This is a Project Manual and Advertisement for Bids for the Camp Hill Road Force Main Replacement (Contract No. CB-76/UDT-15) issued by the Bucks County Water and Sewer Authority (BCWSA) in Upper Dublin Township, Montgomery County, Pennsylvania. The project consists of the installation of approximately 1,872 linear feet of 6-inch PVC sanitary sewer force main with associated appurtenances, including abandonment of the existing force main, connection to an existing manhole, installation of a quick-connect assembly, excavation and backfill, testing, pavement restoration in Camp Hill Road, finish grading and seeding, bypass pumping to maintain pump station operation during construction, traffic control, erosion control measures, and all necessary work for a complete and operational force main. The work is structured as a single unit-price contract and must be performed in strict accordance with the contract drawings and project manual. A pre-bid conference is scheduled for August 13, 2026, at 10:00 a.m. at the Authority's Tradesville Wastewater Treatment Facility in Warrington, Pennsylvania, with attendance optional. Sealed bids must be submitted electronically via PennBid by 10:00 a.m. on August 25, 2026. The contractor must substantially complete the work within 150 calendar days of the contract commencement date and achieve final completion within 180 calendar days. Liquidated damages are assessed at $500 per day for each day of delay beyond the substantial completion and final payment deadlines.
Bids must be accompanied by bid security equal to ten percent of the bid amount in the form of a certified check, bank money order, or bid bond. The successful bidder must furnish Performance Bonds, Payment Bonds, and Maintenance Bonds (10 percent of contract price) in accordance with the contract documents. The project is subject to Pennsylvania's Act 422 Prevailing Wage Act, and contractors must comply with prevailing minimum wage rates issued by the Pennsylvania Department of Labor and Industry, with weekly certified payrolls required. The Authority is exempt from Pennsylvania state sales and use taxes on materials and equipment incorporated in the work. Contractor responsibility certification is required at least fourteen days before the bid opening date. The BCWSA reserves the right to reject any or all bids, eliminate items from the contract, waive informalities, and award to the bidder deemed to offer the most advantageous bid. No bidder may withdraw their bid within 60 days after the bid opening date. The contract documents were prepared by Gilmore & Associates, Inc., with Engineer Alexander Dyke, P.E., serving as the Owner's representative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-2308071 Camp Hill Road Force Main Replacement Sheet Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
CAMP HILL ROAD
FORCE MAIN REPLACEMENT
CONTRACT #CB-76/UDT-15
UPPER DUBLIN TOWNSHIP
MONTGOMERY COUNTY, PA
JULY 2026
PREPARED FOR:
BCWSA
1275 Almshouse Road Warrington, PA 18976
PREPARED BY:
Gilmore & Associates, Inc.
Engineers • Land Surveyors • Planners • GIS Consultants 65 E. Butler Avenue, Suite 100
New Britain, PA 18901
(215) 345-4330
TABLE OF CONTENTS
00 01 10-1
CAMP HILL ROAD FORCE MAIN REPLACEMENT
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
Division 00 – Procurement and Contracting Requirements
Introductory Information 00 01 01 Project Title Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets
Procurement Requirements 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 21 13.1 Instructions for Submitting Electronic Bids for this Solicitation 00 41 00 Bid Form for Electronic Bidding 00 43 13 Bid Bond 00 45 10 Bidder’s Acknowledgement Form 00 45 13 Bidder Qualification Statement 00 45 19 Non-Collusion Affidavit 00 45 53 Agreement of Surety Company 00 52 00 Agreement 00 61 13.13 Performance Bond 00 61 13.16 Payment Bond 00 61 19 Maintenance Bond 00 62 16 Certificate of Insurance 00 65 19.13 Contractor’s Affidavit 00 65 19.16 Contractor’s Release of Liens 00 65 19.19 Consent of Surety to Final Payment 00 72 00 General Conditions 00 73 00 Supplemental Conditions Appendix A: Prevailing Minimum Wage Determination Appendix B: Public Works Employment Verification Form Appendix C Responsible Contractor Resolution Appendix D: Regulatory Permits 00 91 13 Addenda
SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP
Division 01 – General Requirements
01 12 00 Summary of Project
01 22 00 Measurement and Payment
01 29 00 Contract Considerations
01 31 00 Coordination and Meetings
01 32 36 Audio-Videotaping
01 33 00 Submittals
01 40 00 Quality Control
01 42 13 Organization and Reference Acronyms
01 50 00 Construction Facilities and Temporary Controls
01 54 29 Bypass Pumping
01 55 26 Traffic Regulation
01 57 13 Soil Erosion & Sediment Control
01 57 14 Erosion Control Blanket
01 60 00 Material and Equipment
00 01 10-2
01 70 00 Contract Closeout
EXISTING CONDITIONS SUBGROUP
Division 2 – Existing Conditions
02 41 00 Demolition
02 41 13.13 Milling of Asphalt Pavement
FACILITY CONSTRUCTION SUBGROUP
Division 3 – Concrete 03 30 53 Concrete Work for Utilities
FACILITY FINISHES SUBGROUP
Division 9 – Finishes 09 91 00 Painting
SITE AND INFRASTRUCTURE SUBGROUP
Division 31 – Earthwork 31 11 00 Clearing and Grubbing 31 23 33 Excavation, Backfill & Compaction
Division 32 – Exterior Improvements 32 12 23 Restoration of Paved Surfaces 32 92 00 Finish Grading, Seeding and Sodding
Division 33 – Utilities 33 11 13.01 Abandonment of Underground Utilities 33 34 00 Sewerage Force Mains 33 34 10 Tracer Wire
Division 40 – Process Integration 40 05 23 Valves
END OF DOCUMENT
LIST OF DRAWING SHEETS
00 01 15-1
DOCUMENT 00 01 15
LIST OF DRAWING SHEETS
SHEET NO. SHEET TITLE
1 COVER SHEET
2 INDEX PLAN
3 PLAN & PROFILE STA 0+00 TO 6+00
4 PLAN & PROFILE STA 6+00 TO 12+50
5 PLAN & PROFILE STA 12+50 TO 18+72
6 CONSTRUCTION DETAILS 1
7 CONSTRUCTION DETAILS 2
8 EROSION & SEDIMENT CONTROL NOTES & DETAILS
ADVERTISEMENT FOR BIDS
00 11 13-1
DOCUMENT 00 11 13
ADVERTISEMENT FOR BIDS
Sealed bids will be received by BCWSA (Authority) online at PennBid™ - www.PennBid.net until 10:00 A.M., prevailing time on August 25, 2026, at which time the bids shall be publicly opened for:
Camp Hill Road Force Main Replacement Contract No. CB-76/UDT-15
This project involves the installation of a sanitary sewer force main located in Upper Dublin Township, Montgomery County, PA. The work generally includes complete installation of a sanitary sewer force main and other equipment necessary for the complete operation of a sanitary sewer force main. This Work is to be performed as shown on the Contract Drawings, including structures, piping, fittings, abandonment of existing force main, excavation and backfill, pavement restoration in Camp Hill Road, testing, and all necessary appurtenances for a complete and operating force main as specified in the Project Manual.
All Bid Documents and solicitation details are available at no cost at PennBid™ -www.ebidexchange.com/pennbid. Click on the “Solicitations” then “View” tabs.
Each bid shall be submitted in accordance with the Instructions to Bidders and must be accompanied by a Bid Bond or Certified Check for not less than ten percent (10%) of the Bid amount payable to the Authority along with an Agreement of Surety certifying that the required Performance and Payment Bonds will be provided to the Bidder.
The successful Bidder shall be required to furnish proof of insurance and bonds for Performance, Payment, and Maintenance in such form as meets the approval of the Authority and having as security thereon such Surety company or companies as are approved by the Authority.
A pre-bid conference has been scheduled by the Authority to be held on August 13, 2026 starting at 10:00 A.M. prevailing time at the Authority’s Tradesville Wastewater Treatment Facility located on Pickertown Road in Warrington, PA. 18976. Attendance at the pre-bid conference is not mandatory.
Questions will be received on PennBid™ only until August 20, 2026, at 2:00 P.M.
This project is subject to applicable provisions of Act 422, Pennsylvania Prevailing Wage Act as amended and the prevailing minimum wage rates issued by the Pennsylvania Department of Labor and Industry, and weekly certified payrolls will be required to attest to this.
No Bidder may withdraw his bid within sixty (60) days after the date set for the opening of the bids.
BCWSA reserves the right to reject any or all bids for any cause whatsoever, to eliminate any item or items from the contract, to waive any informality in the bids or to make an award to Bidder who, in the judgment of the Authority, makes the most advantageous bid. Additionally, BCWSA requires Contractor Responsibility Certification at least fourteen (14) days before the date set for the opening of the bids.
The following professional consultants are responsible to the Authority for the project: Gilmore & Associates, Inc., 65 East Butler Avenue, Suite 100, New Britain, PA 18901, attention: Alexander Dyke, P.E.
By order of: John W. Butler, COO Owner: BCWSA Date: 7/28/2026 http://www.pennbid.net/ http://www.ebidexchange.com/pennbid
INSTRUCTIONS TO BIDDERS
00 21 13-1
DOCUMENT 00 21 13
Page
Article 1 - Defined Terms 3
Article 2 - Copies of Bidding Documents 3
Article 3 - Qualifications of Bidders 3
Article 4 - Examination of Bidding Documents, Other Related Data, and Site 3
Article 5 - Pre-Bid Meeting 5
Article 6 - Site and Other Areas 5
Article 7 - Interpretations and Addenda 5
Article 8 - Bid Security 6
Article 9 - Contract Times 6
Article 10 - Liquidated Damages 6
Article 11 - Substitute and "Or-Equal" Items 6
Article 12 - Subcontractors, Suppliers, and Others 6
Article 13 - Preparation of Bid 7
Article 14 - Basis of Bid; Evaluation of Bids 7
Article 15 - Submittal of Bid 7
Article 16 - Modification and Withdrawal of Bid 7
Article 17 - Opening of Bids 7
Article 18 - Bids to Remain Subject to Acceptance 8
Article 19 - Evaluation of Bids and Award of Contract 8
Article 20 - Contract Security and Insurance 8
Article 21 - Signing of Agreement 8
Article 22 - Sales and Use Taxes 9
Article 23 - Retainage 9
00 21 13-2
Page
Article 24 - Contracts to be Assigned 9
Article 25 - Blasting & Pre-Blasting Survey 9
Article 26 - Permits 9
Article 27 - Rock Removal 9
Article 28 - Government Requirements 9
Article 29 - Sequence of Construction 9
Article 30 - Coordination of Related Work at the Site 9
Article 31 - Steel Products Procurement Act 9
Article 32 - Information Concerning Owner and Engineer 10
Article 33 - E-Verify® Program 10
00 21 13-3
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings below:
A. Bidder: The individual or entity who submits a Bid directly to Owner.
B. Issuing Office: The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
C. Successful Bidder: The lowest responsible Bidder submitting a responsive Bid to whom Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents are available online for no cost at PennBid.
(www.ebidexchange.com/pennbid )
2.02 Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer in making Bidding Documents available on the above terms do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder's qualifications to perform the Work, Bidder must submit with his Bid a completed
Bidder Qualification Statement. In lieu of the Bidder Qualification Statement, Bidder may submit with his Bid, a completed Construction Contractor's Qualification Statement for Engineered Construction developed by The Associated General Contractors of America (AGC Document No. 220).
3.02 If additional information is necessary to demonstrate qualifications to perform the Work, within five (5) days of Owner's request, Bidder shall submit written evidence such as financial data, previous experience, present commitments and such other data as may be reasonably requested.
3.03 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE
4.01 Subsurface and Physical Conditions
A. The Supplementary Conditions identify:
1. Those reports known to Owner of explorations and tests of subsurface conditions at or contiguous to the Site.
2. Those drawings known to Owner of physical conditions relating to existing surface and subsurface structures at or contiguous to the Site (except Underground Facilities).
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground
Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
http://www.ebidexchange.com/pennbid
00 21 13-4
4.03 Hazardous Environmental Condition
A. The Supplementary Conditions identify any reports and drawings known to Owner relating to any
Hazardous Environmental Condition identified at the Site.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated surface or physical conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in Paragraph 4.06 of the General Conditions.
4.05 On request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.06 A. Reference is made to Paragraph 1.18 of the Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents. On request, Owner will provide to each Bidder for examination access to or copies of contract documents (other than portions thereof related to price) for such other work.
B. Paragraph 6.13.C of the General Conditions indicates that if an Owner safety program exists, it will be noted in the Supplementary Conditions.
4.07 It is the responsibility of each Bidder before submitting a Bid to do the following:
A. Examine and carefully study the Bidding Documents, and the other related data identified in the Bidding
Documents;
B. Visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. Become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, or performance of the Work;
D. Carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the
Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in Paragraph 4.02 of the Supplementary Conditions as containing reliable “technical data”, and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in Paragraph 1.06 of the Supplementary Conditions as containing reliable “technical data”;
E. Consider the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs;
00 21 13-5
F. Agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.
G. Become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. Promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
I. Determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 - PRE-BID MEETING
5.01 A pre-bid meeting has been scheduled by the Authority to be held on Thursday August 13, 2026, starting at 10:00 A.M. prevailing time at the Tradesville Wastewater Treatment Facility located on Pickertown Road in Warrington, PA. Attendance at the pre-bid meeting is not mandatory.
ARTICLE 6 - SITE AND OTHER AREAS
6.01 The Sites are identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be directed to Engineer by clicking on the Questions tab within PennBid. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda and posted within the PennBid Documents.
Notifications of addenda will be emailed to all parties recorded by Engineer as having downloaded the Bidding Documents. Questions received after the posted cut-off date of August 20, 2026 at 2:00 P.M. may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
00 21 13-6
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of ten percent (10%) of
Bidder’s maximum Bid price and in the form of a certified check, bank money order or a Bid Bond (on the form in Project Manual or equivalent) issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions.
8.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Agreement, furnished the required contract security and insurance certificate(s) and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Agreement and furnish the required contract security and insurance certificate(s) within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Agreement, after all bids are rejected by Owner or after the date the bid acceptance period has expired, whichever occurs first, whereupon Bid security furnished by such Bidders will be returned.
8.03 Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within seven days after the Bid opening.
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be based on materials and equipment specified or described in the Bidding
Documents without consideration of possible substitute or “or-equal” items. Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement.
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.
12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities.
Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and
00 21 13-7
Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.
12.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom
Contractor has reasonable objection.
ARTICLE 13 - PREPARATION OF BID
13.01 Document 00 21 13.1, entitled Instructions for Submitting Electronic Bids for This Solicitation contains a full description of what documents are to be submitted electronically along with instructions on how to submit sealed bids.
ARTICLE 14 - BASIS OF BID; EVALUATION OF BIDS
14.01 Lump Sum
A. Bidders shall submit a Bid on a unit price basis as set forth in the electronic Bid Form. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the electronic Bid schedule including any incidental Bid items.
B. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Paragraph 11.03 of the General Conditions.
14.02 Bid prices shall include all taxes of whatever nature applicable to the Work or Bidder's performance thereof.
ARTICLE 15 - SUBMITTAL OF BID
15.01 Bids are to be submitted electronically via the PennBid Program. Document 00 21 13.1 entitled Instructions for Submitting Electronic Bids for This Solicitation is included as part of this solicitation and provides instructions on what information needs to be submitted along with how to submit it.
15.02 A Bid shall be submitted via PennBid no later than the date and time prescribed in the advertisement or invitation to bid.
15.03 The Bidder is solely responsible for submitting his Bid by the time indicated in the advertisement or invitation to bid.
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A bid may be withdrawn any time prior to the bid closing date and time by clicking on the “Withdraw Bid” button within PennBid.
16.02 Bids may be withdrawn within two (2) business days after the opening of Bids only by the withdrawing Bidder's strict compliance with 62 PA.C.S. §512 and any subsequent amendments.
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
00 21 13-8
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period. Thirty (30) day extensions of the date for the award may be made by the mutual consent of Owner and the lowest responsible and responsive Bidder.
ARTICLE 19 - EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, non-responsive, unbalanced, or conditional Bids. Owner reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
19.03 In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work in accordance with the Contract Documents.
19.06 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project.
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by such Bonds and required insurance certificate(s).
ARTICLE 21 - SIGNING OF AGREEMENT
21.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement to Owner with the required Bonds and insurance certificate(s). Owner shall deliver one fully signed counterpart to Successful Bidder within sixty (60) days of the date of the Notice of Award.
00 21 13-9
ARTICLE 22 - SALES AND USE TAXES
22.01 Owner is exempt from Pennsylvania state sales and use taxes on certain materials and equipment to be incorporated in the Work. Contractor will be provided with a copy of Owner's tax-exempt certificate. Said taxes shall not be included in the Bid. Refer to Paragraph 1.15 of the Supplementary Conditions for additional information.
ARTICLE 23 - RETAINAGE
23.01 Provisions concerning Contractor’s rights to deposit securities in lieu of retainage are set forth in the
Agreement.
ARTICLE 24 - CONTRACTS TO BE ASSIGNED
24.01 Not Used
ARTICLE 25 - BLASTING AND PRE-BLASTING SURVEY
25.01 Blasting will not be permitted on this project.
ARTICLE 26 - PERMITS
26.01 Paragraph 1.25 of the Supplementary Conditions presents the respective obligations of Owner and
Contractor, regarding the obtaining of permits and/or approvals from governmental agencies relative to the proposed Work.
ARTICLE 27 - ROCK REMOVAL
27.01 The Total Bid Price is to include rock removal required to accomplish construction of the proposed Work.
ARTICLE 28 - GOVERNMENT REQUIREMENTS
28.01 Bids shall be submitted based on full and total compliance with all Federal and State laws, regulations, statutes and requirements pertaining to the Work. Bidder shall refer to Paragraph 1.12 of the Supplementary Conditions.
ARTICLE 29 - SEQUENCE OF CONSTRUCTION
29.01 Section 01 12 00 (Summary of Project) notes the sequence of construction relative to this project.
ARTICLE 30 - COORDINATION OF RELATED WORK AT THE SITE
30.01 Reference is made to Paragraph 1.19 of the Supplementary Conditions relative to claims between contractors. The general contractor is the prime contractor who will have authority and responsibility for coordination of activities involving other parties and/or prime contractors relative to construction of the Project.
ARTICLE 31 - STEEL PRODUCTS PROCUREMENT ACT
31.01 The Bidder shall comply with the Steel Products Procurement Act, Pennsylvania Act No. 3, 1978, including any revisions. See Document 00 73 00 Supplementary Conditions, paragraph 1.14.
00 21 13-10
ARTICLE 32 - INFORMATION CONCERNING OWNER AND ENGINEER
32.01 Owner:
Telephone: 215-343-2538
Attention: John W. Butler, Chief Operating Officer (b.john@BCWSA.net)
32.02 Engineer:
Gilmore and Associates, Inc.
65 E. Butler Avenue, Suite 100
Telephone: (215) 345-4330
Attention: Alexander Dyke, P.E. (adyke@gilmore-assoc.com)
ARTICLE 33 - E-VERIFY® PROGRAM
33.01 Contractor will be required to enroll in the E-Verify® program to electronically verify the employment eligibility of employees to legally work in the United States.
INSTRUCTIONS FOR SUBMITTING ELECTRONIC BIDS FOR THIS SOLICITATION
00 21 13.1-1
DOCUMENT 00 21 13.1
Using the PennBid™ electronic bid management system to respond to this Request-for-Quotation.
Many PA municipalities, Authorities, and private firms are utilizing the PennBid™ electronic procurement Program for their solicitations, RFPs, and RFQs. Using PennBid is beneficial to both the agencies as well as the bidders.
Costs and bidding effort is greatly reduced as bid documents are available online, all Q&A’s are via email, and sealed bids can be submitted and updated online. Interested bidders need to register only once, a free process that takes only a few minutes. Once registered, bidders have access to publically available bids and solicitations from every Agency within PennBid, plus are available for By-Invitation-Only RFPs and RFQs. Bidders can obtain all project documents and submit and update their confidential bids online.
Sealed Bid Confidentiality – The confidentiality of the sealed bid system is a cornerstone of the PennBid
Program. At no time before Bid Opening can anyone see your electronic bid.
Confidentiality of Identity – When questions are asked and answered, bidder identity is not disclosed to other bidders.
1. Documents – All documents may be downloaded directly to your computer. Documents can be electronically sent to your suppliers and sub-contractors.
2. Being added to the “Bidders List” – By downloading any document, you are automatically added to the list of bidders for this solicitation.
3. Questions – By clicking on the “Questions” tab, you can see all questions that have been asked and answered related to this solicitation. You can also ask questions directly through this tab. When the agency answers the question, both the question and answer is emailed directly to all bidders.
4. Submitting and Updating Bids – You may submit and update your bid anytime up to the bid due date and time by clicking on the “Bid” tab. You need only to provide the per unit price. The PennBid Program will automatically calculate the extended price (no more math errors). You can update any line item without affecting the rest of your quote.
What to submit with this bid
Click on the “Bid” tab and select the Contract you are bidding on:
▪ Enter financial bid.
▪ Answer questions
▪ Attach a single electronic file or zipped folder containing the documents listed below.
o 00 4313 – Bid Bond or other Bid Security o 00 4510 – Bidder’s Acknowledgement Form o 00 4513 – Bidder Qualification Statement or Construction Contractor's Qualification Statement for Engineered Construction (AGC Document No. 220) except for providing the recent Financial Statement.
o 00 4519 – Non-Collusion Affidavit o 00 4553 – Agreement of Surety
00 21 13.1-2 o 00 7300 Appendix B – Public Works Employment Verification Form
Important Note 1 - The three apparent low bidders shall submit the above documents in original form and signatures to the agency receiving the bids within 3 business days following bid opening. The recent Financial Statement shall be included with the Bidder Qualification Statement at this time.
Important Note 2 - If the PennBid Program is idle for 50 minutes, a logout warning will appear. Bidders must acknowledge. If bidder does not acknowledge that they want to continue working, they will be logged out and bidder’s data will not be saved or submitted.
How to submit your bid
The Bid tab contains the electronic bid form. All Per Unit Price fields must be filled out. To no-bid a line item, insert a zero (0). PennBid will automatically complete the line extensions and bid totals. At the bottom of the page, check the Verification Statement and click Submit Bid. Completed bid form can be printed or saved to Excel by clicking the icons in the middle of the bid form page.
Submitting documents with electronic bid
An electronic copy of the documents listed above is to be submitted with the electronic bid. To attach these documents:
1. Fill out required documents and scan to create a single electronic file or saved as a single zipped folder containing all documents.
2. From the Bid tab, click on “browse” (middle of the page), then click on the file or zipped folder name. The file will be attached to your bid submission when the Submit Bid button is clicked.
Important Note 3 – When uploading a proposal or other document, the maximum individual file or folder size is 20Mb.
Verifying that your bid was submitted.
If submitted properly, you will receive an acknowledgement appearing in the middle of your screen saying, “Your bid has been submitted.”
Withdrawing Your Bid
You may withdraw your bid anytime up to bid due date and time by simply clicking on Withdraw Bid, located at the bottom of the Bid tab.
Help Guides
There are several Help Guides available from the PennBid™ Home Page.
BID FORM
00 41 00-1
DOCUMENT 00 41 00
BID FORM
The Bid Form associated with a specific Contract may be found on the “PennBid” website at the “Bids “tab for the specific Contract.
DAMAGES FORM
EJCDC C-435 Bid Bond (Damages Form)
Prepared by the Engineers Joint Contract Documents Committee.
BID BOND
00 43 13-1
DOCUMENT 00 43 13
Any singular reference to Bidder, Surety, Owner, or other party shall be considered plural where applicable.
BIDDER (Name and Address):
SURETY (Name and Address of Principal Place of Business):
OWNER (Name and Address):
1275 Almshouse Road Warrington, PA 18976
BID
Bid Due Date:
Description (Project Name and Include Location):
BOND
Bond Number:
Date (Not earlier than Bid due date):
Penal sum $
(Words) (Figures)
Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.
BIDDER SURETY
(Seal) (Seal)
Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal
By: By:
Signature Signature (Attach Power of Attorney)
Print Name Print Name
Title Title
Attest: Attest:
Signature Signature
Note: Above addresses are to be used for giving any required notice. Provide execution by any additional parties, such as joint venturers, if necessary.
DAMAGES FORM
EJCDC C-435 Bid Bond (Damages Form)
00 43 13-2
1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder any difference between the total amount of Bidder’s Bid and the total amount of the Bid of the next lowest, responsible Bidder who submitted a responsive Bid as determined by Owner for the work required by the Contract Documents, provided that:
1.1 If there is no such next Bidder, and Owner does not abandon the Project, then Bidder and Surety shall pay to Owner the penal sum set forth on the face of this Bond, and
1.2 In no event shall Bidder’s and Surety’s obligation hereunder exceed the penal sum set forth on the face of this Bond.
1.3 Recovery under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.
2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.
3. This obligation shall be null and void if:
3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or
3.2 All Bids are rejected by Owner, or
3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).
4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.
5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from Bid due date without Surety’s written consent.
6. No suit or action shall commence under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after Bid due date.
7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.
8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.
9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.
10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.
11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.
BIDDER’S ACKNOWLEDGEMENT FORM
00 45 10-1
DOCUMENT 00 45 10
PROJECT IDENTIFICATION: Camp Hill Road Force Main Replacement
CONTRACT IDENTIFICATION AND NUMBER: Contract No. CB-76/UDT-15
1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with
OWNER in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
2.01 Bidder accepts all the terms and conditions of the Advertisement or Invitation to Bid and Instructions to
Bidders, including without limitation those dealing with the disposition of Bid security. The Bid will remain subject to acceptance for sixty (60) days after the Bid opening, or for such longer period that Bidder may agree to in writing upon request of OWNER.
3.01 In submitting this Bid, Bidder represents, as set forth in the Agreement, that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of all of which is hereby acknowledged.
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied regarding the general, local and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in paragraph 4.02 of the General Conditions, and
(2) reports and drawings of a Hazardous Environmental Condition, if any, which has been identified in the Supplementary Conditions as provided in paragraph 4.06 of the General Conditions.
E. Bidder has obtained and carefully studied (or assumes responsibility for having done so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.
F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by OWNER and others at the Site that relates to the Work as indicated in the Bidding Documents.
00 45 10-2
H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.
I. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that
Bidder has discovered in the Bidding Documents, and the written resolution thereof by ENGINEER is acceptable to Bidder.
J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance of the Work for which this Bid is submitted.
4.01 Bidder further represents that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any individual or entity to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over OWNER.
5.01 Bidder is aware that the Total Bid Price is to include rock removal required to accomplish construction of the proposed Work.
6.01 Bidder will complete the Work in accordance with the Contract Documents for the submitted bid amount.
Unit Prices have been computed in accordance with paragraph 11.03.B of the General Conditions.
Bidder acknowledges that estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents.
7.01 Bidder agrees that the Work will be substantially complete within one hundred fifty (150) calendar days after the date when the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.07.B of the General Conditions within one hundred eighty (180) calendar days after the date when the Contract Times commence to run.
7.02 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified above, which shall be stated in the Agreement.
8.01 The following documents are attached to and made a condition of this Bid:
A. Required Bid security;
B. Required Agreement of Surety;
C. Required Bidder's Qualification Form with supporting data;
D. Required Non-Collusion Affidavit
9.01 Communications concerning this Bid shall be addressed to the following individual:
Alexander Dyke, P.E., Gilmore & Associates, Inc.
If the address, telephone number, and fax number of the above individual is different than noted at the end of the Bid Form, note the address, telephone number, and fax number of the above individual:
00 45 10-3
Business Address: Gilmore & Associates, Inc.
65 E. Butler Avenue, Suite 100
New Britain, PA 18901
Telephone No.: (215) 345-4330
Email: adyke@gilmore-assoc.com
10.01 The terms used in this Bid with initial capital letters have the meanings indicated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
Submitted on , 20___.
Name of Bidder:
Corporation State of Incorporation:
Date of Qualification To do Business:
Partnership General Partner:
Individual Doing Business as:
Business Address:
Telephone No.: (____)
Fax No.: (____)
Name of Person authorized to sign (typed or printed):
Title of Person authorized to sign (typed or printed):
(Authorized Signature)
SEAL Affix Corporate Seal
If Corporation
Attested by Corporate Secretary or An Assistant Secretary if Corporation
BIDDER QUALIFICATION STATEMENT
00 45 13-1
DOCUMENT 00 45 13
1. INTRODUCTION
1.1 This document must be included as part of the Bid submission. Failure to submit a fully completed and executed Bidder Qualification Statement may be considered justification for rejection of the bid.
1.2 This Bidder Qualification Statement is submitted with respect to the following project:
2. GENERAL INFORMATION
2.1 Name of Bidder:
2.2 Address of Bidder:
2.3 Telephone No. of Bidder:
3. ORGANIZATIONAL BACKGROUND
3.1 Type of Organization:
Corporation Individual
Partnership Joint Venture
Other:
3.2 How long has your organization been in business?
a. As a Contractor? Years
b. As a Contractor engaged in construction work of the type proposed under this Contract:
______ Years
c. Under your current business name? ______ Years
3.3 If the bidder is a corporation, complete this section:
a. Date & State of Incorporation:
b. Names & Titles of Officers:
00 45 13-2
3.4 If the Bidder is other than a corporation, describe the structure of your organization including date of initiation as a business and list the principals involved:
3.5 What portions of the work (i.e. trades work items, etc.) included in the proposed contract will be performed by subcontractors?
4. WORK HISTORY
4.1 Attach or list the following information on similar projects which your organization has completed in the past five (5) years. Name and type of project, owner, engineer, contract amount, date of completion.
00 45 13-3
4.2 Attach or list the following information on similar project which your organization now has in progress: name and type of project, owner, engineer, contract amount, scheduled date of completion.
4.3 Has your organization ever defaulted on or otherwise failed to complete any work under contract?
If so, note the circumstances:
4.4 Has any officer, partner or principal of your organization ever been an officer, partner or principal of another organization which defaulted on or otherwise failed to complete any work under contract? If so, note the circumstances:
4.5 Provide the construction experience (length, type) of the principal individuals of your organization which would be assigned to perform the proposed work under this Contract:
5. REFERENCES
5.1 Bonding Company
And Agent
00 45 13-4
5.2 Bank
5.3 Trade
6. FINANCIAL STATEMENT
6.1 Attach a copy of a recent financial statement as prepared by your auditor.
7. CERTIFICATION
7.1 This Bidder Qualification Statement has been prepared on behalf of the following organization:
Name of Organization:
Name of Preparer:
Title of Preparer:
Date:
7.2…