06 Bid Schedule RMA Lake Mary Paving(Public).pdf
PDF 97 KB Posted
- Attached to
- Lake Mary Parking Area and Trail Paving - RMA CO
- Solicitation number
- 140F0621Q0039
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140F0621Q0039_Amd_0004.pdf | ||
| Sol_140F0621Q0039_Amd_0003.pdf | ||
| Sol_140F0621Q0039_Amd_0002.pdf | ||
| Sol_140F0621Q0039_Amd_0001.pdf | ||
| PP_Questionaire Revised_0001.doc | DOC document | |
| 03 Submittals.pdf | ||
| PP_Questionaire.doc | DOC document | |
| 09 Drawings 21-026 RMA Lake Mary Paving.pdf | ||
| Sol_140F0621Q0039.pdf | ||
| 08 Specifications 21-026.pdf | ||
| B03 - DOL Wage Determination.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
21‐026
ROCKY MOUNTAIN ARSENAL NATIONAL WILDLIFE REFUGE
COMMERCE CITY, COLORADO
Unit Total QTY Unit Cost Cost
ACCESSIBLE SPOTS
1 1 LS
2 1 LS
3 1 CY
4 Van Accessible Sign with Handicap Sign and Post 1 LS 5 Install Existing Parking Blocks 1 LS
6 14 CY
7 5 ST
Accessible Spots Total
EAST PIER
1 1 LS
2 1 LS
3 1 LS
4 7 CY
5 56 CY
6 East Pier Gravel Transition 0.25 CY
7 1 EA
8 Parking Area Gravel Transition 7 CY 9 Boardwalk Area Gravel Transition 0.25 CY
10 West Pier Area Gravel Transition 0.5 CY
East Pier Total
Total Base Bid
Project Description: Pave surfaces as described in the drawings and specifications at Rocky Mountain Arsenal NWR.
Transition Gravel
Furnish all labor, materials, and equipment to complete the following work in accordance with the attached specifications.
Accessible Spots Concrete Paint Accessible Spots Concrete
Entire Parking Area Site preparation
Accessible Spots Mobilization/Demobilization, Bonding, Overhead, & Profit
East Pier Mobilization/Demobilization, Bonding, Overhead, & Profit Remove Bridge Edging East Pier Site preparation
East Pier Concrete and Trail
East Pier Concrete Block at Pier, Excludes Physical Concrete
East Pier Gravel
BID SCHEDULE
21‐026
ROCKY MOUNTAIN ARSENAL NATIONAL WILDLIFE REFUGE
COMMERCE CITY, COLORADO
Unit Total QTY Unit Cost Cost
Alternate I PARKING AREA (PRIORITY #1)
1 1 LS
2 3 CY
3 50 CY
4 9 ST
Parking Area Total (Priority #1) Alternate II BOARDWALK (PRIORITY #2)
1 1 LS
2 1 LS
3 1 LS
4 Boardwalk Gravel 2 CY 5 Boardwalk Concrete and Trail 9 CY
Boardwalk Total (Priority #2) Alternate III WEST PIER (PRIORITY #3)
1 1 LS
2 1 LS
3 West Pier Gravel 5 CY
4 30 CY
5 1 EA
6 West Pier Gravel Transition 0.5 CY
West Pier Total (Priority #3)
ACCESSIBLE SPOTS & EAST PIER BASE PROJECT (BP)
BP + OPTION 1
BP + OPTION 1 + OPTION 2
BP + OPTION 1 + OPTION 2 + OPTION 3
Parking Area Mobilization/Demobilization, Bonding, Overhead, & Profit
Parking Area Asphalt Parking Area Asphalt Paint
Parking Area Gravel
West Pier Site preparation
West Pier Concrete and Trail West Pier Concrete Block at Pier, Excludes Physical Concrete
Boardwalk Mobilization/Demobilization, Bonding, Overhead, & Profit Remove Existing Concrete Slab Boardwalk Site Preperation
West Pier Mobilization/Demobilization, Bonding, Overhead, & Profit
File details come from the government source that posted it. Updated .