05 Schedule.pdf
PDF 80 KB Posted
- Attached to
- Community Pool - Site, Earthwork & Utilities
- Solicitation number
- RFP-WOP-240000003020-2
- Issued by
- Ottawa County, Michigan
About this file
This document appears to be a preliminary project schedule for the West Ottawa Community Pool Bid Package 01 Utility Relocation project. The schedule outlines the key milestones and timelines for the pre-construction, procurement, and construction phases of the project, which is expected to be completed over a 50-day period from October 7, 2024 to December 13, 2024.
The pre-construction phase includes finalizing the bid package, a 10-day bidding period, bid submission, review, and board approval, followed by the issuance of subcontracts. The procurement phase covers the acquisition of storm structures and piping, watermain, and the dewatering plan over a 20-day period. The construction phase involves mobilization, fencing and jobsite setup, utility relocation, dewatering implementation, site demolition, storm and watermain relocation, flushing, testing, restoration, and cleanup.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 05.1 Site Logistics.pdf | ||
| Comm Pool Earthwork Advertisement.pdf | ||
| 04 Instructions-CMa Ed -WO Pool.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 PRE-CONSTRUCTION 20 days Mon 8/26/24 Fri 9/20/24
2 Finalize Bid Package 2 days Mon 8/26/24 Tue 8/27/24
3 Bidding 10 days Wed 8/28/24 Tue 9/10/24 2
4 Bids Due 1 day Wed 9/11/24 Wed 9/11/24 3
5 Post Bids 1 day Thu 9/12/24 Thu 9/12/24 4
6 Rec. to Award 1 day Thu 9/12/24 Thu 9/12/24 5SS
7 Board Approval 1 day Mon 9/16/24 Mon 9/16/24 6FS+1 day
8 Issue Subcontracts 4 days Tue 9/17/24 Fri 9/20/24 7
9 PROCUREMENT 20 days Mon 9/23/24 Fri 10/18/24
10 Storm Structures and Piping 3 wks Mon 9/23/24 Fri 10/11/24 8
11 Watermain 3 wks Mon 9/23/24 Fri 10/11/24 8
12 Dewatering Plan 4 wks Mon 9/23/24 Fri 10/18/24 8
13 CONSTRUCTION 50 days Mon 10/7/24 Fri 12/13/24
14 Mobilization 1 day Mon 10/7/24 Mon 10/7/24 12FS-2 wks
15 Fencing and Jobsite Setup 5 days Tue 10/8/24 Mon 10/14/24 14
16 Mis-Dig and SESC 2 days Tue 10/15/24 Wed 10/16/24 15
17 Owner Utility Relocation (Gas, Irrigation, Comm., Elec.)5 days Thu 10/17/24 Wed 10/23/24 16
18 Implement Dewatering 10 days Thu 10/24/24 Wed 11/6/24 17,12
19 Site Demo 5 days Thu 11/7/24 Wed 11/13/24 18
20 Storm and Watermain Relocation 3 wks Thu 11/14/24 Wed 12/4/24 19
21 Flushing and testing 2 days Thu 12/5/24 Fri 12/6/24 20
22 Restoration and Cleanup 5 days Mon 12/9/24 Fri 12/13/24 21
8/18 8/25 9/1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15
September October November December
West Ottawa Community Pool
BP 01 Utility Relocation - Preliminary Project Schedule
Wed 8/28/24 Page 1