1__A04_Asphalt_Repair_Rocky_MTN_NWR_SOW_5_5_26.pdf
PDF 4 MB Posted
- Attached to
- CO-ROCKY MTN ARSNL NWR-ASPHALT
- Solicitation number
- 140FGA26Q0024
About this file
This is a Statement of Work for asphalt paving contractor services at Rocky Mountain Arsenal National Wildlife Refuge.
The U.S. Fish and Wildlife Service seeks a contractor to complete an asphalt patch remove and replace operation on approximately 170 feet of the south lane on Auto Tour Route South (FWS 012AZ, also known as E. 64th Avenue), located directly east of the Lower Derby Lake parking lot in Commerce City, Colorado. The project encompasses approximately 208 square yards of surface area requiring excavation to a 6-inch depth in failed areas, subgrade compaction and preparation, tack coat application, placement of 6 inches of compacted full-depth asphalt, and disposal of excess materials. The USFWS will provide traffic control and signage. The contractor is responsible for coordinating traffic control operations with USFWS to ensure safety. Work must not begin until receipt of the official Notice to Proceed, with performance scheduled from November 1, 2026 through March 31, 2027, during normal duty hours of Monday through Friday, 7:00 a.m. to 4:30 p.m. The NAICS code is 237310 (Highway Street and Bridge Construction). Government acceptance is contingent upon completion of all items listed in the Statement of Work in compliance with state and federal codes. Quality control will be maintained according to industry standards. The Project Lead is David Lucas (Refuge Manager) and the Contracting Officer Representative is Tom Ronning (Refuge Operations Specialist), both located at Rocky Mountain Arsenal NWR, 6550 Gateway Road, Commerce City, Colorado 80022, telephone 303.289.0232.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FGA26Q0024.pdf | ||
| 2__A04_SPEC_-_Asphalt_Crackseal_Entrance_Road.pdf | ||
| 3__B03_WDOL__CO20250006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rocky Mountain Arsenal NWR Asphalt Repair 5.5.2026
STATEMENT OF WORK
Paving Contractor
Asphalt Patch R&R on Auto Tour Route South at Rocky Mountain Arsenal NWR NAICS: 237310 - Highway Street and Bridge Const.
1. General:
This project aims to repair all asphalt surfaces within the identified project area on the Auto Tour Route South east of the Lower Derby Lake parking lot.
This Statement of Work (SOW) describes the general performance of the project and does not attempt to show the exact construction of the work in complete detail. The Contractor is responsible for providing high-quality completed work that maintains the performance intent established by this document.
Overview – The U.S. Fish and Wildlife Service (FWS) needs the Contractor to complete a concrete asphalt patch remove and replace (R&R) on approximately 170 feet of the south lane on the Auto Tour Route South (FWS 012AZ) (also known as “E. 64th Avenue”) directly east of the Lower Derby Lake parking lot. This patch is approximately 170 feet long and 11 feet wide (the width of the south lane of this two-lane roadway).
Specifically, the contractor will reconstruct the roadway in areas where the road was damaged (approximately 208 square yards of surface area):
• The contractor will excavate to a depth of 6” in failed areas
• The contractor will compact and prep subgrade
• The contractor will apply tack coat
• The contractor will pave 6” of compacted full-depth asphalt
• The contractor will dispose of excess materials
The USFWS will be responsible for traffic control and signage on this project.
2. Place of Performance and Period of Performance
Rocky Mountain Arsenal NWR, 6550 Gateway Road, Commerce City, CO 80022
Auto Tour Route South (FWS 012AZ) (also known as “E. 64th Avenue”) directly east of the Lower Derby Lake parking lot. This patch is approximately 170 feet long and 11 feet wide (the width of the south lane of this two-lane roadway).
Period of Performance: Work must not begin until the official Notice to Proceed (NTP) is received from the Contracting Officer.
Performance Start: November 1, 2026 Performance End: March 31, 2027
Normal duty hours Monday thru Friday 7:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.s’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).
3. Scope
Project Description / Scope of Work
RT#012AZ, AUTO TOUR ROUTE SOUTH
Asphalt patch remove and replace (R&R) approximately 170 feet of the south lane on the Auto Tour Route South (FWS 012AZ) directly east of the Lower Derby Lake parking lot.
Reference specifications within SECTION 321216 - ASPHALT PAVING attached.
It will not be necessary to close the road for this repair and the repair area is small. Contractor is responsible for coordinating traffic control with the USFWS to ensure contractor and public safety during operations.
See Photos and Spec sheet (attachment 1) for additional information/requirements
5. Government-Furnished Equipment (GFE) / Government-Furnished Information
(GFI)
NA
6. Evaluation and Acceptance
The contractor will be evaluated as detailed herein. Government acceptance is contingent upon:
All of the items listed with the State of Work are completed and are operational following state and federal codes.
7. Quality Control/Quality Assurance:
QC will be maintained according to industry standards and made available to the agency with the contractor’s proposal.
8. Technical Coordinator:
The U.S. Fish and Wildlife Service Project Lead (PL) for this requirement is:
David Lucas Refuge Manager Rocky Mountain Arsenal NWR, 6550 Gateway Road, Commerce City, CO 80022 303.289.0232 david_c_lucas@fws.gov
The U.S. Fish and Wildlife Service Contracting Officer Representative (COR) for this requirement is:
Tom Ronning Refuge Operations Specialist Rocky Mountain Arsenal NWR, 6550 Gateway Road, Commerce City, CO 80022 303.289.0232 tom_ronning@fws.gov
Photographs:
Figure 1. Auto Tour Route South looking east. Project bounds are south lane as identified with yellow spray paint.
Figure 2. Sample of "alligator" cracking and subsistence of the road within the project area.
Figure 3. Auto Tour Route South looking west. Project bounds are south lane as identified with yellow spray paint.
File details come from the government source that posted it. Updated .