1. 26Z2AT1 Foundation Drain SOW.pdf
PDF 531 KB Posted
- Attached to
- FCI Loretto - Install Foundation Drain
- Solicitation number
- 15BBF
About this file
This is a Statement of Work (SOW) for the Federal Bureau of Prisons, Federal Correctional Institution (FCI) Loretto, Pennsylvania, for Project #26Z2AT1, Install Foundation Drain. The SOW was approved by the Construction and Environmental Review Section on February 13, 2026.
The contractor shall excavate and install approximately 25 feet of foundation drainage and 20 feet of solid drainage piping adjacent to the exterior of the Training Center. Specific work includes excavating a trench approximately 2 feet by 3 feet wide, 4 feet deep, and 25 feet long along the Training Center side; removing spoils from the property and replacing with clean stone; cleaning and waterproofing the wall per manufacturer specifications; installing geotech fabric, perforated drainage piping, and clean stone; excavating an additional 55 feet to connect the new foundation drain to the existing downspout; and restoring the work area with mulch and seed. The contractor must obtain all measurements and manufacturer installation recommendations and comply with BOP Technical Design Guidelines, seismic zone requirements, environmental compliance, Life Safety codes, NFPA, ADA-ABA, and Federal, State, and Local codes. The contractor is responsible for ensuring on-site presence during installation, maintaining a clean work area with daily debris removal, and proper disposal of all waste materials.
Work hours are 7:00 AM to 3:30 PM, Monday through Friday, excluding weekends and federal holidays, with any alternate hours requiring written COR approval five working days in advance. The contractor must provide all security clearance documentation for employees, attend a mandatory four-hour orientation and security procedures training, and wear issued picture ID/contractor badges. All construction materials and equipment must be coordinated with the COR for temporary storage in a secure, lockable gang box with dual locks. Tools must be inventoried daily upon entry and exit. Extension cords classified as "Double A" high-risk tools must exit the facility daily; ladders must be chained and locked to a stationary fixture. The contractor shall provide all required Personal Protective Equipment (PPE), and must not bring cell phones, cameras, or two-way pagers into the facility. BOP will provide minimal electricity (120V), restroom services, and water; the contractor provides all other supplies and materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 15BBNF26Q00000033.pdf | ||
| 2. Wage Determination PA20260002.pdf | ||
| Instructions to Offerors.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Justice Federal Bureau of Prisons
Facilities Management
Washington, DC 20534
February 13, 2026
MEMORANDUM FOR SEAN O’BRIEN, CONSTRUCTION REPRESENTATIVE
PROJECT RESOURCES SECTION
FROM: Kimberly Hudson, Chief
Construction and Environmental Review Section
SUBJECT: Statement of Work Approval, Project #26Z2AT1 Install Foundation Drain
The Construction and Environmental Review Section, Facilities Management Branch, has reviewed and approved the Statement of Work (SOW) to be used for solicitation services at FCI Loretto for Project #26Z2AT1, Install Foundation Drain. There are no additional square footage modifications to the primary structure, nor changes to the utilities to this project.
This SOW specifically addresses the installation of the foundation drain under project 26Z2AT1 as defined herein and should not be interpreted as an open-ended approval for future, unrelated work.
If you have any additional questions or concerns, please contact Henry Guo, Architect, at sguo@bop.gov.
INSTALL FOUNDATION DRAIN
FEDERAL CORRECTIONAL INSTITUTION (FCI)
LORETTO
STATEMENT OF WORK
Prepared By:
U.S. DEPARTMENT OF JUSTICE
Federal Bureau of Prisons Federal Correctional Institution 772 Saint Joseph Street Loretto, Pennsylvania 15940 bop00351 Approved
STATEMENT OF WORK
INSTALL FOUNDATION DRAIN
FCI LORETTO- B&F PROJECT 26Z2AT1
1. SPECIFICATIONS:
A. INTRODUCTION
The Federal Bureau of Prisons (BOP), Federal Correctional Institution (FCI) in Loretto Pennsylvania, intends to make a single award to a responsible entity to provide all necessary equipment, labor, materials, and incidentals to install a foundation drain located at the exterior of the Training Center at the FCI, located at 772 Saint Joseph Street in Loretto Pennsylvania.
B. SCOPE OF WORK
The contractor shall be responsible for excavating and installing approximately 25’ feet of foundation drainage and 20’ of solid drainage piping adjacent to the exterior of the Training Center. The contractor shall be responsible for:
- Excavating approximately 2’x3’ wide, 4’ deep, and 25’ long trench located along the side of the Training Center -Remove spoils to an outside location and replace with clean stone. The spoils will be removed from the property upon completion of the project.
-Clean and prep wall and apply a waterproofing system per the manufacturer’s specifications.
-Install Geotech fabric, perforated drainage piping, and clean stone to serve as a foundation drain.
-Excavate approximately an additional 55’ to connect the newly installed foundation drain to the existing downspout.
-Restore the work area with mulch and seed.
It shall be the Contractors responsibility to obtain all measurements and manufactures installation recommendations.
Compliance will be addressed as applicable to this project, inclusive of BOP Technical Design Guidelines, seismic zone requirements, environmental compliance, Life Safety, NFPA, ADA-ABA, and Federal, State, and Local codes and regulations.
C. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS
The general contractor to be always on-site during the installation. If the general contractor is not available a company supervisor must be on-site during the project. At no time will the BOP COR assume responsibility.
D. UTILITIES
The BOP will provide minimal electricity service (120V), for battery chargers, radios, small hand tools, etc. In addition, provide restroom services, and water. The contractor will provide all other supplies and materials needed to complete this project.
E. ACCEPTANCE
The contractor awarded the contract will be responsible for ensuring the premises are always kept clean and free from accumulations of waste materials and rubbish. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work.
The Contractor shall be responsible to remove all debris and waste materials from the job site at FCI Loretto upon conclusion and acceptance of the project. These items must be disposed of in accordance with all Federal, State, and local laws.
II. CONTRACTOR SECURITY/WORKING REGULATIONS
A. Work Hours:
Work Hours for the contractor are 7:00 AM – 3:30 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work and must be approved by the Warden. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.
Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour workday. The Government assumes no responsibility to the Contractor nor to any of his subcontractors for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines.
Contractors should plan for a certain amount of time accrued for security considerations, i.e., check-in screening, delay due to inmate movements, institution lock-down, institution emergencies, etc. In the event of an institutional emergency, the Contractor will be instructed to secure all work, secure, and stow all tools, equipment and materials, and the Contractor will be escorted out of the institution. Work will resume once the institution emergency passes.
B. Delivery of Materials:
All construction materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the institution COR for temporary storage.
Any construction-related deliveries which are directly shipped to the contractor can be received between the hours of 7:0 0 a.m. to 2:00 p.m., Monday through Friday, excluding Federal Holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor or his representative is not present to verify and accept the delivery.
Under no circumstances will FCI Loretto or its staff be responsible for the acceptance of any Contractor or company deliveries. The contractor shall be responsible for providing their own means of loading and unloading contractor material or equipment.
The contractor shall not use the institution entry/driveway for the loading, unloading, or storage of any materials and equipment. The contractor will not impede/block the driveway at any time during or after the work shift.
C. Storage of Materials and Equipment:
All construction materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor. The storage area will be a secure lockable gang box or similar, size to be determined by the contractor and the COR. The container will be secured using a padlock protocol with two locks to secure it. One shall be a contractor lock and the other lock provided by the institution. If necessary, a heavy-duty chain provided by the contractor may be used to facilitate the locking requirement. All materials and equipment stored within the container will be maintained in a safe and orderly fashion
All tools will be inventoried prior to entering the institution and will be inventoried back in to ensure accurate accountability when exiting the institution at the end of each workday.
Materials cannot be stored at a height that would create a fall hazard. All tools will be inventoried prior to entering the Institution. At the start of each workday all tools will be inventoried out on a daily tool inventory sheet and at the end of the workday all tools will be inventoried back in to ensure accurate accountability of all tools at the end of each workday.
All contractor-owned extension cords that will be used during the project, regardless of length, shall be in good condition with no broken outer Insulation. Extension cords are considered a “high risk” tool having a Federal Bureau of
Prisons’ tool classification of Double A. All contractors-owned extension cords used for this project will be required to exit the institution at the end of every workday for the duration of the project.
All contractor-owned ladders approved for use within the institution, regardless of the size, shall be stored in a pre-determined area and secured to a stationary fixture with a heavy link chain and lock which would prevent removal.
D. Security Clearance/Contractor Badges:
The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the institution and be security cleared for badging. Security clearance documents will only be accepted from the prime contractor. If submitted by a sub-contractor, they will be rejected. It is the prime contractor’s responsibility to review security clearance submissions to ensure they are complete.
All contractors and their construction staff awarded the project will be required to attend a four (4) hour orientation and security procedures training. The contractors and any subcontract staff are required to attend. This training must be accomplished prior to any contract or subcontract employee being granted access to federal property to start work.
In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractor’s or subcontractor employee was not able to pass the security clearance process.
All contractors/subcontractors working at FCI Loretto will be issued and required to wear a picture ID/contractor badge provided by the institution. For security reasons, the badge will be worn in a visible manner as directed by the COR.
All contractors and subcontractor employees will provide a check list of all employees on site each day to the COR, verifying the number of workers on site each day and that all workers are approved to be on site.
E. Safety and Personal Protective Equipment:
All contractors and employees shall have and wear the required personal protective equipment (PPE) prescribed by industry standards at all times while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that the COR can make timely notifications to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box.
Should a system require Lock-out/Tag-out, the system will be required to have both Contractor and FCI Loretto locks on the isolation point to prevent shock. All Lock-out/Tag-out procedures will follow the institution Lock-out program.
F. Additional Considerations:
1. Contractors will NOT be allowed to bring cell phones, cameras or two-way pagers into FCI Loretto. The Facilities Department maintains a digital camera that will be utilized by BOP staff to document the project work. The Contractor may request copies of these documentation photos for record keeping.
2. Contractor will be permitted to wear jeans in the institution, however, green, or khaki-color clothing will not be allowed. The clothes will be proper and suitable for the services that are being provided.
3. Lunches will be consumed at the work site. The contractor shall ensure they have everything they need for their lunch when they check in first thing in the morning.
4. Federal smoking policy on Federal property states that smoking is only allowed in designated areas. This policy will be strictly enforced.
END OF STATEMENT OF WORK
| STATEMENT OF WORK: | |
| undefined: | |
| Row1: | |
| Row2: | |
| Row2_2: | |
| Row3: | |
| Row4: | |
| Row5: | |
| UPRow1: | |
| S c 11 1 olMPI: | |
| undefined_2: | |
| l: | |
| fill_24: | |
| undefined_3: | |
| undefined_4: | |
| undefined_5: | |
| DNRow1: | |
| DNRow2: | |
| DNRow3: | |
| DNRow4: | |
| DNRow5: | |
| undefined_6: | |
| UP: | |
| UP_2: | |
| rCjl I: | |
| I1PRow1: | |
| undefined_7: | |
| undefined_8: | |
| Q 2 z 0 1 u w Q z 0 w 1 z w u C z z 0 1 u LLRow1: | |
| DAlE 11218: | |
| JCB NO: | |
| DWG NO: | |
| 2026-02-13T11:31:48-0500 | |
| KIMBERLY HUDSON |
| 2026-02-13T11:31:14-0500 | |
| KIMBERLY HUDSON |
File details come from the government source that posted it. Updated .