This document is a Statement of Work (SOW) for a federal contract opportunity to repair a failed culvert and several sinkholes on Bee Canyon OHV Road in the San Jacinto Ranger District of the San Bernardino National Forest. The contract requires the contractor to provide equipment, labor, materials, and services to excavate sinkholes, rebuild and reconstruct the road surface, install a 24-inch overside drain, re-install a corrugated metal pipe, lay erosion control mat, construct two rolling dips with armoring, and grade one mile of road.
The related federal contract opportunity, Solicitation Number 127EAW24R0053, is a Total Small Business Set Aside valued between $100,000 and $250,000. The projected start date is September 2024, with a 120-calendar day period of performance. An organized site visit is scheduled for July 8, 2024, and all Requests for Information must be submitted by July 16, 2024. The contracting agency is the Department of Agriculture Forest Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A00001 - Due Date Extension and RFIs.pdf | ||
| RFI Official Responses - 1.pdf | ||
| 8. Davis-Bacon Act WD # CA20240026.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 5. Project Location and PDL Map.pdf | ||
| 6. Bee Canyon Project Drawings.pdf | ||
| 3. FS Supplemental Specifications.pdf | ||
| 9. RFI Form.docx | DOCX document | |
| 7. Fire Plan.pdf | ||
| 127EAW24R0053 Bee Canyon Road Rehabilitation.pdf | ||
| 4. FP - 14 Specifications.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SCOPE OF CONTRACT
The purpose of this contract is to repair a failed culvert and several sinkholes on Bee Canyon
OHV Road (System Road 5S07) on the San Jacinto Ranger District of the San Bernardino
National Forest. This contract provides for the equipment, labor, materials, and services necessary to perform work ordered by the Government in compliance with its terms, specifications, drawings, and provisions, for the
Excavate sinkholes which tunneling under the road surface to the opening end, rebuild and reconstruct to road surface elevation, install a 24” overside drain (material provided), re-install a corrugated metal pipe at failure location (80’x 36”) with geogrid reinforcement by layers, lay erosion control mat to protect the slope, construct two rolling dips with armoring and grade one miles of road.
Project Location
National Forest San Bernardino
Ranger District San Jacinto Ranger District
County Riverside
This project is located near Hemet, Riverside County, CA, 9 mile east of Hemet, off CA-74.
Google Maps Search Address: “Bee Canyon OHV Road 5S07”.
Driving direction: From the USFS Cranston Fire Station continue via CA-74 E, approximately
0.7 miles turn left onto Bee Canyon Truck Trail. The project site is on Bee Canyon OHV Road
5S07 approximately 1.7 miles from CA-74
The project is on Bee Canyon OHV Road, 5S07, between its intersection with CA-74 and the project location with elevation change from 2000 ft. to 2400 ft. See provided map for specific project locations. Detailed project site maps are included in this solicitation.
The Forest Service highly recommends a site visit prior to bidding to ensure complete knowledge of project conditions and the concerns regarding logistics and operations. For additional information about the locations or access to the specific routes contact Christopher Soohoo or Bo
Zhang at the Forest Supervisors Office, (909)893-0648 or (840)466-7868 respectively.
Period of Performance
Projected start date: September, 2024
Restricted work: Limit construction activities within road prism and CO approved staging areas.
Load limits apply over bridge.
Time for completion: 120 calendar days from the issuance of the “Notice to Proceed”.
SECTION C
Requirements
The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities to perform the Statement of Work/Specifications referenced below (see Specifications in Section
C).
The is the Contractor responsibility to secure special permit(s) as required for Mobilization of heavy equipment/heavy load on public roads.
The Contractor shall repair all damages caused by their operations or equipment prior to partial or final payment.
The Contractor shall legally dispose of all project related trash, debris and excess as it accumulates on site.
The Contractor shall adhere to the pertinent requirements addressed in the Fire Plan (see
Attachment). Fire Plan restrictions may require work to cease at 1:00 pm or not be initiated at all on a high fire activity day.
The Contractor is responsible for traffic control and equipment requirements in work areas when working on National Forest System Lands.
All ground disturbing equipment shall be thoroughly cleaned of debris and dirt before mobilizing onto Forest lands to prevent the introduction of invasive weeds into those areas. No separate measurement and payment will be included for this item.
Specifications
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S. Customary Units and Forest Service Supplemental Specifications (FSSS). FP-14 and
State of California specifications or typical when referred to as well as Construction Best
Practices.
Temporary traffic control shall be in accordance with the manual on uniform traffic control devices (MUTCD) latest version.
FSSS (Attached)
Drawing Sheets (Attached)
Fire Plan (Attached)