This is a Statement of Work for USS KEARSARGE (LHD-3) requesting equipment rental services to support an INR 250 Reception onboard the vessel.

The contractor shall provide four 4-stall executive porta-potty restroom trailers to accommodate a 400-guest reception. All equipment must be delivered by 26 June 2026, with the reception scheduled for 04 July 2026. Rented items will remain onboard until the vessel returns to port on 10 July 2026, for a total rental period of 15 days. All electrical equipment must be certified safe for shipboard use and meet applicable NAVSEA and fire performance standards. The contractor is responsible for removing and disposing of any hazardous materials brought onboard, with no hazardous materials to be left unattended. Delivery must occur during permitted working hours of 0700-2200. Questions should be directed to Dave Vaughn at david.e.vaughn6.civ@us.navy.mil.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

1. Purpose:

USS KEARSARGE (LHD-3) requests consideration of contracting services for the rental of equipment to support the INR 250 Reception being held on board.

2. Period of Performance:

The required delivery date for all items is 26 June 2026. The reception will be held on 04 July 2026. Rented items will remain onboard until the vessel returns to port on 10 July 2026.

Total number of rental days is 15.

3. Breakdown of Requirements:

The contractor shall provide the following rental items for a 400-guest reception.

Category Item Quantity Executive Porta-Potties 4-Stall Restroom Trailer 4

Note: All items will remain onboard from the time of delivery until the ship returns to port on 10 July 2026.

4. General Requirements:

a. All electrical equipment must be safe for shipboard use and meet all applicable NAVSEA and fire performance standards.

b. The use of proper personal protective equipment is highly encouraged during loading and setup.

c. It is the responsibility of the contractor to remove and dispose of any hazardous material they bring onboard. No hazardous materials are to be left unattended at any time.

5. Permitted Working Hours for Delivery:

0700-2200

6. Point of Contact:

Please forward any questions to Dave Vaughn at david.e.vaughn6.civ@us.navy.mil.

mailto:david.e.vaughn6.civ@us.navy.mil

File details come from the government source that posted it. Updated .