This document is a Schedule of Items for the Black Hills National Forest Forestwide Recreation Roof and Siding Replacement project. The project includes the removal and replacement of roofing systems, siding, and fascia on various informational kiosks, restroom buildings, and pumphouses located throughout the Black Hills National Forest. The work is organized into Base Bid Items and Option Bid Items, with contractors required to submit pricing for all items. The Base Bid Items include the core scope of work, while the Option Bid Items may or may not be awarded based on pricing and availability of funding. The document also includes notes on the contract schedule, payment protection requirements, and instructions for contractors to provide a quote expiration date. The related federal contract opportunity, Solicitation Number 1240LT24Q0061, is for the same project and provides additional details on the scope of work, safety requirements, and scheduling expectations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
BLACK HILLS NATIONAL FOREST
FORESTWIDE RECREATION ROOF AND SIDING REPLACEMENT
THE FOLLOWING ARE BASE BID ITEMS:
Item Number Description Type
Msrmt Unit Quantity Unit Price Total
B1 Mobilization LS LS 1 -
B2 Cascade Springs Gazebo: Roof Replacement, Fascia Replacement, and Paint.
LS LS 1 -
B3 Cascade Springs Toilet: Roof Replacement, Fascia Replacement, and Paint.
LS LS 1 -
B4 Cascade Falls Toilet: Roof Replacement, Fascia Replacement, and Paint.
LS LS 1 -
B5
Pactola Visitor Center Pumphouse: Roof Replacement, Fascia Replacement, Siding Replacement, and Stain.
LS LS 1 -
B6
Palmer Gulch Trailhead Toilet:
Roof Replacement, Fascia Replacement, Siding Replacement, and Stain.
LS LS 1 -
B7
Roubaix Campground Loop B Pumphouse: Roof Replacement, Fascia Replacement, Siding Replacement, and Stain.
LS LS 1 -
B8
Whitetail Campground Pumphouse: Roof Replacement, Fascia Replacement, and Paint.
LS LS 1 -
BASE BID ITEMS TOTAL = $
THE FOLLOWING ARE OPTION BID ITEMS: Option bid Items may or may not be awarded based on pricing and availability of funding at time of award.
O1 Supervisor’s Office Kiosk:
Roof Replacement. LS LS 1 -
O2 Mystic Office Kiosk – Front Entrance: Roof Replacement. LS LS 1 -
O3 Mystic Office Kiosk – Parking Lot: Roof Replacement. LS LS 1 -
O4 Pactola Visitor Center Kiosk: Roof Replacement. LS LS 1 -
O5 Norbeck Overlook Kiosk:
Roof Replacement LS LS 1 -
O6 Ditch Creek Trailhead Kiosk:
Roof Replacement. LS LS 1 -
O7 Newton Fork Kiosk: Roof Replacement. LS LS 1 -
O8 Pactola South Kiosk: Roof Replacement. LS LS 1 -
O9 Westbury Kiosk: Roof Replacement. LS LS 1 -
OPTION BID ITEMS TOTAL = $
THE FOLLOWING ARE INCREASE/DECREASE BID ITEMS:
Contractor to provide unit price for Change in Quantity higher or lower than Quantities listed in Base Bid Items as stated in the project Specifications Section. Increase/Decrease Item may or may not be awarded based on price and availability of funding.
ID1 Sheathing: Replace Damaged ½” Sheathing. AQ per
Sheet 10 $ $
PROJECT BID ITEMS TOTAL = $
Date offer will be honored through: ____________________
Contractor Name: ___________________________ UEI:________________________
Email:_______________________________ Phone:_______________________
B.2 SCHEDULE NOTES
a) Please provide a quote expiration date with your quote. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
b) One Firm Fixed Price award is expected to be made from this solicitation, contractors must submit pricing for all items.
c) As per FAR 28.102-1 (b) (1) Pursuant to 40 U.S.C. 3132, for construction contracts Awards greater than $35,000, but not greater than $150,000 require one of the following payment protections: Payment Bond, or an Irrevocable Letter of Credit. Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond premiums under Pay Item B1.
d) Items labeled as option items are not required to be exercised by the government. If exercised, the contractor will be required to perform the option item work in accordance with the terms and conditions of this contract (See Section I, FAR 52.217-7 Option for Increased Quantity -Separately Priced Line Item.
| BASE BID ITEMS |
| OPTION BID ITEMS |
| SCHEDULE NOTES |