This document is an advertisement for bids for the Holly High School Track & Field Renovations project located in Holly, Michigan. The project is being bid by the Holly Area School District, and the bidding documents were prepared by GMB Architecture + Engineering. The bid documents can be downloaded from Pipeline, and a pre-bid meeting will be held on December 21, 2023, at the project site. Bids must be delivered by 12:00 noon on January 11, 2024, to the Holly Area School District Administration Building or AUCH Construction. Bids will be publicly opened and read at 1:30 PM on January 11, 2024. A bid bond or cashier's check in the amount of at least 5% of the proposal must be submitted with each bid over $29,572.00. Successful bidders whose proposals are $50,000 or more will be required to furnish a Satisfactory Performance and Payment Bond in the amount of 100% of their bid.
The contract opportunity is limited to the jurisdictions of Huron County and the Village of Holly, Michigan. Pricing terms, set asides, incumbents, funding requirements and sources, and other salient information are not provided in the document. The Holly Area School District reserves the right to reject any and/or all bids and to accept the bid that, in its opinion, is in the best interest of the owner.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADVERTISEMENT FOR BIDS
HOLLY AREA SCHOOLS
Holly High School Track & Field Renovations
Holly Area School District will receive firm prime contractor bids for the Holly High School Track & Field
Renovations project located at 6161 E. Holly Road in Holly, Michigan.
The bidding documents consist of plans and specifications as prepared by GMB Architecture + Engineering, 85 East Eighth Street, Suite 200, Holland, MI 49423. Documents may be downloaded from Pipeline.
Contact Rich Gorski or Eric Jones at AUCH Construction, 248-334-2000, if you need assistance viewing or obtaining documents from Pipeline. A copy of the documents will also be available for review at the offices of AUCH Construction, 65 University Drive, Pontiac, MI, 48342, 248-334-2000, on or after
December 13, 2023.
A Pre-Bid meeting will be held at Holly High School, located at 6161 E Holly Rd, Holly, MI 48442 on
Thursday, December 21 at 3:00 PM. The meeting will be held on-site at the main entrance.
An opaque envelope bearing your proposal must identify your company, the project being bid “Holly High
School Track & Field Renovations” and “Sealed Bid, Do Not Open”. The proposal shall be addressed to the attention of Mr. Scott Roper, Superintendent, Holly Area Schools, 920 Baird Street, Holly, MI 48442.
E-mailed and electronically submitted bids will not be accepted.
Bids must be delivered no later than 12:00 noon, Thursday January 11, 2024 to Holly Area School
District at the address noted above or AUCH Construction. Each proposal must be submitted on the forms furnished by the Construction Manager and must be completed in full. Familial Disclosure Statement and the Affidavit of Compliance to the Iran Economic Sanctions Act must both be completed and notarized. A bid bond executed by a U.S. Treasury Listed Surety Company acceptable to AUCH Construction or a cashier’s check in the amount of at least 5% of the sum of the proposal payable to Holly Area Schools shall be submitted with each proposal in excess of $29,572.00. All proposals shall be firm for a period of sixty
(60) days.
Bids will be publicly opened and read at a meeting convened at the Holly Area Schools Administration
Building located at 920 Baird Street, Holly, MI 48442 starting at 1:30 PM on January 11, 2024.
Successful bidders whose proposals are $50,000 or more will be required to furnish a Satisfactory
Performance and Payment Bond in the amount of 100% of their bid. The cost of the Bond shall be included in each proposal.
The Board of Education reserves the right to reject any and/or all bids in whole or in part and to waive any informalities therein. The Board of Education reserves the right to accept that bid which in its opinion, is in the best interest of the Owner.
Jennifer Young
Secretary Board of Education
Holly Area Schools