1. Phase 2 Invitation to Bid_Rebid 2_090826.pdf
PDF 170 KB Posted
- Attached to
- UConn Gampel Pavilion Reno - Phase 2 REBID 2
- Solicitation number
- 300284- P2 Rebid 2
- Issued by
- Connecticut
About this file
This Invitation to Bid is issued by DPR Construction as the Construction Manager for the University of Connecticut's Gampel Pavilion Renovations Phase 2 (Rebid #2) project located at 2098 Hillside Road, Storrs, Connecticut. The project seeks bids from qualified trade contracting companies for renovation work on the approximately 171,000-square-foot, 10,299-seat multipurpose dome originally constructed in 1988. The scope of work includes selective and structural demolition, sitework, concrete work, structural steel installation, drywall and CMU partitions, curtainwall assemblies, flooring systems, interior finishes, new elevator installation, and mechanical/electrical/plumbing systems. Four bid packages are offered: Landscaping ($100,000 estimated), Waterproofing ($50,000 estimated), Doors, Frames & Hardware ($350,000 estimated), and Epoxy Flooring ($450,000 estimated). A pre-proposal virtual meeting is scheduled for September 14, 2026, from 11:00 a.m. to 11:30 a.m., with requests for information due by September 17, 2026, at 2:00 p.m. Bids are due September 24, 2026, at 1:30 p.m., with opening conducted via Teams meeting. Construction is targeted to begin January 11, 2027, with multiple completion dates through December 6, 2027, based on the basketball season schedule. All project documents are accessible through Building Connected, and the selected bidder must execute the contract within seven calendar days of award notification.
Bids must include a cost proposal using the DPR-provided bid form with no substitutions permitted. Bid security is required for bids exceeding $50,000, consisting of either a bid bond, certified check, or letter of credit in the amount of ten percent of the bid for projects under $100,000 and twenty-five percent for projects exceeding $100,000. Prevailing wages pursuant to Connecticut General Statutes are mandatory. The lowest responsible bidder will be determined by adding the total bid amount plus any alternates, with the contractor demonstrating financial ability, managerial capability, and technical expertise. The Good Faith Efforts Plan requires that not less than thirty percent of the total contract price be awarded to Connecticut Department of Administrative Services-certified Small Business Enterprises and not less than ten percent to Minority Business Enterprises. A ten percent self-performance requirement applies to all awarded contracts. Liquidated damages of $500 per calendar day will be assessed for failure to meet substantial completion dates. Proposals remain valid for ninety calendar days and may be withdrawn after that period without notice. Financial prequalification documents are strongly recommended at bid submission and are required within five business days of award notification for open ITB bidders.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2. Phase 2_Worksheets to Complete by BidderR1.xlsx | XLSX spreadsheet | |
| 300284- P2 Rebid 2_Sep_9_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GAMPEL PAVILION RENOVATION
PROJECT #: 300284
2098 HILLSIDE ROAD
STORRS, CT 06268
CONTRACTOR OPEN INVITATION TO BID
UCONN GAMPEL PAVILION RENOVATIONS – PHASE 2 (REBID#2)
Date: Tuesday, September 8, 2026
1. Intent of this Solicitation DPR Construction has been selected as the Construction Manager (CM) for the Gampel Pavilion Renovation Project. The purpose of this Invitation to Bid (ITB) is to solicit bids of experienced and qualified trade contracting companies for the Gampel Pavilion Renovations project on UConn’s Storrs campus.
• Critical Dates:
Pre-Proposal Meeting
▪ Virtual Meeting Date and Time September 14, 2026 11:00pm - 11:30am
▪ Virtual Meeting Teams Link Teams Meeting Link
RFI Due Date and Time September 17, 2026 2:00pm Proposal Due Date and Time September 24, 2026 1:30pm
▪ ITB Bid Opening Teams Meeting Link 2:00pm
• Scope Review Meetings: Will be held virtually with the lowest qualified bidder:
o Scope Review Schedule included with this Invitation to Bid.
o Bidder must have their team present that has been proposed for the project in this Invitation to
Bid
▪ Lead Foreman(s) / Superintendent
▪ Project Manager
▪ Safety Officer
▪ Estimator o Scope Review Teams Meeting Link will be provided.
• If your Company is submitting multiple bid packages, a separate and complete submission must be submitted for each package. Your submission should indicate which package you are submitting for.
• Pre-Proposal Virtual Meeting: The pre-proposal conference will virtual.
• Bid Opening: Will be via a virtual conference at 1:30pm on September 24th. Bid is due on the Proposal Due Date and Time stated above. Link to Teams Meeting for the bid opening is above.
• Location of Solicitation: All Project Documents will be available for download through Building Connected: Building Connected. Bid Documents will be accessible at time of receipt of this ITB, including specific Scopes of Work (ie DPR Bid Form).
• Request for Information: All RFI questions are to be submitted on the ITB Form provided and posted to Building Connected at link provided above. No phone calls or RFI questions emailed directly to DPR will be accepted. No RFI questions will be accepted after due date and time stated above.
https://teams.microsoft.com/meet/212746075784893?p=49s7fg94tDbVsXZCQs https://teams.microsoft.com/meet/241567636863762?p=IpHz846UfTk6Qud7QF https://app.buildingconnected.com/projects/69246dfb4fc8f18c3528051e/info
• Clarifications, Addenda and Interpretations: Bidders shall promptly notify DPR of any ambiguity, inconsistency, or error which they may discover upon review of the plans, specifications and Contract Documents. Any and all interpretations of the drawings, specifications, RFI responses, contract documents, and supplemental instructions, will be in the form of a clarification/addendum, and posted in Building Connected. Failure of a Bidder to receive any such clarification/addendum or interpretation shall not release a Bidder from the obligations under its Bid as submitted.
• Consideration of bids: Cost Proposals received in response to this ITB are opened during a public opening. To ensure the integrity of the bidding process, the Total Bid Amount and prices for any Alternates are read at the bid opening. After the bid opening and before the contract award, the lowest responsible Bidder is determined by adding together the Total Bid Amount plus any Alternates (additive or deductive) accepted by the DPR Construction and the University. DPR Construction and the University reserves the right to elect to implement some, all, or none of the Alternates (if applicable) set forth in this Bid, as may be in the best interest of the University and DPR Construction. Prices for Alternates are not negotiable since they are a component in determining the lowest responsible Bidder.
The lowest responsible Bidder shall also demonstrate, to the satisfaction of DPR Construction and the University, that they possess the proven financial ability (for packages over $100,000), managerial ability, technical ability, and the integrity, necessary to perform the Scope of Work faithfully and efficiently for this Project, without conflict of interest and within the scheduled durations outlined in Section 2. Bids shall be evaluated utilizing the objective technical criteria listed within the ITB, as well as any additional information obtained from persons or other sources identified in the Bid. Proposals, shall remain in effect for ninety (90) calendar days after time and date of receiving bids, may be accepted by Owner anytime within that period, and may be withdrawn after that time by the bidder without notice. The selected bidder shall execute the Contract Agreement within seven (7) calendar days after receiving written notification of award of contract or presentation of the contract agreement, whichever is later.
o A bid security in the form of a bid bond, certified check or a treasurer’s or cashier’s check issued by a responsible bank or trust company, payable to DPR Construction (reference the attached bid bond form) must accompany all bids if the Total Bid Amount is over $50,000. Bid bonds must be issued by a surety licensed in Connecticut and listed on the Department of Treasury’s Listing of Approved Sureties with an underwriting limitation of no less than the full amount of the bid. The bid security shall be in the amount equal to TEN PERCENT (10%) of the amount of the bid. In lieu of bid bond or certified check, a letter of credit that shall be in the amount of TEN PERCENT (10%) of the total bid amount for any bid valued less than $100,000 and in the amount of twenty-five percent (25%) of the bid amount for any bid value that exceeds $100,000 may be submitted.
o DPR Construction and the University reserve the right to request a hard copy of the bid bond at any time.
o Reference item 17 below for the required Good Faith Efforts Plan and CHRO Contract Compliance Plan Program for the S/MBE requirements on the project.
o The Bidder and DPR Construction agree that the materials and equipment to be furnished and the work to be performed will be in accordance with the Contract Documents for the University of Connecticut Gampel Pavilion Renovation Project, Phase 1.
• A Bid with incomplete responses, inaccurate information, or missing documents will be deemed a non-responsive Proposal and the Proposal will not be accepted.
Complete and provide information and supplemental documents for all ITB Form worksheets:
▪ Project Relevant Experience
▪ Project Team Qualifications
▪ Integrity Questionnaire
▪ Prequalification at Award (for reference only. Information will be required after bid award)
▪ Project References o Submit required information utilizing the ITB Form provided in the ITB. No substitution of the Form is permitted.
o Any Bid omitting or adding items, altering the ITB Form, or containing conditional or alternative language/pricing (if applicable), may be deemed a non-responsive Bid and the Bid may be rejected.
o Do not submit additional documents other than what is requested above. Any additional documents submitted will not be accepted and may deem your Company’s bid non-responsive.
o All Bids must be submitted no later than the closing date and time for this event. No submissions may be accepted that are submitted after the due date and time.
o DPR Construction and the University reserve the right to reject any or all Bids and to waive any informalities, irregularities, or technical defects in the Bids, if it is deemed to be in the best interest of DPR Construction and the University, provided the reasons for any such waiver are stated in writing by DPR Construction and the University and made a part of the contract file.
2. Project Schedule and Duration – Phase 2
• Targeted Start of Construction/Mobilization on Site January 11, 2027
• Courtside Club Complete August 16, 2027
• Training Table and Servery Complete August 16, 2027
• Fan Amenities October 15, 2027
• Market and All-American Club November 9, 2027
• New Elevator & Stair North October 15, 2027
• AD Suite April 12, 2027
• Visitors Locker Room November 1, 2027
• North Canopy & Natatorium October 15, 2027
• Kinesiology North December 6, 2027
• New Stair November 1, 2027
➢ Note that phase completion is based upon the start and end to each of the men’s and women’s basketball season and is non-negotiable. In order to achieve these dates, multiple crews (potentially 4 crews simultaneously) will be required for work occurring in multiple levels and locations, simultaneously, requiring completion on the same date.
3. Liquidated Damages: Liquidated Damages of Five Hundred Dollars and 00/100 ($500.00) per calendar day shall be assessed if the Contractor fails to achieve Substantial Completion or causes delay to the Substantial Completion of any portion of the work within the Contract Time.
4. Wage Rate: Prevailing Wages are required for this Project and subject to Connecticut General Statutes §31- 53, §31-54, and §31-55: https://www.cga.ct.gov/current/pub/chap_557.htm#sec_31-53. UConn’s stipulated rates are available with the bid documents. Note that these rates are updated on a yearly basis and are subject to change. Awarded contractors will have an opportunity to submit their own labor rates, for UConn approval. Note division 1 requirements in submitting your own labor rates for approval.
5. Overall Project Summary and Overview DPR Construction (DPR) is the awarded Construction Manager for the Gampel Pavilion Renovations project.
The University of Connecticut (UConn) is undertaking a focused renovation to Gampel Pavilion on the Storrs campus. Gampel Pavilion is an approximately 171,000 square feet, 10,299- seat multipurpose dome that was originally constructed beginning in 1988 and opened in January 1990. Gampel Pavilion consists of four floor levels that include the court/floor level (Activity Level), entrance / street level (Concourse Level), mechanical level (Fan Room Level) and upper concourse (Upper Level). Gampel Pavilion is the largest on-campus venue for college basketball in the New England area. The goal of this project’s renovation is to modernize and create maximum efficiencies of the existing spaces in Gampel Pavilion while also further increasing new revenue https://www.cga.ct.gov/current/pub/chap_557.htm generating areas and opportunities that support the facility’s use. The renovation scope for the project could include, but are not limited to:
• Courtside Club Complete
• Training Table and Servery Complete
• Fan Amenities
• Market and All-American Club
• New Elevator & Stair North
• AD Suite
• Visitors Locker Room
• North Canopy & Natatorium
• Kinesiology North
• New Stair
6. Project Scope: Phase 2 The project scope will include but is not limited to selective demolition (interior and exterior), structural demolition, sitework, hardscapes, landscaping, shoring, scaffolding, concrete foundations, slab on grade, slab trenching, concrete pits and bases, structural steel & miscellaneous metals, decorative stairs, GWB and CMU partitions, curtainwall assemblies, equipment screens, D/F/H, interior windows, ACT, interior specialties, tile, vinyl wall covering, paint, epoxy flooring, vinyl floor tile, resinous flooring, resilient base, acoustical ceiling finishes, new elevator, M/E/P-FP systems, telecommunications, sound and AV systems, access control and surveillance systems, integrated automation, interior architectural woodwork and casework.
7. Bid Packages and Estimated Values: The table below identifies the anticipated bid packages along with the estimated values for each of the bid packages and the spending allocation goals. Reference Section 18 below for the Good Faith Efforts Plan on the Spending Allocation Goals for this project.
UConn – Gampel Pavilion Renovations Bid Packages
Bid Package No. Bid Package Name
Prequalified/ Open ITB
Estimated Value
Spending Allocation
Goal
01A Landscaping Open ITB $100,000 30/10
10 Waterproofing Open ITB $50,000 30/10
13 Doors, Frames & Hardware Open ITB $350,000 30/10
20C Epoxy Flooring Open ITB $450,000 30/10
8. Proposed Team Qualifications: Complete this worksheet included in the workbook issued with this ITB. The Bidder must demonstrate the ability to staff the Project with high quality, experienced personnel. Describe the qualifications and responsibilities of the key personnel who will be assigned to the Project including their experience on similar assignments and their specific responsibilities for the proposed Project.
9. Previous Relevant Experience: Complete this worksheet included in the workbook issued with this ITB. The Bidder must meet the requirements and describe their overall qualifications, including background in this field and the services that it provides.
10. Integrity Questionnaire: Complete this worksheet included in the workbook issued with this ITB.
11. Prequalification at Award: Reference this worksheet included in the workbook issued with this ITB for financial information that will be required if and at award of work.
12. Project References: Complete this worksheet included in the workbook issued with this ITB. The Bidder must provide GC/CM, owner and design team references. This should include valid names, email addresses and telephone numbers.
13. Cost Proposal: Submit a Cost Proposal utilizing the Bid Form (DPR Attachment 2 to be provided with Subcontract Agreement documents). No substitution of the Bid Form is permitted. No exceptions, additional documents, clarifications, or additional terms and conditions can be submitted with the Bid Form.
14. Financial Ability: The lowest responsible Bidder must demonstrate the financial ability and bond letter (if bondable) to complete a construction project with a minimum value that is at least equal to the amount of your Bid. Although these documents are not required to be submitted with the Bid, it is strongly recommended that this information be provided as part of the response to this Invitation to Bid as identified on the ITB Workbook (re: Prequalification at Award worksheet). If awarded, prequalification with DPR will be required as identified on the Prequalification at Award worksheet in the ITB Workbook, for open ITB bidders only (RFQ qualified Bidders information has already been submitted).
15. Failure of the lowest responsible Bidder to submit financial documents within 5 business days of notification from DPR Construction, or failure to pass DPR Construction’s financial requirements will result in a non-responsive Bid. SBE/MBE PARTICIPATION: DPR Construction and the University of Connecticut are committed to providing a professionally inclusive environment within which small and minority businesses. As such, we encourage participation by Small (SBE) businesses, Minority-Owned (MBE) businesses, Woman-Owned (WBE) businesses, and businesses owned by persons with a disability (DisBE), certified as such by the Connecticut’s Department of Administrative Services Supplier Diversity Division. CT DAS Supplier Diversity Certificates are required for set-aside bid packages and must be active as of the due date of the ITB.
o For further information, visit: https://portal.ct.gov/DAS/Services/Licensing-Certification-Permitting-and-
Codes/Small-Minority-Business-Center o To learn about the University of Connecticut’s Supplier Diversity Program, visit:
https://supplierdiversity.ubs.uconn.edu o Proposers that intend to submit for a set-aside designated bid package on this project must provide their
Connecticut Department of Administrative Services certification in the Supplier Diversity program as required by this solicitation.
16. Subcontract Agreement: A draft of DPR Construction’s Subcontract Agreement has been provided with the solicitation documents. DPR Construction reserves the right to modify the contract or waive any informality as it deems to be in the best interest of DPR Construction and the University. By submitting a Bid, your Company accepts the Subcontract Agreement and any modifications that DPR Construction deems necessary to it without exception. Bidders will be notified of any modifications to the Subcontract Agreement made by DPR Construction. Any exceptions to the Subcontract Agreement submitted by the Bidder will not be considered.
a. Self-Performance Requirement: If awarded this contract, the Bidder shall be required to perform not less than ten percent (10%) of the Total Contract Price with its own forces.
17. Good Faith Efforts Plan: The Spending Allocation Goal for this Project is that (1) not less than thirty percent (30%) of the Total Contract Price be awarded to subcontractors who are certified by the Connecticut Department of Administrative Services as “Small Business Enterprises” (“SBEs”) and (2) not less than ten percent (10%) of the Total Contract Price be awarded to subcontractors who are certified by the Connecticut Department of Administrative Services as “Minority Business Enterprises” (“MBEs”) (the 10% Spending Allocation Goal for MBEs may be included in the 30% Spending Allocation Goal for SBEs). If the Contractor is an S/MBE, then any self-performed work may be included in the Spending Allocation Goal, however, self-performing MBE’s must still demonstrate good faith efforts to employ other MBEs as subcontractors and supplier of materials. The Contractor is responsible for ensuring that https://portal.ct.gov/DAS/Services/Licensing-Certification-Permitting-and-Codes/Small-Minority-Business-Center https://portal.ct.gov/DAS/Services/Licensing-Certification-Permitting-and-Codes/Small-Minority-Business-Center https://supplierdiversity.ubs.uconn.edu/ they, and the S/MBEs they have selected, are eligible Connecticut-certified S/MBE contractors. Failure to make good faith efforts will be subject to enforcement that may lead to withholding of contract payments, disqualification from future bidding, and/or civil penalties and legal action by CHRO. For further information see:
CHRO's Contract Compliance Program.
END OF INVITATION TO BIDDERS