1-.2026.06.15 MS-944 - E Pine St Paving COMBINED.pdf

PDF 2 MB Posted

Attached to
R001655. 0001 - East Pine Street Paving
Solicitation number
Not on record
Issued by
Cumberland County, Pennsylvania

About this file

This is a Proposal and Contract form (MS-944) issued by Mount Holly Springs Borough, a First Class Township located in Cumberland County, Pennsylvania, for the East Pine Street Paving project. The project involves roadway resurfacing work along approximately 1,100 linear feet of East Pine Street from the Mountain Creek bridge east to the railroad tracks, covering approximately 4,540 square yards. The scope of work includes milling the existing bituminous surface to 1.5 inches depth, applying tack coat, placing Superpave asphalt wearing course overlay, excavating and preparing temporary subbase material within the Borough's culvert replacement area, constructing bituminous base course and wearing course paving, compacting materials, and completing incidental work including traffic control, joint sealing, utility adjustments, and pavement tie-ins. The project is coordinated with a separate Borough culvert replacement project. Sealed electronic proposals must be submitted via PennBid at https://pennbid.bonfirehub.com no later than July 9, 2026 at 1:00 PM local time, at which point bids will be publicly opened and read. Work must be completed on or before August 28, 2026, with liquidated damages assessed at $870.00 per additional working day for delays, increasing to $975.00 per calendar day after August 28, 2026.

The contract utilizes unit pricing based on a Schedule of Prices with items including Superpave asphalt mixture wearing course (4,540 tons), Superpave asphalt wearing course leveling (64 tons), Class 1 excavation (56 cubic yards), Superpave asphalt base course (365 tons), flexible base replacement (2,190 tons), milling of asphalt pavement surface (4,175 square yards), asphalt tack coat (4,540 square yards), and yellow waterborne pavement markings (as directed). All work must comply with current PennDOT Specifications (Publication 408), with exceptions noted regarding prequalification requirements and volumetistic testing. The successful bidder must provide a certified check or bid bond as proposal guarantee, and upon contract award must submit performance bonds and payment bonds equal to 100% of the contract amount, along with a Workmen's Compensation affidavit. The contractor is responsible for defects occurring within one year of application, must provide design approval five days prior to work start, and must submit oil samples and stone samples for testing. All bidders must submit a completed Form 7126 Anti-Collusion Affidavit with their proposals.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MS-944 (4-22)

TIME

, on the above Letting Date. PROPOSALS MUST BE submitted electronically TIME via PennBid at https://pennbid.bonfirehub.com and specifications on file at as well as the supplements complete all work within calendar days.

3 Accompanying this proposal is a certified check or bid bond in the amount of made payable to the municipality as a proposal guarantee which, it is understood, will be forfeited in case the contractor fails to comply with the requirements of the proposal.

B. PROPOSAL OF:

1 The only person interested in the proposal as principal (s) is (are):

2 None of the above persons are employees of the municipality.

3 This proposal is made without collusion with any other person, firm or corporation.

Mount Holly Springs, PA 17065

1:00 PM

The contractor proposes to furnish and deliver all materials ( including Form CS-4171, CERTIFICATE OF COMPLIANCE and/ or TR-465 DAILY BITUMINOUS MIXTURE CERTIFICATION ) and to do and perform all work on the following project as more specifically set forth in the Schedule of Prices (Attachment), in accordance with drawings and special requirements contained herein and/ or attached hereto and current PennDOT Specifications (Publication 408), except (a) bidders need not be prequalified by PennDOT (Sec.102.01), and (b) Volumetric testing of bituminous paving materials is not required (Sec. 413).

(c) Bitumious Price Adjustments (Sec. 110.04)

INSTRUCTIONS ON PAGE 4

Bids will be opened and read at approximately

July 9, 2026

1:00 PM

Mount Holly Springs Borough

MUNICIPALITY (NAME & TYPE)

If designated as the successful bidder, the contractor will begin work on the date specified in the notice to proceed, or as otherwise provided in the special requirements, and will

10%

PennBid at https://pennbid.bonfirehub.com see attachment 1-A

-1-

It is hereby certified as follows:

NAME / ADDRESS OF CONTRACTOR

CONTRACTORS CERTIFICATION

All plans and specifications referred to above and the site of the work have been examined by the contractor. The contractor understands that the quantities indicated herein are approximate and are subject to change as may be required; and that all work is payable on the basis of the unit price listed on the Schedule of Prices. (Attachment 1).

THIS PROPOSAL INCLUDES

INSTRUCTIONS TO BIDDERS

ADDRESS

A. DEPOSIT OF PROPOSALS.

Sealed Proposals will be received on or before

All proposals must be submitted electronically via PennBid at https://pennbid.bonfirehub.com

PROPOSAL AND CONTRACT

( WHEN EXECUTED )

Karen Johnson

SECRETARY

DATE

on the above Letting Date. 200 Harman Street

BY: DATE:

TITLE:

DATE:

TITLE:

TITLE:

BY:

TITLE:

BY:

TITLE:

TITLE:

ATTESTED BY:

MUNICIPALITY

BY:

-2-

DATE

Mount Holly Springs Borough

The contractor will comply with all requirements of the laws and implementing regulations of the Commonwealth of Pennsylvania and the United States relating to human relations, equal opportunity and non-discrimination in employment, and will pay to workmen employed in the performance of the contract the wages to which they may be entitled.

The contractor will provide the municipality with a performance bond, conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions thereof, and a payment bond, conditioned on the prompt payment of all material furnished and labor supplied or performed in the prosecution of the work, in accordance with the Public Works Contractors’ Bond Law of 1967; and an affidavit accepting the provisions of the Workmen’s Compensation Act of 1915, as amended.

CONTRACTOR

WITNESSED OR ATTESTED BY:

TO BE EXECUTED ONLY IN THE EVENT THE ABOVE PROPOSAL IS ACCEPTED

ACCEPTED ON :

SEAL

County:

CY

SY

TON

SY

TON

SY

SY

LF

SUBTOTAL

EACH MUST BE INCLUDED.

- 3 -

OPTION 3 OR PHASE 3 BID TOTAL

ATTACHMENT 1

TO MS - 944 ( PROPOSAL AND CONTRACT MS - 944 )

Cumberland County Municipality: Mount Holly Springs Borough

LOCATION OF WORK:

TH

IS

P O

R

TI

O N

T O

B E

C O

M

PL

ET

ED

BY

T

H E

M U

N

IC

IP

AL

IT

Y

Unit

SCHEDULE OF PRICES

*Description

Project Number:

DESCRIPTION OF WORK:

Total

4,540

SUPERPAVE ASPHALT MIXTURE DESIGN,

WEARING COURSE, PG 64S-22, < 0.3

MILLION ESALS, 9.5 MM MIX,

1 1/2" DEPTH, SRL-L

Project located along East Pine Street from the Mountain Creek bridge east to the railroad tracks, for an overall project length of approximately 1,100 LF.

The project includes roadway resurfacing work to be completed in conjunction with a Borough project to replace the existing bridge on East Pine Street between Green House Alley and Tail Race Drive with a pipe culvert. The Borough will complete removal of the existing structure, installation of the pipe culvert, backfilling, and placement of temporary subbase material to final grade prior to paving operations.

A. Mill the existing bituminous roadway surface and perform variable depth leveling as needed to provide a uniform riding surface and proper grade. Perform flexible base replacement, as directed.

B. Apply tack coat to all milled and prepared pavement surfaces prior to paving operations.

C. Place bituminous wearing course overlay along East Pine Street within the project limits.

D. Within the Borough’s culvert replacement area, excavate and prepare the temporary subbase installed by the Borough, as necessary, and construct the required bituminous base course and wearing course paving.

E. Compact paving materials in place and complete all incidental work, including traffic control, joint sealing, utility adjustments, and pavement tie-ins.

ESCALATOR CLAUSE:( if adopted by Municipality.)

Unit 5 Price

SUPERPAVE ASPHALT MIXTURE DESIGN,

WEARING COURSE (LEVELING), PG 64S-22,

< 0.3 MILLION ESALS, 9.5 MM MIX, SRL-L

(AS DIRECTED)

CLASS 1 EXCAVATION

SUPERPAVE ASPHALT MIXTURE DESIGN,

BASE COURSE, PG 64S-22,

< 0.3 MILLION ESALs, 25.0 MM MIX, 4" DEPTH

SUPERPAVE ASPHALT MIXTURE DESIGN,

FLEXIBLE BASE REPLACEMENT, PG 64S-22,

< 0.3 MILLION ESALs, 25.0 MM MIX (AS

DIRECTED)

Item 1 No.

Approximate 2 Quantities

0413-2059

0413-0195

4,540

0203-0001 56

0313-0322 365

0316-0337

2,190

SUBTOTAL FROM OTHER ATTACHMENTS

* DESCRIPTION:

Must include ADT on wearing surfaces

USE OF CUTBACK ASPHALT IS PROHIBITED

BETWEEN MAY 1st AND OCTOBER 31st, EXCEPT

AS NOTED IN BULLETIN NO. 25.

FOR OPTION OR PHASE BIDS THE TOTALS FOR

0460-0001

0962-1005

BID TOTAL FOR A NON OPTION / PHASE BID

OPTION 1 OR PHASE 1 BID TOTAL

OPTION 2 OR PHASE 2 BID TOTAL

4" YELLOW WATERBORNE PAVEMENT

MARKINGS

ASPHALT TACK COAT

0491-0012 4,175

MILLING OF ASPHALT PAVEMENT

SURFACE, 1 1/2" DEPTH, MILLED MATERIAL

RETAINED BY CONTRACTOR

x Traffic Control and Safety Devices to be provided by the Contractor.

X Delivery tickets for all materials.

X CS-4171 Certificate of Compliance and/ or TR-465 Daily Bituminous Mixture Certification required for all materials.

X five (5) working days prior to start of project.

8/28/2026 . After 8/28/2026 the rate of $ 975.00 per calendar day.

X Roadway to be power broomed by (contractor x municipality )prior to start of project.

X Excess material to be removed by (contractor x municipality .)

X Municipality to inspect project.

X Need Bill of Lading for each shipment of bituminous material per Section 702.1(c) of Specifications 408.

X Tack Coat required per Section 460, or 413 for superpave, of Specifications 408 and is incidental to paving item unless noted otherwise.

Prime Coat required per Section 461 of Specifications 408.

X Bituminous Seal on all abutting pavement and curbs required.

X Saw cut or Milled Paving Notch required and incidental to paving item unless noted otherwise.

X Scratch/ Leveling Courses to be placed at the discretion of appointed inspector(s).

X Municipality reserves the right to limit work completed.

Taper pavement the last 3 feet to curb.

For FOB Source bids, hauling distance will determine selection of bid award.

Municipality reserves the right to procure material which best suits their requirements after all bids and items are reviewed.

X Incidental Preparation and clean up required. ( Project Construction Materials ) X The municipality reserves the right to make an award on the basis of the aggregate total for all like items on which quotations are received.

Provide design, which meets Specifications Form 408 to the municipality 5 days prior to start of work.

X Contractor responsible for defects that occur within one year of applications.

X Contractor required to review proposed project with Municipality’s Representative prior to bidding.

Oil Samples required from each distributor truck by contractor (1) one quart : A.M. & P.M. and witnessed by municipality and retained by municipality. (Oil samples must be placed in an approved type container that is compatible with oil sample.)

At least three random stone samples to be taken by contractor on project site witnessed by municipality and retained by municipality.

Complete all testing in accordance with Specification Form 408 Section 413 except for superpave volumetric testing.

Notice to Proceed will be the date of Contract acceptance.

X Final Completion Certificate & Notice of Completion required.

X Future award of Contract will be based on quality of work as determined by the municipality.

X Contractor, notify all residents of pending work to be performed.

My signature signifies that I have read and understand the above special provisions to this contract, and by being authorized by this company to act as their authorized representative, and on their behalf hereby agree to adhere to any and all of the provisions pertaining to this contract.

Date

Work to be completed on or before

Mount Holly Springs Borough

Liquidated damages apply at

Full width pavement with one pass required.

Company Municipality

Contractor's Representative Municipality's Representative Date

Notify the Municipality

(5-06) SPECIAL PROVISIONS TO CONTRACT MS-944 ( Attachment 1-A )

CONTAINS IMPORTANT INFORMATION FOR THE CONTRACTOR

The Prime Contractor and subcontractors must comply with all of the following provisions that are marked with an "X".

( Maintenance and Protection of Traffic to comply with current MUTCD, Publication 212 and Publication 213.)

2 If more than one proposal on any project is submitted by an individual, firm or partnership, corporation or association under the same or different names, only one lowest proposal will be considered.

3 Description of Work- - -

A. If additional space is needed, insert appropriately numbered attachment and note “Continued on attached work sheets."

4 Part A of Page 1 to be completed by municipality. Part B of Page 1 to be completed by contractor.

Schedule of Prices - Column #1 (Item), #2 (Approximate quantities), #3 (Unit, i.e., ton, square yard, linear feet, etc.) And #4 (Description, i.e. , bituminous materials - 9.5 mm S & L, 12.5 mm Wearing,

25.0 mm Base Course, etc.) Must be filled in by the municipality to insure equitable bidding.

Columns #5 (Unit Price), #6 (Total) and total amount of bid, must be filled in by the contractor.

If more space is needed, add note at the bottom of the page; “Continued on Attachment No. 1-A”, and add additional sheet designated as Attachment No. 1-A, 1-B, etc.. Repeat for each additional sheet required.

As required by Publication 408, Section 102.06(e),each bidder must submit a completed Form 7126 - Anti-Collusion Affidavit with its bid proposal.

5 If liquidated damages are to be assessed, add the following sentence to Part A #2. If all work is not completed on time, liquidated damages will be assessed at the rate of $870.00 per additional working day.

(OR “. . . as set forth in the attached schedule.”)

6 Payment and Performance bonds are provided only by the successful bidder. Contracts from $4,000.00 up to $5,000.00 in Second Class Townships - performance bond must be not less than 10% or greater than 100% of amount of contract.

Contracts greater than $1,500.00 up to $10,000.00 in First Class Townships, Boroughs and Third Class Cities - bonds must be between 50 % to 100% of the contract amount. Contracts in excess of $5,000.00 in Second Class Townships and in excess of $10,000.00 in First Class Townships, Boroughs and Third Class Cities - bonds must be in 100% of the amount of the contract. Bond Forms MS-944 Attachments 2 and 3 and Workmen’s Compensation Affidavit - Attachment 4 must be submitted by the successful bidder within 20 days of the contract award. Failure to submit the bonds shall constitute grounds to cancel the contract.

7 *Construction projects, where the estimated cost of the total project exceeds $100,000, are subject to the provisions of the Pennsylvania Prevailing Wage Act 442 and amended by Act 89 of 2013. It is the responsibility of the municipality to request the Prevailing Wage Scale for the area and include it in the proposal. If the Prevailing Wage Act applies, this fact shall be noted in the advertisement.

On projects utilizing Federal Revenue Sharing Funds, if the project cost exceeds $2,000 and is financed with 25% or more Federal Revenue Sharing Funds, the Davis Bacon Act applies. Again, it is the responsibility of the municipality to obtain the Davis Bacon Wage Rates, include them in the proposal and note the fact in the advertisement. If both acts are applicable, The Davis Bacon Act has preference over the Pennsylvania Prevailing Wage Act.

8 An ESCALATOR CLAUSE is optional; if used, it must be included in the proposal prepared by the municipality. An escalator clause may not be inserted by the contractor.

*(1961, Aug. 15, P.L. 987; 43 P.S. 165)

-4-

PROPOSAL AND CONTRACT INSTRUCTIONS- FORM 944 (Rev. 1/2014)

The proposal must be typewritten or printed.

Attachment 2

($ ) dollars

WHEREAS, the above bounden Principal has entered into a contract with the above Municipality, bearing even date herewith, for

It is further provided that any alteration which may be made in the terms of the contractor or its specifications with the express authorizing the same to be done on .

BY

TITLE:

TITLE:

TITLE:

TITLE:

- 1 -

CONTRACTOR

SURETY COMPANY

Attest / Witness:

(DATE OF BOND)

(With Corporate Surety)

Attest / Witness:

IN WITNESS WHEREOF, the said Principal and Surety have duly executed this Bond under Seal, pursuant to due and legal action

NOW, THEREFORE, the condition of this obligation is such that if the above bounden Principal, as Contractor, shall in all lawful money to the United States of America, to be paid to the above Municipality or its assigns, to which payment well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

forebearance being hereby waived.

shall be and remain in full force, virtue and effect.

approval of the Municipality or the Principal to the other, shall not in any way release the Principal and the Surety or either or any of them, to and made a part thereof, and such alterations as may be made in said Specifications as therein provided, and shall well and truly, and in a manner satisfactory to the municipality fulfill all obligations as therein set forth, then this Obligation shall be void, but otherwise the same the undertaking of certain obligations as therein set forth.

respects comply with and faithfully perform the terms and conditions of said Contract, including the Specifications and conditions referred their heirs, executors, administrators, successors or assigns from their liability hereunder, notice to the surety of any such alteration or

PERFORMANCE BONDMS-944-S (7-09)

(NAME OF MUNICIPALITY)

Mount Holly Springs Borough in the full and just sum of

(NAME OF STATE)

are held and firmly bound unto

KNOW ALL MEN BY THESE PRESENTS, That we, as Surety as Principal and a corporation incorporated under the laws of the State of

(SURETY COMPANY)

(NAME AND ADDRESS OF CONTRACTOR)

PLACE

SEAL

HERE

PLACE

HERE

MS-944S

KNOW ALL MEN BY THESE PRESENTS, that we a corporation incorporated under the laws of the State of as SURETY, are held and firmly bond unto the , in the full and just sum of

($ )dollars, lawful money of the United States of America, to be paid to the said or its assigns, to which payment well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, the above bounden Principal has entered into a contract with the above municipality hereinafter called Obligee, bearing even date herewith, for the improvement of a certain section of highway or bridge in said Municipality consisting of:

for approximately the sum of: ($ ) dollars.

NOW, THEREFORE, the condition of this obligation is such that if the above bounden PRINCIPAL shall and will promptly pay or cause to be paid in full all sums of money which may be due by contract or otherwise, to any individual, firm, partnership, association or corporation, for all material furnished or labor supplied or performed in the prosecution of the work, whether or not the said for material or labor entered into and became component parts of the work and for rental of the equipment used and services rendered by public utilities in, or in connection with the prosecution of such work, then this obligation to be void, otherwise to remain in full force and effect.

The PRINCIPAL and SURETY, hereby, jointly and severally, agree with the Obligee herein that any individual firm, partnership, association or corporation, which has performed labor or furnished material in the prosecution of the work as provided, and any public utility which has not been paid in full therefor, may sue in assumpsit on this Payment Bond in his, their, or its own name and may prosecute the same to final for such sum or sums as may be justly due him, them or it, and have execution thereon. Provided, however, that the Obligee shall not be liable for the payment of any costs of expenses of such suit.

RECOVERY by any individual, firm, partnership, association or corporation hereunder shall be subject to the provisions of the “Public Works Contractors’ Bond Law of 1967", Act No. 385, approved December 20, 1967,P.L. 869, which Act shall be incorporated herein and made a part hereof, as fully and completely as though its provisions were fully and at length herein recited.

It is further provided that any alterations which may be made in the terms of the contract or in the work to be done or materials to be furnished or labor to be supplied or performed under it or the giving by the Obligee of any extension of time for the performance of the contract or any other forebearance on the part of either the Obligee or the Principal to the other, shall not in any way release the PRINCIPAL and the SURETY or SURETIES of any such alteration, extension of forebearance being hereby waived.

IN WITNESS WHEREOF, the said PRINCIPAL and SURETY have duly executed this Bond under seal this ,20 .

WITNESS:

CONTRACTOR

BY:

TITLE:

SURETY COMPANY

TITLE: TITLE:

Mount Holly Springs Borough

TITLE:

- 2 -

WITNESS:

day of

PAYMENT BOND Attachment 3 as PRINCIPAL and

Mount Holly Springs Borough

PLACE

SEAL

HERE

PLACE

HERE

Attachment 4

State of )

) ss:

County of ) he has being duly sworn according to law deposes and says that they have it has accepted the provisions of the Workmen’s Compensation Act of 1915 of the Commonwealth of Pennsylvania, with has his its supplements and amendments, and have insured their liability thereunder in accordance with the terms of said its

Act with .

( TYPE OR PRINT)

BY

day of A.D. 20 .

My Commission Expires

- 3 -

CONTRACTOR

SIGNATURE

Sworn to and subscribed before me this

( DATE )

SIGNATURE

(SURETY COMPANY)

AFFIDAVIT RE

ACCEPTING PROVISIONS OF THE WORKMEN’S COMPENSATION ACT

Pennsylvania

Cumberland

D-7126 ( 7-09 )

County

Municipality

Project Number

State of Fed. Project No.

( If Applicable )

The undersigned deponent deposes and says that he is the of the

BY

Sworn to and subscribed before me the undersigned notary public this day of , .

Notary Public

My Commission expires

(Contractor) competitive bidding in connection with such contract.

into any agreement, participated in any collusion, or otherwise taken any action in restraint of free

Company; that he is authorized to make this

Publication 408, as amended and that the said company has not, either directly or indirectly, entered affidavit on behalf of said company in compliance with section 102.06 (e) of Department Specifications, CumberlandCounty of

ANTI-COLLUSION AFFIDAVIT

Cumberland County

Mount Holly Springs Borough

Pennsylvania

MS-NCP

MUNICIPALITY

Name of Contractor

Performance of work as specified on the above numbered contract is completed and final pavement inspection has been made by the contractor and municipality in accordance with the terms of the contract awarded.

DATE OF AWARD

Both copies of this form to be filled by the Contractor-Municipality on completion of final pavement restoration.

*DATE

period of one year from this date.

* The contractor is responsible for maintenance of permanent pavement repairs for a

By the affixing of my signature I hereby certify that final

NOTICE OF COMPLETION

IN REFERENCE TO PROJECT #

accordance with the above contract # and is hereby accepted inspection has been made and all work has been performed in

FINAL COMPLETION CERTIFICATE

THIS PORTION TO BE COMPLETED BY MUNICIPALITY

Authorized Agent for the Municipality by the municipality as completed.

Mount Holly Springs Borough

Signature of Contractor

Signature of Municipality

File details come from the government source that posted it. Updated .