This document is a Request for Proposals (RFP) for equipment preselection by the Cities of Round Rock, Austin, Cedar Park, and Leander for the Brushy Creek Regional Wastewater System East Plant Expansion project. The RFP seeks equipment proposals for six specific systems: submersible pumps (influent lift station pumps), process air blowers, cloth media disc filters, UV disinfection equipment, progressive cavity pumps, and sludge dewatering belt filter presses. Sealed proposals are due on October 23, 2025, at 2 P.M. local time at 3400 Sunrise Road, Round Rock, TX. The project involves expanding the East Plant to 40 MGD and includes rehabilitation. Only one equipment package may be submitted per proposal, and proposals will be immediately opened and read aloud publicly. Following submittal, the owner will review and score proposals, with the top-scoring proposer in each equipment category receiving a Notice of Award.

The RFP includes provisions for price adjustments based on metal material price indices and the Producer Price Index, with proposers able to choose between 0-30% of their proposal price subject to adjustment. The evaluation process will weight cost at 50% and non-cost criteria at 50%, with a maximum of 1,000 points possible. Funding is expected to be provided in part by a loan or grant from the Texas Water Development Board. The proposal requires extensive documentation, including manufacturer qualifications, installation references, technical data, and compliance with specified requirements. Proposers must demonstrate experience with similar equipment in the United States, with at least three installations operating for a minimum of one year. The project emphasizes comprehensive technical evaluation, including factors such as performance, warranty, service capability, and compliance with technical specifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BRUSHY CREEK REGIONAL

WASTEWATER SYSTEM EAST PLANT

EXPANSION TO 40 MGD AND REHAB

SELECTION OF EQUIPMENT

SUPPLY PACKAGES

VOLUME 1

DIV 00: PROCUREMENT AND CONTRACTING

DIV 01: GENERAL REQUIREMENTS

DIV 02-19: FACILITY CONSTRUCTION

DIV 20-29: FACILITY SERVICES

DIV 30-39: SITE AND INFRASTRUCTURE

DIV 40-49: PROCESS EQUIPMENT

Prepared by:

PLUMMER | 8911 N Capital of Texas Hwy, Suite 1350| Austin, TX 78759

TBPE REGISTERED FIRM NUMBER F-13

September 2025

PRESELECTION

Project #: 0982-018-01

PAGE INTENTIONALLY LEFT BLANK

TABLE OF CONTENTS

REQUESTS FOR PROPOSALS

BRUSHY CREEK REGIONAL WASTEWATER SYSTEM

SELECTION OF EQUIPMENT SUPPLY PACKAGES

FOR THE EAST PLANT

EXPANSION TO 40 MGD AND REHABILITATION

Section

Number Title

00 01 20-PS 1 Request For Proposal

00 11 13-PS 1 Instruction to Proposers

00 31 00-PS 1 Proposal Form for Preselected Equipment

00 73 00-PS 1 Preselection Special Conditions

00 80 00-PS 1 TWDB Required Documents

01 60 00-PS 5 Product Requirements

01 75 25-PS 5 Equipment Testing and Startup

01 78 23-PS 5 Operation and Maintenance Data

01 78 36-PS 5 Warranties

01 79 00-PS 5 Demonstration and Training

09 91 00-PS 1 Painting and Protective Coatings

10 90 00-PS 1 Identification, Stenciling, and Tagging

26 20 00.01-PS 7 NEMA Frame Induction Motors, 600 Volts and Below

DIVISION 00 – PROCUREMENT AND CONTRACTING

N/A

DIVISION 01 – GENERAL REQUIREMENTS

DIVISION 02-19 - FACILITY CONSTRUCTION

DIVISION 20-29 - FACILITY SERVICES

DIVISIONS 30-39 – SITE AND INFRASTRUCTURE

PLUMMER ASSOCIATES, INC

0982-018-01

TABLE OF CONTENTS

BCE EQUIP PRESELECTION

SEPTEMBER 2025

BRUSHY CREEK REGIONAL WASTEWATER SYSTEM

SELECTION OF EQUIPMENT SUPPLY PACKAGES

FOR THE EAST PLANT

EXPANSION TO 40 MGD AND REHABILITATION

Section

Number Title

40 05 23-PS 5 Stainless Steel Process Pipe and Tubing

40 05 51-PS 5 Common Requirements for Valves

40 05 52-PS 5 Miscellaneous Valves

40 05 56-PS 5 Gates, Slide and Weir

40 05 57.23-PS 3 Electric Motor Actuators

40 05 61-PS 5 Gate Valves

40 05 64.33-PS 1 Industrial Butterfly Valves for Air Service

40 05 65-PS 1 Valves for Flow Control and Check Service

40 05 78.29-PS 5 Combination Air and Vacuum Release Valves

40 05 91-PS 3 Common Control Panel Requirements for Process Equipment

43 11 11-PS 8 Blowers, Singlestage Centrifugal

43 11 17-PS 8 Blowers, Multistage Centrifugal

43 22 10-PS 5 Common Requirements for Pumps

43 23 57-PS 5 Pumps, Progressive Cavity (BFP Feed Pumps and Polymer Pumps)

43 25 00-PS 4 Pumps, Submersible - Immersible

46 61 41-PS 5 Cloth Media Effluent Filters - Disc Filters

46 66 00-PS 4 Ultraviolet Disinfection Equipment

46 77 22.10-PS 5 Belt Filter Press System

DIVISIONS 40-49 – PROCESS EQUIPMENT

PLUMMER ASSOCIATES, INC

0982-018-01

TABLE OF CONTENTS

BCE EQUIP PRESELECTION

SEPTEMBER 2025

BRUSHY CREEK REGIONAL WASTEWATER SYSTEM

SELECTION OF EQUIPMENT SUPPLY PACKAGES

FOR THE EAST PLANT

EXPANSION TO 40 MGD AND REHABILITATION

0 Specification Furnished by the City of Round Rock 1 Perran Sean Hutton (Texas P.E. 137209) 2 Not Used 3 Patrick Norman Moseley (Texas P.E. 72794) 4 Gregory Theron Blackburn (Texas P.E. 121663) 5 Hannah Elizabeth Leppla (Texas P.E. 130165) 6 Maziar Mahdavi (Texas P.E. 144981) 7 Juan Pablo Cantu (Texas P.E. 90105) 8 Suparna Suvasish Mukhopadhyay (Texas P.E. 145575) 9 Alex Kavanaugh (Texas P.E. 145083)

10 Homero Saenz (Texas Architect 25047)

SEALING ENGINEER / ARCHITECT INDEX

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE

NOT INTENDED FOR CONSTRUCTION, BIDDING, OR

PERMIT PURPOSES.

PERRAN SEAN HUTTON

TEXAS P.E. NO.: 137209

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE

NOT INTENDED FOR CONSTRUCTION, BIDDING, OR

PERMIT PURPOSES.

PATRICK NORMAN MOSELY

TEXAS P.E. NO.: 72794

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND

ARE NOT INTENDED FOR CONSTRUCTION, BIDDING,

OR PERMIT PURPOSES.

GREGORY THERON BLACKBURN

TEXAS P.E. NO.: 121663

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE

NOT INTENDED FOR CONSTRUCTION, BIDDING, OR

PERMIT PURPOSES.

HANNAH ELIZABETH LEPPLA

TEXAS P.E. NO.: 130165

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND

ARE NOT INTENDED FOR CONSTRUCTION, BIDDING,

OR PERMIT PURPOSES.

MAZIAR MAHDAVI

TEXAS P.E. NO.: 144981

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE

NOT INTENDED FOR CONSTRUCTION, BIDDING, OR

PERMIT PURPOSES.

JUAN PABLO CANTU

TEXAS P.E. NO.: 90105

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND

ARE NOT INTENDED FOR CONSTRUCTION, BIDDING,

OR PERMIT PURPOSES.

SUPARNA SUVASISH MUKHOPADHYAY

TEXAS P.E. NO.: 145575

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE

NOT INTENDED FOR CONSTRUCTION, BIDDING, OR

PERMIT PURPOSES.

ALEX KAVANAUGH

TEXAS P.E. NO.: 145083

DATE: 08/26/2025

THESE DOCUMENTS ARE FOR INTERIM REVIEW AND

ARE NOT INTENDED FOR CONSTRUCTION, BIDDING,

OR PERMIT PURPOSES.

HOMERO SAENZ

TEXAS ARCHITECT 25047

DATE: 08/26/2025

PLUMMER ASSOCIATES, INC

0982-018-01

TABLE OF CONTENTS

BCE EQUIP PRESELECTION

SEPTEMBER 2025

Not Used

Not Used

Not Used

PLUMMER ASSOCIATES, INC

0982-018-01

K Friese & Associates, LLC

09/09/2025

8. Suparna Savasish Mukhopadhyay

Plummer Associates, Inc.

Suvasish

Luis Miguel Cantu (Texas P.E. 152211)

3. Patrick Norman Moseley

3. Luis Miguel Cantu

INTENDED FOR CONSTRUCTION, BIDDING,

IT PURPOSES.

UPARNA SUVASISH MUKHOPADHYAY

TEXAS P.E. NO.: 145575

DATE: 08/26/2025

CUMENTS ARE FOR INTERIM REVIEW AND

NTENDED FOR CONSTRUCTION, BIDDING,

T PURPOSES.

HOMERO SAENZ

TEXAS ARCHITECT 25047

DATE: 08/26/2025

Suvasish

Freese and Nichols, Inc.

9/10/2025

4. Gregory Theron Blackburn

K Friese & Associates, LLC

1.

5. Hannah Elizabeth Leppla

7. Juan Pablo Cantu

Freese and Nichols, Inc.

3.

3/1/2023 9/9/2025

DanHer 09/09/2025

1. Perran Sean Hutton

09/11/2025

PLUMMER ASSOCIATES, INC. 00 01 20-PS - PAGE 1 OF 2 BCE EQUIP PRESELECTION

0982-018-01 REQUEST FOR PROPOSALS SEPTEMBER 2025

SECTION 00 01 20-PS

REQUEST FOR PROPOSAL

Notice

Notice is hereby given that the City of Round Rock Texas will receive sealed proposals on behalf of the Cities of Round Rock, Austin, Cedar Park, and Leander (OWNER) at 3400 Sunrise Road, Round Rock, TX 78664 until 2 P.M. local time on Thursday, October 23, 2025 for equipment preselection for:

City of Round Rock

BRUSHY CREEK REGIONAL WASTEWATER SYSTEM

EAST PLANT EXPANSION TO 40 MGD AND REHABILITATION

EQUIPMENT PRESELECTION

Equipment proposals are requested for the following systems:

• Submersible pumps (influent pumps)

• Process blowers

• Cloth media disc filters

• UV disinfection equipment

• Progressive cavity pumps

• Sludge dewatering belt filter presses (BFPs).

You are invited to submit a sealed, competitive Proposal to furnish and deliver all equipment and services described and specified within this Request for Proposals (RFP) for an individual equipment package in strict accordance with Section 00 11 13-PS “Instructions to Proposers” and Section 00 73 00-PS “Preselection Special Conditions”. Please note that your Proposal must include all responses to questions, installation lists and references, supporting documentation and information, drawings, technical data, and forms required by this RFP for an individual equipment package. Each Proposer must provide a Cost Proposal with itemized quotation in a separate, sealed envelope within the Proposal for an individual equipment package. Only one equipment package may be included per proposal submitted. Clearly mark which equipment package is to be included in the submitted proposal on the outside of the envelope.

Failure to provide the required information in strict accordance with Section 00 11 13-PS “Instructions to Proposers” and Section 00 73 00-PS “Preselection Special Conditions”, and the documents requested by the City of Round Rock may result in your proposal being deemed non-responsive and disqualified from the preselection process.

Equipment proposal amounts will be immediately opened and read aloud publicly following the close of the Proposal Period. Any Proposal received after closing time will be returned unopened. Proposals may be modified or withdrawn at any time prior to the time set for opening Proposals. Following submittal of the proposals the OWNER will review and score the information to determine the proposal with the highest overall score.

The top-scoring Proposer in each equipment category will receive a “Notice of Award” letter. This letter requires the recipient to confirm agreement with the Equipment Specifications and terms by signing at the bottom and returning the signed copy.

PLUMMER ASSOCIATES, INC. 00 01 20-PS - PAGE 2 OF 2 BCE EQUIP PRESELECTION

0982-018-01 REQUEST FOR PROPOSALS SEPTEMBER 2025

Examination of Documents

The contract documents and appendices will be available at:

https://roundrocktexas.bonfirehub.com/portal.

Proposers must register on this website in order to view and/or download specifications and plans for this project. There is NO charge to view or download documents.

Questions Regarding Proposal Process or Proposal Documents

Any questions concerning the specifications, or other proposal documents or any part thereof must be submitted through the https://roundrocktexas.bonfirehub.com/portal Q&A portal. Questions must be received at least 7 calendar days prior to the proposal deadline.

END OF SECTION

https://roundrocktexas.bonfirehub.com/portal https://roundrocktexas.bonfirehub.com/portal

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 1 OF 12 BCE EQUIP PRESELECTION

0982-018-01 INSTRUCTIONS TO PROPOSERS SEPTEMBER 2025

SECTION 00 11 13-PS

INSTRUCTIONS TO PROPOSERS

ARTICLE 1 - PROPOSAL DOCUMENTS

1.1 Prior to submitting any proposal, proposers (PROPOSERS or PRESELECTED EQUIPMENT SUPPLIER(S)) are required to read all drawings (plans), specifications, and all Contract Documents carefully; to inform themselves by their independent research, test and investigation of the difficulties to be encountered and judge for themselves of the accessibility of the Work and all attending circumstances affecting the cost of doing the Work and the time required for its completion; and obtain all information required to make a proposal. The aforementioned documents may be obtained from https://roundrocktexas.bonfirehub.com/portal. PROPOSERS must register on this website in order to view and/or download specifications and plans for this project. There is NO charge to view or download of documents.

ARTICLE 2 - INTERPRETATIONS AND ADDENDA

2.1 Should the PROPOSER find discrepancies in, or omissions from the drawings (plans), specifications, or Contract Documents, or should the PROPOSER be in doubt as to their meaning, the PROPOSER should notify at once the City of Round Rock (City or OWNER) and obtain clarification or addendum prior to submitting any proposal. Comments and questions shall be received no later than seven business days prior to the proposal Opening Date. Any addenda issued will be posted with the documents at the web address mentioned above no later than two business days prior to the Proposal Opening Date. Prior to submitting a proposal, the PROPOSER is responsible for determining if any addenda have been issued and for following any instructions required in any addenda issued.

ARTICLE 3 - PROPOSALS

3.1 It shall be the responsibility of the PROPOSER to see that his proposal is received at the place and time named in the Request for Proposal in the Project Manual. Proposals received after the scheduled opening time will be returned unopened.

3.2 Proposals shall be submitted in sealed envelopes plainly marked "Sealed Proposal" and showing the name of the project, the job number if applicable, specific equipment packaged and the opening date and time.

3.3 PROPOSERS shall be responsible for submitting a copy of the Cost Proposal Form, along with all of the information required with the proposal listed below.

3.4 No conditional nor combined proposals will be accepted.

3.5 A PROPOSER wishing to withdraw his submitted sealed proposal prior to the scheduled proposal opening time must do so by presenting in person a written request signed by an authorized representative of the PROPOSER to a City employee at the location for which sealed proposals are to be addressed. No telephone, facsimile, or email requests will be accepted. The City will expend the time and effort that the City in its sole discretion determines is necessary to investigate the authenticity of a request before complying with a request. The City shall in its sole discretion, determine if the City will comply with a request and the City shall not be held liable for not complying with a request. If the City does not comply with a request, the request shall automatically become null and void.

http://www.civcastusa.com/

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 2 OF 12 BCE EQUIP PRESELECTION

3.6 A PROPOSER wishing to revise his sealed proposal after submittal but before the scheduled proposal opening time must first withdraw his proposal as provided for in the Instructions to Proposers and then submit a sealed proposal in accordance with the Instructions to Proposers. No revisions to a proposal will be allowed after the scheduled proposal opening time.

3.7 Until the award of the contract, the City reserves the right to reject any and all proposals and to waive technicalities; to advertise for new proposals; or to do the work otherwise when the best interest of the City will be thereby promoted.

3.8 In case of ambiguity or lack of clarity in the statement of prices in the proposals, the City reserves the right to consider the most favorable analysis thereof, or to reject the proposal. Unreasonable or unbalanced prices submitted in a proposal may result in rejection of such proposal or other proposals.

3.9 Any quantities given in any portion of the Proposal Documents, including the drawings (plans), are estimates only, and the actual amount of work required may differ somewhat from the estimates.

The basis for payment shall be the actual amount of work done or material furnished as specified in Section 00 73 00-PS “Preselection Special Conditions”.

3.10 Proposals shall be submitted on a separate contract basis. No Texas sales tax shall be included in the prices proposal for materials consumed or incorporated into the Work. The future contract (between Owner and General Contractor) will be issued by an organization which is qualified for exemption pursuant to the provisions of Section 151.309(5) of the Texas Tax Code. The Owner will issue an exemption certificate to the selected PROPOSER (PRESELECTED EQUIPMENT SUPPLIER).

The PRESELECTED EQUIPMENT SUPPLIER must then issue a resale certificate to the material supplier for materials purchased. The PRESELECTED EQUIPMENT SUPPLIER must have a valid sales tax permit in order to issue a resale certificate.

3.11 Upon obtaining consumable materials, the PRESELECTED EQUIPMENT SUPPLIER will issue a resale certificate in lieu of payment of sales tax, and the following conditions shall be observed;

A. The PRESELECTED EQUIPMENT SUPPLIER will transfer title of consumable, but not incorporated, materials to the General Contractor at the time and point of receipt by the

PRESELECTED EQUIPMENT SUPPLIER;

B. The PRESELECTED EQUIPMENT SUPPLIER will be paid for these consumable materials by the General Contractor as soon as practicable. Payment will not be made directly but considered subsidiary to the pertinent proposal item. The PRESELECTED EQUIPMENT SUPPLIER’S monthly estimate will state that the estimate includes consumables that were received during the month covered by the estimate; and

C. The designated representative of the General Contractor must be notified as soon as possible of the receipt of these materials so that an inspection can be made by the representative.

Where practical, the materials will be labeled as the property of the General Contractor.

3.12 The PRESELECTED EQUIPMENT SUPPLIER, after execution of the contract and pursuant to Internal Revenue Service (IRS) regulations, shall furnish its Taxpayer Identification Number (TIN) to the General Contractor. The Contractor shall provide the appropriate information on a W-9 form (which can be provided by the City upon request). This form shall be submitted by the General Contractor directly to the City’s Accounts Payable Department to ensure security of the information.

3.13 The PRESELECTED EQUIPMENT SUPPLIER shall ensure that all equipment design, features, and performance parameters conform to the requirements established in the Preselection Proposal Documents. The PRESELECTED EQUIPMENT SUPPLIER shall confirm in writing, at the time of GENERAL CONTRACTOR’S equipment submittals, that there are no deviations, modifications, or

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 3 OF 12 BCE EQUIP PRESELECTION

substitutions from the approved preselection design, except as expressly authorized in writing by the Partners. Any unauthorized design changes between the Preselection Proposal and the GENERAL CONTRACTOR’S equipment submittals shall be considered non-compliant.

3.14 The PROPOSER shall issue a proposal price that shall be valid without adjustment, except as noted in this specification section, until the end of February 2027 when the OWNER anticipates proposals from a GENERAL CONTRACTOR for construction. The submitted proposal price shall include all materials and services listed in the contract documents and shall account for all changes in production costs between the time of proposal submission and the end of February 2027.

ARTICLE 4 - INFORMATION REQUIRED WITH PROPOSAL

4.1 Required Information to be submitted by the PROPOSER must be organized into the following response item sections and submitted in an indexed binder:

A. Cover Letter. Cover letter addressed to the Honorable Mayor and City Council that states the PROPOSER’S equipment description and specifications and services to be provided. Include any additional information believed necessary that is not requested elsewhere in the Contract Documents.

B. Proposal Form. Completed and separately sealed Proposal Form. Proposal Form shall include the information in Part 9 of Section 00 31 00-PS “Proposal Form for Preselected Equipment” describing the proposing organization, as well as the related equipment proposal form table filled out with all of the requested information including the percentage of the equipment subject to a material price adjustment.

C. Proposer’s Qualifications. Submit data providing compliance with the specified experience, installations, and references requirements, submit the following for each installation and reference:

1. Treatment plant name and location, including city and state.

2. General description of equipment application (i.e., raw wastewater, municipal).

3. Model and sizes of the equipment installed.

4. Number of units installed.

5. Year of installation.

6. Name, current telephone number, and current e-mail address for contact person at treatment plant.

D. Compliance with Specifications. A copy of the applicable Technical Specification sections from these Contract Documents covering all equipment in the proposal with clear indication of compliance with the requirements of each paragraph. Inclusion of “checkmarks” next to each paragraph shall signify full compliance with specification requirements. Any and all deviations from the specifications, including any upgrades, or exceptions taken to the specifications shall be clearly indicated and each deviation or exception shall be numbered.

A detailed, written explanation shall be provided for each numbered deviation or exception taken. Additional points will be awarded in cases of upgrades of the specification. Failure to include a copy of the technical specifications with clearly marked compliance, exceptions, and deviations may be sufficient cause for elimination from further evaluation.

E. Equipment Data, Standard Drawings, and Supporting Information. Submit the following:

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 4 OF 12 BCE EQUIP PRESELECTION

1. Data completely describing proposed equipment including model number, equipment generation, plan and section views, and listings of all components and materials of construction.

2. Standard installation drawings showing dimensions, weights, and locations of all components, individually and as a combined system. Drawings shall include vibration isolators, locations for anchor bolts, and required process connection sizes and types.

Weights shall be provided for each system component, combined weight for all components that must be installed as a unit. Connection information shall include pipe size, connection type, and flange class.

3. Values for all required utilities, including wash water flow, quality, pressure, foul air venting requirements, flow and pressure for lubrication system cooling water, etc.

4. Dimensions of system components, including diameter, length, width, heights, and clearances.

5. Required clearances for disassembly and maintenance, and indication of how and where disassembly occurs and removal from system.

6. Gearbox system data sheets, description, torque capacity, and reduction ratio (as applicable). Lubrication system data sheets, layout, and requirements.

7. Static and dynamic loads, including indication of load distribution and any vibration isolation.

8. Electrical information, including nameplate motor horsepower for all motors.

Maximum total electrical current draw at 480 volts.

9. Standard interconnecting wiring diagrams for system components.

10. Standard process and instrumentation diagrams (P&ID).

11. Dimensions of all required control panels.

12. Dimensions of PROPOSER furnished motor controller units (i.e. VFDs, etc.).

13. Complete description of control systems and instruments included, including proposed PLCs, sequence of operation and list of functions monitored, controlled, and alarmed. Include summaries of available operating modes.

14. Loading rates, capacities, flow and head curves, and other process information per the requirements in each specification.

15. Any other information that demonstrates compliance with or exceedance of specified requirements, especially for those items included in the selection process.

16. Vibration monitoring equipment product data (if any).

17. Performance curves for pumps and blowers showing efficiencies, NPSH, shutoff and run-out conditions. For pumps and blowers to be run using variable speed drives, include curves at full speed and minimum possible speed.

18. Materials of construction for all components.

19. Itemized quotation, a complete listing of all items furnished with quantities, manufacturers, model numbers, descriptions, and sizes.

20. Information on pipe and fittings, materials, coatings, and linings.

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 5 OF 12 BCE EQUIP PRESELECTION

21. Warranties and guarantees.

22. Calculation for kW of power used and design conditions listed in specifications.

F. Operational and Maintenance Considerations. Provide a summary of the system’s operating sequence and recommended operator attention. Provide a summary of required maintenance activities, including frequency of maintenance and part replacement and estimated manhours for each activity. Indicate those maintenance activities that are recommended to be performed by the manufacturer or manufacturer’s service representatives.

G. Service and Support Facilities. Provide information describing service centers that would provide service to the City of Round Rock. Describe the services provided at each service center, including each center’s manufacturing, and rebuilding capabilities. Indicate the number off service personnel assigned to each service center that would provide service to the City of Round Rock. Indicate the training and qualifications for the service personnel that would provide service to the City of Round Rock. Provide typical response time for service calls, including time required for travel to the City of Round Rock and the typical response time for spare parts delivery for all recommended spare parts.

H. Scope of Supply. Provide list of all items to be included in your scope of supply and all items specifically excluded from your scope of supply but necessary for a fully functioning and operable system.

I. Maintenance Service Contracts. Provide list of services included in specified service contracts.

J. The PROPOSER must assure the City that he/she will to the best of his/her knowledge, information, and belief, be cognizant of, comply with, and enforce, where applicable and to the extent required, all applicable federal or state statutes and local ordinances.

K. Disclosure of any obligations posing a potential conflict of interest, including service on City boards and/or commissions and any current contracts with the City of Marble Falls. This would apply to the Proposer as well as representatives of the Proposer and entities subcontracted by the Proposer.

L. Any material which the proponent wishes to submit and which is not specifically requested in the above categories.

ARTICLE 5 - METHOD FOR EVALUATION OF EQUIPMENT AND SCORING CRITERIA

5.1 The proposal will be scored based on two components – the score from the evaluation criteria and the cost. The cost component will be weighted at 50%, and the non-cost criteria score will be weighted at 50%. The score from both components will be added together to get the total score.

The maximum points a proposal may receive is 1,000. The cost will have a maximum of 500 points, and the evaluation criteria will have a maximum of 500 points. The proposal with the highest score will be chosen for the project. Details on how the score of each component will be calculated are described below:

A. Evaluation Criteria

1. The total points within each section will be added to provide the total score for the Evaluation Criteria shown in Article 5. Additional points may be added in cases where the Supplier exceeds expectations.

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 6 OF 12 BCE EQUIP PRESELECTION

B. Cost

1. For equipment items where the only information required on the proposal form is the equipment proposal price, the proposal price will be used in the cost calculation score.

For equipment items that include power usage or other operational data costs, the Net Present Value calculated from the proposal will be used in the cost calculation score.

2. The lowest proposer will receive the full points for the cost section. From there, each proposer will receive a fraction of the total points based on their ratio to the lowest proposal.

Example: Low proposal is $1,000. Next proposal is $2,000. Low proposal receives 500 points.

Next proposal will receive 1,000

2,000 ∗ 500 = 250 𝑝𝑜𝑖𝑛𝑡𝑠

5.2 The point-based scoring for the evaluation process will be based on:

A. Completion and submission of all documents and information required in this invitation to proposal and the quality, completeness, and accuracy of the PROPOSER’S proposal.

Proposals deemed by the selection committee to be non-responsive or non-conforming shall be eliminated from further evaluation. All PROPOSERS are strongly cautioned to thoroughly review all requirements and provide all required information in complete and accurate proposals.

B. The PROPOSER’S experience, qualifications, installations, and references relative to minimum specified requirements. Exceeding minimum requirements will result in higher scores.

C. The favorability of responses by references contacted by the City of Round Rock regarding performance, safety, service, maintenance requirements, and ease of operation and controls. References provided must meet minimum specified requirements. Highly favorable responses by contacted references will result in higher scores.

D. The length and coverage of the PROPOSER’S proposed warranty relative to minimum specified requirements. Exceeding minimum requirements will result in higher scores.

E. The PROPOSER’S service capability relative to minimum specified requirements. Exceeding minimum requirements will result in higher scores.

F. Conformance with required criteria and specifications included within these Contract Documents. Non-conformance will result in lower scores. Exceptions are discouraged, and any exception taken to those specifications must be identified, thoroughly explained, and justified. Exceptions to the minimum criteria noted above may exclude the PROPOSER and associated system from further evaluation. Furnishing materials that exceed minimum specifications may result in higher scores at the discretion of the Partners.

G. After receiving proposals from all of the PROPOSERS showing their specific equipment scope of supply the ENGINEER will determine a construction cost adjustment factor to account for the different structural, piping, electrical, controls, etc. that will be needed for a fully operational system. Systems that require fewer additional construction costs will receive higher points, and systems that require more construction cost will receive fewer points.

5.3 Points within the ranges noted in the table below will be awarded by the selection committee for these criteria of the evaluation process.

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 7 OF 12 BCE EQUIP PRESELECTION

EVALUATION CRITERIA AND POINT RANGES

Category Criterion

Point Range

Minimum Maximum

1. Quality of Proposal

• Level of completeness and accuracy of proposal

• Overall extent of deviations or exceptions taken to special conditions

• Overall extent of deviations or exceptions taken to technical requirements

Subtotal 0 50

2. Experience and Qualifications*

• Level of conformance with United States experience requirements

• Level of conformance with United States installations and references requirements for same size equipment

• Level of conformance with Texas installations and references requirements

3. Favorability of References

• Actual performance in comparison to specified or guaranteed values

• Quality and timeliness of service

• Startup service reference

• Required maintenance and ease of maintenance

• Ease of operation and controls

• Owner’s experience with similar equipment from the Supplier

Subtotal 0 90

4. Warranty

• Length and coverage of warranty – exceeding minimum requirements will be considered in scoring.

Subtotal 0 30

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 8 OF 12 BCE EQUIP PRESELECTION

5. Service Capability

• Number of currently operating service centers and service center capabilities within an 8-hour drive to Round Rock, Texas

• Level of conformance with service requirements for service calls and spare part delivery

• Maintenance frequency

• Ease of maintenance

Subtotal 0 80

6. Compliance with Technical Specifications

• Materials of construction

• Construction/manufacturing characteristics

(sizes, thicknesses, etc.)

• Hydraulic/process requirements

• Safety aspects

• Training/testing/startup

• Automatic cleaning systems

• Motors

• Controls and instrumentation

• Valve and actuators

• Electrical

Subtotal 0 150

7. Indirect construction cost adjustment for differences in equipment

• Adjustment for different features/requirements of required facilities to accommodate different preselected equipment manufacturers

Total Points for Evaluation 0 500

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 9 OF 12 BCE EQUIP PRESELECTION

ARTICLE 6 - PRICE ADJUSTMENTS

6.1 Prices may be adjusted based on two parts: an index for metal material prices and the Producer Price Index. The index for metal material prices will be used to adjust the price of the material from September 2025 through February 2027. The Producer Price Index will be used to adjust the price of the equipment for orders placed after February 2027. Further explanation for each component is below.

6.2 Any impacts from tariffs, changes in tariff rates, or shifts in the tariff climate will be reflected through the adjustments driven by the applicable indices and will not be accounted for as a separate adjustment.

6.3 Price Index for Metal Materials

A. Due to the substantial impact that changes in metal material prices may have on the PROPOSER, this Agreement shall include an adjustment factor based on a metals commodity index.

B. The equipment proposal in the Proposal Form may be adjusted up or down in proportion to the change in the index for iron and steel (WPU 101) from the Federal Reserve Economic Database (FRED) from the Federal Reserve Bank of St. Louis as indicated on the website https://fred.stlouisfed.org/series/WPU101. This index will be used as a surrogate for all material price changes. No alternative index will be used for price adjustment.

C. The adjustment will be applied to the equipment proposal price of the equipment, based on the change in the index between the equipment preselection proposal date and the GENERAL CONTRACTOR’s bid date. The proposer can choose the percent adjustment between 0-30 percent that will be applied. The proposer shall specify the percentage of equipment proposal price that shall be subject to adjustment in the Proposal Form. The remainder of the capital cost shall be fixed. If no percentage is included in the proposal form it will be assumed that percent of the proposal to be adjusted by the metals materials price index is zero percent.

𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑃𝑟𝑖𝑐𝑒 = [𝑂𝑟𝑖𝑔𝑖𝑛𝑎𝑙 𝑃𝑟𝑖𝑐𝑒 ∗

𝑊𝑃𝑈101 𝑓𝑜𝑟 𝑀𝑜𝑛𝑡ℎ 𝑜𝑓 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑜𝑟 𝐵𝑖𝑑 𝐷𝑎𝑡𝑒

𝑆𝑒𝑝𝑡𝑒𝑚𝑏𝑒𝑟 2025 𝑊𝑃𝑈101

∗ 𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑜𝑓 𝑃𝑟𝑖𝑐𝑒 𝑡𝑜 𝑏𝑒 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑] + [𝑂𝑟𝑖𝑔𝑖𝑛𝑎𝑙 𝑃𝑟𝑖𝑐𝑒

∗ (1 − 𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑜𝑓 𝑃𝑟𝑖𝑐𝑒 𝑡𝑜 𝑏𝑒 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑)]

6.4 Producer Price Index

A. The Proposer agrees that this Proposal and Price shall remain valid for inclusion in the GENERAL CONTRACTOR’s bid and through the GENERAL CONTRACTOR’S Notice to Proceed.

If the OWNER has not issued a Notice to Proceed by the end of July 2027, the OWNER and PROPOSER agree that the portion of the Price not adjusted by the materials price index shall be scaled based on the Producer Price Index. The base Producer Price Index shall be the December 2026 Producer Price Index. The Revised Price shall be calculated as follows:

𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑃𝑟𝑖𝑐𝑒 = [(𝑂𝑟𝑖𝑔𝑖𝑛𝑎𝑙 𝑃𝑟𝑖𝑐𝑒 − 𝑃𝑜𝑟𝑡𝑖𝑜𝑛 𝐴𝑑𝑗𝑢𝑠𝑡𝑒𝑑 𝑏𝑦 𝑊𝑃𝑈 101)

𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑟 𝑃𝑟𝑖𝑐𝑒 𝐼𝑛𝑑𝑒𝑥 𝑓𝑜𝑟 𝑀𝑜𝑛𝑡ℎ 𝑜𝑓 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑜𝑟 𝐴𝑑𝑣𝑒𝑟𝑡𝑖𝑠𝑒𝑚𝑒𝑛𝑡 𝐷𝑎𝑡𝑒

𝐷𝑒𝑐𝑒𝑚𝑏𝑒𝑟 2026 𝑃𝑟𝑜𝑑𝑢𝑐𝑒𝑟 𝑃𝑟𝑖𝑐𝑒 𝐼𝑛𝑑𝑒𝑥

+ 𝑊𝑃𝑈 101 𝑃𝑜𝑟𝑡𝑖𝑜𝑛

https://fred.stlouisfed.org/series/WPU101

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 10 OF 12 BCE EQUIP PRESELECTION

ARTICLE 7 - PROPOSALS BASED ON PRESENT WORTH

7.1 Some of the equipment items included in this proposal package require proposals for power consumption and other consumable items. The proposal price for these items will be based on the present worth of the equipment proposal price and the present worth of the power and other consumable items over a period of 10 years using the following formulas. Evaluation will be based on number of equipment units provided in the scope.

𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐶𝑜𝑠𝑡

= 𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑇𝑖𝑚𝑒 𝑎𝑡 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑃𝑜𝑖𝑛𝑡 ∗ 8760 ℎ𝑟𝑠 𝑦𝑒𝑎𝑟 ∗ 𝑃𝑜𝑤𝑒𝑟 𝐶𝑜𝑠𝑡

∗ 𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑊𝑜𝑟𝑡ℎ 𝐶𝑜𝑛𝑣𝑒𝑟𝑠𝑖𝑜𝑛 𝐹𝑎𝑐𝑡𝑜𝑟

Assumptions:

Operation period for evaluation = 10 years

Power cost = $0.04/kWh

Discount Factor = 3%

Conversion factor for present worth cost of expenses over operation period for evaluation = 8.530

Labor Cost = $41/hour

𝐵𝑖𝑑 𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑊𝑜𝑟𝑡ℎ = 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡 𝐵𝑖𝑑 𝑃𝑟𝑖𝑐𝑒 + 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐶𝑜𝑠𝑡

Example Calculations:

Example 1: Proposal price $250,000

Proposal power consumption at design point = 100 kW

Equipment Runs 100% of the time

Operating cost = 100% * 8760 hrs/yr * $0.04/kWh * 100 kW * 8.530

Operating cost = $298,891.20

Proposal Present Worth = $250,000 + $298,891.20

Proposal Present Worth = $548,891.20

Example 2: Proposal price $100,000

Proposal power consumption at design point 1 = 50 kW

Equipment Runs 50% of the time

Proposal power consumption at design point 2 = 30 kW

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 11 OF 12 BCE EQUIP PRESELECTION

Equipment Runs 30% of the time

Proposal power consumption at design point 3 = 70 kW

Equipment Runs 20% of the time

Operating cost = (50% * 8760 hrs/yr * $0.04/kWh * 50 kW * 8.530) +

(30% * 8760 hrs/yr * $0.04/kWh * 30 kW * 8.530) +

(20% * 8760 hrs/yr * $0.04/kWh * 70 kW * 8.530)

Operating cost = $143,467.78

Proposal Present Worth = $100,000 + $143,467.78

Proposal Present Worth = $243,467.78

7.2 Equipment proposals that include a proposal power amount will be subject to a power test. If the equipment uses more power than indicated in the proposal form a penalty will be assessed based on the formula listed in specification Section 00 73 00-PS “Preselection Special Conditions”. No credit will be given for using less power than proposal.

End of Section

PLUMMER ASSOCIATES, INC. 00 11 13-PS - PAGE 12 OF 12 BCE EQUIP PRESELECTION

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 1 OF 16 BCE EQUIP PRESELECTION

0982-018-01 PROPOSAL FORM FOR PRESELECTED EQUIPMENT SEPTEMBER 2025

SECTION 00 31 00-PS

PROPOSAL FORM FOR PRESELECTED EQUIPMENT

Project Name:

Brushy Creek Regional Wastewater Treatment System East Plant Expansion to 40 MGD and Rehabilitation Equipment Preselection

ARTICLE 1 - PROPOSAL RECIPIENT

1.1 This Proposal is submitted to:

City of Round Rock

Attn: Rebecca Vento, Project Manager

Utilities and Environmental Services

3400 Sunrise Rd.

Round Rock, TX 78665

ARTICLE 2 - PROPOSER’S ACKNOWLEDGEMENTS

2.1 The undersigned Proposer proposes and agrees, if this Proposal is accepted, to enter into an Agreement with the City of Round Rock, to perform all Work as specified or indicated in the Proposal Documents for the prices and within the times indicated in this Proposal and in accordance with the other terms and conditions of the Proposal Documents.

2.2 Proposer accepts all of the terms and conditions of the Request for Proposal and Instructions to Proposers, including without limitation those dealing with the disposition of Proposal security.

2.3 Proposer accepts the provisions of the Contract Documents included in Appendix A as to liquidated damages in the event of its failure to complete Work in accordance with the schedule set forth in the Agreement.

ARTICLE 3 - PROPOSER’S REPRESENTATIONS

3.1 In submitting this proposal, Proposer represents, as set forth in the Agreement, that:

A. Proposer has examined and carefully studied the Proposal Documents, the other related data identified in the Proposal Documents, and the following Addenda, receipt of which is hereby acknowledged.

Addendum No. Addendum Date

B. Proposer has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 2 OF 16 BCE EQUIP PRESELECTION

C. Proposer is familiar with and is satisfied as to all federal, state and local laws and regulations that may affect cost, progress and the furnishings of Goods and Special Services.

D. Proposer has obtained and carefully studied (or accepts the consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Proposer, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Proposal Documents to be employed by Proposer, and safety precautions and programs incident thereto.

E. Proposer does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Proposal for performance of the Work at the price(s) proposed and within the times and in accordance with the other terms and conditions of the Proposal Documents.

F. Proposer is aware of the general nature of work to be performed by OWNER and others at the Site that relates to the Work as indicated in the Proposal Documents.

G. Proposer has correlated the information known to Proposer, information and observations obtained from visits to the Site, reports and drawings identified in the Proposal Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Proposal Documents.

H. Proposer has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that Proposer has discovered in the Proposal Documents, and the written resolution thereof by ENGINEER is acceptable to Proposer.

I. The Proposal Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Proposal is submitted.

ARTICLE 4 - FURTHER REPRESENTATIONS

4.1 Proposer further represents that:

A. This Proposal is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation;

B. Proposer has not directly or indirectly induced or solicited any other Proposer to submit a false or sham Proposal;

C. Proposer has not solicited or induced any individual or entity to refrain from proposal; and

D. Proposer has not sought by collusion to obtain for itself any advantage over any other Proposer or over Owner.

ARTICLE 5 - BASIS OF PROPOSAL

5.1 Proposer will complete the Work in accordance with the technical specifications and future Contract Documents (included in Appendix A) for the prices shown in the attached Proposal Form Table.

ARTICLE 6 - TIME OF COMPLETION

6.1 Proposer agrees that the Equipment and Services to be furnished will be provided complete on or before the dates or within the number of calendar days indicated in the General Contractor’s Agreement (future bid document), or as modified by the days listed in this proposal form if used.

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 3 OF 16 BCE EQUIP PRESELECTION

ARTICLE 7 - DEFINED TERMS

7.1 The terms used in this Proposal have the meanings indicated in the General Conditions and the Preselection Special Conditions. The significance of terms with initial capital letters is described in the General Conditions.

ARTICLE 8 - VENUE

8.1 Proposer agrees that venue shall lie exclusively in Williamson County, Texas, for any legal action.

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 4 OF 16 BCE EQUIP PRESELECTION

ARTICLE 9 - PROPOSAL SUBMITTAL

This Proposal submitted by:

If Proposer is:

A Corporation

Corporation Name: (Seal)

(typed or printed)

State of Incorporation:

Type: (General Business, Professional, Service, Limited Liability)

By:

(signature - attach evidence of authority to sign)

Name:

(typed or printed)

Title:

(CORPORATE SEAL)

Attest:

(signature of Corporate Secretary)

Date of Qualification to do business in is (State where Project Located) (Date)

A Joint Venture:

Name of Joint Venture:

(typed or printed)

First Joint Venture Name: (Seal)

By:

(signature of first joint venture partner- attach evidence of authority to sign)

Name:

(typed or printed)

Title:

Second Joint Venture Name: (Seal)

By:

(signature of second joint venture partner- attach evidence of authority to sign)

Name:

(typed or printed)

Title:

(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 5 OF 16 BCE EQUIP PRESELECTION

Contact for receipt of official communications:

Name:

Business Address:

Phone: Facsimile:

E-mail:

Proposal Submitted on:

State Contractor License No. . (If applicable)

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 6 OF 16 BCE EQUIP PRESELECTION

COST PROPOSAL FORM

REQUEST FOR PROPOSALS (RFP) FOR THE BRUSHY CREEK REGIONAL WASTEWATER SYSTEM – EAST PLANT

EXPANSION TO 40 MGD AND REHABILITATION

EQUIPMENT PRESELECTION

DATE:

PROJECT NAME: Brushy Creek Regional Wastewater System – East Plant Expansion to 40 MGD Equipment and Rehabilitation Preselection

Proposal of ________________________________________________________________________

(hereinafter called Proposer).

To the Honorable Mayor and City Council City of Round Rock, Texas (hereinafter called Owner)

Ladies and Gentlemen:

The Proposer, in compliance with your Request for Proposals (RFP) for the Brushy Creek Regional Wastewater System – East Plant Expansion to 40 MGD and Rehabilitation Equipment Preselection Project having carefully examined the requirements of the RFP, the specifications included in the RFP, Instructions to Proposers, general requirements including selection process and evaluation criteria, Special Conditions and all other related RFP documents, and being familiar with all of the technical and performance requirements and operating conditions, hereby intends to furnish all labor, materials, supplies, and services for supply and installation of all equipment in accordance with the RFP at the Total Firm System Price (Price) stated below. The Price covers all expenses incurred in supplying, inspecting, testing, training, and starting up the expansion and upgrades in accordance with the requirements of the RFP.

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 7 OF 16 BCE EQUIP PRESELECTION

Section 43 11 11-PS: Blowers, Single-stage Centrifugal – Design Alternative A

PROPOSAL

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

1a For all Work defined in the RFP to supply 1 complete single-stage centrifugal blower (Section 43 11 11- PS “Blower, Single Stage Centrifugal, Integrally Geared, Guided Vane”), with individual blower protection devices.

LUMP

SUM

1 $ _______________

1b Guaranteed 4160V input power usage at primary design operating point running 10% of the time.

kW

_________ N/A

Price Index for Metal Materials Adjustment: The Proposer shall specify the percentage of the proposal price subject to adjustment as described in Section 00 11 13-PS “Instructions to Proposers.”

The proposer can choose the percent adjustment between 0-30% that will be applied. If the Proposer would not like to make adjustments to the price based on a metal materials index enter 0% / zero%.

Failure to fill out adjustment amount will be taken as a 0% / zero% proposal.

(Percentage in Figures)

(Percentage in Words)

___________ Proposer’s Initials

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 8 OF 16 BCE EQUIP PRESELECTION

Section 43 11 17-PS: Blowers, Multistage Centrifugal – Design Alternative A

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

2a For all Work defined in the RFP to supply 1 complete multistage centrifugal blower (Section 43 11 17- PS “Blowers, Multistage Centrifugal”), with individual blower protection devices.

LUMP

SUM

1 $ _______________

2b Guaranteed 4160V input power

Price Index for Metal Materials Adjustment: The Proposer shall specify the percentage of the proposal

The proposer can choose the percent adjustment between 0-30% that will be applied. If the Proposer

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 9 OF 16 BCE EQUIP PRESELECTION

Section 43 11 11-PS: Blowers, Singlestage Centrifugal – Design Alternative B

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

3a For all Work defined in the RFP to supply 2 complete singlestage centrifugal blower (Section 43 11 11- PS “Blower, Single Stage Centrifugal, Integrally Geared, Guided Vane”), with individual blower protection devices.

LUMP

SUM

1 $ _______________

3b Guaranteed 4160V input power

Price Index for Metal Materials Adjustment: The Proposer shall specify the percentage of the proposal

The proposer can choose the percent adjustment between 0-30% that will be applied. If the Proposer

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 10 OF 16 BCE EQUIP PRESELECTION

Section 43 23 57-PS: Pumps, Progressive Cavity (BFP Feed, Dewatering Polymer Feed Pumps)

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

4a For all Work defined in the RFP to supply complete progressive cavity pumps for BFP feed (Section 43 23 57-PS “Pumps, Progressive Cavity (BFP Feed Pumps and Polymer Pumps)”).

Qty of 2 BFP feed pumps.

LUMP

SUM

1 $_______________

4b For all Work defined in the RFP to supply complete progressive cavity pumps for polymer feed (Section 43 23 57-PS “Pumps, Progressive Cavity (BFP Feed Pumps and Polymer Pumps)”).

Qty of 6 polymer feed pumps.

SUM

1 $_______________

Price Index for Metal Materials Adjustment: The Proposer shall specify the percentage of the proposal

The proposer can choose the percent adjustment between 0-30% that will be applied. If the Proposer

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 11 OF 16 BCE EQUIP PRESELECTION

Section 43 25 50-PS: Pumps, Submersible - Immersible

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

5a For all Work defined in the RFP to supply complete submersible-immersible pumps for ILS 1 (Section 43 25 00-PS “Pumps, Submersible - Immersible”).

Qty of 2 submersible pumps.

SUM

1 $_______________

5b Guaranteed 480V input power usage at primary design operating point for one influent lift station pump at ILS 1 running 100% of the time.

5c For all Work defined in the RFP to supply complete submersible-immersible pumps for ILS 2 (Section 43 25 00-PS “Pumps, Submersible - Immersible”).

Qty of 2 submersible pumps.

SUM

1 $_______________

5d Guaranteed 480V input power usage at primary design operating point for one influent lift station pump at ILS 2 running 100% of the time.

Price Index for Metal Materials Adjustment: The Proposer shall specify the percentage of the proposal

The proposer can choose the percent adjustment between 0-30% that will be applied. If the Proposer

Acknowledgement of Compatibility: Proposer acknowledges the existing VFD capacities at ILS 1 as described in section 43 25 00-PS “Pumps, Submersible - Immersible” and has confirmed that the proposed motor and the existing VFD are compatible.

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 12 OF 16 BCE EQUIP PRESELECTION

Section 46 61 41-PS: Cloth Media Effluent Filters - Disc Filters

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

6 For all Work defined in the RFP to supply complete cloth media effluent filters (Section 46 61 41-PS “Cloth Media Effluent Filters - Disc Filters”).

LUMP

Price Index for Metal Materials Adjustment: The Proposer shall specify the percentage of the proposal

The proposer can choose the percent adjustment between 0-30% that will be applied. If the Proposer

PLUMMER ASSOCIATES, INC. 00 31 00-PS - PAGE 13 OF 16 BCE EQUIP PRESELECTION

Section 46 66 00-PS: Ultraviolet Light Disinfection Equipment

PACKAGE

DESCRIPTION UNIT QUANTITY PROPOSAL AMOUNT

7a For all Work defined in the RFP to supply complete ultraviolet light disinfection equipment (Section 46 66 00-PS “Ultraviolet Disinfection…