About this file

This bid specification document is issued by the South Hills Area Council of Governments (SHACOG) on behalf of the Municipality of Mt. Lebanon in Allegheny County, Pennsylvania for the CD 51-7.5 2025 ADA Ramp Project. The project involves the installation of handicapped curb ramps at various locations throughout Mt. Lebanon, including concrete sidewalk replacement and concrete curb replacement work using PennDOT Class AA concrete with truncated domes meeting accessibility standards. The scope includes three unit price bid items: handicap ramp installation (280 square feet), concrete sidewalk replacement (515 square feet), and concrete roll and straight curb replacement (89 linear feet). Bidding documents are available through PennBid beginning October 29, 2026, with bids due by 10:00 A.M. on November 19, 2026, and electronic opening at 10:01 A.M. the same day. The contractor must achieve substantial completion within 45 calendar days and final completion within 60 calendar days from the contract commencement date, with liquidated damages of $300 per calendar day for delays. All work must be completed by May 31, 2027. Site visits are required, and questions should be submitted through PennBid's "Clarifications from Vendors" feature.

Bids must be submitted on a unit price basis and accompanied by a bid bond of 10 percent of the maximum bid price. The successful bidder must provide performance and payment bonds each equal to 100 percent of the contract price and a two-year maintenance bond in the amount of 50 percent of the final contract value. Insurance requirements include workers' compensation (statutory with $1,000,000 employer's liability), commercial general liability ($2,000,000 aggregate), and business auto liability ($1,000,000 combined single limit). The project is funded in part through the U.S. Department of Housing and Urban Development (HUD) Community Development Block Grant funds and is designated as a Section 3 project requiring utilization of lower-income residents and Section 3 business concerns to the greatest extent feasible. Compliance is mandatory with the Davis-Bacon Act, prevailing wage requirements, Title VI of the Civil Rights Act, Section 504 of the Rehabilitation Act, the Americans with Disabilities Act, and Executive Orders 11625 and 12138 regarding minority and female business enterprise utilization. Bidders must obtain a Unique Entity Identification (UEID) number through SAM.gov. Award is contingent upon HUD fund release, with payment processing potentially requiring 4 to 8 weeks from SHACOG processing.

View the file

Other files

File Type Posted
2-CDBG Procurement Packet.pdf PDF
1-Brentwood Bid Specs - CDBG Year 50 Curb Ramps.pdf PDF
1-Heidelberg Borough CD 50 ADA Ramp Specifications Complete 2.pdf PDF
1-2026-7-2 Mt Lebanon 2024 ADA Ramp Project -bid specs.pdf PDF
1-IFB CD 50-3.11.2 Borough of Jefferson Hills Demolition Project.pdf PDF
2-CDBG Procurement Paperwork.pdf PDF
11-Hardwood Bark Mulch spec 26.pdf PDF
10-Ballfield Mixture spec 26.pdf PDF
9-Mushroom Compost spec 26.pdf PDF
22-Road Aggregates spec 26.pdf PDF
8-Guide Rails-Components spec 26.pdf PDF
17-Wood Carpet spec 26.pdf PDF
4-Plastic Pipe spec 26.pdf PDF
16-Thermoplastic Pavement Markings spec 26.pdf PDF
14-Wastewater Treatment Chemicals spec 26.pdf PDF
18-Precast Concrete Inlets spec 26.pdf PDF
21-Topsoil spec 26.pdf PDF
1-Bid Instructions Spring 26.pdf PDF
5-Line Painting - Beads spec 26.pdf PDF
20-Weed Killer spec.26.pdf PDF
23-Swimming Pool Chemicals spec 26.pdf PDF
15-Traffic Signs-Sign Posts spec.26.pdf PDF
6-Fertilizer spec 26.pdf PDF
19-Liquid Asphalt spec 26.pdf PDF
12-Bituminous Surfacing Materials spec 26.pdf PDF
2-Manhole Inserts spec 26.pdf PDF
13-Frames, Rings, Grates spec 26.pdf PDF
3-Portable Toilet Rental Service spec 26.pdf PDF
7-Guide Rails-Installation spec 26.pdf PDF
2-CDBG Procurement Paperwork.pdf PDF
1-CD 50-7.5 Bid Specs.pdf PDF
3-Project Bid Form CD50-7.5.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOUTH HILLS AREA COUNCIL OF GOVERNMENTS

ALLEGHENY COUNTY

PENNSYLVANIA

CONTRACT DOCUMENTS

FOR:

CD 51 7.5

2025 ADA Ramp Project-Mt. Lebanon

Municipality of Mt. Lebanon

Installation of handicapped curb ramps at various locations throughout the Municipality of Mt. Lebanon.

C-97043-0025

Penn BID Bid Opening: November 19th, 2026 at 10:00 am

2600 Old Greentree Road Phone: 412 / 429-1130

2nd Floor Facsimile: 412 / 429-3230

Scott Township, Pennsylvania

15106

00010 Table of Contents

00010-1

TABLE OF CONTENTS

DIVISION 0 - BIDDING DOCUMENTS AND CONTRACT

00001 – Project Title Page

00010 – Table of Contents

00100 – Invitation to Bid – Advertisement

00105 – Instructions to Bidders - SHACOG

00110 – Proposal, Bid Forms and Supplements

00130 – Bid Bond

00180 – Non-Collusion Affidavit

00190 – Public Works Employment Verification Form

00200 – Instructions to Bidders

00490 – Bidding Addenda

00510 – Notice of Award

00520 – Agreement

00550 – Notice to Proceed

00605 – Certificate of Insurance

00610 – Performance Bond

00615 – Payment Bond

00620 – Application for Payment

00700 – General Conditions

00800 – Supplementary Conditions

00830 – Prevailing Wages

00940 – Work Change Directive

00941 – Change Order

00942 – Field Order

DIVISION 1 – GENERAL REQUIREMENTS

01100 – Summary

01110 – Project Specifications

01250 – Contract Modification Procedures

01270 – Unit Prices

01290 – Payment Procedures

01322 – Photographic Documentation

01330 – Submittal Procedures

DIVISION 2 – SITE CONSTRUCTION

02220 – Traffic Control

02751 – Cement Concrete Pavement

02920 – Lawns and Grasses

ATTACHMENTS

Allegheny County Economic Development Procurement Compliance Package

Ramp Location Map

ADA Ramp Designs

Details

RC-67M

Invitation for Bids South Hills Area Council of Governments HEREBY GIVES NOTICE that specifications and proposal forms for furnishing all labor and materials and professional consulting and/or construction services for the following project entitled:

CD 51-7.5a – Mt. Lebanon ADA Ramps Project may be obtained through pennbid.net (“PennBid”) available October 29, 2026.

Complete sets of bidding documents and bid specifications are available at no cost and may ONLY be received and accepted via the online electronic bid service of PennBid.

Questions regarding these projects shall be submitted via the “Clarifications from Vendors” feature within PennBid. Bids will be received until 10:00 A.M. November 19th, 2026, by the SHACOG through PennBid. Bids will be electronically opened at 10:01 A.M. on Thursday, November 19th, 2026. Bids must be accompanied by a bid bond of not less than 10%.

“Compliance is required with the Davis-Bacon Act and other Federal Labor Standard Provisions; Title VI and other applicable provisions of the Civil Rights Act of 1964; the Department of Labor Equal Opportunity Clause (41 CFR 60 – 1.4); Section 109 of the Housing and Community Development Act of 1974; Executive Order 11625 (Utilization of Minority Business Enterprise); Executive Order 12138 (Utilization of Female Business Enterprise); in compliance with Section 504 of the Rehabilitation Act of 1973 and the Americans with Disabilities Act of 1990.

Further, notice is hereby given that this is a Section 3 Project under the Housing and Urban Development Act of 1968, (as amended) and must to the greatest extent feasible, utilize lower income residents for employment and training opportunities and Section 3 Business concerns and all contracts and subcontracts for this project shall contain the “Section 3 Clause” as set forth in 24 CFR, Part 135.38. Moreover, compliance is required by the prime contractor and all subcontractors with the Federal General Conditions included in the contract documents between the County of Allegheny through its Department of Economic Development and the operating agency. These Federal General Conditions are to be incorporated by reference into all construction contracts between operating agency and contractor, contractor and subcontractor(s), and subcontractor(s) and lower tiered subcontractor(s).”

The South Hills Area Council of Governments and/or the Municipality of Mt. Lebanon, reserve the right to reject any and all bids, alternates or parts of bids and to waive any informality in the proposals received.

Patrick Conners, SHACOG Executive Director

SOUTH HILLS AREA COUNCIL OF GOVERNMENTS

INSTRUCTIONS TO BIDDERS

1. All proposals must be submitted electronically through pennbid.net

2. The communities for which bids are being requested have different specifications and instructions for construction of projects identified, bidders must submit proposals in accordance with the specifications of these communities, including using their forms for the submission of proposals as well as completing any required SHACOG forms.

3. If the specifications provide for the submission of alternate bids, the bid must clearly indicate whether an alternate bid is included. Each alternate bid must be clearly and separately set forth.

4. Proposals must be accompanied by a bid bond in the amount of ten (10%) percent of the bid, made payable to SHACOG.

5. The bids will remain firm for a period of ninety (90) days.

6. The successful bidder must furnish a Surety Company Performance Bond in the amount of one hundred (100%) percent of the contract price. The successful bidder must also furnish a Surety Company Labor and Materials Bond in the amount of one hundred (100%) percent of the contract price. Upon completion of the project a TWO (2) year maintenance bond must be provided, dated as of the day of acceptance by the appropriate municipal engineer, in the amount and terms specified in the bid material for that project. In the event no provision for maintenance bond is set forth, the amount shall be fifty (50%) of the contract price for the stipulated two (2) year period.

7. The successful bidder shall furnish certificates of insurance evidencing the following coverage as follows:

• Automobile Liability Insurance $1,000,000 Aggregate Bodily Injury and Property Damage

• Comprehensive General Liability Insurance $1,000,000

Aggregate Bodily injury and Property Damage

• Workers Compensation Insurance $500,000

The above listed coverages are minimums. If higher limits are stipulated in the detailed specifications, those higher limits shall prevail and shall be met by the successful bidder.

8. If the bidder is a Corporation, the proposal must be signed by the President or Vice President and attested to by the Secretary. Alternate signatures must be accompanied by a corporate resolution certifying and authorizing those individuals to submit and sign the proposal. If the bidder is a Sole Proprietor or Partnership, the proposal must be signed by the sole proprietor or a partner. Alternate signatures must be accompanied by a Power of Attorney certifying and authorizing those individuals to submit and sign the proposal.

9. No bid may be withdrawn after the bid opening. (In submitting this bid the bidder specifically waives the provisions of 73 P.S. Section 1601 et seq. Pertaining to Public Contracts and withdrawal of Bids.) All bids will then remain firm for a period of ninety (90) days.

10. Compliance is required with the Davis-Bacon Act (Demolitions are excluded from the Davis-Bacon Act wage requirements) and other Federal and local labor and minority standards. The bidder is cautioned to examine all pertinent bid materials and submit all required bid documents. FAILURE TO SUBMIT ALL REQUIRED FORMS MAY

INVALIDATE THE BID.

11. This project is being funded, in part, through the U.S. Department of Housing and

Urban Development (HUD). The successful bidder must be prepared to comply with all Federal statutes regarding the use of Federal Funds. This includes the submission of weekly payroll forms and other reports as required by HUD, the Department of Labor and the Allegheny County Department of Economic Development.

12. Award of the bid is contingent upon the release of funds by HUD.

13. SHACOG and/or the host municipality reserves the right to waive any informality or to reject any or all proposals.

14. Unique Entity Identification and CAGE Numbers: In accordance with HUD regulations, organizations receiving Federal funding are required to register via the System for Award Management (SAM) to obtain a Unique Entity Identification Number & CAGE Number. In order to get a CAGE number, you must first obtain a UEID number. To obtain this unique identification number go to the following website:

SAM.gov or call 1-866-606-8220 for further information. The UEID number must be renewed on a yearly basis. Proof of registration is mandatory, to be considered for funding.

SPECIAL NOTICE TO BIDDERS

Although SHACOG is the official signatory to the contract with the successful bidder (contractor), SHACOG is acting as agent for the municipality in soliciting this proposal, awarding the contract and monitoring contract performance. All work must be performed to the satisfaction of the subject municipality. Any construction problems or disputes must be resolved by the contractor and the municipality. All requests for payment must be processed through the municipality. No payments will be made unless first approved by the municipality. Although all payments will be made through the SHACOG office, SHACOG will be directly responsible only for that share of the project being paid from Community Development Block Grant Funds. Any and all portions of the project payable by the municipality cannot and will not be paid until those funds are received from the municipality. Payment from Allegheny County Economic Development Funds may take between 4 to 8 weeks from the time it is processed from the SHACOG office. When submitting payment requests, the contractor should, therefore, anticipate the approval time required by the municipality and the processing time required by the County.

SOUTH HILLS AREA COUNCIL OF

GOVERNMENTS

Compliance Paperwork and Instructions for Contractors

1. All signatures must be signed in BLUE INK.

2. Complete all forms as necessary.

3. Submit completed forms electronically with bid.

00110 Bid Form and Proposal The Gateway Engineers, Inc.. All rights reserved.

00110 - 1

C-97043-0025 Proposal From________________________________________

BID FORM & PROPOSAL

ARTICLE 1 – BID RECIPIENT

This Bid is submitted to: South Hills Area Council of Government 2600 Old Greentree Road, Floor 2

Scott Township, PA 15106

The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – PROPOSAL FOR:

CD 51 7.5 2025 ADA RAMP PROJECT – MT. LEBANON

Municipality of Mt. Lebanon

This project includes the installation of handicapped curb ramps at various locations throughout the Municipality of Mt. Lebanon.

TIME OF COMPLETION

Bidder agrees that the Work will be substantially complete within 45 calendar days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions, and will be completed and ready for final payment in accordance with Paragraph 14.07.B of the General Conditions within 60 calendar days after the date when the Contract Times commence to run or liquidated damages in the amount of $300 per calendar day will be charged.

All work must be completed and ready for final payment prior to May 31, 2027.

Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the Contract Times.

00110 - 2

ARTICLE 3 – BASIS OF BID

Bidder will complete the Work in accordance with the Contract Documents for the following price(s):

Item No.

Description

Unit

Estimated Quantity

Bid Unit Price

Bid Price

1. Handicap Ramp installation with PennDOT Class AA Concrete and truncated domes meeting PennDOT requirements including traffic control, resident notification, restoration, complete in place in accordance with Details provided.

S.F. 280 $____________ $_____________

2. Concrete Sidewalk Replacement, with Class AA Concrete including removal of the existing sidewalk, complete in place incl. 6” thick sidewalk, No. 9 gauge wire mesh, removal & disposal of old sidewalk, misc. excavation, and 6" thick aggregate base.

S.F. 515 $____________ $_____________

3. Concrete Roll and Straight Curb Replacement (including the curb that is depressed as part of the ramp) with PennDOT Class AA Concrete, including removal & disposal of the existing curb and bituminous roadway restoration, complete in place in accordance with Details provided.

L.F.

TOTAL BASE BID $ _____

ARTICLE 4 – BIDDER'S ACKNOWLEDGEMENTS

Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities, determined as provided in the Contract Documents.

00110 - 3

ARTICLE 5 – BIDDER'S REPRESENTATIONS

In submitting this Bid, Bidder represents that:

A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged.

B. Addendum No. Addendum Date

C. Bidder has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.

D. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work.

E. Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.

F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.

I. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.

J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.

K. Bidder will submit written evidence of its authority to do business in the state where the Project is located not later than the date of its execution of the Agreement.

00110 - 4

ARTICLE 6 – FURTHER REPRESENTATIONS

Bidder further represents that:

A. this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

D. Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.

ARTICLE 7 – ATTACHMENTS TO THIS BID

The following documents are attached to and made a condition of this Bid:

A. Required Bid security in the form of a Certified Check or Surety Company Bond in the amount of 10% in favor of South Hills Area Council of Government, as a proposal deposit which, it is understood, will be forfeited in case of failure to comply with the requirements and provisions of this proposal.

B. List of Proposed Subcontractors

C. List of Proposed Suppliers

D. Affidavit of Non-Collusion

E. Public Works Employment Verification Form

F. Allegheny County Procurement Package

ARTICLE 8 – DEFINED TERMS

The terms used in this Bid with initial capital letters have meanings stated in the Instruction to Bidders, the General Conditions, and the Supplementary Conditions.

00110 - 5

ARTICLE 9 – BID SUBMITTAL

This Bid submitted by:

If Bidder is:

An Individual

Name (typed or printed): _____________________________________________________

By: ______________________________________________________________ (SEAL) (Individual’s signature)

Doing business as: __________________________________________________________

A Partnership

Partnership Name: __________________________________________________ (SEAL)

By: ______________________________________________________________________ (Signature of general partner)

Name (typed or printed): _____________________________________________________

A Corporation

Corporation Name: __________________________________________________ (SEAL)

State of Incorporation: _________________________________ Type (General Business, Professional, Service, Limited Liability): _____________________

By: _______________________________________________ (Signature )

Name (typed or printed): ______________________________

Title: _____________________________________________ (CORPORATE SEAL)

Attest _____________________________________________

Date of Authorization to do business in _________________________ is ____/____/____.

Bidder's Business Address _________________________________________________________

Phone No. Fax No. ____________________________

Email ______________________________________________________

SUBMITTED on ________________________, 20____.

PENAL SUM FORM

Bid Bond EJCDC C-430 (2013 Edition)

000130-1

BID BOND

Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable.

BIDDER (Name and Address):

SURETY (Name, and Address of Principal Place of Business):

OWNER (Name and Address):

BID

Bid Due Date:

Description (Project Name— Include Location):

BOND

Bond Number:

Date:

Penal sum $

(Words) (Figures)

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this

Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal)

Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Title Title

Note: Addresses are to be used for giving any required notice.

Provide execution by any additional parties, such as joint venturers, if necessary.

Bid Bond EJCDC C-430 (2013 Edition)

000130-2

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be

Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding

Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding

Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding

Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by

Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States

Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

Non Collusion Affidavit Copyright © 2013 The Gateway Engineers, Inc. All rights reserved.

000180-1

NON_COLLUSION AFFIDAVIT

Contract/Bid No._______________

State of_________________________________:

:s.s.

County of_______________________________:

I state that I am_____________________________________________________________

(Title) of________________________________________________________________________

(Name of my firm) and that I am authorized to make this affidavit on behalf of my firm, and its owners, directors, and officers. I am the person responsible in my firm for the price(s) and the amount of this bid.

I state that:

(1) The price(s) and amount of this bid have been arrived at independently and without consultation, communication or agreement with any other contractor, bidder or potential bidder.

(2) Neither the price(s) nor the amount of this bid, and neither the approximate price(s) nor approximate amount of this bid, have been disclosed to any other firm or person who is a bidder or potential bidder, and they will not be disclosed before bid opening.

(3) No attempt has been made or will be made to induce any firm or person to refrain from bidding on this contract, or to submit a bid higher than this bid, or to submit any intentionally high or noncompetitive bid or other form of complementary bid.

(4) The bid of my firm is made in good faith and not pursuant to any agreement or discussion with, or inducement from, any firm or person to submit a complementary or other noncompetitive bid.

(5) _______________________________________, its affiliate’s subsidiaries, (Name of my firm) officers, directors and employees are not currently under investigation by any governmental agency and have not in the last four years been convicted or found liable for any act prohibited by State or Federal law in any jurisdiction, involving conspiracy or collusion with respect to bidding on any public contract, except as follows:

Non Collusion Affidavit

000180-2

I state that ________________________________understands and acknowledges

(Name of my firm) that the above representations are material important, and will be relied on by

(Name of public entity) in awarding the contract(s) for which this bid is submitted. I understand and my firm understands that any misstatement in this affidavit is and shall be treated as fraudulent concealment from ____________________________________of the true facts relating

(Name of public entity) to the submission of bids for this contract.

(Name)

(Title)

SWORN TO AND SUBSCRIBED

BEFORE ME THIS________DAY

OF____________________20____.

Notary Public My Commission Expires:

(Seal)

Public Works Employment Verification Form Copyright © 2015 The Gateway Engineers, Inc. All rights reserved.

000190-1

COMMONWEALTH OF PENNSYLVANIA

PUBLIC WORKS EMPLOYMENT VERIFICATION FORM

Date _______________________

Business or Organization Name (Employer)_______________________________________ Address ____________________________________________________________________ City _____________________________________ State___________ Zip Code __________

___Contractor ___ Subcontractor (check one)

Contracting Public Body ______________________________________________________ Contract/Project No __________________________________________________________ Project Description ___________________________________________________________ Project Location _____________________________________________________________

As a contractor/subcontractor for the above referenced public works contract, I hereby affirm that as of the above date, our company is in compliance with the Public Works Employment Verification Act (‘the Act’) through utilization of the federal E‐Verify Program (EVP) operated by the United States Department of Homeland Security. To the best of my/our knowledge, all employees hired post January 1, 2013 are authorized to work in the United States.

It is also agreed to that all public works contractors/subcontractors will utilize the federal EVP to verify the employment eligibility of each new hire within five (5) business days of the employee start date throughout the duration of the public works contract. Documentation confirming the use of the federal EVP upon each new hire shall be maintained in the event of an investigation or audit.

I, _________________________, authorized representative of the company above, attest that the information contained in this verification form is true and correct and understand that the submission of false or misleading information in connection with the above verification shall be subject to sanctions provided by law.

Authorized Representative Signature

Public Works Employment Verification Form Copyright © 2015 The Gateway Engineers, Inc. All rights reserved.

000190-2

Instructions to Bidders

000200 – 1

INSTRUCTIONS TO BIDDERS

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General

Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

B. Successful Bidder – The lowest, qualified, responsible bidder to whom the Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the

Notice to Bidders may be obtained from the Issuing Office. The deposit is non-refundable.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor

Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

2.04 During the bidding period, Bidders may be furnished with Addenda for additions to or alterations of the plans or specifications which shall be included in the work covered by the Proposal and become part of the Contract Documents. Such Addenda shall be signed by the Bidder and submitted with the Bid.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within five days of Owner’s request, Bidder shall submit (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:

A. Evidence of Bidder’s authority to do business in the state where the Project is located.

B. Bidder’s state or other contractor license number, if applicable.

C. Subcontractor and Supplier qualification information; coordinate with provisions of Article

12 of these Instructions, “Subcontractors, Suppliers, and Others.”

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

3.05 If the Owner requires pre-qualification for the Project, the Bidder shall include the pre-qualification documentation for himself/herself/theirselves and his/her/their subcontractors and suppliers in the Bid documents.

000200 – 2

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION

OF SITE; OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any

Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the

Supplementary Conditions. Bidder is responsible for any interpretation or conclusion

Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and

Engineer by owners of such Underground Facilities, including Owner, or others.

C. No claims for additional compensation will be allowed because of obstructions or conditions on the location of the work which may add to the difficulties or costs of construction, even though such obstructions or conditions are not shown on the Contract Plans. The bidder shall make his own investigation to determine all underground structures and utility lines.

D. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and

Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the

Site, if any, and possible changes in the Contract Documents due to any Hazardous

Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

000200 – 3

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.

B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

C. On request, and to the extent Owner has control over the Site, and schedule permitting, the

Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the

General Conditions indicate, if an Owner safety program exists, it will be noted in the

Supplementary Conditions.

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the

Site by Owner or others (such as utilities and other prime contractors) and relates to the

Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

4.06 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given

Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

000200 – 4

C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to

Technical Data in such reports and drawings;

E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by

Bidder; and (3) Bidder’s safety precautions and programs;

F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the

Site that relates to the Work as indicated in the Bidding Documents;

H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;

and

J. agree that the submission of a Bid will constitute an incontrovertible representation by

Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the

Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 A pre-Bid conference may be held in accordance with the requirements of the Bidding Documents and the Notice to Bidders. Representatives of Owner and Engineer will be present to discuss the

Project. Bidders are encouraged to attend and participate in the conference. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to

Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of

000200 – 5

Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.

ARTICLE 8 – BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding

Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and 6.02 of the

General Conditions.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the

Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract

Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the

Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Bid Form and in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, for failure to timely attain Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Project Specifications and Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by

Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer at least 15 days prior to the date for receipt of Bids. Each such request shall comply with the requirements of Paragraphs 7.04 and 7.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.

000200 – 6

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of

“or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or

Contractor to retain any Subcontractor, Supplier, or other individual or entity against which

Contractor has reasonable objection.

12.02 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after

Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the Work. If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such

Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating

Bids and making the Contract award.

12.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the

Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the

Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then

Bidder may enter the words “No Bid” or “Not Applicable.”

13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature). The corporate address and state of incorporation shall be shown. The corporate seal shall be affixed and attested by the corporate secretary or an assistant corporate secretary.

13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature). The official address of the partnership shall be shown below the signature

13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person. The state of formation of the firm and the official address of the firm shall be shown.

000200 – 7

13.05 A Bid by an individual shall show the Bidder’s name and official address.

13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.

13.07 All names shall be printed in ink below the signatures.

13.08 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.09 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

13.10 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID

14.01 Unit Price and Lump Sum

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form. The Proposal may be a combination of unit price and lump sum items.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the

Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .