasterers 5/4/2025 $33.66 $22.42 $56.08

Cement Finishers & Plasterers 5/3/2026 $35.66 $22.42 $58.08

Cement Finishers & Plasterers 5/3/2027 $34.92 $25.16 $60.08

Cement Masons 6/1/2024 $37.78 $15.05 $52.83

Drywall Finisher 5/1/2025 $33.24 $25.08 $58.32

Electricians 6/2/2025 $65.43 $42.20 $107.63

Electricians 6/1/2026 $67.92 $43.81 $111.73

Electricians 5/31/2027 $70.29 $45.34 $115.63

Elevator Constructor 1/1/2025 $61.41 $44.95 $106.36

Elevator Constructor 1/1/2026 $64.06 $46.01 $110.07

Glazier 5/1/2024 $39.48 $23.81 $63.29

Iron Workers (Bridge, Structural Steel, Ornamental, Precast, Reinforcing)

7/1/2025 $38.76 $33.38 $72.14

Laborers (Class 01 - See notes) 5/1/2024 $31.09 $19.59 $50.68

Laborers (Class 01 - See notes) 5/1/2025 $32.09 $20.14 $52.23

Laborers (Class 02 - See notes) 5/1/2024 $32.12 $19.59 $51.71

Laborers (Class 02 - See notes) 5/1/2025 $33.12 $20.14 $53.26

Laborers (Class 03 - See notes) 5/6/2024 $31.74 $19.59 $51.33

Laborers (Class 03 - See notes) 4/27/2025 $32.74 $20.14 $52.88

Laborers (Class 04 - See notes) 5/6/2024 $33.24 $19.59 $52.83

Laborers (Class 04 - See notes) 4/27/2025 $34.24 $20.14 $54.38

Laborers (Class 05 - See notes) 5/1/2024 $33.09 $19.59 $52.68

Laborers (Class 05 - See notes) 5/1/2025 $34.09 $20.14 $54.23

Laborers (Class 06 - See notes) 5/1/2024 $32.44 $19.59 $52.03

Laborers (Class 06 - See notes) 5/1/2025 $33.44 $20.14 $53.58

Marble Mason 5/1/2025 $36.57 $21.69 $58.26

Marble Mason 5/1/2026 $38.52 $21.69 $60.21

Millwright 6/1/2025 $43.00 $22.95 $65.95

Millwright 6/1/2026 $44.97 $22.95 $67.92

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 11/6/2025 Page 2 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Operators (Building, Class 01 - See Notes) 5/1/2024 $43.73 $30.08 $73.81

Operators (Building, Class 01 - See Notes) 5/1/2025 $44.89 $30.92 $75.81

Operators (Building, Class 01 - See Notes) 5/1/2026 $46.05 $31.76 $77.81

Operators (Building, Class 01A - See Notes) 5/1/2024 $45.98 $30.74 $76.72

Operators (Building, Class 01A - See Notes) 5/1/2025 $47.14 $31.58 $78.72

Operators (Building, Class 01A - See Notes) 5/1/2026 $48.30 $32.42 $80.72

Operators (Building, Class 02 - See Notes) 5/1/2024 $43.45 $29.99 $73.44

Operators (Building, Class 02 - See Notes) 5/1/2025 $44.61 $30.83 $75.44

Operators (Building, Class 02 - See Notes) 5/1/2026 $45.77 $31.67 $77.44

Operators (Building, Class 02A - See Notes) 5/1/2024 $45.70 $30.66 $76.36

Operators (Building, Class 02A - See Notes) 5/1/2025 $46.86 $31.50 $78.36

Operators (Building, Class 02A - See Notes) 5/1/2026 $48.02 $32.34 $80.36

Operators (Building, Class 03 - See Notes) 5/1/2024 $40.73 $29.18 $69.91

Operators (Building, Class 03 - See Notes) 5/1/2025 $41.88 $30.03 $71.91

Operators (Building, Class 03 - See Notes) 5/1/2026 $43.04 $30.87 $73.91

Operators (Building, Class 04 - See Notes) 5/1/2024 $39.59 $28.85 $68.44

Operators (Building, Class 04 - See Notes) 5/1/2025 $40.74 $29.70 $70.44

Operators (Building, Class 04 - See Notes) 5/1/2026 $41.90 $30.54 $72.44

Operators (Building, Class 05 - See Notes) 5/1/2024 $39.13 $28.73 $67.86

Operators (Building, Class 05 - See Notes) 5/1/2025 $40.30 $29.56 $69.86

Operators (Building, Class 05 - See Notes) 5/1/2026 $41.45 $30.41 $71.86

Operators (Building, Class 06 - See Notes) 5/1/2024 $38.26 $28.46 $66.72

Operators (Building, Class 06 - See Notes) 5/1/2025 $39.42 $29.30 $68.72

Operators (Building, Class 06 - See Notes) 5/1/2026 $40.58 $30.14 $70.72

Operators (Building, Class 07A- See Notes) 5/1/2024 $53.10 $34.27 $87.37

Operators (Building, Class 07A- See Notes) 5/1/2025 $54.56 $35.21 $89.77

Operators (Building, Class 07A- See Notes) 5/1/2026 $56.03 $36.14 $92.17

Operators (Building, Class 07B- See Notes) 5/1/2024 $52.75 $34.17 $86.92

Operators (Building, Class 07B- See Notes) 5/1/2025 $54.22 $35.10 $89.32

Operators (Building, Class 07B- See Notes) 5/1/2026 $55.69 $36.03 $91.72

Painters Class 1 (see notes) 5/1/2024 $30.36 $24.15 $54.51

Painters Class 1 (see notes) 5/1/2025 $31.32 $24.44 $55.76

Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03

Painters Class 2 (see notes) 5/1/2025 $35.58 $25.08 $60.66

Painters Class 3 (see notes) 5/1/2025 $42.67 $25.09 $67.76

Pile Driver Divers (Building, Heavy, Highway) 1/1/2025 $62.82 $22.72 $85.54

Pile Driver Divers (Building, Heavy, Highway) 1/1/2026 $64.70 $23.47 $88.17

Piledrivers 1/1/2025 $41.88 $22.72 $64.60

Piledrivers 1/1/2026 $43.13 $23.47 $66.60

Plasterers 6/1/2024 $38.46 $14.45 $52.91

Plumbers and Steamfitters 12/1/2024 $51.49 $24.67 $76.16

Plumbers and Steamfitters 12/1/2025 $51.69 $27.67 $79.36

Roofers (Composition) 5/1/2024 $44.13 $34.77 $78.90

Roofers (Composition) 5/1/2025 $46.03 $34.77 $80.80

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 11/6/2025 Page 3 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Roofers (Shingle) 5/1/2024 $34.35 $22.20 $56.55

Roofers (Slate & Tile) 5/1/2024 $37.35 $22.20 $59.55

Sheet Metal Workers 5/1/2024 $36.13 $31.23 $67.36

Sheet Metal Workers 5/1/2025 $37.30 $32.31 $69.61

Sign Makers and Hangars 7/15/2024 $32.32 $25.82 $58.14

Sign Makers and Hangars 7/15/2025 $33.48 $26.41 $59.89

Sprinklerfitters 4/1/2024 $46.45 $28.62 $75.07

Sprinklerfitters 4/1/2025 $49.75 $29.21 $78.96

Terrazzo Finisher 5/1/2024 $35.66 $20.76 $56.42

Terrazzo Finisher 5/1/2025 $36.32 $21.68 $58.00

Terrazzo Grinder 5/1/2024 $36.42 $20.76 $57.18

Terrazzo Grinder 5/1/2025 $37.10 $21.68 $58.78

Terrazzo Mechanics 5/1/2024 $36.44 $22.51 $58.95

Terrazzo Mechanics 5/1/2025 $37.17 $23.43 $60.60

Tile & Marble Finisher 5/1/2025 $34.55 $18.09 $52.64

Tile & Marble Finisher 5/1/2026 $36.50 $18.09 $54.59

Tile Setter 5/1/2025 $36.57 $21.69 $58.26

Tile Setter 5/1/2026 $38.52 $21.69 $60.21

Truckdriver class 1(see notes) 5/1/2025 $41.87 $0.00 $41.87

Truckdriver class 2 (see notes) 5/1/2025 $41.94 $0.00 $41.94

Truckdriver class 3 (see notes) 5/1/2025 $42.43 $0.00 $42.43

Window Film / Tint Installer 6/1/2019 $24.52 $12.08 $36.60

Window Film / Tint Installer 6/1/2024 $26.37 $14.83 $41.20

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 11/6/2025 Page 4 of 7

Project: 25-09818 - Heavy/Highway Effective

Expiration Date

Hourly Rate Fringe Benefits

Total

Carpenter 5/1/2025 $36.87 $20.49 $57.36

Carpenter 5/1/2026 $37.63 $21.18 $58.81

Carpenter Welder 5/1/2025 $37.62 $20.49 $58.11

Carpenter Welder 5/1/2026 $38.38 $21.18 $59.56

Carpenters - Piledriver/Welder 1/1/2025 $37.62 $20.49 $58.11

Carpenters - Piledriver/Welder 1/1/2026 $38.38 $21.18 $59.56

Cement Finishers 6/1/2016 $32.43 $11.35 $43.78

Electric Lineman 1/1/2025 $66.33 $30.40 $96.73

Electric Lineman 9/1/2025 $68.06 $32.29 $100.35

Iron Workers (Bridge, Structural Steel, Ornamental, Precast, Reinforcing)

7/1/2024 $37.26 $32.63 $69.89

Laborers (Class 01 - See notes) 5/1/2024 $25.61 $19.49 $45.10

Laborers (Class 01 - See notes) 5/1/2025 $26.61 $19.99 $46.60

Laborers (Class 02 - See notes) 5/1/2024 $32.23 $19.49 $51.72

Laborers (Class 02 - See notes) 5/1/2025 $33.23 $19.99 $53.22

Laborers (Class 03 - See notes) 5/1/2024 $29.22 $19.49 $48.71

Laborers (Class 03 - See notes) 5/1/2025 $30.22 $19.99 $50.21

Laborers (Class 04 - See notes) 5/1/2024 $29.57 $19.49 $49.06

Laborers (Class 04 - See notes) 5/1/2025 $30.57 $19.99 $50.56

Laborers (Class 05 - See notes) 5/1/2024 $30.24 $19.49 $49.73

Laborers (Class 05 - See notes) 5/1/2025 $31.24 $19.99 $51.23

Laborers (Class 06 - See notes) 5/1/2024 $29.66 $19.49 $49.15

Laborers (Class 06 - See notes) 5/1/2025 $30.66 $19.99 $50.65

Laborers (Class 07 - See notes) 5/1/2024 $29.95 $19.49 $49.44

Laborers (Class 07 - See notes) 5/1/2025 $30.95 $19.99 $50.94

Laborers (Class 08 - See notes) 5/1/2024 $30.43 $19.49 $49.92

Laborers (Class 08 - See notes) 5/1/2025 $31.43 $19.99 $51.42

Millwright 6/1/2025 $45.46 $23.33 $68.79

Millwright 6/1/2026 $47.52 $23.33 $70.85

Operators (Heavy, Class 01 - See Notes) 5/1/2024 $42.30 $29.66 $71.96

Operators (Heavy, Class 01 - See Notes) 5/1/2025 $43.46 $30.50 $73.96

Operators (Heavy, Class 01 - See Notes) 5/1/2026 $44.61 $31.35 $75.96

Operators (Heavy, Class 01A - See Notes) 5/1/2024 $44.55 $30.32 $74.87

Operators (Heavy, Class 01A - See Notes) 5/1/2025 $45.71 $31.16 $76.87

Operators (Heavy, Class 01A - See Notes) 5/1/2026 $46.86 $32.01 $78.87

Operators (Heavy, Class 02 - See Notes) 5/1/2024 $42.02 $29.57 $71.59

Operators (Heavy, Class 02 - See Notes) 5/1/2025 $43.18 $30.41 $73.59

Operators (Heavy, Class 02 - See Notes) 5/1/2026 $44.34 $31.25 $75.59

Operators (Heavy, Class 02A - See Notes) 5/1/2024 $44.27 $30.24 $74.51

Operators (Heavy, Class 02A - See Notes) 5/1/2025 $45.43 $31.08 $76.51

Operators (Heavy, Class 02A - See Notes) 5/1/2026 $46.59 $31.92 $78.51

Operators (Heavy, Class 03 - See Notes) 5/1/2024 $39.11 $28.70 $67.81

Operators (Heavy, Class 03 - See Notes) 5/1/2025 $40.26 $29.55 $69.81

Operators (Heavy, Class 03 - See Notes) 5/1/2026 $41.43 $30.38 $71.81

Operators (Heavy, Class 04 - See Notes) 5/1/2024 $37.96 $28.38 $66.34

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 11/6/2025 Page 5 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Operators (Heavy, Class 04 - See Notes) 5/1/2025 $39.12 $29.22 $68.34

Operators (Heavy, Class 04 - See Notes) 5/1/2026 $40.28 $30.06 $70.34

Operators (Heavy, Class 05 - See Notes) 5/1/2024 $37.51 $28.25 $65.76

Operators (Heavy, Class 05 - See Notes) 5/1/2025 $38.67 $29.09 $67.76

Operators (Heavy, Class 05 - See Notes) 5/1/2026 $39.83 $29.93 $69.76

Operators (Heavy, Class 06 - See Notes) 5/1/2024 $36.64 $27.98 $64.62

Operators (Heavy, Class 06 - See Notes) 5/1/2025 $37.80 $28.82 $66.62

Operators (Heavy, Class 06 - See Notes) 5/1/2026 $38.96 $29.66 $68.62

Operators (Heavy, Class 07A - See Notes) 5/1/2024 $51.39 $33.77 $85.16

Operators (Heavy, Class 07A - See Notes) 5/1/2025 $52.85 $34.71 $87.56

Operators (Heavy, Class 07A - See Notes) 5/1/2026 $54.32 $35.64 $89.96

Operators (Heavy, Class 07B - See Notes) 5/1/2024 $51.04 $33.67 $84.71

Operators (Heavy, Class 07B - See Notes) 5/1/2025 $52.51 $34.60 $87.11

Operators (Heavy, Class 07B - See Notes) 5/1/2026 $53.97 $35.54 $89.51

Operators (Highway, Class 01 - See Notes) 5/1/2024 $41.41 $29.39 $70.80

Operators (Highway, Class 01 - See Notes) 5/1/2025 $42.56 $30.24 $72.80

Operators (Highway, Class 01 - See Notes) 5/1/2026 $43.72 $31.08 $74.80

Operators (Highway, Class 01a - See Notes) 5/1/2024 $43.66 $30.07 $73.73

Operators (Highway, Class 01a - See Notes) 5/1/2025 $44.81 $30.92 $75.73

Operators (Highway, Class 01a - See Notes) 5/1/2026 $45.97 $31.76 $77.73

Operators (Highway, Class 02 - See Notes) 5/1/2024 $40.24 $29.04 $69.28

Operators (Highway, Class 02 - See Notes) 5/1/2025 $41.39 $29.89 $71.28

Operators (Highway, Class 02 - See Notes) 5/1/2026 $42.55 $30.73 $73.28

Operators (Highway, Class 03 - See Notes) 5/1/2024 $39.55 $28.83 $68.38

Operators (Highway, Class 03 - See Notes) 5/1/2025 $40.70 $29.68 $70.38

Operators (Highway, Class 03 - See Notes) 5/1/2026 $41.87 $30.51 $72.38

Operators (Highway, Class 04 - See Notes) 5/1/2024 $39.10 $28.70 $67.80

Operators (Highway, Class 04 - See Notes) 5/1/2025 $40.26 $29.54 $69.80

Operators (Highway, Class 04 - See Notes) 5/1/2026 $41.41 $30.39 $71.80

Operators (Highway, Class 05 - See Notes) 5/1/2024 $38.58 $28.56 $67.14

Operators (Highway, Class 05 - See Notes) 5/1/2025 $39.73 $29.41 $69.14

Operators (Highway, Class 05 - See Notes) 5/1/2026 $40.89 $30.25 $71.14

Operators (Highway, Class 06 - See Notes) 5/1/2024 $41.64 $29.46 $71.10

Operators (Highway, Class 06 - See Notes) 5/1/2025 $42.80 $30.30 $73.10

Operators (Highway, Class 06 - See Notes) 5/1/2026 $43.95 $31.15 $75.10

Operators (Highway, Class 06/A - See Notes) 5/1/2024 $43.89 $30.12 $74.01

Operators (Highway, Class 06/A - See Notes) 5/1/2025 $45.05 $30.96 $76.01

Operators (Highway, Class 06/A - See Notes) 5/1/2026 $46.21 $31.80 $78.01

Operators (Highway, Class 07/A - See Notes) 5/1/2024 $50.32 $33.45 $83.77

Operators (Highway, Class 07/A - See Notes) 5/1/2025 $51.79 $34.38 $86.17

Operators (Highway, Class 07/A - See Notes) 5/1/2026 $53.25 $35.32 $88.57

Operators (Highway, Class 07/B - See Notes) 5/1/2024 $48.91 $33.03 $81.94

Operators (Highway, Class 07/B - See Notes) 5/1/2025 $50.37 $33.97 $84.34

Operators (Highway, Class 07/B - See Notes) 5/1/2026 $51.84 $34.90 $86.74

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 11/6/2025 Page 6 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03

Painters Class 2 (see notes) 5/1/2024 $34.16 $24.75 $58.91

Painters Class 3 (see notes) 5/1/2024 $41.01 $24.75 $65.76

Pile Driver Divers (Building, Heavy, Highway) 1/1/2022 $56.40 $20.50 $76.90

Piledrivers 5/1/2025 $36.87 $20.49 $57.36

Piledrivers 5/1/2026 $37.63 $21.18 $58.81

Steamfitters (Heavy and Highway - Gas Distribution) 5/1/2025 $54.39 $44.73 $99.12

Truckdriver class 1(see notes) 5/1/2025 $41.87 $0.00 $41.87

Truckdriver class 2 (see notes) 5/1/2025 $41.94 $0.00 $41.94

Truckdriver class 3 (see notes) 5/1/2025 $42.43 $0.00 $42.43

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 11/6/2025 Page 7 of 7

Well Drilling Advertisement.docx

File details come from the government source that posted it. Updated .