1.03_CDRLS TIN 310_21YRA39.pdf

PDF 169 KB Posted

Attached to
High-pressure air compressor - repair, qty 1
Solicitation number
N0010421QF020
Issued by

View the file

Other files

File Type Posted
3.00_Solicitation#N0010421QF020_21YRA39.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REFURB INST. NO. 5130-012-0729 Rev E Chg-2

DD Form 1423, JUN 90 Previous editions are obsolete Encl (4) Page 1 of 4

CONTRACT DATA REQUIREMENTS LIST

A. CONTR. LINE ITEM NO. B. EXHIBIT A C. CATEGORY: XX TDP TM OTHER

D. SYSTEM/ITEM HPAC

REFURBISHMENT

E. CONTRACT/PR NO. F. CONTRACTOR DRESSER-

RAND

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUHORITY (Data Item Descript) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ. 9. DIST STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF

FIRST

SUBMISSION

14. DISTRIBUTION

DR - DRAFT

RG - REGULAR

RP - REPRO

8. APP CODE 11. AS OF

DATE

13. SUBSEQUENT

SUBMISSION

16. REMARKS

1. A001 2. SUBMEPP INSPECTION REPORTS 3.

N/A

4. DI-MGMT-80389C (SUBRIR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

7. DD

9. DIST

STATEMENT

REQUIRED

D

10. AS

12. AS REQUIRED

14. DISTRIBUTION

b.

Copies

8. N/A

11. 0 13 AS REQUIRED D

R

R G

R P

16. Remarks: Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible See Enclosure 1.

DODACC N45404 1

NAVSUP WSS N743

NAVSUP WSS N97121 1

TOTAL 3

1. A002 2. SUBMEPP CONDITION REPORT

3. N/A

4. DI-MGMT-82048 (SUBCR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP b.

Copies

11. 13. AS REQUIRED D

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Contractor own format is acceptable.

TOTAL 3

G. PREPARED BY

//s// T. C. Chan 1846TC

H. DATE

4/27/21

I. APPROVED BY

//s// Stacy Woodley 1831SW

J. DATE

4/27/21

A. CONTR. LINE ITEM NO. B. EXHIBIT A C. CATEGORY:

XX TDP TM OTHER

D. SYSTEM/ITEM HPAC REFURBISHMENT E. CONTRACT/PR NO. F. CONTRACTOR

DRESSER-RAND

1. A003 2. SUBMEPP UNPLANNED PARTS USAGE REPORTS 3. N/A

4. DI-MISC-80678 (SUBUPUR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

7. DD

9. DIST

STATEMENT

Required

b. Copies

11. 0

13. AS REQUIRED D

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Contractor own format is acceptable. Report data to be traceable to Rotatable Pool Serial No. Unplanned parts listed shall include prices

DODACC N45404 1

NAVSUP WSS N743 1

NAVSUP WSS N97121 1

TOTAL 3

1. A004 2. REASSEMBLY QUALITY ASSURANCE REPORT (RQAR). 3. N/A

4. DI-QCIC-81890 (SUBRQAR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

7. DD

9. DIST

STATEMENT

11.

13. AS REQUIRED D

R

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Contractor own format is acceptable.

TOTAL 3

1. A005 2. SUBMEPP WELDING PROCEDURES &

WELDING PROCEDURE QUAL. TEST REPORT

3. N/A

4. DI-MISC-80875A (SUBWP) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

7. DD 9. . DIST

10. AS REQUIRED 12. AS REQUIRED

b Copies 8.

Acceptance required prior to welding

11.

13. AS REQUIRED D

R

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Weld procedures are required to meet the requirements within NAVSEA

S9074-AR-GIB-010/278.

NAVSUP WSS N743 1

NAVSUP WSS N97121 1

COPY IN CRATE 1

TOTAL 4

G. PREPARED BY

//s// T. C. Chan 1846TC

H. DATE

4/27/21

I. APPROVED BY

//s// Stacy Woodley 1831SW

J. DATE

DD Form 1423, JUN 90 Previous editions are obsolete Encl (4) Page 2 of 4

A. CONTR. LINE ITEM NO.

B. EXHIBIT A C. CATEGORY: XX TDP TM OTHER

D. SYSTEM/ITEM HPAC REFURBISHMENT E. CONTRACT/PR NO.

F. CONTRACTOR DRESSER-RAND

1. A006 2. SUBMEPP TEST PROCEDURE 3. Certification of Compliance

4. DI-MISC-80678 (SUB-NDT) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

REQUIRED

D

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work

Work Flow) to the maximum extent possible. NDT procedures are required to meet the requirements within NAVSEA T9074-AS-GIB-010/271.

DODACC N45404 1

NAVSUP WSS N743 1

NAVSUP WSS N97121 1

TOTAL 3

1. A007 2. SUBMEPP REPAIR PROCEDURE 3. MAGNETIC PARTICLE TEST PROCEDURES

4. DI-MGMT-81580 (SUB-RP) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Contractor own format is acceptable.

TOTAL 3

1. A008 2. SUBMEPP TEST INSPECTION REPORT 3. N/A

4. . DI-NDTI-80809B (SUB-NDTR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

7.DD

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible.

NAVSUP WSS N743 1

NAVSUP WSS N97121 1

TOTAL 3

1. A009 2. SUBMEPP Operational Test Data Reports 3.

4. DI-MISC-808678 (SUBOTDR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

9. . DIST

REQUIRED

D

14 . DISTRIBUTION

11. 0 13. AS REQUIRED D

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Contractor own format is acceptable.

SUBMEPP CODE 1831 1

NAVSUP WSS N743 1

NAVSUP WSS N97121

TOTAL 3

G. PREPARED BY

//s// T. C. Chan 1846TC

H. DATE

4/27/21

I. APPROVED BY

//s// Stacy Woodley 1831SW

J. DATE

DD Form 1423, JUN 90 Previous editions are obsolete Encl (4) Page 3 of 4

A. CONTR. LINE ITEM NO.

B. EXHIBIT A C. CATEGORY: XX TDP TM OTHER

D. SYSTEM/ITEM HPAC REFURBISHMENT E. CONTRACT/PR NO.

F. CONTRACTOR DRESSER-RAND

1. A010 2. SUBMEPP Noise Test Data Report 3.

4. DI-MISC-80678 (SUBNTDR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

REQUIRED

D

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Contractor own format is acceptable. DODACC N45404 1

NAVSUP WSS N743 1

NAVSUP WSS N97121 1

COPY IN CRATE 1

TOTAL 4

1. A011 2. SUBMEPP Certification of Compliance 3. Certification of Compliance

4. DI-MISC-80678 (SUBCC) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Aera Work Flow) to the maximum extent possible. Contractor own format is acceptable Certifying that each Item has been refurbished per para 5 & tested per para 6. One report for each Item, identifiable to the unique Ser. Nos.

Include a positive statement indicating if welding or NDT were accomplished, identify the procedures used used & identify any welding accomplished that that did not require weld procedure qualification tests

COPY IN CRATE 1

TOTAL 4

1. A012 2. SUBMEPP Final Inspection Report 3.

4. DI-QCIC-81068 (SUBFIR) 5. RI 5130-012-0729 Rev E Chg -2 6. SUBMEPP

9. . DIST

REQUIRED

D

14 . DISTRIBUTION

11. 0 13. AS REQUIRED D

R G

R P

16. REMARKS Certification documentation must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. Use Enclosure (2)

SUBMEPP CODE 1831 1

NAVSUP WSS N743 1

NAVSUP WSS N97121

COPY IN CRATE 1

TOTAL 4

G. PREPARED BY

//s// T. C. Chan 1846TC

H. DATE

4/27/21

I. APPROVED BY

//s// Stacy Woodley 1831SW

J. DATE

DD Form 1423, JUN 90 Previous editions are obsolete Encl (4) Page 4 of 4

File details come from the government source that posted it. Updated .