This document is a Summary of Work section from a USPS solicitation for the Murray Hill Annex Façade Restoration project dated 04/05/2024. The scope of work encompasses comprehensive exterior and interior restoration of a postal facility, including power washing of brick, limestone, granite, and metal façades; repairs and repointing of surfaces; replacement of architectural elements like wood entrance, roof systems, and signage; and interior repairs involving wall restoration, paint removal, and asbestos removal. Specific tasks include north entry vehicular entrance wood replacement, south arch truck door repairs, steel remediation, roof system and bulkhead replacement, skylight installation, drainage system updates, and ground-level landscape fabric installation.

The contractor is required to provide a detailed price proposal that includes separate line items for various fees and charges payable to state, local, and community development agencies, such as water service connection, electrical and telephone company fees, off-site inspection fees, sanitary sewer connection, and environmental permits. The contract includes provisions for adjusting the contract price based on actual utility and permit costs, with the contractor responsible for coordinating with utilities, making payments, and providing evidence of expenses within 30 days of incurring them. The specification was last revised on 10/1/2022 and covers all necessary materials, labor, tools, equipment, and services to complete the postal facility restoration project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

011000–1

USPS MURRAY HILL ANNEX Date: 04/05/2024 SUMMARY OF WORK

FAÇADE RESTORATION

SECTION 011000

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SCOPE

A. The Contractor must provide all material, labor, tools, plant, supplies, equipment, transportation, superintendence, temporary construction of every nature, and all other services and facilities necessary to complete the construction of a postal facility for the Postal Service, including all incidental work described in the contract documents.

B. Scope of work (summary only – see drawings and specifications for the complete scope):

1. The project consists of exterior façade restoration and interior work.

2. Power washing of all brick, limestone, granite and metal façades.

3. Repairs, repointing and new coatings on all brick, limestone, granite.

4. North entry vehicular entrance wood replacement.

5. Repairs to south arch truck door.

6. Remediation of exposed steel.

7. Demo/replacement of billboard signage.

8. Repairs to underside of roof slab.

9. Fifth floor - interior and exterior wall repair including new lintels, repair/replace slab and fireproofing.

10. Third and Fourth floor - interior removal of stains and damaged paint.

11. Misc. painting.

12. Remove/replace roof system and bulkheads on main roof and lower roof, including new skylights, replace roof hatch access and ladder, installation of drainage system, replacement of parapets

13. Misc. interior crack and spalling repairs.

14. Removal and disposal of non-friable ACM.

15. Ground level - install weed barrier landscape fabric.

C. All work shall be in accordance with applicable codes and local regulations that may apply. In case of conflict in or between the Contract Documents and a governing code or ordinance, the more stringent standard shall apply.

1.2 NOT USED

1.3 MISCELLANEOUS CONTRACT EXPENSES

A. In accordance with the terms and conditions of the contract provisions and clauses, including those concerning Permits and Responsibilities and Building Codes, Fees and Charges, the Contractor must include in its price proposal a separate line item for the cost each of the of the following fees or charges payable to State, local, or special community development agencies:

Water service connection and meter fee Electrical company required fees Telephone company required fees Off-site inspection fees Sanitary sewer connection fee Environmental Permits/Registrations Other permits or fees

011000–2

USPS MURRAY HILL ANNEX Date: 04/05/2024 SUMMARY OF WORK

FAÇADE RESTORATION

B. If the actual cost of any item identified above is more or less than the amount listed, the contract price will be adjusted accordingly by a contract modification. The adjustment will not include overhead and profit. The Contractor must, within 30 days after incurring the expenses, inform the Contracting Officer that the payment has been made. Evidence of the actual amount paid must be provided. The contract amount will be adjusted upward or downward as necessary to accommodate actual charges from the utilities. The Contractor must provide all coordination with the utilities in accomplishing their work and must make all payments to the utilities for their work.

C. The Contractor must include all additional fees, as required, in the price proposal.

1.4 NOT USED

1.5 NOT USED

1.6 NOT USED

PART 2 – PRODUCTS

NOT USED

PART 3 – EXECUTION

NOT USED

END OF SECTION