This is a Project Manual and Bid Package for the Wyomissing Firehouse Restoration Project, issued by the Borough of Wyomissing in Berks County, Pennsylvania. The project involves restoration of the exterior portion of the Wyomissing Fire Department firehouse located at 1259 Penn Ave, Wyomissing, Pennsylvania. Work includes exterior facade washing, damaged brick replacement, mortar joint repointing, water damage repair with stainless steel drip installation, roof termination bar covering, window and door lintel treatment, and water repellant application. Sealed bids are due by 11:00 am on March 11, 2026, submitted online through the PennBid Program. The bidder inquiry deadline is 12:00 pm on March 4, 2026, with no responses provided for requests received after that date. Bids will be publicly opened at 11:00 am on March 11, 2026, with the bid tabulation made available immediately. The Borough reserves the right to hold bids for up to 60 days for review and investigation of bidder qualifications. Contract award is scheduled for 7:00 pm on April 7, 2026. The contractor must substantially complete the work within 90 calendar days from the Notice to Proceed, with an earliest start date of May 6, 2026, and an estimated completion date of November 2, 2026.
Bids must be accompanied by a 10 percent bid security in the form of a cashier's check, certified check, or bid bond payable to the Borough of Wyomissing. Upon contract award, the successful bidder must provide performance bonds, payment bonds, maintenance bonds, and insurance documentation within ten days to secure the Notice of Award. The contract includes liquidated damages assessed at $1,000 per calendar day for failure to achieve Substantial Completion. Prevailing wage requirements apply per the Pennsylvania Labor & Industry Wage Rates. The project is funded in part by the Multimodal Transportation Fund (MTF) Program with partial reimbursement under the Commonwealth Financing Authority (CFA), requiring bidders to comply with grant agreement requirements and CFA procedures. The Borough retains the right to delete all or portions of the project in its sole discretion, with compensation adjustments determined by the Engineer or through dispute resolution if parties cannot agree. No escalator clauses apply. Progress payments will be made monthly with 10 percent retainage until 50 percent completion, then 5 percent thereafter, with final payment due within 30 days of Engineer recommendation subject to all punch list items completion and required documentation submission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-Division 01 Bid Docs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL FOR:
WYOMISSING FIRE DEPARTMENT
RESTORATION PROJECT
Wyomissing Borough, Berks County, PA
Issued for Bid – February 11, 2026
Bid Due – 11:00 am on March 11, 2026
Awarded – 7:00 pm on April 7, 2026
OWNER:
WYOMISSING BOROUGH
22 READING BOULEVARD
WYOMISSING, PA 19610
610-376-7481
ENGINEER:
McCARTHY ENGINEERING ASSOCIATES
1011 N. PARK ROAD
SUITE 100
WYOMISSING, PA 19610
610-373-8001 www.mccarthy-engineering.com
PROJECT No. 260004
McCarthy #260004 FIREHOUSE RESTORATION Wyomissing Borough Berks County
TABLE OF CONTENTS 00004 - 1
GENERAL
DIVISION 0 – BIDDING REQUIREMENTS AND CONTRACT FORMS
*For Bidding
*001113 ADVERTISEMENT FOR BIDS
*002113 INSTRUCTIONS TO BIDDERS
*004143 BID FORM
*004313 BID SECURITY FORM
*004314 NON-COLLUSION AFFIDAVIT
004324 CHANGE ORDER FORM
005000 AGREEMENT
005100 NOTICE OF AWARD
005101 NOTICE OF INTENT TO AWARD
005102 NOTICE TO PROCEED
005103 CERTIFICATE OF SUBSTANTIAL COMPLETION
006100 PERFORMANCE BOND
006101 MAINTENANCE BOND
006102 PAYMENT BOND
006103 STATEMENT OF SURETY COMPLETION
006500 CONTRACTOR’S QUALIFICATION STATEMENT
007000 GENERAL CONDITIONS
008000 SUPPLEMENTAL CONDITIONS
008200 PREVAILING WAGE REQUIREMENTS & MOU
008300 WAIVER OF LIENS
008400 WORKMEN’S COMPENSATION AFFIDAVIT
008500 CERTIFICATE OF INSURANCE REQUIREMENTS
008600 PUBLIC WORKS EMPLOYMENT VERIFICATION FORM
CERTIFICATE OF RELEASE
CERTIFICATION STATEMENT
DIVISION 1 - GENERAL REQUIREMENTS
011000 SUMMARY OF WORK
012000 PRICE AND PAYMENT PROCEDURES
013000 ADMINISTRATIVE REQUIREMENTS
013216 CONSTRUCTION PROGRESS SCHEDULE
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017000 EXECUTION AND CLOSEOUT REQUIREMENTS
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
ADVERTISEMENT FOR BIDS
WYOMISSING FIREHOUSE RESTORATION PROJECT
Sealed proposals will be received by the Borough of Wyomissing, online via the PennBid™ Program, until 11:00 am, on Wednesday, March 11, 2026 for the Wyomissing Firehouse Restoration Project.
The work will consist of restoration of the exterior portion of the Wyomissing Fire Department firehouse located at 1259 Penn Ave, Wyomissing, Pennsylvania. The scope of work includes but is not limited to:
washing of exterior façade, replacing damaged brick, rout out and repoint mortar joints, repair water damaged elements and install stainless steel drips, covering of exposed roof termination bar, treat window and door lintels, and application of water repellant to the exterior for the Wyomissing Fire Department Restoration Project.
Bidders must conform to the General Conditions and detailed Specifications in the bid package. All documents and solicitation details are available at no cost at PennBid™ - www.PennBid.net.
Only questions submitted online via PennBid™ shall be considered. Responses will be provided on the website and be visible to all Bidders. Any changes to the plans or specifications will be provided as an Addendum and notice will be given to Bidders through the website via email. No responses will be provided for requests received after 12:00 pm on March 4, 2026.
The bids will be opened and the bid tabulation summaries will be made publicly available on Wednesday, March 11, 2026 at 11:00 am (local time) on PennBid™. Bids may be held by the Borough of Wyomissing for a period not to exceed 60 days from the date of Bid opening for the purpose of reviewing the Bids, receipt of government approvals, and investigating the qualifications of Bidders, prior to awarding the Contract. Bids may be publicly awarded on April 7, 2026 at 7:00pm (local time) at the Borough of Wyomissing at 22 Reading Blvd Wyomissing, PA 19610.
The bid must be accompanied by a Cashier’s Check, Certified Check, or Bid Bond in the amount of Ten Percent (10%) of the bid, made payable to the Borough of Wyomissing. Also required are a properly executed Bid Form, Non-Collusion Affidavit, Certification Statement, and Contractor’s Qualification Statement. The successful bidder shall also be required to provide a Performance Bond in the amount of one hundred percent (100%) of the Contract amount within ten (10) calendar days of written notice of acceptance of the Bid.
The Borough of Wyomissing reserves the right to reject any or all proposals or to accept any portion of any bid, and to award Contracts as is deemed best for the Borough. The Borough of Wyomissing also reserves the right to waive any defects, errors, omissions, irregularities, or informalities in bids received.
Michele Bare, Borough Manager Borough of Wyomissing http://www.pennbid.net/
McCarthy #260004 FIREHOUSE RESTORATION Borough of Wyomissing
EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
Page Article 1 – Defined Terms
Article 2 – Copies of Bidding Documents
Article 3 – Qualifications of Bidders
Article 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 5 – Bidder’s Representations
Article 6 – Pre-Bid Conference
Article 7 – Interpretations and Addenda
Article 8 – Bid Security
Article 9 – Contract Times
Article 10 – Liquidated Damages
Article 11 – Substitute and “Or-Equal” Items
Article 12 – Subcontractors, Suppliers, and Others
Article 13 – Preparation of Bid
Article 14 – Basis of Bid
Article 15 – Submittal of Bid
Article 16 – Modification and Withdrawal of Bid
Article 17 – Opening of Bids
Article 18 – Bids to Remain Subject to Acceptance
Article 19 – Evaluation of Bids and Award of Contract
Article 20 – Bonds and Insurance
Article 21 – Signing of Agreement
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 1
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – on PennBid.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the advertisement or invitation to bid.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall submit with its Bid
(a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:
A. Evidence of Bidder’s authority to do business in the state where the Project is located
B. Bidder’s state or other contractor license number, if applicable
C. Subcontractor and Supplier qualification information; coordinate with provisions of Article 12 of these Instructions, “Subcontractors, Suppliers, and Others.”
D. Other required information regarding qualifications
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF
SITE; OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE
4.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 2
4.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify:
a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.
b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).
c. reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.
4.03 Site Visit and Testing by Bidders
A. Bidder shall conduct the required Site visit during normal working hours and shall not disturb any ongoing operations at the Site.
B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 3
doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.
D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
4.04 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.
4.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 5 – BIDDER’S REPRESENTATIONS
5.01 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;
B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;
E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 4
means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;
F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work; and
J. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
ARTICLE 6 – PRE-BID CONFERENCE
6.01 A pre-Bid conference is not required for the scope of this project.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and
6.02 of the General Conditions.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required Performance Bond, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required Performance Bond within 10 days
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 5
after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 90 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 – LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Supplementary Conditions.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.
12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the any portions of the Work.
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 6
If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.
ARTICLE 13 – PREPARATION OF BID
13.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink. Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown. The corporate seal (optional) may be affixed and attested by the corporate secretary or an assistant corporate secretary.
13.03 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
13.04 A Bid by an individual shall show the Bidder’s name and official address.
13.05 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.
13.06 All names shall be printed in ink below the signatures.
13.07 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.08 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 7
13.09 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
ARTICLE 14 – BASIS OF BID
14.01 Base Bid with Alternates
A. Bidders shall submit the base Bid in the same format as the Bid Form and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.
14.02 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Unit Price Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
14.03 Allowances
A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
14.04 Price-Plus-Time Bids
A. The Owner will consider the time of Substantial Completion commitment made by the Bidder in the comparison of Bids.
B. Bidder shall designate the number of days required to achieve Substantial Completion of the Work and enter that number in the Bid Form as the total number of calendar days to substantially complete the Work.
C. The total number of calendar days for Substantial Completion designated by Bidder shall be less than or equal to a maximum of 90. If Bidder purports to designate a time for Substantial Completion that is less than the allowed minimum, or greater than the allowed maximum, Owner will reject the Bid as nonresponsive.
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 8
D. The Agreement as executed will contain the Substantial Completion time designated in Successful Bidder’s Bid, and the Contractor will be assessed liquidated damages at the rate stated in the Agreement for failure to attain Substantial Completion within that time.
E. Bidder shall also designate the time in which it will achieve Milestones and achieve readiness for final payment. Such time commitments shall be consistent with the “Time of Substantial Completion” to which Bidder commits. The Agreement as executed will contain, as binding Contract Times, Successful Bidder’s time commitments regarding Milestones, as applicable, and readiness for final payment.
14.05 Escalator Clause
A. No escalator clause shall apply for this scope of work.
ARTICLE 15 – SUBMITTAL OF BID
15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Security (Bond) Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.
15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid.
15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.
ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.
16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.
ARTICLE 17 – OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 9
ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.
19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.
19.03 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form. To determine the Bid prices for purposes of comparison, Owner shall announce to all bidders a “Base Bid plus alternates” budget after receiving all Bids, but prior to opening them.
For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its additive alternate Bids for which Owner determines funds will be available at the time of award.
C. Bid prices will be compared after adjusting for differences in time of Substantial Completion (total number of calendar days to substantially complete the Work) designated by Bidders. The adjusting amount will be determined at the rate set forth in the Agreement for liquidated damages for failing to achieve Substantial Completion, or such other amount that Owner has designated in the Bid Form.
1. The method for calculating the lowest bid for comparison will be the summation of the Bid price shown in the Bid Form plus the product of the Bidder-specified time of Substantial Completion times the rate for liquidated damages $600.00 per day.
2. This procedure is only used to determine the lowest bid for comparison and contractor selection purposes. The Contract Price for compensation and payment purposes remains the Bid price shown in the Bid Form.
19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
INSTRUCTION TO BIDDERS – ADDENDUM 1 002113 - 10
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 20 – BONDS AND INSURANCE
20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by required bonds and insurance documentation.
ARTICLE 21 – SIGNING OF AGREEMENT & FILING OF FORMS
21.01 Contract forms are to be submitted as outlined in the Invitation to Bid, Bid Form, Notice of Intent to Award, Notice of Award, and/or Agreement according to the following timelines.
A. At the time of the initial bid, submit the Bid Form, Bid Security, Certification Statement, Non- Collusion Affidavit, Qualification Statement, Blank Waiver of Liens, and Bidder Responsibility Questionnaire.
B. After opening and review of bids, OWNER or ENGINEER/ARCHITECT will send the Notice of Intent to Award to the apparent lowest qualified bidder. The form of this Notice is to be returned with the following within 10 days in order to secure the Notice of Award (actual award):
1. PERFORMANCE BOND
2. MAINTENANCE BOND
3. PAYMENT BOND
4. Insurance Certificates
5. PA Labor Compliance MOU
6. Workmen’s Compensation Affidavit, and
7. Public Works Employment Verification Form.
C. Upon receipt of these forms, the Notice of Award will be sent, which must be signed and returned along with the Agreement within a second period of 10 days.
D. Within 10 days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
E. The Statement of Surety Company (004315) and Waiver of Liens (008300) shall be submitted in accordance with instructions indicated on those forms relative to requests for payment.
However, the general Lien Waiver Agreement shall be submitted within 10 days of the executed Agreement and no less than 10 days before Work begins.
BID FORM 004143 - 1
BID FORM
NAME OF PROJECT: WYOMISSING FIREHOUSE RESTORATION PROJECT
ADDRESS OF PROJECT: BOROUGH OF WYOMISSING, BERKS COUNTY, PA
OWNER: Borough of Wyomissing 22 Reading Boulevard Wyomissing, PA 19610 ATTN: Michele Bare, Council Manager
BASE BID
In compliance with the Project Manual, the undersigned, having carefully examined the Bidding Documents and having had the opportunity to visit the site and examine all conditions affecting the work, proposes to do all such work, including the furnishing of all necessary labor, machinery, equipment, materials, supplies, transportation and incidentals as required by the Bidding Documents, for the sum of:
Total Bid Sum:
Sum expressed in words
Dollars $ Sum expressed in words (continued) Sum expressed in figures
SCHEDULE
If awarded a contract for the work described by the Contract Documents, the undersigned will complete the work, without exception, in the following number of calendar days from the time of issuance of the Notice to Proceed:
Total Number of Calendar Days to Complete the Work 180 Days
Earliest Start Date May 6, 2026
Estimated Date of Final Completion November 2, 2026
SCHEDULE OF VALUES/PRICES:
BASE BID
ITEM EST. UNIT TOTAL
NO. DESCRIPTION QTY. UNIT PRICE AMOUNT
100 – SOUTH ELEVATION
101. Clean Exterior Facade 1 LS $ $
102. Cut out and Repoint Mortar Joints 8 LF $ $
103. Cut and Replace 8 x 8 Bricks 1 EA $ $
BID FORM 004143 - 2
104. Apply Water Repellant on Glass Block Sills 5 SF $ $
105. Repair Damaged Limestone Coping with Color Matching Limestone Repair Mortar 1 EA $ $
106. Repair Previous Anchors in utility Brick With Color Matching Brick Repair Mortar 1 EA $ $
106. Post Mortar Wash Repointed Areas 1 LS $ $
200 – EAST ELEVATION
201. Clean Exterior Facade 1 LS $ $
202. Cut out and Repoint Mortar Joints 12 LF $ $
203. Cut and Replace 8 x 8 Bricks 5 EA $ $
204. Apply Water Repellant on Glass Block Sills 8 SF $ $
205. Cut Out Joints Over Soldier Brick Heads And Install Stainless Steel Drip 11 LF $ $
206. Sand, Prime, and Paint Steel Lintel Heads 1 LS $ $
207. Post Mortar Wash Repointed Areas 1 LS $ $
300 – NORTH ELEVATION
301. Clean Exterior Facade 1 LS $ $
302. Cut out and Repoint Mortar Joints 12 LF $ $
303. Cut and Replace 8 x 8 Bricks 3 EA $ $
304. Cut Out Joints Over Soldier Brick Heads And Install Stainless Steel Drip 29 LF $ $
305. Sand, Prime, and Paint Steel Lintel
306. Remove Temporary Blocking at Window Head and Install Matching Utility Brick 3 EA $ $
307. Post Mortar Wash Repointed Areas 1 LS $ $
400 – WEST ELEVATION
401. Clean Exterior Facade 1 LS $ $
BID FORM 004143 - 3
402. Cut out and Repoint Mortar Joints 24 LF $ $
403. Cut and Replace 8 x 8 Bricks 3 EA $ $
404. Cut Out Joints Over Soldier Brick Heads And Install Stainless Steel Drip 20 LF $ $
405. Sand, Prime, and Paint Steel Lintel
406. Remove Temporary Blocking at Window Head and Install Matching Utility Brick 3 EA $ $
407. Post Mortar Wash Repointed Areas 1 LS $ $
408. Apply Water Repellant on Glass Block Sills 1 SF $ $
500 – ROOF ELEVATION
401. Clean Exterior Facade 1 LS $ $
402. Cut out and Repoint Mortar Joints 349 LF $ $
403. Cut and Replace 8 x 8 Bricks 3 EA $ $
404. Install Stainless Steel Flashing Cut Into Coping Stone 30 LF $ $
405. Install Elastomeric Coating on Chimney Cap 31 SF $ $
406. Install Water Repellant on 8 x 8 Brick Units 1 LS $ $
407. Post Mortar Wash Repointed Areas 1 LS $ $
408. Cut Out Joints and Install Stainless Steel Compression Reglet to Cover Exposed Termination Bar on 8 x 8 Brick 28 LF $ $
PROEJCT TOTAL $
ALTERNATE #1
A1. Apply Water Repellant on Entire Building Facade 1 LS $ $
PROEJCT TOTAL W/ ALTERNATE $
VALUE ENGINEERING:
The Bidder may at his/her option, provide value engineering suggestions and provide add/deduct amounts for such items.
BID FORM 004143 - 4
GOOD FAITH:
In submitting this Bid, Bidder represents, as set forth in the Agreement, that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Document, and the following Addenda, receipt of all which is hereby acknowledged.
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and test of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities).
E. Bidder has obtained and carefully studied (or assumes responsibility for having done so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.
F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by OWNER and others at the Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.
I. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by ENGINEER is acceptable to Bidder.
J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
K. Bidder further represents that this Bid is genuine and not in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of
BID FORM 004143 - 5
any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any individual or entity to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over OWNER.
L. Bidder acknowledges that the Borough of Wyomissing may delete all or a portion of the project, in one or more instances, in its sole discretion, which it deems appropriate. In such instance, the Borough of Wyomissing and the CONTRACTOR will deduct from the Contract price an amount equal to the value of the Work to be deducted including overhead and profit. If the parties do not agree as to the dollar amount of the deduction, the ENGINEER will render a decision which will be final and binding upon both parties.
M. The Bidder agrees to progress payments in accordance with Article 51 of the General Conditions and the Supplementary Conditions at such unit values as indicated in Section UNIT PRICES and the UNIT PRICES FORM (the total of the unit values and quantities being equal to the Total Bid Sum), as prepared by the Bidder.
N. The following documents are attached to and made a condition of this Bid:
1) Bid Security Form
2) Certification Statement
3) Non-Collusion Affidavit
4) Contractor’s Qualification Statement
5) Unit Prices Form (if not included herein)
6) Bidder Responsibility Questionnaire
7) Waiver of Liens (Blank)
O. Communications concerning this Bid shall be addressed to the address of Bidder indicated below or the following address:
Name:
Title:
Phone:
Fax:
Email:
CONCLUSION:
Contractors are requested not to bid on this Contract if they cannot adhere strictly to the following requirements. In submitting this bid we agree:
1. To hold our bid open for a period of ninety (90) calendar days past the date for receipt of bids.
2. To complete, sign, and submit with the bid the attached Certification Statement certifying that we have not been and are presently not suspended, debarred or otherwise precluded by any Federal or State entity from the benefits which may result from obtaining this Contract.
3. To complete, sign, and submit with the bid the attached Non-Collusion Affidavit and the Contractor’s Qualification Statement.
4. To submit a Bid Security in accordance with the attached form in the sum of 10% of the Bid Total which is to become the property of the Owner in the event the Contract and
BID FORM 004143 - 6
Bond are not executed within the time above set forth as liquidated damages for the delay and additional expense to the Owner caused thereby.
5. To enter into and execute a contract, if awarded on the basis of this bid, and to furnish performance and payment bonds in accordance with the Instructions to Bidders and Supplementary Conditions.
6. To accomplish the work in accordance with the Contract Documents.
7. To comply with the County CRP conditions.
The Undersigned hereby acknowledges the receipt of the following Addenda to the Contract Documents.
Addendum No. 1 ________________________________, dated ___________________.
Addendum No. 2 ________________________________, dated ___________________.
Addendum No. 3 ________________________________, dated ___________________.
(Signatures)
Respectfully submitted by Authorized Signing Officer:
Signature Date
Printed Name
Title
Company Name and Address
If Partnership, list full names of all partners
If Corporation, affix Corporate Seal and list state of incorporation
State (Affix Seal)
END OF SECTION 004143
BID SECURITY FORM 004313 - 1
BID BOND/SECURITY FORM
KNOW ALL MEN BY THESE PRESENTS, that
_____________________________________________, as Principal, and (Name of Contractor)
_____________________________________________, as Surety, (Name of Surety) a corporation duly organized under the laws of the State of ________________, licensed to do business in the State of Pennsylvania, are held and bound unto the Borough of Wyomissing, as the Obligee, in the sum of ten percent (10%) of the amount bid, for payment of which the Principal and Surety, bind themselves, jointly and severally.
Surety and Principal understand and agree that this Bond has been requested, and is given, as bid security under the provisions of the Contract Documents and requirements. This Bond is submitted as a condition precedent for Obligee's consideration of Principal's bid, as evidence of the Principal's good faith (e.g., complying with Obligee’s bid procedures, such as providing bid documentation, and to fully indemnify the Obligee for Obligee's benefit against any possible failure or refusal by the Principal to enter into any written contract that may be awarded to it by the Obligee following the Obligee's acceptance of the Principal's bid.
The Principal expressly covenants that it will not withdraw the bid herewith submitted, will comply with the "AWARD OF CONTRACT" provision contained in Principal's PROPOSAL, and, if it is awarded the contract, will, within the time stated in the "AWARD OF CONTRACT" provision, enter into a formal contract and give a good and sufficient bond to secure the performance of the terms and conditions of the contract.
Signed this _______ day of ___________________, Year: ____, for Project Number_260004__
THE CONDITIONS OF THIS OBLIGATION ARE: that if Obligee accepts the bid of Principal and Principal enters into a contract with Obligee for the project and gives bond with good and sufficient surety for the faithful performance of such contract: or in the event of the failure of Principal to demonstrate its good faith or to enter into the contract and give the bond, if Principal pays to Obligee the difference (not to exceed the penalty hereof) between this bid amount and the amount for which Obligee legally contracts with another party to perform that work, if the latter amount be in excess of the former, then this obligation shall be null and void, otherwise to remain in full force and effect.
Name of Principal SEAL (if applicable)
** By:__________________________________
Name of Surety Company SEAL
** By:__________________________________
Title: __________________________________
** THIS BOND MUST BE SIGNED BY A DULY AUTHORIZED REPRESENTATIVE OF THE SURETY
AND THE PRINCIPAL. UNSIGNED BONDS ARE NOT RESPONSIVE AND A BID WILL BE
REJECTED IF THE BOND IS NOT PROPERLY SIGNED.
NOTE: A copy of the agent's Power of Attorney for the Surety Company must be attached to this bond form.
NON-COLLUSION AFFIDAVIT 1 of 3
BOROUGH OF WYOMISSING
NON-COLLUSION AFFIDAVIT
Contract/Bid No. .
I, , certify that I am the of .
[Name of Individual Executing Affidavit] [Title] [Contractor/Bidder]
And that I am authorized to make this Affidavit on its behalf and on the behalf of its owners, officers and directors. I also certify that I am the person responsible at my firm for the prices included in the bid for
Contract no. and for calculating the amount of the bid submitted by this company for that
Contract.
I hereby certify and affirm that:
(1) The price(s) and amount of this bid have been arrived at independently and without consultation, communication or agreement with any other contractor, bidder or potential bidder.
(2) Neither the price(s) nor the amount of this bid, and neither the approximate price(s) nor approximate amount of this bid, have been disclosed to any other firm or person who is a bidder or potential bidder, and no such prices or amounts will be disclosed before bid opening.
(3) No attempt has been made or will be made to induce any firm or person from bidding on this contract, or to submit a bid higher than this bid, or to submit any…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .