1. RFQ Sheets - KSPAN 100% BOM By Contract.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- Earth work, concrete and rebar material Federal contract opportunity
- Solicitation number
- W9124V23Q0011
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 2. Rebar Statement of Work.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract 3 - Concrete & Base
| Contract - Concrete & Base Material |
| Total |
| Description | U/I | Estimated Qty | Unit Price | Total Cost |
| Structural 4000 PSI w/4-6% Air entrainment Concrete Footers | CY | 67 | ||
| 3/4" minus structural fill | CY | 1766 | ||
| 3" minus structural fill | CY | 107 | ||
| Structural 4000 PSI w/4-6% Air entrainment Concrete Stem Walls | CY | 167 | ||
| Structural 4000 PSI w/4-6% Air entrainment Concrete Stem Wall Caps | CY | 31 | ||
| Structural 4000 PSI w/4-6% Air entrainment Concrete Floor / Exterior Pads | CY | 392 | ||
| Delivery to jobsite, Fort Harrison (Helena), MT | LS | 1 |
Contract 4 - Rebar & Steel Contract - General Construction Material Contract - Rebar & Steel
| Total | $0.00 | Total | ||
| Recommended Vendors | Power Townsend | Home Depot | Lowes |
| Item No. | BOM Type | Shop Designator | BOM Component | Description | U/I | Qty | Unit Price | Total Cost |
| ERROR:#REF! | Initial | Dirt | Steel | #5 Rebar 20' sticks | Pounds | 46372 | ||
| ERROR:#REF! | Initial | Dirt | Steel | Provide and Bend Rebar per SOW | pounds | 7927 | ||
| ERROR:#REF! | Initial | Structures | Steel | 3/4" Schedule 40 Black Iron Pipe - 10' Length | EA | 33 | ||
| ERROR:#REF! | Initial | Structures | Steel | Angle Iron 3"x3"x1/4" - 20' Long | EA | 28 | ||
| ERROR:#REF! | Initial | Dirt | Steel | 7 ft. x 42 in.x 1/8" Remesh Sheet | EA | 8 | ||
| ERROR:#REF! | Initial | Structures | Steel | 4"x4"x20' square tubing - .25" thick | EA | 6 | ||
| ERROR:#REF! | Initial | Structures | Steel | 2"x4"x20' rectangular tubing - .25" thick | EA | 2 | ||
| Delivery to jobsite, Fort Harrison (Helena), MT | LS | 1 |
Contract 5 - Concrete Pumping
| Contract - Concrete Pumping | ||||||
| Total | ||||||
| Description | Method of Procurement | Rotation | U/I | Qty | Unit Price | Total Cost |
| Concrete Line Truck (min 220' horizontal capability) | ||||||
| Mobilize & Mileage - Fort Harrison, MT (Outside of Helena, MT) | Mobilizations | 4 | ||||
| Total Maximum Concrete Pumped (all mobs combined) | CY | 347 | ||||
| Maximum Number of Hours (8 hours per mobilization) | Hrs. | 32 | ||||
| Concrete Arial Pump Truck (30 meter minumum) | ||||||
| Mobilize & Mileage - Fort Harrison, MT (Outside of Helena, MT) | Mobilizations | 8 | ||||
| Total Maximum Concrete Pumped (all mobs combined) | CY | 265 | ||||
| Maximum Number of Hours (8 hours per mobilization) | Hrs. | 8 |