1. DI-MGMT-82086_Fact Finding Report.pdf
Data Item Description PDF 163 KB Posted
- Attached to
- Wavemaker Drive Repairs BPA
- Solicitation number
- N0016722Q0140
View the file
Who attaches DI-MGMT-82086
| Agency | Files |
|---|---|
| Department of the Navy Naval Sea Systems Command | 1 |
Other files
| File | Type | Posted |
|---|---|---|
| N0016722Q01400001.docx | DOCX document | |
| 2. CDRL A002_TECHNICAL REPORT_S1.pdf | ||
| N0016722Q0140 CSS.docx | DOCX document | |
| 4. CDRL A004_GFP_S1.pdf | ||
| 2. DI-MISC-80508B (Technical Report-StudyServices).pdf | ||
| 10. GFP - MotiFlex e100 repair FULL LIST.xlsx | XLSX spreadsheet | |
| 1. CDRL A001 Initial Report.pdf | ||
| 3. MIL-PRF-63034B(TM)_WARRANTY.pdf | ||
| 4. DI-MGMT-80441C (GFP List).pdf | ||
| 3. CDRL A003_WARRANTY_S1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
Title: FACT FINDING REPORT
Number: DI-MGMT-82086 Approval Date: 20161208
AMSC Number: N9746 Limitation: N/A
DTIC Applicable: No GIDEP Applicable: No
Preparing Activity: SH Project Number: MGMT-2017-006
Applicable Forms: N/A
Use/Relationship: This DID will capture relevant facts regarding an unplanned event and will document the severity level of problems associated with the unplanned event.
This DID contains the format and content preparation instructions for the data product generated by the specific requirement delineated in the contract.
Requirements:
1. Format. The report shall be in a format similar to that of Figures 1, 2 and 3.
2. Content The report shall contain tall of the information specified in Figures 1, 2 and 3 and shall contain the following information:
a. Chronological statement of relevant facts
b. Working copy of cause and Corrective Action Form(s)
c. Any other document(s) used during the Fact Finding Investigation
d. The identity of the senior manager who performed the review
e. Complete chronological statement of relevant facts from the unplanned event
f. Any other document(s) used during the Fact Finding Investigation (e.g.
Independent Statements from individual(s), appropriate references, technical work documents)
g. A copy of critique meeting attendance from if a critique meeting was held
h. Identity of any similar unplanned event(s)
Source: https://assist.dla.mil -- Downloaded: 2021-06-24T19:28Z Check the source to verify that this is the current version before use.
DI-MGMT-82086
Figure 1
Preliminary Report
Final Report
FACT FINDING REPORT FORM
SENIOR MANAGER REVIEW: CONFIDENTIAL
ACTIVITY RESPONSIBLE FOR INVESTIGATION OF UNPLANNED EVENT:
CRITIQUE DATE/TIME (indicate "report only" if no critique held):
REPORT SERIAL NUMBER: DATE REPORT ISSUED:
DATE/TIME OF ACTUAL UNPLANNED EVENT:
DATE/TIME WHEN UNPLANNED EVENT WAS DISCOVERED:
LOCATION OF UNPLANNED EVENT (i.e. building /facility, room/space):
TITLE (based on the most obvious problem):
SEVERITY LEVEL ASSIGNED:
DESCRIPTION OF THE UNPLANNED EVENT:
IMMEDIATE CORRECTIVE ACTIONS TAKEN:
PREVIOUS SIMILAR UNPLANNED EVENT ( s) : YES NO , IF YES, LI ST SERIAL NUMBER ( s)
PROCEDURE NUMBER: STEP BEING WORKED:
DISCOVERED BY: PHONE#:
CHAIRPERSON: PHONE #:
ORGAN IZATION (S) RESPONSIBLE FOR IDENTIFIED PROBLEMS OR ASSIGNED ACTIONS/OPEN ITEMS
ORG:______ ORG:_______ ORG:______ ORG:______ ORG:_______ ORG:
CHAIRPERSON/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE SIGNATURES
SUPERVISOR/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE BY/DATE:
CONCURRENCE BY/DATE
Figure 2
CRITIQUE MEETING ATTENDANCE SHEET FORM
REPORT SERIAL NUMBER: DATE/TIME:
PRINT NAME ORGANIZATION/SHOP PHONE #
Figure 3
CAUSE AND CORRECTIVE ACTION FORM
REPORT SERIAL NUMBER: EVENT SEVERITY LEVEL: MANAGER/TECHNICAL CODE:
DATE ISSUED:
This form contains the problem descriptions that were identified as being partially or wholly the responsibility of . As the manager, you are responsible to follow up and take the appropriate actions to correct the listed problems.
PROBLEM # PROBLEM SEVERITY LEVEL
DESCRIPTION:
CAUSE:
SHORT-TERM CORRECTIVE ACTIONS:
ESTIMATED COMPLETION DATE: ____________ ACTUAL COMPLETION DATE:
LONG-TERM CORRECTIVE ACTIONS:
ESTIMATED COMPLETION DATE: ACTUAL COMPLETION DATE:
ACTION ASSIGNMENT SIGNATURES
CRITIQUE CHAIRPERSON DATE:
(Prime contractor)
SUPERVISOR REPRESENTATIVE: DATE:
RESPONSIBLE ORGANIZATION: DATE:
ACTION COMPLETION/ACCEPTANCE SIGNATURES
RESPONSIBLE ORGANIZATION:
PRIME CONTRACTOR ACCEPTANCE:
SUPERVISOR REPRESENTATIVE: DATE:
End of DI-MGMT-82086