0302-03 SOW Rev2 .docx
DOCX document 19 KB Posted
- Attached to
- Cooling System Service Federal contract opportunity
- Solicitation number
- N0017823Q6732
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 23Q6732_Update_Released.pdf | ||
| 0302-03 DID DI-MGMT.pdf | ||
| 0302-03 CDRL A001.pdf | ||
| 23Q6732_Released.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HD-1140A AN/SPY-1D(V) ELECTRONIC COOLING WATER (ECW) SYSTEM
STATEMENT OF WORK
1.0 BACKGROUND
Surface Combat Systems Center, Wallops Island, VA has a requirement to provide a chelate flush of the SPY-1D(V) Radar System as it continues to experience increased cooling flow faults due to contaminants in the closed loop cooling system which results in loss of maximum high power capability. The SPY-1D(V) Radar System cannot support mission requirements and maintainability with the flow restriction in the cooling water loop.
| 2.0 | APPLICABLE DOCUMENTS |
| 2.1 | AEGIS Electronic Cooling Water Systems Technical Manual SW279-DJ-PRO-010/SPY/FCS, Revision 2; |
| 2.2 | Hazardous Materials State and Federal Environmental Laws; |
| 2.3 | Hazardous Materials Occupational Safety and Health Administration (OSHA) Regulations; and |
| 2.4 | Center for Disease Control (CDC) Regulations. |
| 3.0 | REQUIREMENTS |
| 3.1 | The Contractor shall provide personnel with experience on chelate flushing on AN/SPY-1A/B/D (SPY) ECW systems. |
| 3.2 | The Contractor shall provide chemical cleaning with citric acid solution referenced in AEGIS Electronic Cooling Water Systems Technical Manual SW279-DJ-PRO-010/SPY/FCS, Revision 2, during a single availability timeframe. |
| 3.3 | The Contractor shall provide chemical cleaning of the system conducted IAW the above applicable documents and regulations. |
3.4 The Contractor shall provide containers for waste disposal and remove from site for proper disposal.
3.5 The Contractor shall provide Rainmaker for producing distilled water and refill ECW system upon completion of flush.
| 3.6 | The Contractor shall only perform minor repair of leaks or minor removal of obstructions from piping that will not increase cost. Any repair work identified that will require additional funding to the contract must be immediately brought to the attention of the TPOC and should be included in the Final Condition report (CDRL A001). |
| 3.7 | The Contractor shall perform all work under this order at Surface Combat Systems Center (SCSC). |
| 3.8 | The Contractor shall coordinate with the technical point of contact (TPOC) as to when the system is offline for this work. |
*The contractor shall not perform any services beyond those identified in the contract. If any additional services/repairs are identified during the work, the contractor shall submit a quote to the TPOC and Contracting Officer for approval and subsequent contract modification prior to completing the repairs.
*The Government reserves the right to modify this contract at a later date to cover additional repair services identified during the initial work.
4.0 DATA DELIVERABLES
The Contractor shall deliver data IAW CDRL A001.
5.0 TRAVEL
The Contractor will be required to travel in performance of this contract. The number of trips and types of personnel traveling shall be limited to the minimum required to accomplish the work requirements and shall be coordinated with the technical point of contact. All travel shall be conducted in accordance with the Federal Travel Regulations (FTR).