1.02 SOW- CCTV APL-15, 69, YRBM-20.pdf
PDF 108 KB Posted
- Attached to
- CCTV Equipment
- Solicitation number
- N00244-25-Q-S052
About this file
This Statement of Work (SOW) details a video surveillance system upgrade for three U.S. Navy COMPACFLT Berthing and Messing Barges (APL-15, APL-69, and YRBM-20). The project requires procuring and installing 14 IP cameras at various exterior locations on each barge, along with a comprehensive hardware package including a 4U rackserver, hard drives, video management system server, and associated licenses. Specific equipment includes Milestone XProtect software, XNV-6080RSA 2MP network stainless IR dome cameras, mounting hardware, and 2,200 feet of CAT5e cabling.
The project has a 60-day delivery timeline and will be inspected and accepted at the destination address in San Diego, VA. The upgrade is necessary to modernize outdated surveillance systems and ensure continued functionality for the U.S. Navy. The materials and collected data will be reviewed and accepted by the Barge Administrator, with all equipment to be procured in accordance with the specified NAVSEA Drawing 401-8680128.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought.pdf | ||
| Specs Materials YRBM-20.pdf | ||
| NAVSEA Drawing 401-8680128.pdf | ||
| Specs Materials APL-15.pdf | ||
| Specs Materials APL-69.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Video Surveillance System Upgrade on APL-15, APL-69, and YRBM-20 COMPACFLT Berthing and Messing Barges
1.0 SCOPE
This Statement of Work (SOW) specifies the general requirements for upgrading the Closed-Circuit Television (CCTV) Video Surveillance systems on the APL- 15, APL-69, and YRBM-20 COMPACFLT Berthing and Messing Barges.
1.1 GENERAL
COMPACFLT Messing and Berthing Barges require service life upgrades necessary to ensure continued functionality for the U.S. Navy. Currently, those materials are out of date or have come to their end of life. These upgrades bring the CCTV video surveillance systems to current, modern specifications.
1.2 DELIVERY:
60 Days ACD
1.3 INSPECTION and ACCEPTANCE / FOB
Inspection and acceptance shall be at destination.
Ship to address is:
COMPACFLT Berthing and Messing Program 3755 Brinser St. Suite 4 San Diego, VA 92136
2.0 DETAILS
The proposed requirements for this SOW are as follows:
2.1 Equipment
Procure all equipment in accordance with the List of Materials outlined on NAVSEA Drawing 401-8680128.
2.3 Locations - Cameras
14 IP cameras covering the exterior of barge with materials referenced in NAVSEA Drawing 401-8680128:
*01 Level Forward Bulkhead, Frame 9, Port, Looking Forward *01 Level Forward Bulkhead, Frame 9, Starboard, Looking Forward Main Deck, Frame 15, Port, Looking Forward Main Deck, Frame 15, Port, Looking Aft
Main Deck, Frame 15, Starboard, Looking Forward Main Deck, Frame 15, Starboard, Looking Aft Main Deck, Frame 21, Port, Looking Forward Main Deck, Frame 21, Port, Looking Aft Main Deck, Frame 21, Starboard, Looking Forward Main Deck, Frame 21, Starboard, Looking Aft Main Deck, Frame 26, Port, Looking Forward Main Deck, Frame 26, Port, Looking Aft Main Deck, Frame 26, Starboard, Looking Forward Main Deck, Frame 26, Starboard, Looking Aft
2.4 Hardware
In the CCTV rack located on the barge quarterdeck.
(1) CSN RS25 - 4U Rackserver for 25x IP Cameras
* Recording server, 4U Rack space
* 3x HDD bays
(3) WD Purple 8TB, 3,5" SATA 24/7
(1) Programing of CCTV Server and Cameras
(1) Installation of CCTV Video Management System Server
(1) Milestone XProtect, Express+ Base License
(14) Milestone XProtect, Express+ Camera License
(14) Registration of 1x camera on CCTV Server
3.4.1 Hardware Cameras
(14) XNV-6080RSA 2MP Network Stainless IR Dome Camera
(14) SBP-300HM6S Hanging mount Stainless steel adapter for XNV
(14) SBP-300WMS Wall mount bracket for XNV and QNP
2.5 Cabling
Procure 2,200 feet of CAT5e cable Line Item 11 of NAVSEA Drawing 401- 8680128.
3.0 ACCEPTANCE PLAN
Materials used, and collected data required under this task will be made available for review and to ensure compliance and accepted by the Barge Administrator.