This is a Notice to Bidders and Special Provisions document from the California Department of Transportation (Caltrans) for a construction contract to install lighting, striping, and signage upgrades on State Highway 154 in Santa Barbara County near Santa Ynez, spanning from 0.1 mile north of Route 246 to 0.1 mile south of Route 246 (District 05, Post Mile R8.0/R8.2). The project, identified as Contract No. 05-1R5704 and Federal-Aid Project HSST-S154(006), involves 38 bid items including lead compliance planning, traffic control systems, pavement markings and removal, thermoplastic striping, roadside sign installation and modification, lighting system modifications, and flashing beacon system modifications. Contractors must hold either a Class A license or a combination of Class C licenses (C-10, C-32) constituting the majority of work. Bids opened on November 19, 2026, with an estimated project cost of $820,000, and contractors must complete all work within 50 working days. Electronic sealed bids were accepted via the Bid Express website with a 10 percent bidder's security requirement.

The contract requires prevailing wage compliance as determined by the California Department of Industrial Relations, with the higher rate applied when federal minimum wage determinations exceed state prevailing wage rates. Buy America requirements apply to manufactured products, iron or steel products, and construction materials, with exemptions for tools, temporary work, and excluded materials such as cement and aggregates. Contractors must submit environmental product declarations for hot mix asphalt and concrete materials if applicable, comply with prompt payment requirements for subcontractors within 7 days of progress payments, and manage treated wood waste according to Health and Safety Code requirements. Traffic control restrictions apply based on designated lane closure requirements and special days including Martin Luther King Jr. Day, Farmworkers Day, and local community events, with detailed hour-by-hour closures specified for conventional highways and city streets. All work must comply with Department of Transportation standard specifications (2025 edition), project plans approved August 10, 2026, and includes provisions for dispute resolution and DRA/DRB meeting compensation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bids open Thursday, November 19, 2026

Dated October 19, 2026

STATE OF CALIFORNIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

AND

SPECIAL PROVISIONS

FOR CONSTRUCTION ON STATE HIGHWAY IN SANTA BARBARA COUNTY

NEAR SANTA YNEZ FROM 0.1 MILE NORTH OF ROUTE 246 TO 0.1 MILE

SOUTH OF ROUTE 246

In District 05 On Route 154

Under

Bid book dated October 19, 2026 Standard Specifications dated 2025

Project plans approved August 10, 2026 Standard Plans dated 2025

Identified by

Contract No. 05-1R5704

05-SB-154-R8.0/R8.2

Project ID 0524000090

Federal-Aid Project

HSST-S154(006)

SPECIAL NOTICES

See sections 2 and 3 for contractors' registration requirements.

The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.

See section 2 for submittal requirements for DVBE quotes and Non–Small Business

Subcontractor Preference.

For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).

See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.

The flagging and temporary traffic control requirements have been revised. See sections 7-

1.03, 7-1.04, and 12.

See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.

See section 14-11.14 for changes to the management of treated wood waste.

See section 6-1.01 and 6-1.04 of these Special Provisions for the requirements of Buy

America/Build America for manufactured products.

See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.

Contract No. 05-1R5704 i

TABLE OF CONTENTS

NOTICE TO BIDDERS

BID ITEM LIST

SPECIAL PROVISIONS

ORGANIZATION

DIVISION I GENERAL PROVISIONS

1 GENERAL

2 BIDDING

5 CONTROL OF WORK

6 CONTROL OF MATERIALS

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

8 PROSECUTION AND PROGRESS

9 PAYMENT

DIVISION II GENERAL CONSTRUCTION

12 TEMPORARY TRAFFIC CONTROL

14 ENVIRONMENTAL STEWARDSHIP

15 EXISTING FACILITIES

DIVISION III EARTHWORK AND LANDSCAPE

19 EARTHWORK

21 EROSION CONTROL

DIVISION VI STRUCTURES

49 PILING

55 STEEL STRUCTURES

DIVISION IX TRAFFIC CONTROL DEVICES

82 SIGNS AND MARKERS

82-6 SIGN POST SUPPORT SYSTEM

84 MARKINGS

DIVISION X ELECTRICAL WORK

86 GENERAL

87 ELECTRICAL SYSTEMS

ii

STANDARD PLANS LIST

The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.

RSP A3A Abbreviations (Sheet 1 of 3)

RSP A3B Abbreviations (Sheet 2 of 3)

RSP A3C Abbreviations (Sheet 3 of 3)

A10A Legend - Lines and Symbols (Sheet 1 of 5)

A10B Legend - Lines and Symbols (Sheet 2 of 5)

A10C Legend - Lines and Symbols (Sheet 3 of 5)

A10D Legend - Lines and Symbols (Sheet 4 of 5)

A10E Legend - Lines and Symbols (Sheet 5 of 5)

A20A Pavement Markers and Traffic Lines - Typical Details

A20B Pavement Markers and Traffic Lines - Typical Details

A20C Pavement Markers and Traffic Lines - Typical Details

A20D Pavement Markers and Traffic Lines - Typical Details

A20E Traffic Lines - Typical Details for Contrast Striping

A20F Pavement Markers and Traffic Lines - Typical Details

A20G Exit Ramp with Enhanced Pavement Markers for Wrong Way Details

A24A Pavement Markings - Arrows

A24B Pavement Markings - Arrows and Symbols

A24C Pavement Markings - Symbols and Numerals

A24D Pavement Markings - Words

A24E Pavement Markings - Words

A24F Pavement Markings - Crosswalks

A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details

A24H Pavement Markings - Arrows

A73A Object Markers

A73B Markers

H1 Landscape and Erosion Control Symbols

T1A Temporary Crash Cushion - Sand Filled (Unidirectional)

T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)

T1B Temporary Crash Cushion - Sand Filled (Bidirectional)

T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)

T3C Temporary Barrier System (Cross Bolt) iii

T3D Temporary Barrier System (Cross Bolt)

T3E Temporary Barrier System (Cross Bolt)

T3F Temporary Barrier System (Cal F-23)

T3F2 Temporary Barrier System (Cal F-23)

T3G Temporary Barrier System (Staking or Anchoring)

T3G2 Temporary Barrier System (Staking or Anchoring)

T9 Traffic Control System Tables for Lane and Ramp Closures

RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways

T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional Highways and Expressways

RSP T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways

RSP T13B Traffic Control System - Two Lane Conventional Highways

T17 Traffic Control System for Moving Lane Closure on Two Lane Highways

T19 Traffic Control System - Construction Work Zone Speed Limit Reduction on Conventional Highways

T22 Traffic Control System for Construction Work Zone Speed Limit Reduction on Two Lane Conventional Highways

RS1 Roadside Signs - Typical Installation Details No. 1

RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2

RS3 Roadside Signs - Laminated Wood Box Post - Typical Installation Details No. 3

RS4 Roadside Signs - Typical Installation Details No. 4

S89 Roadside Sign - Formed Single Sheet Aluminum Panel

S93 Framing Details for Framed Single Sheet Aluminum Signs, Rectangular Shape

S94 Roadside Framed Single Sheet Aluminum Signs, Rectangular Shape

S95 Roadside Single Sheet Aluminum Signs, Diamond Shape

ES-1A Electrical Systems (Legend)

ES-1B Electrical Systems (Legend)

ES-1C Electrical Systems (Legend)

ES-2E Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - B Series)

ES-4A Electrical Systems (Signal Head Mounting)

ES-4C Electrical Systems (Signal Heads and Mountings)

ES-4D Electrical Systems (Signal Head Mounting)

ES-6A Electrical Systems (Lighting Standard, Types 15 and 21)

ES-6B Electrical Systems (Electrolier Anchorage and Grouting for Type 15 and Type 21, Barrier Rail Mounted)

ES-6E Electrical Systems (Lighting Standard, Types 30 and 31)

ES-6F Electrical Systems (Lighting Standard, Slip Base Plate) iv

ES-7B Electrical Systems (Signal and Lighting Standard, Type 1 and Equipment Identification Characters)

ES-7J Electrical Systems (Flashing Beacon on a Type 1, Type 15-FBS, and Type 40 Standard)

ES-7M Electrical Systems (Signal and Lighting Standard, Details No. 1)

ES-7N Electrical Systems (Signal and Lighting Standard, Details No. 2)

RSP ES-7O Electrical Systems (Signal and Lighting Standard, Details No. 3)

ES-8A Electrical Systems (Non-Traffic Pull Box)

ES-8B Electrical Systems (Traffic Pull Box)

ES-11 Electrical Systems (Foundation Installations)

ES-13A Electrical Systems (Splice Insulation Methods Details)

ES-13B Electrical Systems (Kinking and Banding Detail)

ES-14B Electrical Systems (EMS and FBE Wiring Diagrams)

CANCELED STANDARD PLANS LIST

The 2025 standard plan sheets listed below are canceled and not applicable to this contract.

Plan No.

Date

Canceled Plan No.

Date Canceled

Plan No.

Date

Canceled

P8 04-20-26

NOTICE TO BIDDERS

Bids open Thursday, November 19, 2026

Dated October 19, 2026

General work description: Install lighting, striping, and signage upgrades.

The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON

STATE HIGHWAY IN SANTA BARBARA COUNTY NEAR SANTA YNEZ FROM 0.1 MILE NORTH OF

ROUTE 246 TO 0.1 MILE SOUTH OF ROUTE 246.

District-County-Route-Post Mile: 05-SB-154-R8.0/R8.2

Contract No. 05-1R5704

The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-10, C-32.

Federal-aid project no.:

HSST-S154(006)

Bids must be on a unit price basis.

Complete the work within 50 working days.

The estimated cost of the project is $820,000.

The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.

The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.

For bid results go to:

https://ppmoe.dot.ca.gov/cc

Select Electronic Bidding under the Bidding tab.

District office addresses are provided in the Standard Specifications.

Present bidders' inquiries to the Department and view the Department's responses at:

https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries

Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.

Submit your bid with bidder's security equal to at least 10 percent of the bid.

Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.

The federal minimum wage rates for this Contract as determined by the United States Secretary of Labor are available at https://sam.gov/content/home.

If the minimum wage rates as determined by the United States Secretary of Labor differs from the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors must not pay less than the higher wage rate. The Department does not accept lower State wage rates not specifically included in the federal minimum wage determinations. This includes helper, or other classifications based on hours of experience, or any other classification not appearing in the federal wage determinations. Where federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors must not pay less than the federal minimum wage rate that most closely approximates the duties of the employees in question.

The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.

Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.

Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.

Department of Transportation

BID ITEM LIST

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM

0002 080060 LEVEL 2 CRITICAL PATH METHOD SCHEDULE LS LUMP SUM

0003 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 50

0004 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM

0005 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM

0006 120207 PORTABLE RADAR SPEED FEEDBACK SIGN

SYSTEM

DAY 60

0007 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM

0008 129161 AUTOMATED FLAGGER ASSISTANCE DEVICE

DAY

EA 60

0009 130100 JOB SITE MANAGEMENT LS LUMP SUM

0010 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM

0011 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM

0012 141120 TREATED WOOD WASTE LB 330

0013 210010 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 1

0014 210430 HYDROSEED SQFT 29,900

0015 210610 COMPOST (CY) CY 190

0016 378000 MICRO-SURFACING TON 14

0017 397005 TACK COAT TON 0.3

0018 810120 REMOVE PAVEMENT MARKER EA 250

0019 810230 PAVEMENT MARKER (RETROREFLECTIVE) EA 250

0020 820250 REMOVE ROADSIDE SIGN EA 4

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0021 820610 RELOCATE ROADSIDE SIGN EA 2

0022 820750 FURNISH SINGLE SHEET ALUMINUM SIGN

(0.063"-UNFRAMED)

SQFT 170

0023 820760 FURNISH SINGLE SHEET ALUMINUM SIGN

(0.080"-UNFRAMED)

SQFT 80

0024 820840 ROADSIDE SIGN - ONE POST EA 23

0025 037124 SIGN POST SUPPORT SYSTEM EA 10

0026 820900 INSTALL ROADSIDE SIGN PANEL ON EXISTING

POST

EA 2

0027 840516 THERMOPLASTIC PAVEMENT MARKING

(ENHANCED WET NIGHT VISIBILITY)

SQFT 2,450

0028 840517 PREFORMED THERMOPLASTIC PAVEMENT

MARKING

SQFT 150

0029 840619 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY) (BROKEN

12-3)

LF 340

0030 840621 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY) (BROKEN

17-7)

LF 700

0031 846007 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

LF 9,570

0032 846009 8" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

LF 890

0033 846010 8" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY) (BROKEN

12-3)

LF 520

0034 846030 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 10,700

0035 846035 REMOVE THERMOPLASTIC PAVEMENT

MARKING

SQFT 2,320

0036 872131 MODIFYING LIGHTING SYSTEMS LS LUMP SUM

0037 872136 MODIFYING FLASHING BEACON SYSTEMS LS LUMP SUM

0038 999990 MOBILIZATION LS LUMP SUM

SPECIAL PROVISIONS

ORGANIZATION

Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.

Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.

Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.

DIVISION I GENERAL PROVISIONS

1 GENERAL

Add to section 1-1.01:

Bid Items and Applicable Sections

Item code

Item description Applicable section

037124 SIGN POST SUPPORT SYSTEM 82

2 BIDDING

Delete section 2-1.20.

Delete section 2-1.33B(2)(b).

5 CONTROL OF WORK

Delete section 5-1.13B.

Replace section 5-1.13E with:

5-1.13E Prompt Payment

Section 5-1.13E applies to all contracts.

Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.

Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:

1. Subcontractor’s or entity’s business name

2. Description of work performed

2.1. Bid item numbers or change order numbers

2.2. Written narrative of work performed

3. Value of work performed

4. Amount paid to subcontractor or entity

5. Withhold amount, if applicable

6. Explanation of withhold reasoning, if applicable

Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.

If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:

1. Value of the disputed work

2. Amount of the withhold being taken

3. Bid item numbers or change order numbers associated with the disputed work

4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated

5. Corrective actions to be taken for release of withheld amount

The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.

The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:

1. Withhold was not applied in good faith

2. Requested additional withhold documentation records were not provided

3. Payment information was not submitted through the prompt payment monitoring system

4. Required withhold notification was not provided

The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.

Add between the 6th and 7th paragraph of section 5-1.43E(1)(a):

DRA and DRB meetings may be held either virtually or on-site at the job location upon mutual agreement by the Contractor, the Department, and the DRA or DRB.

DRA and DRB meetings include:

1. Initial project meeting

2. Progress meetings

3. Dispute meetings

On-site meetings are held at a physical location and include on-site time, travel time, transportation, lodging, and incidentals for each day or portion thereof.

Virtual meeting includes virtual meeting time, equipment, and incidentals for each hour or portion thereof, either all or part of the DRA and DRB members, with the following requirements:

1. Obtain authorization for virtual meeting 14 days before the meeting

2. Use of Webex, Zoom or MS Teams virtual platforms

Obtain authorization for DRA or DRB members before spending any time on DRA- or DRB- related tasks.

Hourly off-site DRA and DRB related tasks include reviewing the plans, specifications, evaluating positions, preparing recommendations, completing forms, or performing any other off-site DRA- or DRB-related tasks.

Replace section 5-1.43E(1)(i) with:

5-1.43E(1)(i) Payment

Pay the DRA or each DRB member for meeting participation as follows:

1. $250 per hour for agreed hourly off-site DRA- or DRB-related tasks

2. For attending a virtual off-site meeting with a limit of $1,000 per meeting at hourly off-site DRA-or

DRB-related tasks rate

3. $2,500 per day for each on-site meeting

Department does not pay for (1) DRA- or DRB-work performed after Contract acceptance or (2) cost of preparing for or attending ADR meetings.

The Department pays:

1. $250 per hour for agreed off-site DRA- or DRB-related tasks

2. For each DRA or DRB member attending a virtual off-site meeting with a limit of $1,000 per meeting at hourly off-site DRA-or DRB-related tasks rate

3. $2,500 per DRA on-site meeting

4. Up to $7,500 per DRB on-site meeting

Payment is full compensation for each meeting and off-site DRA- or DRB-related tasks.

The Department does not adjust the unit price for an increase or decrease in the quantity of:

1. DRA on site meeting

2. DRB on site meeting

3. Hourly off-site DRA- or DRB-related task

Within 60 days of receipt of Department's payment, submit copies of associated invoices and supporting documents in the form of a canceled check or bank statement for DRA- or DRB-payment verification.

6 CONTROL OF MATERIALS

Add to end of section 6-1.01:

If you fail to submit the form for materials subject to Buy America, the Department may:

1. Withhold from the next progress payment

2. Reject your request for a De Minimis Costs waiver for non-compliant construction materials or manufactured products

Replace section 6-1.03B with:

6-1.03B Submittals

6-1.03B(1) General

Not Used

6-1.03B(2) Work Plan

For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:

1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).

2. Land use history of the local material location and surrounding property

3. Sampling protocol

4. Number of samples per volume of local material

5. QA and QC requirements and procedures

6. Qualifications of sampling personnel

7. Stockpile history

8. Name and address of the analytical laboratory that will perform the chemical analyses

9. Analyses that will be performed for lead and pH

10. Other analyses that will be performed for possible hazardous constituents based on:

10.1. Source property history

10.2. Land use adjacent to source property

10.3. Constituents of concern in the ground water basin where the job site is located

The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.

If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.

6-1.03B(3) Analytical Test Results

At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:

1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.

2. Chain of custody of samples

3. Analytical results no older than 1 year

4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit

5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location

6-1.03B(4) Sample and Analysis

Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:

1. Before bringing the local material to the job site

2. As described in the local material plan

3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)

The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.

Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:

Minimum Number of Samples and Analytical Tests for Local Material

Maximum volume of imported borrow (cu yd)

Minimum number of samples and analytical tests

< 5,000 8

5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof

10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof

20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof

40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof

> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof

Do not collect composite samples or mix individual samples to form a composite sample.

Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).

The analytical test results must demonstrate that the local material:

1. Is not a hazardous waste

2. Has a pH above 5.0

3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg

4. Is free of possible contaminants identified in the local material plan

5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location

6-1.03C Local Material Management

Do not place local material until authorized.

If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).

Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.

Replace section 6-1.04 with:

6-1.04 BUY AMERICA

6-1.04A General

Buy America requirements do not apply to the following:

1. Tools and construction equipment used in performing the work.

2. Temporary work that is not incorporated into the finished project.

An article, material, or supply to be permanently incorporated in the project should only be classified into one of the following categories:

1. Iron or steel products

2. Manufactured products

3. Construction materials

4. Excluded materials

Excluded materials means cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives.

6-1.04B Crumb Rubber (Pub Res Code § 42703(d))

Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:

1. Produced in the United States

2. Derived from waste tires taken from vehicles owned and operated in the United States

6-1.04C Iron or Steel Products

Iron or steel products must be melted and manufactured in the United States except:

1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials

2. If the total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total bid or $2,500, the material may be used if authorized

Furnish iron or steel products to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured.

All melting and manufacturing processes for these materials, including an application of a coating, must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.

6-1.04D Manufactured Products

Manufactured products mean articles, materials, or supplies that have been:

1. Processed into a specific form and shape; or

2. Combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies

Per 23 CFR 635.410, these products must be manufactured in the United States.

Manufacturer, in the case of manufactured products, means the entity that performs the final manufacturing process by bringing individual elements together that produces a manufactured product.

If an item is classified as an iron or steel product, a construction material, or an excluded material under the definitions set forth under this Buy America section, then it is not a manufactured product. However, an article, material, or supply classified as a manufactured product under this Buy America section may include components that are construction materials, iron or steel products, or excluded materials.

Iron or steel used in precast concrete manufactured products or enclosures for Intelligent Transportation Systems (ITS) must meet the requirements of section 6-1.04C regardless of the amount used.

Iron or steel used in other manufactured products must meet the requirements of section 6-1.04C if the cost of steel and iron components is 50 percent or more of the total cost of the manufactured product.

Furnish manufactured products to be incorporated into the work with certificates of compliance with each project delivery. The manufacturer's certificate of compliance must identify where the manufacturing occurred and attest specifically to compliance with the 23 CFR 635.410 standard.

6-1.04E Construction Materials

The following construction materials must be produced in the United States under standards in 2 CFR 184.6:

1. Non-ferrous metals

2. Plastic and polymer-based products such as:

2.1. Polyvinylchloride

2.2. Composite building materials

3. Glass

4. Fiber optic cable including drop cable

5. Optical fiber

6. Lumber

7. Engineered wood

8. Drywall

All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United States.

Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where the construction material was manufactured and attest specifically to compliance with the 2 CFR 184.6 standard.

Minor additions of articles, materials, supplies, or binding agents to these construction materials do not change the categorization of the construction material.

6-1.04F Buy America Waiver for the De Minimis Costs for Manufactured Products and Construction Materials

A De Minimis Costs waiver can waive the application of FHWA's Buy America requirements for manufactured products and construction materials under a single project when the total cost of non-compliant manufactured products and construction materials is no more than the lesser of $1,000,000 or 5 percent of the total applicable costs for the project.

The percentage threshold is calculated based on the following formula:

X = NC / TA

where:

X = percent threshold NC = total cost of non-compliant construction materials and manufactured products TA = total applicable project costs (steel, iron, construction materials and manufactured products;

does not include excluded materials)

This threshold is based on the actual cost of the steel, iron, construction materials, and manufactured products, not the anticipated cost of those materials. The contractor must account for compliant and non-compliant Department-Furnished Materials for the project in the De Minimis Costs Waiver Worksheet calculation if provided by the Department as supplemental project information.

See further instructions for the De Minimis Costs waiver request in the Notice of Materials to be Used form.

Add to section 6-1:

6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE

Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.

See section 6-1.06B for definitions.

For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:

Material or product Material specifications

Hot mix asphalta Section 39-2, "Hot Mix Asphalt" Excludes RHMA, OGFC, and BWC materials.

Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."

Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.

aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.

bFor each concrete plant providing 250 cubic yards or more on the project by mix design.

The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.

The requirements in section 6-1.08 do not apply to informal-bid contracts.

For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:

1. Applicable product category rule has expired without replacement as of the bid opening date.

2. Applicable product category rule was issued less than 50 days before the bid opening date.

Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer. If the Engineer determines the development of a facility-specific environmental product declaration cannot be achieved, an environmental product declaration will not be required for that material or product.

You must register on the Department’s Data Interchange for Materials Engineering (DIME) at least 15 days before submitting environmental product declarations. Follow the registration process at:

https://dime.dot.ca.gov/

Within 30 days of initial placement of each applicable material or product, submit a facility-specific, product stage, environmental product declaration informational submittal to DIME and provide proof of submission in PDF file format to the Engineer. The DIME entry information must include intended use of materials and estimated quantities of materials to be used as represented by the environmental product declaration.

Failure to provide a required environmental product declaration informational submittal will result in a $6,000 performance failure withhold for each missing declaration. The Department returns the withhold within 30 days after receipt of the compliant declaration if submitted prior to Contract acceptance.

Withholds become permanent deductions if the declaration is not submitted before Contract acceptance.

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

Replace Section 7-1.02K(6)(j)(iii) with:

7-1.02K(6)(j)(iii) Unregulated Earth Material Containing Lead

Section 7-1.02K(6)(j)(iii) includes specifications for handling, removing, and disposing of unregulated earth material containing lead. Management of this material exposes workers to health hazards that must be addressed in your lead compliance plan. This material contains average lead concentrations below 80 mg/kg total lead and below 5 mg/L soluble lead and is not regulated by DTSC as a hazardous substance or a hazardous waste. This material does not require disposal at a permitted landfill or solid waste disposal facility. The RWQCB has jurisdiction over reuse of this material at locations outside the job site limits.

Unregulated earth material exists throughout the job site.

Lead is typically found within the top 2 feet of material within the highway. Reuse all of the excavated material on the right-of-way.

Handle the material under all applicable laws, rules, and regulations, including those of the following agencies:

1. Cal/OSHA

2. CA RWQCB, Region 3, Central Coast

8 PROSECUTION AND PROGRESS

Replace the row for DBE and DVBE in the table in the 2nd paragraph of section 8-1.03 with:

DVBE Final utilization reports

Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:

Schedule Baseline schedule and weekly statement of working days report

Replace section 8-1.04C with:

8-1.04C Delayed Start

Section 8-1.04B does not apply.

Start job site activities within 180 days after receiving notice that the Contract has been approved by the Attorney General or the attorney appointed and authorized to represent the Department.

Do not start job site activities until the Department authorizes or accepts your submittal for:

1. CPM baseline schedule

2. WPCP or SWPPP, whichever applies

3. Contingency plan for opening closures to traffic

4. Electrical equipment

5. Sign Panels

Do not start other job site activities until all the submittals from the above list are authorized or accepted and the following information is received by the Engineer:

1. Notice of Materials To Be Used form.

2. Written statement from the vendor that the order for sign panels has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.

3. Written statement from the vendor that the order for electrical material has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.

You may start job site activities before the 180th day after Contract approval if you:

1. Obtain specified authorization or acceptance for each submittal before the 180th day

2. Receive authorization to start

Submit a notice 72 hours before starting job site activities. If the project has more than 1 location of work, submit a separate notice for each location.

Replace the 4th and 5th paragraphs of section 8-1.05 with:

The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.

The weekly statement of working days report shows:

1. Working days and non–working days during the reporting week

2. Time adjustments

3. Calculations of work completion dates, including working days remaining

4. Controlling activities

Delete the 6th paragraph of section 8-1.05.

9 PAYMENT

Replace the 1st paragraph of section 9-1.11D with:

For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.

Replace item 2 in the list in the paragraph of section 9-1.16C with:

2. Material cost exceeds either of the following:

2.1. $50,000

2.2. $25,000 if the requestor is certified as one or more of the following:

2.2.1. DVBE

2.2.2. Small business as certified by Department of General Services, Office of Small

Business and Disabled Veteran Business Enterprise Services

DIVISION II GENERAL CONSTRUCTION

12 TEMPORARY TRAFFIC CONTROL

Replace section 12-3.20 with:

12-3.20 TEMPORARY BARRIER SYSTEMS

12-3.20A General

12-3.20A(1) Summary

Section 12-3.20 includes specifications for temporary barrier systems.

Temporary barrier system consists of:

1. New or undamaged used interconnected barrier segments

2. Segment connection hardware

3. Stakes and anchor bolts

Value engineering change proposals for the use of Type K temporary railing are not allowed.

If a discrepancy exists, governing ranking in descending order is:

1. These specifications

2. Approved manufacturer's drawings

3. Approved manufacturer's installation instructions

Markers must comply with section 82.

12-3.20A(2) Definitions anchored: Method for attaching temporary barrier segments to concrete pavement.

approach zone: Area immediately upstream of the protected area.

clear area width: Minimum width throughout the length of the barrier system that must be maintained clear of obstructions, objects, and work resources during non-working hours. The width is measured perpendicular from the non-traffic side toe.

departure zone: Area immediately downstream of the protected area.

freestanding: Temporary barrier not attached to the pavement.

height differential: May be an excavation, a downward slope greater than 4:1, or a difference in elevation. The height differential is measured down from the top of pavement.

minimum system length: Sum of approach zone, protected area, and departure zone.

set back distance: Measured between the closest toe of temporary barrier and the edge of traveled way for each direction of traffic.

staked: Method for attaching temporary barrier segments to asphalt concrete pavement.

12-3.20A(3) Submittals

Submit as informational submittal for each type of temporary barrier system:

1. Certificate of compliance.

2. Manufacturer's installation instructions and Department approved manufacturer’s drawings from the

Department’s Division of Safety Programs website, except for temporary concrete barriers Cross Bolt and CAL F-23.

3. Manufacturer's concrete QC test results and daily production log of precast concrete activities, under section 90-4. QC test results must include the concrete mix design number and barrier stamped ID.

Submit connection bolt test reports that certify compliance with the applicable ASTM requirements, for temporary barrier systems Cross Bolt. The test reports must be from a laboratory that is accredited to International Standards Organization/International Electrotechnical Commission 17025 by the American Association for Laboratory Accreditation (A2LA) or the ANSI-ASQ National Accreditation Board.

Submit a signed manufacturer's replacement evaluation report within 10 days of damage to a temporary steel barrier system.

12-3.20A(4) Quality Assurance

12-3.20A(4)(a) General

QC sampling, testing, and inspection personnel must have an ACI Concrete Field-Testing Technician, Grade 1 certification.

Temporary concrete barrier segments must:

1. Comply with the requirements for tier 3 precast concrete in section 90-4

2. Be fabricated at a plant on the Authorized Facility Audit List

Concrete must be sampled and tested as shown in the following table.

Concrete QC Tests Quality characteristic Test method Minimum testing frequency

Compressive strength ASTM C172/C172M, ASTM C31/C31M, and

ASTM C39/C39M

Once per 300 cu yd of concrete cast, or every day of casting, whichever is more frequent

Slump ASTM C143/C143M Temperature at time of mixing ASTM C1064/C1064M Density ASTM C138 Once per 600 cu yd of concrete cast or every 7 days of batching, whichever is more frequent

Air content ASTM C231/C231M or

ASTM C173/C173M

If concrete is air entrained, once for each set of cylinders, and when conditions warrant

A daily production log of precast concrete activities must be maintained under section 90-4.01C(4).

12-3.20A(4)(b) Quality Control

Not Used

12-3.20B Materials

12-3.20B(1) General

Temporary barrier segment must:

1. Be a minimum 31-1/2 inches in height

2. Have at least two lifting holes

3. Be designed to be used with temporary traffic screen when required

Temporary barrier segment may have your name or logo on each barrier segment. The name or logo must be no more than 4 inches in height and must be located no more than 12 inches above the bottom of the barrier segment.

Temporary barrier systems must comply with a minimum MASH Test Level 3.

Except for Cross Bolt, and CAL F-23, temporary barrier systems must:

1. Be on the Authorized Materials List for highway safety features

2. Comply with the manufacturer's drawings shown on the Department's Division of Safety Programs website and the manufacturer's installation instructions

12-3.20B(2) Temporary Concrete Barriers

12-3.20B(2)(a) General

Not Used

12-3.20B(2)(b) Temporary Concrete Barriers Type F

12-3.20B(2)(b)(i) General

Temporary concrete barrier Type F segment must:

1. Be precast concrete with a minimum 5,000-psi compressive strength.

2 Have bar or welded wire reinforcement steel that complies with section 52.

3. Have a finished surface that complies with section 51-1.03F(2).

4. Include the manufacturer's name, lot number, and month and year of manufacture stamped on the top of each barrier segment. The stamped information must be:

4.1. No more than 6 inches in height

4.2. From 3/16 to 1/4 inch in depth

4.3. Centered on the top width of the barrier segment

5. Use one of the following segment connections:

5.1. Loop and pin

5.2. "J" hook

5.3. Cross Bolt

6. Comply with the tolerances shown in the following table:

Precast Barrier Tolerances Dimension Tolerance(±)

Length (in) 1 Insert placement (in) 1/2 Horizontal alignment (in) 1/8 per 10 feet of length Deviation of ends (in):

Horizontal skew Vertical batter

1/4 1/8 per foot of depth

Bar reinforcement steel must:

1. Comply with ASTM A615 or ASTM A706, Grade 60

2. Be galvanized under section 52-3, when shown

Welded wire reinforcement must comply with ASTM A1064.

Stake must:

1. Be steel and comply with ASTM A36/A36M-14 or ASTM A529-14, Grade 50

2. Be 1-1/2 inches in diameter and 36 inches long, except "J" Hook must be 48 inches long

3. Have a 1/2-by-3-1/2-by-3-1/2-inch plate welded 2 inches down from the upper end using a 3/8-inch fillet weld under AWS D1.1 or D1.4

Anchor bolt must:

1. Be a steel bolt or threaded rod 1-1/8 inches in diameter

2. Comply with ASTM A307

3. Include a 1/2-by-3-1/2-by-3-1/2-inch plate washer:

3.1. With a 1-3/8-inch-diameter hole in the center

3.2. Complying with ASTM A36/A36M

3.3. Galvanized post fabrication under section 75-1.02B

Threaded rod must include a nut complying with ASTM A563.

Anchor steel plate must:

1. Be 1/2 inch thick

2. Comply with ASTM A572, Grade 50

3. Be galvanized post fabrication under section 75-1.02B

Chemical adhesive must be on the Authorized Materials List for chemical adhesives and must be for a threaded rod at least 1 inch in diameter.

12-3.20B(2)(b)(ii) Temporary Barrier Systems Cross Bolt

Cross Bolt hardware includes:

1. Connection bolt

2. Nut complying with ASTM A563

3. Hardened washer complying with ASTM F436, Type 1

4. Plate washer complying with ASTM A36/A36M and galvanized post fabrication under section 75-

1.02B

Connection bolt must:

1. Be a 7/8-inch bolt or threaded rod and comply with one of the following:

1.1. HS threaded rod ASTM A193, Grade B7

1.2. HS threaded rod ASTM A449, Type 1

1.3. HS nonheaded anchor bolt ASTM F1554, Grade 105, Class 2A

2. Have a permanent grade symbol and manufacturer's identifier

12-3.20B(2)(c)(iii) Temporary Barrier Systems CAL F-23

Connecting loop must:

1. Be a steel bar 3/4 inch in diameter

2. Comply with ASTM A36/A36M, cold roll

3. Be galvanized after fabrication

Connecting pin must:

1. Comply with ASTM A449

2. Be forged steel, no welds

3. Be 1 inch in diameter and a minimum 30-1/4 inches long

4. Be galvanized under ASTM F2329 and A153

12-3.20B(3) Temporary Steel Barriers

Temporary steel barrier segment must:

1. Be galvanized steel.

2. Have a joint connection.

3. Include permanent identification information with no more than 6 inches in height and 12 inches in length and centered on the top width of the segment. The identification information must include:

3.1. Manufacturer's name

3.2. Serial number

3.3. Lot number

3.4. Month and year of manufacture

Temporary steel barrier HV2 segment must be filled to a depth of 11-13/16 inches with concrete ballast.

12-3.20B(10) Temporary Terminal Sections

Not Used

12-3.20C Construction

12-3.20C(1) General

Clean temporary barrier segments at time of installation and at least every 6 months thereafter.

Install temporary barrier systems based on the requirements shown in the following tables:

Minimum Clear Area Width

Temporary barrier system

Configuration

Height differentials 3 feet or less

(ft)

Height differentials greater than 3 feet up to 8 feet

(ft)

Edge of deck or height differentials greater than

8 feet (ft)

Fixed objects, falsework members, or temporary supportsa

(ft) Cross Bolt 10-foot & 30-foot

Freestanding 1 2 5 5 3 stakes or anchor bolts per segment traffic side

1 1 2 3

Cross Bolt 20-foot

Freestanding 1 2 5 5 4 stakes or anchor bolts per segment traffic side

1 1 2 3

CAL F-23

12-foot

Freestanding 4 5 8 8 3 stakes or anchor bolts per segment traffic side

1 1 2 3

CAL F-23

20-foot

Freestanding 4 5 8 8 4 stakes or anchor bolts per segment traffic side

1 1 2 3

J-J hooks 12.5-foot

Freestanding 3 4 8 7 3 stakes per segment traffic side

1 1 2 3

2 anchor bolts per segment traffic side

1 1 2 3

J-J hooks 20-foot

Freestanding 3 4 8 7 4 stakes per segment traffic side

1 1 2 3

3 anchor bolts per segment traffic side

1 1 2 3

ProMASH 30-foot

Freestanding 1 2 4 4 3 stakes on traffic side

1 1 1 2

3 stakes each side (total 6)

1 1 1 2

ProMASH 20-foot

Freestanding 1 2 5 5 3 stakes on traffic side

1 1 2 3

3 stakes each side (total 6)

1 1 1 2

ProMASH 10-foot

Freestanding 2 3 6 6 2 stakes on traffic side

1 1 3 4

2 stakes each side (total 4)

1 1 2 3

REBLOC

39.33-foot

SDS

Freestanding

4 4 7 7

MDS

Staked or

Anchored every

6.5 feet

1 1 2 4

Zoneguard 50-foot

Freestanding Staked or anchored at both ends only

6 7 9 10

SDS

Staked or anchored every 250 feet

5 6 8 9

MDS

Staked or anchored every 33 feet

1 1 3 4

HV2

19-foot

Freestanding 4 5 7 8

Defender 12-3/4-foot

Staked every 30 feet

1 2 4 5

HighwayGuard 19.8-foot

SDS

Staked or

Anchored every 190 feet

4 5 7 8

LDS

Staked or

Anchored every 40 feet

1 2 5 5

MDS

Staked or

Anchored every

6.5 feet

1 1 1 2 aThe minimum clear area width to a falsework or temporary support footing can be 2 feet less than the clear area width shown. Measure clear area width to the footing edge closest to traffic.

Minimum System Length, Curve Radius, and Setback

Temporary barrier system

Barrier segment length

(ft)

Minimum system length

(ft) Minimum curve radius (ft)

Minimum setback

(ft) Posted speed greater than

45mph

Posted speed 45mph or less

Cross Bolt 10

160 120

CAL F-23 12

160 120

J-J hooks 12.5

ProMASH 10

REBLOC

SDS

MDS 39.33

Zoneguard Freestanding

SDS

MDS

50 250 250 800 NAa NAa

HV2 19 323 323 262 5

Defender 12.75 260 260 755 2 HighwayGuard SDS 19.8 393 393 NAa 7 HighwayGuard LDS 19.8 200 200 NAa 2 HighwayGuard

MDS

19.8 160 120 NAa NAa a Not approved.

Place temporary barrier system:

1. Approach zone length of a minimum:

1.1. 60 feet on facilities with a posted speed of 45 mph or less

1.2. 100 feet on facilities with a posted speed greater than 45 mph

2. Departure zone length of a minimum 60 feet

Place temporary barrier systems on concrete or asphalt concrete pavement.

Before anchoring temporary barrier systems on bridge decks, confirm the anchor will not penetrate closer than 1-1/2 inches from the bottom…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .