This is a USPS Specification document for Section 011000 (Furnished Equipment) outlining the scope and contract requirements for construction of a postal facility.
The Contractor must provide all materials, labor, tools, plant, supplies, equipment, transportation, superintendence, and temporary construction necessary to complete the postal facility construction, including customer and employee parking retaining walls and pavement. All work must comply with applicable codes and local regulations, with the more stringent standard applied in cases of conflict. Under miscellaneous contract expenses, the Contractor must include separate line items in the price proposal for fees and charges payable to state, local, or special community development agencies, specifically: water service connection and meter fees, electrical company required fees, off-site inspection fees, sanitary sewer connection fees, environmental permits and registrations, and other permits or fees. If actual costs differ from proposed amounts, the contract price will be adjusted by modification without overhead and profit markup. The Contractor must notify the Contracting Officer within 30 days of incurring expenses and provide evidence of actual payments. The Contractor is responsible for all coordination with utilities and making all payments for their work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Event management for suppliers - Coupa.pdf | ||
| Coupa Supplier Registration Form.docx | DOCX document | |
| COUPA Supplier Registration Quick Reference Guide.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
011000 Attachment A – Page 1
POSTAL SERVICE
USPS Date: 10/1/2021 FURNISHED EQUIPMENT
SECTION 011000
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SCOPE
A. The Contractor must provide all material, labor, tools, plant, supplies, equipment, transportation, superintendence, temporary construction of every nature, and all other services and facilities necessary to complete the construction of a postal facility for the Pos tal Service, including all incidental work described in the contract documents
B. Customer’s and Employee’s parking retaining wall and pavement.
C. All work shall be in accordance with applicable codes and local regulations that may apply. In case of conflict in or between the Contract Documents and a governing code or ordinance, the more stringent standard shall apply.
1.3 MISCELLANEOUS CONTRACT EXPENSES
A. In accordance with the terms and conditions of the contract provisions and clauses, including those concerning Permits and Responsibilities and, Building Codes, Fees and Charges, the Contractor must include in its price proposal a separate line item for the cost each of the of the following fees or charges payable to State, local, or special community development agencies:
Water service connection and meter fee Electrical company required fees
Of f -site inspection fees Sanitary sewer connection fee Environmental Permits/Registrations Other permits or fees
B. If the actual cost of any item identified above is more or less than the amount listed, the contract price will be adjusted accordingly by a contract modification. The adjustment will not include overhead and profit. The Contractor must, within 30 days after incurring the expenses, inform the Contracting Officer that the payment has been made. Evidence of the actual amount paid must be provided. The contract amount will be adjusted upward or downward as necessary to accommodate actual charges f rom the utilities. The Contractor must provide all coordination with the utilities in accomplishing their work and must make all payments to the utilities for their work.
C. The Contractor must include all additional fees, as required, in the price proposal.
PART 2 – PRODUCTS
NOT USED
PART 3 – EXECUTION
NOT USED
END OF SECTION
USPS Specification Last Revised: 10/1/2022