GSPB PLAZA - ELECTRICAL PACKAGE
Solicitation number
2026-01204A
Issued by
Baldwin County, Alabama

About this file

This is a Trade Contractor Bid Package for the electrical work associated with the Gulf Shores Pedestrian Bridge Plazas project in Gulf Shores, Alabama, managed by J.T. Harrison Construction Company, LLC as the Construction Manager on behalf of the City of Gulf Shores. The scope of work includes site step lighting, wall lighting, light poles, suspension lighting, tree lighting, landscape lighting, security poles, foundations for pole lights, conduit for utilities, lighting rough-in for concrete walls and structures including restroom trailers, restroom buildings, and splash pads. The project involves construction of pedestrian plaza areas with hardscaping, landscaping, and public amenities supporting the pedestrian bridge corridor. Bidders may submit proposals for this electrical package individually or in combination with other available trade packages. The bid package requires trade contractors to submit shop drawings and submittal data within 10 days of Notice to Proceed and to maintain a full-time superintendent with a minimum of 10 years' experience on-site throughout the project duration. All materials and equipment must be new, and trade contractors are responsible for daily debris removal, safety program compliance including OSHA adherence, coordination with other trades, as-built drawing maintenance, and project scheduling in Microsoft Project format.

Pricing proposals must exclude all sales and use taxes. The trade contractor bears responsibility for temporary facilities including office trailers, water, power, and storage containers at their own expense, as well as line locating renewal and obtaining a City of Gulf Shores Business License. Liquidated damages are assessed at 6 percent per annum on the total contract sum for project delays, with schedule deviations to be remedied through overtime hours and weekends. The City of Gulf Shores shall furnish Builders Risk insurance for the project. Testing services are provided through partnerships with Neel-Schaffer, Inc. and Thompson Engineering, with retesting costs resulting from non-compliance borne by the trade contractor. All utility shutdowns, overtime, and tie-ins require Construction Manager approval and coordination. The trade contractor must indemnify and hold harmless the City of Gulf Shores, the Construction Manager, the Architect, Engineers, and their respective agents and employees from all claims arising from performance of work or failure to comply with contract documents.

View the file

Other files

File Type Posted
4-ADVERTISEMENT FOR BIDS INFO.docx DOCX document
3-Plans-BID.pdf PDF
2-Specifications-BID.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Trade Contractor Package GSPBP #3 - Electrical

Summary of Work

Pedestrian Bridge Plazas

Gulf Shores, AL Trade Contractor Bid Package GSPBP-03 – Electrical Package Bid Documents

Advertisement for Bids

Instructions to Bidders

Form of Bid Bond

Proposal Form

Accounting of Sales Tax

MASTERSPEC

ARCHITECTURAL/STRUCTURAL/CIVIL LIBRARY

BASIC VERSION

TABLE OF CONTENTS – NOVEMBER, 2000

Contract Requirements

Form of Agreement

Insurance Requirements

Form of Performance Bond

Form of Payment Bond

Contract Change Order

Technical Specifications

DIVISION 1 - GENERAL REQUIREMENTS

DIVISION 26 – ELECTRICAL

DIVISION 27 – COMMUNICATIONS

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

End of Index

MASTERSPEC

ARCHITECTURAL/STRUCTURAL/CIVIL LIBRARY

BASIC VERSION

TABLE OF CONTENTS – NOVEMBER, 2000

Summary of Work:

In general, the scope of work covered in this bid package includes all work shown on the drawings and called for in the specifications and includes, but is not limited to, the following items:

1. The Trade Contractor shall provide all materials, labor, and equipment necessary to complete the scope of work within the scheduled time.

2. The Trade Contractor shall include the cost of debris and trash removal from the building and site daily to a trash receptacle furnished by the Construction Manager. The Construction Manager shall remove the trash off site at no cost to the Trade Contractor. Upon 24-hour notice from the Construction Manager to the Trade Contactor, the Owner shall have the right to clean up the Trade Contractor’s construction debris at a rate of $125 per hour, which will be deducted from the Trade Contractor’s contract.

3. It shall be the Trade Contractors responsibility to run a safe job. Each Trade Contractor shall be responsible to follow all OSHA rules, regulations, and guidelines as it pertains to each specific scope of work being performed by either Trade Contractor’s employees or Trade Contractor’s subcontractors. Special attention shall be paid to safety as it applies to trenching, fall protection, confined space operation, scaffold safety, as well as equipment operation. Weekly safety meetings shall be held onsite and will be attended by all employees presently working onsite. A written safety program will be required from each Trade Contractor and shall be in place at the Construction Manager’s jobsite trailer prior to beginning work on the project. The safety program shall include hazardous safety data sheets, scaffolding safety, as well as fall protection.

4. It shall be the responsibility of this Trade Contractor to provide appropriate certifications for all equipment and employees (including Trade Contractor’s subcontractor’s employees) operating equipment under the control of said Trade Contractor. It is the Trade Contractor’s responsibility to provide certification papers on equipment and employees to the Construction Manager prior to delivery of equipment on site. Any person caught operating a piece of equipment on site without proper certification will be asked to leave the site until appropriate certification is obtained.

5. Each Trade Contractor shall furnish telephone communication as their trade shall require. The Trade Contractor’s superintendent shall maintain a mobile phone capable of direct communication with the Construction Manager.

6. The Trade Contractor shall employ a superintendent on the jobsite of not less than 10 years’ experience in trades related field. This superintendent must remain on the jobsite full time throughout the duration of the project. Resumes shall be submitted to and approved by the Owner and Construction Manager prior to beginning work associated on Contract. It shall be at the Construction Manager’s discretion if the submitted superintendent is qualified for this project. This superintendent shall be capable of making all decisions required on behalf of the Trade Contractor. The superintendent shall be at each weekly progress meeting and shall be capable of scheduling responsible work.

7. All Trade Contractors working on site or working subcontractors on site, shall have a competent person employed by the Trade Contractor. This person shall have a minimum certification of OSHA 10 Hour Training Course and working knowledge of specific Trade Contractor’s Safety Program.

8. The Trade Contractor shall comply with bidding requirements, contract forms, and the general conditions of the contract as outlined in the Table of Contents.

9. The Trade Contractor is responsible for coordination of their work with other Trades.

10. The Trade Contractor shall be responsible for his scope of work until fully accepted by the Owner.

11. Temporary water will be supplied at central locations on the project at no cost to the Trade Contractor.

12. This Trade Contractor will indemnify and hold harmless City of Gulf Shores (Owner), Harrison Construction Company, LLC. (Construction Manager), Architect, Engineers, and their employees, agents, Subcontractors, and leased workers from and against all claims of any sort relating to or in any way arising out of or resulting from performance of the work described in this agreement or from any failure by Trade Contractor or its Subcontractors or leased workers to observe any term or condition contained in the drawings and/or specifications for the project and all addenda thereto. The indemnity includes, but is not limited to, claims for injury or death to person or damage to personal property, claims on infringement of any intellectual property rights, and penalties imposed on account of any violation of or failure to comply with any law or regulation by Trade Contractor or its Subcontractors, or leased workers. Trade Contractor and its Subcontractor will maintain all such insurance as is necessary to cover these indemnity obligations under his agreement and to protect the Owner and Construction Manager from claims under workers’ compensation laws or statues and any other claims for injury, death, or damage.

13. All utility shutdowns, overtime, and tie-ins will be scheduled through the Construction Manager. Premium time shall be included for any shutdowns which may be required.

14. The Trade Contractor shall provide sufficient onsite insured dry storage or bonded warehouse space as required.

15. The Owner has partners with Neel-Schaffer, Inc. and Thompson Engineering for all on site testing services. Retesting as a result of non-compliance with the contract documents shall be paid by the Trade Contractor.

16. This Trade Contractor shall be responsible for all cutting and patching as it pertains to their scope of work.

17. The Trade Contractor shall visit the site prior to bidding to be familiar with existing conditions.

18. Each Trade Contractor shall be responsible for furnishing and paying for their own temporary facilities such as office trailers, water and power, storage containers, etc. It will be at the discretion of the Construction Manager as to which Trade Contractors may use an office trailer on site.

19. The Trade Contractors’ proposal shall Exclude the cost of all sales and use taxes.

20. It shall be the responsibility of this Trade Contractor to submit a project schedule including project specific milestones to the Construction Manager within 10 days upon receiving a Notice to Award. The schedule needs to be submitted electronically in Microsoft Project format. The Construction Manager will compile all of the Trade Contractor schedules and create a Master Schedule within 5 days from receiving Trade Contractor Schedules. Each Trade Contractor will have 5 days to review the Master Schedule and submit back to the Construction Manager with any notes. The Construction Manager will then finalize the Master Schedule and submit to each Trade Contractor as a no cost Change Order to each contract.

21. Liquidated damages shall be accessed in the amount of 6% per annum on the total Contract Sum for delays to the Project Schedule. Any deviation from the schedule, identified as the responsibility of this Trade Contactor, shall be made up on overtime hours and weekends.

22. The ADEM permit for this project is already in place. Stormwater monitoring, inspections, and reports will be handled by TTL Civil Engineering. This Trade Contractor will be responsible for implementing, utilizing, and maintaining appropriate BMPs throughout the duration of the project. Any deficiencies or erosion control maintenance items shall be corrected by this Trade Contractor. Any erosion control measures damaged by other trade contractors shall be repaired or replaced by responsible trade contractor(s).

23. Building permits are still required. Please apply for all applicable city permits through CitizenServe, but, the city will waive all fees associated with the permits. It shall be each Trade Contractor’s responsibility to obtain specific inspections as required to meet the overall project schedule.

24. The Owner shall furnish Builders Risk for the project.

25. All Trade Contractors personnel shall wear hard hats for the duration of the project. Each employee must wear ID badges that bear the company name, employee name, and employee picture.

26. No Trade Contractor employees or their subcontractor’s employees under the age of 18 years old will be allowed on the project without written authorization from the Construction Manager. No one under the age of 18 years old shall be allowed on site without authorization. No Exceptions.

27. Each Trade Contractor shall fill out a daily report of work and file in the Construction Managers Field office each day when work has been performed. The Construction Manager shall furnish forms for this report.

28. Each Trade Contractor shall be responsible for maintaining 2 updated sets of as-built drawings on the project site. Construction Manager shall periodically review record Drawings for compliance with this requirement. Upon review, if deficiencies are found, pay applications shall be held until compliance.

29. This Trade Contractor is to furnish a complete set of electronic copies of all Submittal Data to Construction Manager in PDF Format for required approval. Physical samples and color charts are to be hand delivered to the onsite office trailer. Each Transmittal shall bear complete itemized description of submittal package including related number matching specification section. Submittals shall be submitted in a complete format as specified under the submittal heading in each specification section. Each submittal shall be reviewed and stamped by the Trade Contractor prior to submission to Construction Manager. Within seven (7) days of an approved submittal, the Trade Contractor shall provide two (2) hard copies of each submittal to the jobsite office of the Construction Manager.

30. Each Trade Contractor shall be responsible for any line locating and renewal throughout the project.

31. This Trade Contractor must obtain a current City of Gulf Shores Business License and shall keep a copy of said license on site at all times.

Scope of Work:

1. This Trade Contractor is responsible for all Bidding Documents, Contract Documents, and Technical Specifications as shown in the Project Specification Book.

2. All shop drawings and submittal data are to be submitted to the Construction Manager within 10 days of Notice to Proceed.

3. This Trade Contractor shall confirm, coordinate, and accept the layout established by previous Trade Contractor prior to beginning work.

4. This Trade Contractor is responsible for but not limited to the following:

a. Site step lighting, wall lighting, light poles, suspension lighting, tree lighting, landscape lighting, security poles, etc.

b. Foundations for pole lights (pole lights to be provided and installed by Baldwin EMC)

i. Anchor Bolts provided by Baldwin EMC

c. Conduit for Utilities at Bathroom Trailer

d. All Lighting Rough in for concrete walls

e. All Lighting utility rough in for restroom trailer, restroom building, and splash pad.

5. The GSPBP-01 Sitework Contractor will install all required erosion control measures and BMP’s. Each Trade Contractor shall protect all erosion control measures. Any erosion control measures damaged by a certain Trade Contractor, said Trade Contractor shall correct the damaged erosion control measures at their own expense.

6. This Trade Contractor shall be responsible for cleaning electrical equipment, fixtures, and panels at the end of the project. This includes, but is not limited to, removing dirt, grime, dust, smudges, etc. from surfaces acceptable to the Owner, Architect, Engineer, and Construction Manager.

7. All material and equipment to be utilized on this project shall be new. In no case, will repurposed, reused, or contractor inventoried material be accepted on this project.

8. Where exposed materials occur, this Trade Contractor is responsible for installing materials in a clean and orderly fashion.

9. It is this Trade Contractor’s responsibility to coordinate with the Construction Manager and other trade packages before digging near any existing structures.

10. It is this Trade Contractor’s responsibility to coordinate with Construction Manager on lay-down of any stored materials.

End of Electrical Trade Package