This Description of Requirements document outlines specifications for 85 firemen's boots to be delivered to the Supervisor of Shipbuilding, Gulf Coast in Pascagoula, Mississippi. The boots are required to support a new ship under construction and must be delivered within 30 days of order receipt between the hours of 8:00 AM and 3:30 PM Central Time, Monday through Friday. Boot sizes and quantities range from size 9 to size 14. Payment will be made monthly in arrears via electronic funds transfer. Inspection and acceptance will occur at the destination facility, where USS Richard McCool personnel will inspect for quality and defects. The contractor is responsible for quality control and delivery of items in accordance with FAR terms. Access to the Navy installation requires enrollment in the Defense Biometric Identification System for background checks, identity verification, and installation access authorization.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION OF REQUIREMENTS (DOR)
DAMAGE CONTROL EQUIPMENT
1.0 INTRODUCTION
SUPSHIP Pascagoula New Constructions requires 85 Firemen Boots in support of the new ship currently under construction. US Navy ships are required to carry Damage Control Equipment onboard.
2.0 REQUIREMENTS
PHYSICAL CHARACTERISTICS
LINE # ITEM NUMBER DESCRIPTION
REGULAR
SIZE
QTY
1 8430-00-753-5939 BOOTS, FIREMEN 9 1
2 8430-00-753-5940 BOOTS, FIREMEN 10 28
3 8430-00-753-5941 BOOTS, FIREMEN 11 28
4 8430-00-753-5942 BOOTS, FIREMEN 12 1
5 8430-00-753-5943 BOOTS, FIREMEN 13 16
6 8430-00-753-5944 BOOTS, FIREMEN 14 11
3.0 DELIVERY
The vendor must deliver the Boots 30 Days After Receipt of Order (ARO) and the delivery shall take place between the core business hours of 8:00 AM - 3:30 PM Central Time, Monday through Friday and shall not include after-hours, weekends, and holidays.
4.0 DELIVERY LOCATION
SUPERVISOR of SHIPBUILDING, GULF COAST 2000 Jerry St Pe’ Hwy, Bldg. 2039 Pascagoula, MS 39567
Note: Deliver to Huntington Ingalls Shipbuilding COSAL Warehouse Marked for USS Richard McCool, LPD-29.
4.1 METHOD OF PAYMENT
Payment for this contract shall be made via DFAS Electronics Funds Transfer (EFT) utilizing the Wide Area Work Flow (WAWF) System. The contractor is required to register and setup an account in the WAWF System in order to receive payment. The Government reserves the right to change this payment method through other means only by a contract modification if necessary. Payment shall be Monthly in Arrears.
4.2 INSPECTION REQUIREMENTS
USS RICHARD M MCCOOL personnel will perform inspection of received items. Inspection and acceptance will be conducted at Destination/Government facility. The items will be inspected by using visual inspection for quality and defect. Any defects or issues detected will be communicated back to the supplier/OEM for replacement and/or repair IAW the company’s and FAR warranty clause.
4.3 QUALITY
Quality Control is the responsibility of the Contractor. The Contractor is responsible for the delivery of quality supplies to the Government in accordance with (IA W) the terms and conditions contained in Federal Acquisition Regulation (FAR) Subpart 52.212-4 Contract Terms and Conditions - Commercial Products and Commercial Services.
5.0 DEFENSE BIOMETRIC IDENTIFICATION SYSTEM (DBIDS)
Defense Biometric Identification System (DBIDS). The Defense Biometric Identification System (DBIDS) is a DoD-owned and operated system developed by Defense Manpower Data Center as a force protection program to manage personnel identity and access at DoD installations. DBIDS is a network database system designed to easily verify access authorization of personnel entering military installations by using barcodes and fingerprint biometric identifications.
To improve management and force protection at Navy installations, the Navy is transitioning from using the Navy Commercial Access Control System (NCACS) to the Defense Biometric Identification System (DBIDS) for Contractors and vendors requiring access to an installation at no cost to them. The transition will begin 17 April 2017 and individuals will have up to 180 days to obtain the permanent card. After August 14, 2017, NCACs cards will no longer be accepted.
In order to obtain base access, an individual need to acquire DoD sponsorship, have a thorough identity check, be properly vetted, and have a legitimate reason for base access. Identity checks require a passport or a Real ID Act-compliant state driver's license. Vetting occurs when the individual's background and ID are compared against authoritative criminal justice data bases, and the individual has a letter or official document from the sponsoring organization which articulates the reason for access. When the above criteria are satisfactorily met, DBIDs credentials are issued.
NCACS cardholders will have 120 days from April 17, 2017 to obtain a temporary DBIDS paper pass. After the applicant obtains their DBIDS paper pass, they will have an additional 180 days to obtain an actual DBIDS card at no cost. Those requesting new access onto installations will receive the DBIDS card at the same time they are initially approved for access. After August 14, 2017, NCACS cards will no longer be accepted for installation access.
Additional information is available at https://www.cnic.navy.mil/om/dbids.html.