1. Statement of Work.pdf

PDF 260 KB Posted

Attached to
MPF Carpet Replacement
Solicitation number
FA483024Q0042
Issued by

About this file

This document is a Statement of Work (SOW) for a carpet replacement project at Building 105 on Moody Air Force Base in Georgia. The SOW outlines the contractor requirements, which include moving furniture, removing and disposing of existing carpet, and installing new carpet, rubber cove base, and door transitions. The contractor must use one of the seven carpet contracts awarded under the Air Force Carpet Program and submit samples for customer approval prior to installation. The work must be performed by certified installers and completed within 90 days of contract award. The SOW also includes requirements for disposal, cleaning, safety, and warranty coverage.

The related federal contract opportunity is a combined synopsis/solicitation for the carpet replacement project at the Military Personnel Flight building on Moody AFB, Georgia. The solicitation provides details on the customer's carpet selections, site visit information, and instructions for submitting a base access request. Funds are not currently available for this effort, and the government reserves the right to cancel the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Carpet Replacement

Building 105 23 Force Support Squadron

Moody AFB, Georgia

GENERAL:

The contractor shall provide all personnel, equipment, tools, supplies, materials, supervision, and transportation necessary to:

1. Move furniture and return to exact location.

2. Remove and dispose of indicated existing carpet.

3. Remove indicated portions of existing base from wall and columns.

4. Furnish and install new carpet, rubber cove base, and door transitions.

5. Contractor shall verify all dimensions during site visit.

6. Contractor shall submit physical samples of carpet, transitions, and cove base to customer prior to installation.

PERFORMANCE REQUIREMENTS:

Air Force Carpet Program: As of 14 Aug 2023, carpet installation shall be accomplished in accordance with the Air Force Carpet Program, using the carpet ordering guide and one of the seven contracts awarded for materials. The Air Force Carpet Program includes modular carpet tiles, roll goods, walk-off tiles, and adhesives. Installation will be managed by local installers.

Measurements: The contractor shall be responsible for measuring and verifying the area and perimeter of all spaces receiving carpet, cove base and door transitions.

Product Data: Submit two copies of manufacture’s full technical data and installation instructions for each type of carpet and accessory. Contractor shall submit physical samples to customer prior to installation.

1. The contractor shall move furniture as necessary to remove and install carpet. Furniture shall be returned to the exact location it was moved from.

2. The contractor shall choose one of the vendors to work with and install the carpet selections below in the locations indicated.

Tier 1 C – Type

Contracts

Carpet Selection Contract Number

Mohawk GT465 Taking Steps - Motivated Movement - 855 Ramon FA800323C003

Engineered Floors 5GM-T - 7572 Naturalist Modular Tile - 3231 Teal FA800323C0004

Interface Americas AE 310 - 104627 Smoke FA800323C0005

Mannington Blueprint Collection - Script - 15217 Borough FA800323C0006

Tarkett Crosscut Collection - Stamp 11018 - 28310 Blue Stake FA800323C007

Milliken Nordic Stories - Americas - Isograd - Tip Shear - IGR13-119 Esker FA800323C008

Bentley Mills 8OU230AAK - 5GM-P Outlier - Fringe 801679 FA800323C0009

3. Cove base: Install resilient rubber cove base, (1/8” thick, 4” high, Flexco, or approved equal) in areas where carpet is being installed to replace all existing base removed. Color will match carpet color as close as possible.

4. Transitions if applicable: The contractor shall install transitions in areas where there is a change in floor type or carpet height. Transitions shall match or compliment cove base. Color will match carpet color as close as possible.

Removal and Disposal:

1. Carpet: The contractor shall remove and dispose of carpet indicated on floor plans without disturbing the flooring underneath.

2. Cove Base and Transitions: The contractor shall dispose of a current base from walls and columns and remove existing transitions.

3. Disposal: The contractor is responsible for providing a dumpster at the worksite prior to starting the carpet installation and removing it after completion.

Installation: Contractor Qualifications: All work shall be performed by contractors/installers who are

Certified floor covering installers (by the International Certified Floor Covering Installer Association) or the manufacturer’s approved installers. Foreman on the job site shall be “Certified C-II Minimum.”

For warranties to be valid, all carpet shall be installed in accordance with the installation guidelines set forth by the manufacturer and/or the minimum guidelines set forth in CRI 104-2002, Standard for

Installation Specification of Commercial Carpet, and CRI 105-2002, Standard for Installation of

Residential Carpet.

1. Carpet: The contractor shall work with one of the vendors listed under General

Information and install the carpet choices in the areas indicated. Carpet shall be installed in full accordance with manufacturer’s recommendations to preserve all warranties.

2. Cove Base: The contractor shall install resilient rubber cove base in areas where carpet is being replaced/installed. (1/8” thick, 4” high, Flexco, or approved equal. Color should match carpet color as closely as possible. All outside corners will be factory made outside corner pieces. Color of the vinyl baseboards will be either, approved by requester prior to vendor purchase. Rubber or synthetic entry thresholds will be replaced with new material. Metal or wooden thresholds will be removed and/or replaced as necessary. The Contractor shall verify all dimensions required to install carpet and rubber cove. The Government does not guarantee the above dimensions are 100% accurate.

3. Transitions if applicable: The contractor shall install transitions in areas where there is a change in floor type. Transitions shall match or compliment cove base.

4. Additional Material: The contractor shall provide 5% of extra tiles above the amount installed. These will be given to the customer.

General Information: Carpet criteria shall comply with the Air Force Carpet Program:

https://usaf.dps.mil/sites/aficc/afcc/AFICC/AFFCC/SiteCollectionDocuments/Carpet/CarpetHomePa ge.aspx?PageView=Shared&InitialTabId=Ribbon.WebPartPage&VisibilityContext=WSSWebPartPa ge%20&siteid={448B9DA1-D83A-4721-8055-45432E36427C}&webid={519EE7F0-0F21-43A9-

BD58-A0B7B620A749}&uniqueid={95848866-B5AB-4423-8FA8-2DA9E6AD28CB}

Company Website/Email Contact Information

Mohawk Mohawkgroup.com 800-554-6637

Engineered Floors https://www.engineeredfloors.com/ 800-706-9745

Interface Americas https://www.interface.com/US/enͲUS/homepage 800-634-6032

Mannington Manningtoncommercial.com 800-241-2262

Tarkett www.tarkettna.com 800.899.8916

Milliken https://www.milliken.com/en-us/businesses/floor-covering/segments/government

202-480-6461

Bentley Mills Mindy.dever@bentleymills.com 859-536-7846

Performance Period: Shall not exceed 90 days from date of contract award.

Work Schedule/Hours/Plans: Workdays for this contract will be after normal duty hours

(Monday -Friday, after 5:00 pm). Contractor shall not begin any work until 100% material is complete. Written permission from the designated Government Representative (2d Lt Daniela Brockett) shall be obtained before making any deviation from the schedule.

Vacating Rooms: Furniture shall be moved and returned to its exact location after installation is complete. Heavy filing cabinets will be emptied by government personnel if necessary. A point of contact (2d Lt Daniela Brockett) will be assigned to coordinate scheduling and relocations.

Doors: After carpet installation is complete, the contractor shall ensure that all doors affected by the project can open and close properly.

Cleaning: After carpet installation is complete and prior to returning furniture to its original location, the contractor shall remove all debris, scraps, and any other foreign matter. Contractor shall remove any spots or adhesive from the carpet or adjoining surfaces, to include walls, clip any protruding face yard and vacuum the entire work area.

Safety Requirements: Safety requirement shall be the applicable sections of EM 385-1-1, 30

November 2014 and Occupational Safety and Health Administration (OSHA) regulations. OSHA regulations are available for review at the Base Safety Office, Building 105. EM 385-1-1 is available for reference in the Civil Engineering Office, Building 918. The contractor shall ensure that any lifting devices or ladders meet all applicable safety standards. The contractor shall be required to use those lifting devices that will allow for the existing modular systems furniture to be raised for the installation of the new materials requested. The contractor will be required to disconnect any electrical system connections to or from the modular systems furniture, but contractor and facility manager must contact communications squadron focal point to have them come out to verify and unlock the port before contractor begins unplugging anything.

Site Visit: A site visit will be offered pursuant to Federal Acquisition Regulation (FAR) Clause

52.237-1. Regardless of site visit attendance, contractors acknowledge satisfaction as to the nature and location of the work, the general and local conditions, access to job site; disposal, handling and storage of materials; availability of labor, water, electric power or similar physical conditions at http://www.engineeredfloors.com/ http://www.interface.com/US/enͲUS/homepage http://www.tarkettna.com/ http://www.milliken.com/en-mailto:Mindy.dever@bentleymills.com

Moody Air Force Base; the character of equipment and facilities needed preliminary to and during the performance of the work; and all other matters that can in any way affect the work or costs related to this requirement upon submission of offers. Contractors further acknowledge that any damage to the existing structure in and around facilities will be returned to existing condition prior to the completion of subject work at no additional cost to the Government in accordance with FAR

Clause 52.237-2. The contractor shall provide the Government with a one-year warranty on workmanship. The contractor shall provide any manufacturer’s warranty to the Government.

Power to Modular Furniture: Contactors are responsible to disconnect and reconnect electrical and comm lines connected to modular furniture. The circuit breaker needs to be turned off, verified as correct circuit and then a lock-out/tag-out device applied. Contractor is to coordinate with facility manager to schedule a time for CE Electric shop to open the electrical room and advise the contractor’s electrical person on which breaker needs to be turned off. The contract employee would be responsible to turn off the breaker, verify at the work location that the correct breaker was deenergized, then apply a lock-out device and tag to the breaker. At the completion of the work, contact CE to return and open the mech room for the contractor to complete these steps in reverse order, restoring power to the furniture.

Inspection: Contact must be made with the Civil Engineering Squadron through their customer service line at 229-257-3678 when work has been completed but before payment is made.

File details come from the government source that posted it. Updated .