07-0Y2404 Methacrylate_ Polyester Overlay_ Joint Seal Repair and Spall Repair.pdf
PDF 1 MB Posted
- Solicitation number
- 07-0Y2404
- Issued by
- Los Angeles County, California
About this file
This is a Notice to Bidders and Special Provisions for Construction document issued by the California Department of Transportation (Caltrans) for a highway repair project in Los Angeles County. The project involves methacrylate, polyester overlay, joint seal repair, and spall repair work on Route 110, spanning from the Route 110/47 separation to the Redondo Beach Boulevard undercrossing in Los Angeles and Carson. The contract is identified as 07-0Y2404 (Project ID 0724000293) and is based on the bid book dated July 27, 2026, utilizing 2025 Standard Specifications and Standard Plans with project plans approved on May 15, 2026. Bids are scheduled to open on Tuesday, August 25, 2026. The document specifies requirements for contractor registration, potential claim submissions through the Department's Internet system, DVBE quotes, and non-small business subcontractor preferences. Special provisions address flagging and temporary traffic control requirements, in-use off-road diesel-fueled vehicle compliance, treated wood waste management, and closure restrictions during the 2028 Olympics and Paralympics.
The project includes Small Business Enterprise Participation Goals and both small business and non-small business subcontractor preferences as outlined in multiple sections. Contractors must comply with electronic submittal of certified payroll records using LCPtracker Pro and environmental product declaration requirements for hot mix asphalt and concrete materials. The work is governed by temporary traffic control specifications and detailed standard plans for traffic control systems, including lane closures, ramp closures, temporary crash cushions, and traffic control devices. The special provisions reference multiple divisions of work including general construction, earthwork and landscape, surfacings and pavements, structures, and traffic control devices, with comprehensive specifications for each category.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Tuesday, August 25, 2026
Dated July 27, 2026 OSD
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN LOS ANGELES COUNTY IN
LOS ANGELES AND CARSON AT VARIOUS LOCATIONS FROM ROUTE 110/47
SEPARATION TO REDONDO BEACH BOULEVARD UNDERCROSSING
In District 07 On Route 110
Under
Bid book dated July 27, 2026 Standard Specifications dated 2025
Project plans approved May 15, 2026 Standard Plans dated 2025
Identified by
Contract No. 07-0Y2404
07-LA-110-R0.9/11.2
Project ID 0724000293
SPECIAL NOTICES
See sections 2 and 3 for contractors' registration requirements.
The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
See section 14-11.14 for changes to the management of treated wood waste.
See section 12-4.02C(3)e for closure restrictions during Olympics and Paralympics in 2028.
See sections 1-1.06, 1-1.07B, 2-1.23, 2-1.24, 2-1.33B(3), 5-1.13D, and 5-1.13F for “Small
Business Enterprise Participation Goal Requirement” and “Small Business and Non-Small Business Subcontractor Preferences.”
See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.
Contract No. 07-0Y2404 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
1 GENERAL
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
14 ENVIRONMENTAL STEWARDSHIP
DIVISION III EARTHWORK AND LANDSCAPE
19 EARTHWORK
DIVISION V SURFACINGS AND PAVEMENTS
39 ASPHALT CONCRETE
DIVISION VI STRUCTURES
51 CONCRETE STRUCTURES
60 EXISTING STRUCTURES
DIVISION IX TRAFFIC CONTROL DEVICES
84 MARKINGS
ii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
RSP A3A Abbreviations (Sheet 1 of 3)
RSP A3B Abbreviations (Sheet 2 of 3)
RSP A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
RSP T3A Temporary Railing (Type K)
T3B Temporary Railing (Type K)
T3C Temporary Barrier System (Cross Bolt)
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
T9 Traffic Control System Tables for Lane and Ramp Closures
T10 Traffic Control System for Lane Closure on Freeways and Expressways
RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways
T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional Highways and Expressways
T14 Traffic Control System for Ramp Closure
T15 Traffic Control System for Moving Lane Closure on Multilane Highways
T16 Traffic Control System for Moving Lane Closure on Multilane Highways
T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details iii
T26 Temporary Automated End of Queue Warning System Type 1 (Queue <= 3.5 Miles)
T30 Temporary Pedestrian Access Routes - Typical Sidewalk Closure and Pedestrian Detour
T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)
B6-21 Joint Seals (Maximum Movement Range = 2")
RS1 Roadside Signs - Typical Installation Details No. 1
RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2
RS4 Roadside Signs - Typical Installation Details No. 4
CANCELED STANDARD PLANS LIST
The 2025 standard plan sheets listed below are canceled and not applicable to this contract.
Plan No.
Date
Canceled Plan No.
Date Canceled
Plan No.
Date
Canceled
P8 04-20-26
NOTICE TO BIDDERS
Bids open Tuesday, August 25, 2026
Dated July 27, 2026
General work description: Methacrylate, polyester overlay, joint seal repair and spall repair.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN LOS ANGELES COUNTY IN LOS ANGELES AND CARSON AT VARIOUS
LOCATIONS FROM ROUTE 110/47 SEPARATION TO REDONDO BEACH BOULEVARD
UNDERCROSSING.
District-County-Route-Post Mile: 07-LA-110-R0.9/11.2
Contract No. 07-0Y2404
The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-8, C-12.
The Department establishes no DVBE Contract goal but encourages bidders to obtain DVBE participation.
The SBE Contract goal is 5 percent.
Bids must be on a unit price basis.
Complete the work within 180 working days.
The estimated cost of the project is $7,900,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq., the Department gives preference to certified small businesses and non–small businesses who commit to 25 percent certified small business participation.
Under Pub Cont Code § 6107, the Department gives preference to a "California company," as defined, for bid comparison purposes over a nonresident contractor from any state that gives or requires a preference to be given to contractors from that state on its public entity construction contracts.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 180
0003 090200 DISPUTE RESOLUTION ADVISOR ON-SITE
MEETING
EA 2
0004 090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-
ADVISOR-RELATED TASKS
HR 2
0005 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0006 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0007 120207 PORTABLE RADAR SPEED FEEDBACK SIGN
SYSTEM
DAY 180
0008 128655 TEMPORARY AUTOMATED END OF QUEUE
WARNING SYSTEM (TYPE 1)
DAY 8
0009 128659 END OF QUEUE MONITORING AND WARNING
WITH TRUCK MOUNTED CHANGEABLE
MESSAGE SIGN
DAY 45
0010 130100 JOB SITE MANAGEMENT LS LUMP SUM
0011 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM
0012 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0013 141103 REMOVE YELLOW THERMOPLASTIC TRAFFIC
STRIPE (HAZARDOUS WASTE)
LF 5,030
0014 193006 (F) - STRUCTURE BACKFILL (SLURRY CEMENT) CY 0.7
0015 390132 HOT MIX ASPHALT (TYPE A) TON 500
0016 397005 TACK COAT TON 5.4
0017 398200 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 8,720
0018 420203 GRIND EXISTING BRIDGE DECK SQYD 8,418
0019 511118 CLEAN EXPANSION JOINT LF 3,801
0020 519081 JOINT SEAL (MR 1/2") LF 3,305
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 519100 JOINT SEAL (MR 2") LF 252
0022 046492 BONDED JOINT SEAL (MR 1") LF 244
0023 600001 PUBLIC SAFETY PLAN LS LUMP SUM
0024 600011 RAPID SETTING CONCRETE (PATCH) CF 791
0025 600033 REMOVE UNSOUND CONCRETE CF 791
0026 600037 PREPARE CONCRETE BRIDGE DECK SURFACE SQFT 326,299
0027 600041 FURNISH POLYESTER CONCRETE OVERLAY CF 30,448
0028 600043 (F) - PLACE POLYESTER CONCRETE OVERLAY SQFT 304,438
0029 600045 (F) - TREAT BRIDGE DECK SQFT 21,861
0030 600047 FURNISH BRIDGE DECK TREATMENT MATERIAL GAL 273
0031 810230 PAVEMENT MARKER (RETROREFLECTIVE) EA 970
0032 037137 CONCRETE BARRIER MARKER EA 600
0033 840517 PREFORMED THERMOPLASTIC PAVEMENT
MARKING
SQFT 60
0034 846030 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 14,100
0035 847210 6" TRAFFIC STRIPE TAPE (WARRANTY) LF 10,100
0036 847213 6" TRAFFIC STRIPE TAPE (WARRANTY)
(BROKEN 17-7)
LF 14,100
0037 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to section 1-1.01:
Bid Items and Applicable Sections
Item code
Item description Applicable section
090200 DISPUTE RESOLUTION ADVISOR ON-SITE MEETING 5
090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-ADVISOR-RELATED
TASKS
046492 BONDED JOINT SEAL (MR1") 51
037137 CONCRETE BARRIER MARKER 82
Add to the table in the 1st paragraph of section 1-1.06:
SBE Small Business Enterprise
Add to section 1-1.07B:
small business enterprise: Small business or small business for the purpose of public works, as certified by the Department of General Services, Office of Small Business and DVBE Services, and as defined in Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information
Means Description Included in the Information Handout 1. Asbestos and Lead Assessment Survey Report
2. Form TOTE-1 – WARRANTY BOND
3. DOTOCR-0003 Final Report Utilization of Small Business Enterprises
Available as specified in the Standard Specifications
Bridge as-built drawings
Replace section 2-1.23 with:
2-1.23 SMALL BUSINESS ENTERPRISE PARTICIPATION GOAL REQUIREMENT
2-1.23A General
Section 2-1.23 applies if an SBE participation goal requirement is shown on the Notice to Bidders.
The SBE participation goal requirement is in addition to any DVBE goal shown on the Notice to Bidders and the DVBE requirements in section 2-1.22.
Make work available to SBEs and select work parts consistent with the available SBEs, including subcontractors, suppliers, service providers, and truckers.
Meet the SBE participation goal requirement shown on the Notice to Bidders. A bid that demonstrates an SBE participation commitment less than the SBE participation goal requirement is nonresponsive.
Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
The Department of General Services determines whether an SBE was certified on the bid opening date.
The Department of Transportation confirms an SBE’s certification status.
2-1.23B SBE Submittals
Submit SBE information under section 2-1.33.
For the SBE participation goal requirement, submit the following:
1. Completed Small Business Enterprise – Commitment form. Failure to submit the completed form by 4 p.m. on the 4th business day after bid opening may result in a nonresponsive bid.
2. Copy of the quote for each SBE shown on the Small Business Enterprise – Commitment form that describes the type and dollar amount of work shown on the form. Quotes are not required for work that will be completed by SBE prime bidders. Failure to submit a copy of the quote for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.
3. Completed Small Business Enterprise – Confirmation form from each SBE listed on the Commitment form. The form for each SBE is required to establish that the SBE will be participating in the Contract for the type and dollar amount of work shown on the form. Failure to submit completed Confirmation forms for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.
4. If an SBE is participating as a joint venture partner, submit a copy of the joint venture agreement.
The Department may contact you and SBEs to clarify quotes and supporting documentation.
If you elect, at time of bid, to pursue the optional small business or non-small business preference, see section 2-1.24 for the requirements arising from your request for the preference. SBE participation listed to meet the SBE participation goal requirement should not be listed for the preference.
Replace section 2-1.24 with:
2-1.24 SMALL BUSINESS AND NON–SMALL BUSINESS SUBCONTRACTOR PREFERENCES
2-1.24A General
Section 2-1.24 applies to a non-federal-aid contract.
The Department applies small business preferences and non–small business preferences under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.
Any contractor, subcontractor, supplier, or service provider who qualifies as a small business or small business for the purpose of public works is encouraged to apply for certification as an SBE by submitting its application to the Department of General Services, Office of Small Business and DVBE Services.
The Department of General Services determines whether an SBE was certified on the bid opening date.
The Department of Transportation confirms an SBE’s certification status before applying the small business or non-small business preference.
Contract award is based on the total bid, not the reduced bid.
Pursuant to Govt Code § 14838, SBE participation listed on the Small Business Enterprise – Commitment form used to meet the SBE participation goal requirement should not be listed on the Certified Small Business Listing for the Non-Small Business Preference form. Listing the same SBE participation on both the Small Business Enterprise – Commitment form and on the Certified Small Business Listing for the Non-Small Business Preference form may result in disallowance of the SBE’s participation toward the small business or non-small business preference.
2-1.24B Small Business Preference
The Department allows a bidder certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, a preference if:
1. Bidder submitted a completed Request for Small Business Preference or Non–Small Business Preference form with its bid
2. Low bidder did not request the preference or is not certified as a small business
The Bidder's signature on the Request for Small Business Preference or Non–Small Business Preference form certifies that the Bidder is certified as an SBE at the date and time of bid or has submitted a complete application to the Department of General Services. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
The small business preference is a reduction for bid comparison in the total bid submitted by the small business contractor by the lesser of the following amounts:
1. 5 percent of the verified total bid of the low bidder
2. $50,000
If the Department determines that a certified small business bidder is the low bidder after the application of the small business preference, the Department does not consider a request for non–small business preference.
2-1.24C Non–Small Business Subcontractor Preference
At time of bid, the Department allows a bidder not certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, the option of requesting the non-small business subcontractor preference. If a bidder elects to pursue that option at the time of bid, the bidder is required to meet the corresponding commitment.
For the non-small business subcontractor preference, submit the following:
1. Completed Request for Small Business Preference or Non–Small Business Preference form with your bid
2. Completed Certified Small Business Listing for the Non–Small Business Preference form which shows you are subcontracting at least 25 percent to certified SBEs
Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
Failure to submit a completed Certified Small Business Listing for the Non–Small Business Preference form by 4 p.m. on the 4th business day after bid opening will result in a nonresponsive bid.
The non–small business subcontractor preference is a reduction for bid comparison in the total bid submitted by the non–small business contractor requesting the preference by the lesser of the following amounts:
1. 5 percent of the verified total bid of the low bidder
2. $50,000
Delete section 2-1.33B(2)(b).
Replace the table in the 1st paragraph of section 2-1.33B(3)(b)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract with a DVBE Goal Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa
Time of bid
Certified DVBE Summary No later than 4 p.m. on the 4th business day after bid opening
California Company Preference Time of bid
Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea
Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
Replace the table in the 1st paragraph of section 2-1.33B(3)(c)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract without a DVBE Goal Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa
Time of bid
California Company Preference Time of bid
Certified DVBE Summaryb No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea
Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
bSubmit only if you obtain DVBE participation or you are the apparent low bidder, 2nd low bidder, or 3rd low bidder and you choose to receive the specified incentive.
Replace the table in the 1st paragraph of section 2-1.33B(3)(b)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract with a DVBE Goal Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa
Time of bid
Certified DVBE Summary No later than 4 p.m. on the 4th business day after bid opening
California Company Preference Time of bid Request for Small Business Preference or Non– Small Business Preferencea
Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
Replace the table in the 1st paragraph of section 2-1.33B(3)(c)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract without a DVBE Goal Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa
Time of bid
California Company Preference Time of bid
Certified DVBE Summaryb No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea
Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
bSubmit only if you obtain DVBE participation or you are the apparent low bidder, 2nd low bidder, or 3rd low bidder and you choose to receive the specified incentive.
5 CONTROL OF WORK
Replace section 5-1.13E with:
5-1.13E Prompt Payment
Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Replace section 5-1.15 with:
5-1.15 SAFETY REPRESENTATIVE
5-1.15A General
Designate an on-site safety representative to superintend project safety for the duration of this Contract.
The safety representative may perform other non-safety related work if safety responsibilities are fulfilled.
The safety representative must be available after work hours as needed. The safety representative is not required to be on-site during plant establishment period, erosion control establishment period, or temporary suspensions when no other Contract work is being performed.
Develop a written site-specific safety program (SSSP) that incorporates known hazards associated with the project.
5-1.15B Submittals
Submit a resume of the safety representative before starting work on the project, including education, completed safety training, and safety experience in heavy construction, heavy industrial, or oil and energy industry.
Submit a copy of the safety representative's certificate for the Cal/OSHA 30-hour – Cal/OSHA Standards for the Construction Industry or OSHA 510 - OSHA Standards for the Construction Industry training course as an informational submittal. The certificate must include:
1. Name of the entity providing certification
2. Name of the individual receiving certification
3. Date when the certification was provided
4. Expiration date, if applicable
Submit a copy of the SSSP as an informational submittal:
1. At least 15 days before starting work
2. At least 48 hours before starting work whenever a revision is made to the SSSP
5-1.15C Certifications
The safety representative must have completed training and received a certificate of completion for the Cal/OSHA 30-hour - Cal/OSHA Standards for the Construction Industry or OSHA 510 – OSHA Standards for the Construction Industry training course.
The safety representative must have one of the following certifications:
1. Certified Safety Professional from the Board of Certified Safety Professionals
2. Construction Health and Safety Technician from the Board of Certified Safety Professionals
3. Occupational Hygiene and Safety Technician from the Board of Certified Safety Professionals
4. Safety Trained Supervisor from the Board of Certified Safety Professionals
5. Safety Trained Supervisor Construction from the Board of Certified Safety Professionals
6. Associate Safety Professional from the Board of Certified Safety Professionals
7. Master Safety Professional from the National Association of Safety Professionals
8. Certified Safety Director from the National Association of Safety Professionals
5-1.15D Qualifications
The safety representative must be a competent and qualified person, as defined by Cal/OSHA, and must provide safety oversight on the project. The safety representative must have:
1. At least 3 years of safety experience in heavy construction, heavy industrial, or oil and energy industry
2. Knowledge in the area of safety procedure for all types of work being performed on this project
3. Knowledge of Department specifications and plans, Cal/OSHA policy and procedures, and 8 CA
Code of Regs safety requirements
The safety representative must have completed safety training and maintain valid certifications for:
1. First aid
2. Cardiopulmonary resuscitation
5-1.15E Duties and Responsibilities
The safety representative must be available by:
1. Cellular telephone
2. Two-way radio
3. Mobile internet access
The safety representative must:
1. Develop the SSSP
2. Conduct the on-site new project orientation for each worker assigned to the project
3. Review the construction work plans for each subcontractor before starting work
4. Conduct or attend pre-planning sessions for high hazard work such as excavations, demolition, confined space entry, falsework, crane hoisting, high-risk utilities such as high-pressure pipelines with fuel or natural gas, and tunneling or boring
5. Conduct weekly job site safety meetings
6. Review work schedules, including subcontractors' work schedules, to ensure adequacy of job hazard analyses and address all safety concerns and issues
7. Ensure safety data sheets are available on-site for all materials and have a hazard communication program for informing workers of material hazards
8. Verify compliance with hazardous waste requirements under section 14-11, including spill prevention and control measures
9. Conduct daily safety inspections of the job site for hazards and compliance with safety requirements in the specifications and 8 CA Code of Regs
10. Report all incidents to the Engineer immediately, including the investigation of any close calls
When monitoring the job site, including work zones with certified flaggers or traffic control technicians, take immediate corrective action and notify the Engineer if an imminent danger is identified.
If the Engineer determines the safety representative is not meeting the intended duties and responsibilities, you must replace the safety representative within 30 days of written notice from the Engineer. If you need to replace the safety representative, notify the Engineer and provide replacement safety representative resume and required certifications at least 15 days before the replacement.
You may submit a secondary safety representative to act on behalf of the designated safety representative during extended shifts, continuous operations, or short-term absences that will not exceed 14 days in duration. The secondary safety representative must meet the same required qualifications and certifications as the designated safety representative.
Add to the end of section 5-1.20A:
During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:
Coincident or Adjacent Contracts
Contract no. County–Route–Post Mile Location Type of work 07-2XT1704 LA-110-3/4.6 Route 110 in the community of Harbor City
REMOVE AND
REPLACE THE
DAMAGED AND
BROKEN CONCRETE
SLABS
07-1XL604 LA-110-6/9.5 South of Torrance Blvd TO REPAIR THE
WASHED-OUT
SLOPE, RECONNECT
EXISTING RCBS TO
THE DETENTION
07-1Q9904 LA-110-14.2/22.0 LA County on SB Route 110 at Route 105 Interchange
INSTALL ROUTE
SHIELD PAVEMENT
MARKINGS
07-3009U4 LA-110-R0.7/24.1 In and near the cities of Los Angeles and Carson, FROM Gaffey Street to Route 110
MAJOR PAVEMENT
REHABILITATION
Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.
Add to the end of section 5-1.20C:
This project does not include work on the railroad property, but a railroad is shown on the general plan sheet within the project limits. Do not trespass on the railroad property at LA-110-PM 5.11 - DOT#028110S- Br.NO#53-0967- West Watson OH- Harbor City - BNSF.
Add to the end of section 5-1.33:
You must use tier 4 interim or tier 4 final engines for off-road diesel-fueled vehicles subject to 13 CA Code of Regs § 2449 instead of the use of lowered tiered engines. However, the requirement to use tier 4 interim or tier 4 final engines does not apply to vehicles registered to operate on public roads when those vehicles are used solely to deliver materials or supplies to the job site.
For off-road diesel-fueled vehicles subject to 13 CA Code of Regs§ 2449:
1. At least 15 days before use of vehicles submit an inventory list to the Engineer and tier4@dot.ca.gov for authorization. The list must include the following information for each vehicle:
1.1. Diesel off-road on-line reporting system (DOORS) identification number issued to the vehicle owner by the California Air Resources Board
1.2. Company or agency name associated with the DOORS identification number
1.3. California Air Resources Board issued equipment identification number for the vehicle
1.4. Vehicle product identification number as listed in DOORS
1.5. Corresponding identifying number required in this section
1.6. Serial number
1.7. Vehicle type
1.8. Vehicle manufacturer, model number and model year
1.9. Number of engines as indicated in DOORS
1.10. For each engine:
1.10.1. Serial number
1.10.2. Manufacturer name, model, and model year
1.10.3. Maximum horsepower
1.10.4. EPA issued engine family name
1.10.5. Engine displacement in liters
1.10.6. California Air Resources Board issue executive order for the engine family from the off-road certification database. For the database go to the California Air Resources Board website: https://www.arb.ca.gov/msprog/offroad/cert/cert.php
1.10.7. Emission standard category for the engine family, such as tier 4 interim or tier 4 final
1.10.8. Photograph of the engine label
2. Submit an updated inventory list at least 5 business days before using a vehicle not on the list or replacing a vehicle on the list for authorization. Allow 5 business days for review.
Flexibility engines certified under the California Air Resources Board’s flexibility program provisions are noncompliant engines unless a previously issued executive order for that engine family indicates the emission standard category is tier 4 interim. You may access these executive orders at the California Air Resources Board website: https://www.arb.ca.gov/msprog/offroad/cert/cert.php For example:
Executive Order U-R-002-0747 was issued on March 16, 2020, for Flexibility Program Engine Family Name “DCEXL15.0AAK,” a Cummins Inc. 2020 model engine. Executive Order U-R-002-0592-2 issued On December 30, 2013, for Engine Family DCEXL15.0AAK indicates the “Emission Standard Category” is tier 4 interim. Use of Engine Family “DCEXL 15.0AAK is compliant.
If you operate a vehicle that is noncompliant with these requirements, the Department deducts a $2000 penalty for each noncompliant engine for each day of operation.
6 CONTROL OF MATERIALS
Replace section 6-1.03B with:
6-1.03B Submittals
6-1.03B(1) General
Not Used
6-1.03B(2) Work Plan
For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:
1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).
2. Land use history of the local material location and surrounding property
3. Sampling protocol
4. Number of samples per volume of local material
5. QA and QC requirements and procedures
6. Qualifications of sampling personnel
7. Stockpile history
8. Name and address of the analytical laboratory that will perform the chemical analyses
9. Analyses that will be performed for lead and pH
10. Other analyses that will be performed for possible hazardous constituents based on:
10.1. Source property history
10.2. Land use adjacent to source property
10.3. Constituents of concern in the ground water basin where the job site is located
The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.
If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.
6-1.03B(3) Analytical Test Results
At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:
1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.
2. Chain of custody of samples
3. Analytical results no older than 1 year
4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit
5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location
6-1.03B(4) Sample and Analysis
Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:
1. Before bringing the local material to the job site
2. As described in the local material plan
3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)
The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.
Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:
Minimum Number of Samples and Analytical Tests for Local Material
Maximum volume of imported borrow (cu yd)
Minimum number of samples and analytical tests
< 5,000 8
5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof
10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof
20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof
40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof
> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof
Do not collect composite samples or mix individual samples to form a composite sample.
Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).
The analytical test results must demonstrate that the local material:
1. Is not a hazardous waste
2. Has a pH above 5.0
3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg
4. Is free of possible contaminants identified in the local material plan
5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location
6-1.03C Local Material Management
Do not place local material until authorized.
If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).
Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.
Replace section 6-1.04 with:
6-1.04 BUY AMERICA
6-1.04A General
Not Used
6-1.04B Crumb Rubber (Pub Res Code §42703(d))
Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:
1. Produced in the United States
2. Derived from waste tires taken from vehicles owned and operated in the United States
Add to section 6-1:
6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE
Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.
See section 6-1.06B for definitions.
For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:
Material or product Material specifications
Hot mix asphalta Section 39-2, "Hot Mix Asphalt" Excludes RHMA, OGFC, and BWC materials.
Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."
Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.
aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.
bFor each concrete plant providing 250 cubic yards or more on the project by mix design.
The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.
The requirements in section 6-1.08 do not apply to informal-bid contracts.
For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:
1. Applicable product category rule has expired without replacement as of the bid opening date.
2. Applicable product category rule was issued less than 50 days before the bid opening date.
Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer. If the Engineer determines the development of a facility-specific environmental product declaration cannot be achieved, an environmental product declaration will not be required for that material or product.
You must register on the Department’s Data Interchange for Materials Engineering (DIME) at least 15 days before submitting environmental product declarations. Follow the registration process at:
https://dime.dot.ca.gov/
Within 30 days of initial placement of each applicable material or product, submit a facility-specific, product stage, environmental product declaration informational submittal to DIME and provide proof of submission in PDF file format to the Engineer. The DIME entry information must include intended use of materials and estimated quantities of materials to be used as represented by the environmental product declaration.
Failure to provide a required environmental product declaration informational submittal will result in a $6,000 performance failure withhold for each missing declaration. The Department returns the withhold within 30 days after receipt of the compliant declaration if submitted prior to Contract acceptance.
Withholds become permanent deductions if the declaration is not submitted before Contract acceptance.
Replace the paragraphs of section 7-1.02C with:
Submit to the Department the following certifications before performing the work:
I am aware of the emissions reduction regulations being mandated by the California Air Resources Board. I will comply with such regulations before commencing the performance of the work and maintain compliance throughout the duration of this Contract.
I am aware of the requirements to use tier 4 interim or tier 4 final engines under section 5-1.33 and I will comply with the requirements. I am aware that the Department deducts a $2,000 penalty for each noncompliant engine for each day of operation.
Contract signing constitutes submittal of these certifications.
8 PROSECUTION AND PROGRESS
Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:
Schedule Baseline schedule and weekly statement of working days report
Replace the 4th and 5th paragraphs of section 8-1.05 with:
The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.
The weekly statement of working days report shows:
1. Working days and non–working days during the reporting week
2. Time adjustments
3. Calculations of work completion dates, including working days remaining
4. Controlling activities
Delete the 6th paragraph of section 8-1.05
9 PAYMENT
Replace the 1st paragraph of section 9-1.11D with:
For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
Add to the beginning of section 12-3.32C:
Add between the 9th and 10th paragraphs of section 12-3.32C:
Start displaying the message on the sign 5 minutes before closing the lane or shoulder or when directed by the Engineer.
Add to the beginning of section 12-3.41C:
Provide the temporary automated end of queue warning system type per closure as shown in the following table:
Lane closure chart no. System type Additional requirements Tables 1 Type 1 See other closure requirements section on table
Add to section 12-4.02A(2):
special days: Martin Luther King Jr and Columbus Day
Add between the 1st and 2nd paragraphs of section 12-4.02A(3)(c):
Submit a contingency plan for each of the following activities:
1. Rapid-set concrete activities
2. HMA paving
3. Methacrylate application
4. Concrete grinding
5. Polyester concrete overlay placement
Replace the 3rd paragraph of section 12-4.02C(1) with:
Do not close on-ramps or off-ramps servicing 2 consecutive local street interchanges in the same direction of travel. The Engineer may authorize a closure if:
1. You submit a request
2. Traffic will be better served
3. Work will be expedited
Add between the 3rd and 4th paragraphs of section 12-4.02C(1):
Except as otherwise shown on chart nos. J1–J15, you may close a ramp if the adjacent freeway lane is allowed to be closed as…