This document is a draft pre-solicitation for the Dutton Hill G-Z Stewardship Integrated Resource Service Contract (IRSC) for the Coconino National Forest in Arizona. The overall project area consists of 8,829 acres across three treatment areas - Double Springs (699 acres), Dutton Hill (4,262 acres), and LO Pocket (3,868 acres) - with the objectives of improving forest health, reducing hazardous fuels, and thinning ponderosa pine stands while providing wood products to local industry. The estimated timber volumes and species composition are not fully known at this time, as final cruise data will be determined under mandatory work items. The contract will be awarded as a commercial services contract with requirements for timber removal, and performance is required by December 31, 2029. Contractors will earn stewardship credits for completing work activities, which can be used to offset the value of included timber. Pricing will be provided for both mandatory and optional work items, as well as total value bid premiums for the timber products. Multiple awards may be made under this solicitation, which was issued by the USDA Forest Service.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dutton Hill G-Z Stewardship IRSC Coconino National Forest Page 1 of 74 Flagstaff Ranger District
Revised 3.2023
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND
SERVICES - OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICIATION ISSUE
DATE
XXXXXX XXXX
7. FOR SOLICITATION INFORMATION CALL:
EMAIL CONTACT PREFERRED
a. NAME b. TELEPHONE NUMBER(No collect calls) 8. OFFER DUE DATE / LOCAL TIME
XXXX
4:00 p.m. PT
9. ISSUED BY CODE 363N 10. THIS ACQUISITON IS UNRESTRICTED OR SET ASIDE % FOR:
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMAN-
OWNED SMALL BUSINESS PROGRAM
EDWOSB
NAICS:
HUBZONE SMALL BUSINESS 115310
SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS 8(A)
SIZE STANDARD:
$34 M
11. DELIVERY FOR FOB DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A RATED
ORDER UNDER DPAS (15 CFR 700)
13b. Rating
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 363N 16. ADMINISTERED BY CODE 363N
COCONINO NATIONAL FOREST
FLAGSTAFF RANGER DISTRICT
1824 S. Thompson St.
Flagstaff, AZ 86005
USDA-FS – Procurement & Property Services National Procurement Operations Stewardship Contracting Branch 1400 Independence Ave. SW, MS-1138 Washington DC 20250-1138
17A. CONTRACTOR/OFFEROR CODE FACILITY
CODE 18a. PAYMENT WILL BE MADE BY CODE 363N
Name:
Address:
Email:
Telephone No:
*Invoice Processing Platform (IPP):
All invoices must be submitted electronically through the Invoice Processing Platform via www.IPP.gov.
*All Invoices for Non-Monetary Credits must be submitted to the Forest COR via email.* SAM UEI (12 characters):
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM N0. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
DUTTON HILL G-Z STEWARDSHIP IRSC
COCONINO NATIONAL FOREST
FLAGSTAFF RANGER DISTRICT
REGION 3 - ARIZONA
See attached Schedule of items
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED.
ADDENDA ARE ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
29. AWARD OF CONTRACT: REF__________________
ONE (1) COPY TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
OFFER DATED________________, YOUR OFFER ON SOLICITATION
____________________________ (BLOCK 5), INCLUDING ANY ADDITIONS OR
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED __________________________________________________________________
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (REV.2/2012)
http://www.ipp.gov/
Page 2 of 74 Flagstaff Ranger District
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
GENERAL INFORMATION:
Proposals shall be valid for 60 days after the date of receipt for the solicitation. If additional time is needed, an extension will be requested. Refer to Section 50 for instructions on preparing your proposal and pricing. Submit technical proposals and price proposals separately, via email, to the individual(s) shown in box 28 of page 1.
All Contractors must be actively registered in the System for Award Management (SAM) https://SAM.gov to be eligible for award under this solicitation. Registration in SAM is a free service – you do not need to pay to register in this system. If your registration is not active, you will not be considered for award.
SCHEDULE OF ITEMS
MANDATORY WORK ACTIVITIES:
ITEM
NO.
DESCRIPTION OF
MANDATORY WORK ACTIVITIES UNIT
ESTIMATED
QUANTITY
UNIT
PRICE TOTAL
1 Double Springs Treatment Area (699 acres)
(a) Cut and Remove Included Timber – Acre 699 $ $
(b) Timber Stand Improvement: Thinning <6” DBH and >6’ in height. Acre 699 $ $
(c) Road Maintenance Mile 7.44 $ $
2 Dutton Hill Treatment Area (4,262 acres)
(a) Repaint Cut Unit Boundaries and Deferrals Feet 311,629 $ $
(b) Repaint Leave Tree Mark Units Acre 619 $ $
(c) Leave Tree Marking: Convert DxP units to LTM Acre 2,639 $ $
(d) Timber Cruise Implementation Plot 40* $ $
3 LO Pocket Treatment Area (3,868 acres)
(a) Repaint Cut Unit Boundaries and Deferrals
Feet 28,852 $ $
(b) Repaint Leave Tree Mark Units Acre 606 $ $
(c) Leave Tree Marking: Convert DxP units to LTM Acre 2,304 $ $
(d) Timber Cruise Implementation Plot 45* $ $
Total All Mandatory Service Items $ https://sam.gov/
Page 3 of 74 Flagstaff Ranger District
OPTIONAL WORK ACTIVITIES:
ITEM
NO.
DESCRIPTION OF
OPTIONAL WORK ACTIVITIES UNIT
ESTIMATED
QUANTITY
UNIT
PRICE TOTAL
4 Dutton Hill Treatment Area (4,262 acres)
(a) Road Maintenance Mile 44.11* $ $
(b) Cut and Remove Included Timber Acre 4,262 $ $
(c) Timber Stand Improvement:
Thinning <6” DBH and >6’ in height Acre 4,262 $ $
5 LO Pocket Treatment Area (3,868 acres)
(a) Road Maintenance Mile 25.88* $ $
(b) Cut and Remove Included Timber Acre 3,868 $ $
(c) Timber Stand Improvement:
Thinning <6” DBH and >6’ in height Acre 3,868 $ $
Total All Optional Service Items $
TIMBER/PRODUCT REMOVAL PRICE SCHEDULE:
Price Schedule # 1: Mandatory Item #1a – Double Springs Treatment Area
SPECIES PRODUCT QUANTITY UNIT OF
MEASURE
FLAT RATE TOTAL VALUE
CS Sawtimber (14”+
DBH)
TBD from cruise Tons $ $
CS Non-Sawtimber (9”
– 13.9” DBH)
TBD from cruise Tons $ $
CS Grn Bio Cv (6” –
8.9” DBH)
TBD from cruise Tons $ $
Double Springs Treatment Area Total – All Products
Tons Total: $
Page 4 of 74 Flagstaff Ranger District
Enter delivered saw log value (paid by mill) to be used in determining appraised timber rates:
Product:_______________ Delivered Value: $_________/ton Location:___________ Product:_______________ Delivered Value: $_________/ton Location:___________ Product:_______________ Delivered Value: $_________/ton Location:___________ Product:_______________ Delivered Value: $_________/ton Location:___________ Product:_______________ Delivered Value: $_________/ton Location:___________ Product:_______________ Delivered Value: $_________/ton Location:___________
Firms are required to provide delivered market value prices for products planned to be delivered and to which facilities. This information provided will be used (kept internally to protect proprietary information), coupled with the variable logging cost entries obtained from logging plans produced by the contractor will be used to determine the final timber rates per Timber Treatment Area. This will not be used for evaluation purposes.
Price Schedule # 2: Optional Item #4b – Dutton Hill Treatment Area
SPECIES PRODUCT QUANTITY UNIT OF
MEASURE
MINIMUM
ACCEPTABLE OFFER
CS Sawtimber (14”+ DBH) Actual Quantity Determined after cruise.
47,502**
Tons TBD from Appraisal
$0.08 - $8.00***
CS Non-Sawtimber (9” – 13.9”
DBH)
Actual Quantity Determined after cruise.
64,331** Tons
TBD from Appraisal $0.08 - $8.00***
CS Grn Bio Cv (6” – 8.9” DBH) Actual Quantity Determined after cruise.
21,006**
Tons $ 0.01
Total Value Bid Premium – All Products Dutton Hill Treatment Area $
Total Value – All Products Dutton Hill Treatment Area (TBD after cruise and appraisal)
N/A – TBD
Will be calculated by FS for evaluation purposes.
Price Schedule # 3: Optional Item #5b – LO Pocket Treatment Area
SPECIES PRODUCT QUANTITY UNIT OF
MEASURE
MINIMUM
ACCEPTABLE OFFER
CS Sawtimber (14”+ DBH) Actual Quantity Determined after cruise.
74,744**
Tons TBD from Appraisal
$0.08 - $8.00***
CS Non-Sawtimber (9” – 13.9”
DBH)
Actual Quantity Determined after cruise.
50,656** Tons
TBD from Appraisal $0.08 - $8.00***
CS Grn Bio Cv (6” – 8.9” DBH) Actual Quantity Determined after cruise.
13,059**
Tons $ 0.01
Total Value Bid Premium – All Products LO Pocket Treatment Area $
Total Value – All Products LO Pocket Treatment Area (TBD after cruise and appraisal)
N/A – TBD
Will be calculated by FS for evaluation purposes.
Page 5 of 74 Flagstaff Ranger District
Notes:
Multiple Awards MAY be made from this solicitation. Offerors are required to provide price proposals for ALL Items on the schedule. Up to 3 awards may be awarded divided by Treatment Areas if determined to be in the best value to the Forest Service. Mandatory Items 2 and 3 will not be awarded as an individual award and shall be awarded with associated treatment area if multiple awards are made. Contractors that have an alternative plan must submit a second Alternative price proposal and Alternative technical proposal indicating their desired number of Treatment Areas.
Unit prices prevail.
These schedules are for pricing/payment purposes. See Instructions to Offerors for business proposal requirements. Unit prices prevail. Price Proposals MUST be provided on ALL Items in Schedules:
Mandatory Work, Optional Work and Total Value Bid Premium for all Timber Products for each Price Schedules 2 and 3. Optional Item 6 allows contractors to market surplus wood products outside the local area.
Contractors are required to submit a primary proposal for all work as shown in the SOI. Contractors proposing to complete work in less than 3 Treatment Areas or that have an alternative plan must submit a second Alternative price proposal and Alternative technical proposal.
*Total quantities are unknown and shown as estimated gross quantity. Completion and acceptance of Item 2d will determine true needed quantities for Item 4b, and completion and acceptance of Item 3d will determine true needed quantities for Item 5b. Contractor shall provide a fixed price per Item based on the estimated quantity shown and the complexity level as described in Appendix A.
Awarded Firm-Fixed unit prices prevail and WILL NOT be renegotiated or changed in future modifications to adjust quantities once known.
** The estimated gross tons of timber products for Optional Items 4b and 5b, was based on a previous timber cruise performed in 2019. There is approximately 132,839 tons to be removed from 4,262 acres for Mandatory Item 4b, and 138,459 tons to be removed from 3,868 acres for Mandatory Item 5b. Once final cruise volumes are established under Mandatory Items 2d and 3d, total tons to be removed will be added through contract modification and Notice to Proceed will be issued.
When Final Cruise for each Treatment Area has been completed and accepted, the FS will complete an independent Timber Sale Appraisal to determine the Advertised Timber Rate and Bid Premiums to be collected. Cruise data accepted from Items 2d and 3d WILL be used for appraisal data entries to calculate logging costs.
*** Contractors shall provide a Total Value Bid Premium for all products per treatment area ≥$0.00, except for Enterprise Treatment Area. The Total Value Bid Premium for each Treatment Area will be distributed evenly over all final awarded products (non-saw and saw timber) per treatment area to have one combined rate for all products per Treatment Area. This will allow maximum flexibility to contractors in marketing all products. To reduce risk to both parties due to over/under-run of products, cruising standards have been increased to “Tree Measurement” maximum allowed error.
Timber products will be scaled due to the use of Designation by Prescription and virtual boundaries.
If the final appraised Timber Rate for Saw timber is between $0.08/ton and $8.00/ton, Total Value Bid Premiums shall be binding and applied in full. If appraised timber rate is greater than $8.00/ton, Bid Premiums shall be lowered incrementally until not applicable. Appraised Timber Rates below
Page 6 of 74 Flagstaff Ranger District
$0.08/ton, potentially indicating deficit conditions, will either prompt reassessment of treatment units (move uneconomical unit acres from Timber Removal Item to Service only treatment) for that Treatment Area to bring appraised Rates above $0.08 or Bid Premiums will be waived.
For evaluation of price proposals, FS will calculate the Total Value of all products per Treatment Area based on the assumptions shown in the Timber Removal Price Schedule and the Total Value Bid Premium offer. The following calculation will be used for both evaluation of proposals as well as when determining final single timber rate per Price Schedule:
[(Saw Volume * Saw Minimum Rate) + (Non-saw volume * Non-Saw Minimum Rate) + (Total Value Bid Premium] = Total Value of all products (Saw Volume + Non-saw Volume)
A site visit has not been scheduled, when a site visit is scheduled the pre-solicitation will be updated.
PERIOD OF PERFORMANCE IS FROM DATE OF AWARD THROUGH December 31, 2029
LAND MANAGEMENT ACTIVITIES.
Performance of land management activities shall be in accordance with Project Description and Work Specifications. Payment for Land Management Work Activities in Schedule of Items will be made in Stewardship Credits and Appropriated Funds.
All Base Work Activities (Mandatory) shall be performed. Optional activities are listed in order of planned priority. Award may be made for optional items in any order that the Contracting Officer determines is in the best interest of the Government.
Page 7 of 74 Flagstaff Ranger District
1. FAR 52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (DEC 2022)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act ( 31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice. (Using IPP now) See #42.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.233-1#FAR_52_233_1 https://www.acquisition.gov/far/52.202-1#FAR_52_202_1
Page 8 of 74 Flagstaff Ranger District
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer- System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act ( 31 U.S.C.3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.-
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act
( 31 U.S.C.3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in https://www.acquisition.gov/far/52.232-33#FAR_52_232_33 https://www.acquisition.gov/far/52.232-34#FAR_52_232_34 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.212-5#FAR_52_212_5 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
Page 9 of 74 Flagstaff Ranger District
(i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if–
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting
Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in
FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance.
https://www.acquisition.gov/far/33.211#FAR_33_211 https://www.acquisition.gov/far/32.607-2#FAR_32_607_2 https://www.acquisition.gov/far/32.608-2#FAR_32_608_2
Page 10 of 74 Flagstaff Ranger District
In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 4701 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws
Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.govinfo.gov/link/uscode/10/4701 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.212-5#FAR_52_212_5 https://www.gsa.gov/forms-library/solicitationcontractorder-commercial-items
Page 11 of 74 Flagstaff Ranger District
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of clause)
ADDENDUM TO FAR 52.212-4 The following clauses are hereby incorporated by reference or full text as appropriate:
NUMBER TITLE DATE
52.236-2 DIFFERING SITE CONDITIONS APR 1984
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984
52.236-5 MATERIAL AND WORKMANSHIP APR 1984
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984
52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991
52.236-8 OTHER CONTRACTS APR 1984
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS APR 1984
52.236-10 OPERATIONS AND STORAGE AREAS APR 1984
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984
52.236-12 CLEANING UP APR 1984
52.236-13 ACCIDENT PREVENTION (ALTERNATE I) NOV 1991
52.236-17 LAYOUT OF WORK APR 1984
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1997
52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995
52.242-14 SUSPENSION OF WORK APR 1984
52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
452.236-71 PROHIBITION AGAINST THE USE OF LEAD-PAINT NOV 1996
452.236-73 ARCHEOLOGICAL OR HISTORIC SITES FEB 1988
452.236-76 SAMPLES AND CERTIFICATES FEB 1988
2. FAR 52.217-7 – OPTION FOR INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM
(MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within the period of performance prior to contract expiration. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
3. PROJECT DESCRIPTION
(a) Description of Work- The Dutton Hill G-Z IRSC comprises three project treatment areas: Double Springs (699 acres), Dutton Hill (4,262 acres), and LO Pocket (3,868 acres). The total project area consists of 8,829 acres of ponderosa pine forest and savanna/grasslands. The intent of this project is to increase the pace and scale of forest restoration treatments by contracting project layout and preparation activities. The objectives of this project are to increase forest health and vigor, reduce hazardous fuels to reduce the threat of catastrophic wildfire within the Wildland Urban Interface by accomplishing the following:
Page 12 of 74 Flagstaff Ranger District
1. Improve forest health by increasing residual tree growth, vigor, and crown development.
2. Reduce fuel loading and re-introduce low-intensity fire by implementing mechanical fuel treatments and preparatory work to manage the effects of the re-introduction of fire as a disturbance mechanism. Removing activity slash from FS lands when feasible.
3. Thin from below in ponderosa pine stands and restoring savanna and grassland vegetation types.
4. Remove included sawtimber and non-sawtimber from the Contract Area.
5. Mechanically remove small diameter trees to landings to be burned by FS or chipped/removed from contract area.
6. Provide wood products to local industry by utilizing timber and other forest products.
(b) Resulting Contract – Any resultant contract will be a commercial services contract with requirements for timber removal.
Project Locations:
LO Pocket T. 20N. R. 4E. Sections 1, 2, 3, 4, 8, 9, 10, 11, 12, 13, 14, 15, 16, 23, and 24 and T. 20N. R. 5E.
Section 6, 7.
Dutton Hill T. 20N. R. 5E. Sections 3, 4, 5, 6, 7, 9, 11, 13, 15, 16, 17, 21 and 23.
Double Springs T. 19N. R. 9E. Section 32; T. 18N. R 9E. Sections 6, 7, 18, 19. T. 18N. R. 8E. 11, 12, 13, 14, and 24.
(c) Under this contract, “Contractor’s Operations” shall include activities of or use of equipment of
Contractor, Contractor’s employees, agents, Subcontractors, or their employees or agents, acting in the course of their employment in operations hereunder on National Forest lands or within Forest Service protection boundary (unless acting under the immediate supervision of Forest Service).
Contractor’s Operations shall be conducted in a workmanlike and orderly manner. The timing of re-quired Forest Service designation of work on the ground and the performance of other Forest Service work shall not be such as to cause unnecessary delay to Contractor.
4. SPECIFICATIONS
General specifications for each Contract Activity individually described by an item number in the Schedule of Service Items can be found in Appendix A. Specifications for timber removal can be found in Appendix B and associated road plans and specifications in Appendix C for Stewardship related projects. Incidental construction or reconstruction specified road work plans, drawings, exhibits, and specifications can be found in Appendix D.
5. CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM
The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format
Page 13 of 74 Flagstaff Ranger District and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.
6. ACCEPTANCE
The Forest Service shall perform an inspection upon Contractor’s written request and assurance that work has been completed. Request shall be for a reasonable portion of work. Acceptance may be made for all or portions of work.
7. GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
Quality assurance plans specific to individual items will be found in Appendix A.
8. FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR
1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after receipt of Notice to Proceed or Order for specific work items, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than December 31, 2029. The time stated for completion shall include final cleanup of the premises.
Performance shall be made only as authorized by orders issued in accordance with the Ordering clauses. Except as this contract otherwise provides, the Government shall order all services within the scope that are required by Government activities specified in the Schedule only with the vendor holding this contract for the specified services. Timber Removal activities shall be scheduled and carried out in accordance with the Timber Removal Specifications in Appendix B and/or C and as approved by the Contracting Officer.
9. AGAR 452.211-74 PERIOD OF PERFORMANCE (FEB 1988)
The period of performance of this contract is from date of award through December 31, 2029.
10. SCHEDULES AND REPORTS
Pursuant to contract requirements, the following submittals are required within 10 days after issuance of a Notice to Proceed for review and/or approval, unless stated elsewhere in the specifications or otherwise mutually agreed:
ITEM DESCRIPTION
Proposed progress schedule showing starting and completion dates of various phases of the work.
List of proposed sub-contractors and their intended work. Sub-contractors must have Contracting Officer’s written approval prior to starting work on the project. Submit on Standard Form 1413.
Traffic Control Plan Designation of Contractor personnel describing responsibilities and authorities
Page 14 of 74 Flagstaff Ranger District
All schedules and reports shall be submitted to the COR.
11. PAYMENT
It is anticipated that funds will be exchanged in the performance of this contract because the value of the timber will not completely offset the value of the work to be performed. When payment is made to the contractor for work performed, it will be made in accordance with the specifications set forth under Measurable Performance Standards.
When harvesting operations are underway, the value of work completed and timber removed will be documented monthly in the Forest Products Financial System which will produce a Statement of Accounts.
12. STEWARDSHIP CREDITS
Stewardship Credits are credits that are earned and established when work listed in the Schedule of Supplies/ Services has been performed and accepted. Stewardship credits shall be earned at the rate as shown in the Schedule. Earned credits may be used to pay for timber value included in Schedule of Items. Unless otherwise indicated in the Schedules, credits will be earned based upon Actual Quantities accomplished and accepted.
13. ESTABLISHMENT OF STEWARDSHIP CREDITS
Notwithstanding references to payments in “Payment” clauses or provisions of this contract, payment for Stewardship Activities will be made with Stewardship Credits as indicated in the award document.
Stewardship Credits will be established on a monthly basis. Stewardship credits will be established for the number of units of each activity that have been completed and accepted. Acceptance may be for all, or a reasonable portion of, any specific activity.
Stewardship credits will not be established for work that is in progress that has not been accepted by the Forest Service. No credits will be established for work performed as indicated in the Schedule of Items and Appendix B Timber Removal Specification if appropriated agency monies are used or unless otherwise agreed.
14. TIMBER PAYMENT GUARANTEE
(1) General—(a) To guarantee payment for timber scheduled for removal under the IRSC, Contractor may earn Stewardship Credits in advance of removal, or provide a Timber Payment Guarantee in the form of an acceptable surety payment bond, cash payment, or a deposit in a Federal Depository negotiable securities of the United States.
(b) Any earned Stewardship Credits and alternate Timber Payment Guarantee together will maintain a minimum unobligated balance equal to the applicable charges for timber the Forest Service estimates will be cut in 60 calendar days plus the value of any outstanding charges, or equal to the total value of the timber that has not been paid for.
(c) Securities shall be deposited through the Contracting Officer accompanied by a power of attorney and agreement authorizing the bond-approving officer to sell or collect such securities if payment is not
Page 15 of 74 Flagstaff Ranger District made within 15 days of billing by Forest Service. The penal sum of such surety bond or the market value at time of deposit of such negotiable securities shall be the maximum amount of the payment guaranteed.
(2) A Timber Payment Guarantee for a single contract shall be provided utilizing FS Form 6500-12.
(3) Blanket Surety Bond—(a) Contractor may furnish an acceptable bond, or deposits securities, to guarantee payment for timber from multiple contracts. Contractor shall not start cutting hereunder until this contract receives an allocation that will meet the obligation for payment guarantee.
(b) The amount of such bond or deposited securities shall be allocated to such contracts by the Forest Service. The Contractor will provide the contact information for the Forest Service representative administering the Blanket Surety Bond.
(c) When there is to be no timber cutting hereunder for 30 days or more and payment of current charges has been made, the allocation to this contract shall be reallocated to other contracts at Contractor’s request.
(d) A Timber Payment Guarantee for multiple contracts (Blanket Guarantee) shall be provided utilizing FS Form 6500-12a.
(4) Letters of Credit for Payment Bond—Contractor may use letters of credit in lieu of a surety bond for payment bond purposes when approved by Contracting Officer.
15. EXCESS STEWARDSHIP CREDITS
In the event there are excess (unused) established Stewardship Credits when all of the included timber has been cut and removed the Forest Service, at its option, shall either add more timber or make cash payment for the unused credits.
16. EXCESS TIMBER VALUE
In the event the value of the included timber exceeds the total value of all of the mandatory activities plus the ordered Optional activities, the Contractor shall make cash payment for the excess timber value.
17. REFUND OF EXCESS CASH
If at any time the credit balance of the Integrated Resource Statement of Account exceeds the charges for timber removed to date and for timber that the Forest Service estimates will be cut within the next 60 calendar days, any portion of such excess from cash in the account shall be refunded if requested by Contractor. If no cutting is planned within the next 60 calendar days, refund of the entire unencumbered cash balance may be made. After a refund, deposits shall be made to meet the requirements of the clause entitled, “TIMBER PAYMENT GUARANTEE” before additional timber may be cut.
18. FINAL PAYMENT - RELEASE OF CLAIMS
Page 16 of 74 Flagstaff Ranger District
The Government shall pay the amount due the Contractor under this contract after—
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.
19. AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled within 10 days after the date of contract award. The conference will be held at Mormon Lake Work Center. 4373 South Lake Mary Road. Flagstaff, Arizona 86005.
20. FAR 52.236-4 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.
(b) Additional informational material made available to contractors including but not limited to: environmental documentation, timber cruise data, maps, access permits, etc.
21. USE OF PREMISES: AGAR 452.236-72 USE OF PREMISES (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor. (b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (i) dispose of solid waste in accordance with applicable Federal, State and local regulations.
The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform his contract in such a manner as not to interrupt or interfere with the conduct of Government business.
Before any camp is opened or operated on National Forest land or lands administered by the Forest Service, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor. Such permission, if granted, will be without charge to the Contractor.
The Contractor shall request permission (in writing) from the appropriate Ranger District to use campsites. If permission is granted, the District Ranger's letter shall specify all conditions and requirements.
It is further stipulated that in addition to clean-up of any camp sites, the Contractor is required to remove all his equipment from National Forest land before final acceptance and payment of the project.
Page 17 of 74 Flagstaff Ranger District
Portable chemical toilets, self-contained holding tanks, approved pit or vault toilets which meet State Code are required.
22. AGAR 452.237-74 KEY PERSONNEL (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel:
Overall Project Manager Logging Supervisor Timber Marking Supervisor/R3 Certified Cruiser Individual Sub-Managers – Individuals supervising individual sub-contracts for work items not covered by personnel noted previously herein.
(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
Key Personnel- Representatives:
Unless otherwise agreed, Contractor shall designate, in writing, a representative who is authorized to receive notices in regard to performance under this contract and take related action. In no case shall Contractor designate any representative to this contract who is currently debarred, proposed for debarment, or suspended by the Federal Government. Contractor’s representative shall provide a copy of the contract to Contractor’s field supervisor and persons authorized to assume responsibilities in the field super- visor’s absence. Prior to initial operations and after shutdowns of 10 days or more, Contractor’s representative shall notify Forest Service 2 days, excluding weekends and Federal holidays, before any operations begin on Contract Area.
Contractor’s representative shall designate, in writing, a field supervisor, one of whose responsibilities shall be on-the-ground direction and supervision of Contractor’s Operations. The field supervisor shall be readily available to the area of operations when operations are in progress and shall be authorized to receive notices in regard to performance under this contract and take related action. The responsibilities of the field supervisor shall include the safeguarding of National Forest resources and performance within the terms of the contract. Contractor representative will furnish Forest Service with names of persons authorized to assume responsibilities in field supervisor’s absence. Such delegations may be made a part of Contractor’s annual Operating Schedule.
Unless Contracting Officer designates another Forest Service representative and notifies Contractor in writing, the COR is the representative of Forest Service. Forest Service representative shall:
(a) Receive notice in regard to performance under this contract, Page 18 of 74 Flagstaff Ranger District
(b) Take action in relation to this contract, and
(c) Be readily available to the area of service work activities and logging operations.
Contracting Officer shall designate…