This document is the Construction Specifications for the GUT813130A Breakpoint Wetland project in Guthrie County, Iowa, which is being prepared by the Natural Resources Conservation Service (NRCS). The work involves site preparation, structure removal, pollution control, seeding and mulching, mobilization, subsurface drain investigation and repair, water removal, sheet piling, excavation, earthfill, topsoiling, concrete work, and tile drains. Key quantities include around 14,500 cubic yards of earthwork, 1,770 square feet of sheet pile, 2,100 linear feet of tile installation, 970 tons of riprap, and 18 acres of seeding. The project is estimated to cost between $390,000 and $440,000. The specifications outline the materials, methods, and requirements for the various work items, as well as measurement and payment terms. No separate payment will be made for some subsidiary items, and the contractor will be responsible for complying with local and federal laws regarding pollution control, weed control, and other requirements.

View the file

Other files

File Type Posted
01-General Requirements.pdf PDF
05 - Storm Water Calculations & Geotechnical Report.pdf PDF
Notice to Bidders.pdf PDF
08 - NNB Permit.pdf PDF
Pre-bid documents.pdf PDF
06 - Appendix II.pdf PDF
07 - Guthrie County Inspection Plan.pdf PDF
02- Submittals.pdf PDF
04 - Plans 06-06-2023.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SPECIFICATIONS

FOR

GUT813130A BREAKPOINT WETLAND

GUTHRIE COUNTY, IOWA

June 2023

PREPARED BY:

PROJECT #4213850

I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that I am a duly licensed Professional Engineer under the laws of the State of Iowa.

Signature Date

Printed or typed name Daniel Jensen

License Number 25063

My License Renewal Date is: December 31, 2023 Pages, Sheets, or Divisions covered by this Seal: All

06/06/2023

NATURAL RESOURCES CONSERVATION SERVICE

CONSTRUCTION SPECIFICATIONS

For

GUT813130A BREAKPOINT WETLAND

Guthrie County, Iowa

List of Specifications

Specification Number Title Pages

IA-1 SITE PREPARATION 2

IA-3 STRUCTURE REMOVAL 2

IA CS-005 POLLUTION CONTROL 3

IA-6 SEEDING AND MULCHING FOR PROTECTIVE COVER 4

CS-08 MOBILIZATION 3

IA-9 SUBSURFACE DRAIN INVESTIGATION, REMOVAL, AND REPAIR 4

IA-11 REMOVAL OF WATER 2

IA-13 SHEET PILING 3

IA-21 EXCAVATION 2

IA-23 EARTHFILL 4

IA-26 TOPSOILING 2

IA-31 CONCRETE 6

IA-46 TILE DRAINS FOR LAND DRAINAGE 5

IA-51 CORRUGATED METAL PIPE CONDUITS 5

IA-61 LOOSE ROCK RIPRAP 2

IA-62 CONCRETE GROUT FOR RIPRAP 3

IA-81 METAL FABRICATION AND INSTALLATION 2

IA-92 FENCES 23

IA-95 GEOTEXTILE 5

These specifications are part of the construction plans. The work shall be performed in accordance with the drawings and specifications unless otherwise approved, in writing, by NRCS. For items of work requiring NRCS inspection, it is the responsibility of the contractor to keep the local NRCS office informed of the progress of work so that timely inspections may be performed. Work installed without NRCS inspection will not be certified as meeting NRCS standards.

Natural Resources Conservation Service

Construction Specification 000 IA CS-00-1 Site Preparation

NRCS, IA SPECIFICATION IA CS-001, Page 1 of 2 July 2013

1. SCOPE

Site preparation work shall consist of clearing, grubbing, stripping, refuse removal, bank sloping and structure removal on the site as necessary to rid the site of all undesirable materials on or near the surface and prepare the site for the structure. All woody growth within the construction area shall be cleared and all stumps and roots one inch in diameter or larger shall be grubbed from the site. In addition, all areas within 25 feet of the footprint of the structure shall be cleared and grubbed except as directed by NRCS. The work shall also consist of the removal and disposal of structures (including fences) that must be removed to perform other items of work.

For wetland restoration, enhancement, or creation projects, the wetland area shall be disturbed as little as possible and existing naturally vegetated spillway areas shall not be disturbed.

2. FOUNDATION PREPARATION

The construction areas shall be stripped a minimum of 6 inches to remove all unsuitable materials such as organic matter, grasses, weeds, sod, debris, and stones larger than 6 inches in diameter.

In an earth embankment foundation area, all channel banks and sharp breaks shall be sloped to no steeper than 1.5 horizontal to 1 vertical.

The foundation area shall be thoroughly scarified before placement of fill material. The surface shall have moisture added or shall be compacted if necessary so that the first layer of fill material can be compacted and bonded to the foundation.

3. STRIPPED MATERIAL DISPOSAL

Suitable soil material shall be stockpiled for use as topsoil. The other stripped materials shall be buried, removed from the site, or disposed of as directed by the owner or NRCS. Whenever possible, material shall not be disposed of in the pool area created by the structure.

Stockpiled materials around a construction site should be placed so as not to hinder subsequent construction operations.

4. DISPOSAL OF REFUSE MATERIALS

Waste materials from clearing and structure removal shall be burned or buried at locations approved by the owner. Buried materials shall be covered with a minimum of 2 feet of earthfill. Whenever possible, material shall not be disposed of in any pool area created by the structure.

All refuse shall be disposed of in a manner which complies with all local and state regulations.

5. SALVAGE

Items to be salvaged shall be as shown on the drawings. Structures and fencing materials that are designated to be salvaged shall be carefully removed and neatly placed in the specified storage areas.

NRCS, IA SPECIFICATION IA CS-001, Page 2 of 2 July 2013

6. SPECIFIC SITE REQUIREMENTS

A. Measurement and Payment

Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and bid items to which they are made subsidiary are identified in Items of Work and Construction Details section of this specification.

For items of work which lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for each item will be made at the contract lump sum price and will constitute full compensation for completion of the work.

For items of work for which specific unit prices are established in the contract, the payment will be made based on the approved quantity measured by the engineer or weight tickets. Payment will constitute full compensation of the work completed as defined by each work item.

B. Items of Work and Construction Details

1. Bid Item No. 1 – Site Clearing, Preparation, and Waste Disposal

This item will consist of work to remove and dispose of existing material to remove vegetation on areas to be excavated or filled. Total depth of vegetative stripping and topsoil stripping shall equal a combined depth of 12", with the estimated cubic yards of top soil removal as shown in the plans. The topsoil replacement quantity shall be paid separately.

This item will also include any tree and brush removal along with any fences. These shall be considered incidental to site stripping.

This item will be paid out as a lump sum.

2. Bid item No. 22 – Crop Damage

This item consists of crop damage that results from construction activities. It is recommended contractor remove corn residue rather than knock it down.

Payment for crop damage will be made to the nearest 0.1 acre as measured by the Engineer or their representative. The unit rate for crop damage will be determined by the Division near the completion of construction and added to the contract with a Change Order. Payment will be made to contractor who will pay landowner.

NRCS, IA SPECIFICATION - Page 1 of 2 February 2011

Construction Specification

000 IA-3 Structure Removal

1. SCOPE

The work shall consist of the removal, salvage and/or disposal of structures (including fences) from the designated areas and as indicated on the drawings.

2. MARKING

Each structure or item to be removed will be marked by means of stakes, flags, painted markers or other suitable methods.

3. REMOVAL

All structures designated for removal shall be removed to the specified extent and depth.

4. SALVAGE

Structures that are designated to be salvaged shall be carefully removed and neatly placed in the specified storage areas. Salvaged structures that are capable of being disassembled shall be dismantled into individual members or sections. Such structures shall be neatly match marked with paint prior to disassembly. All pins, nuts, bolts, washers, plates and other loose parts shall be marked or tagged to indicate their proper location in the structure and shall be fastened to the appropriate structural member or packed in suitable containers. Materials from fences designated to be salvaged shall be placed outside the work area on the property from which they are removed. Wire shall be rolled into uniform rolls of convenient size. Posts and rails shall be neatly piled.

5. DISPOSAL OF REFUSE MATERIALS

Refuse materials resulting from structure removal shall be burned or buried at locations shown on the drawings. Buried materials shall be covered with a minimum of 2 feet of earthfill. Whenever possible, material shall not be disposed of in the pool area created by the structure.

All refuse shall be disposed of in a manner which complies with all local and state regulations.

NRCS, IA SPECIFICATION - Page 2 of 2 February 2011

Specific Site Requirements

A. Items of Work and Construction Details

1. Items of work to be performed in accordance with this specification and the construction details therefore are:

(a) Subsidiary Items, Fence Removal

(1) No separate payment will be made for removal of items as shown on the plans. Compensation for this item will be incidental to other items of work.

(2) This item is subsidiary to Bid Item 5.

NRCS, IA SPECIFICATION - Page 1 of 3 February 2011

Construction Specification

000 000 IA CS-005 Pollution Control 2011

1. SCOPE

The work shall consist of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air during construction operations.

2. MATERIALS

All materials furnished shall meet the requirements shown on the drawings or in the specifications.

3. EROSION AND SEDIMENT CONTROL MEASURES AND WORKS

The measures and works shall include, but are not limited to, the following:

Staging of Earthwork Activities: The excavation and moving of soil materials shall be scheduled so that areas unprotected from erosion will be minimized. These areas will be unprotected for the shortest time feasible.

Seeding: Structures and disturbed areas shall be seeded as soon as possible after construction is completed.

Temporary seedings may be used as an alternative to other stabilization measures as approved by

NRCS.

Mulching: Construction areas that have been disturbed but have no construction activity scheduled for

21 days or more shall have erosion protection measures applied by the 14th day. This erosion protection may be mulching or other approved temporary measures. Construction areas shall not be left open during a winter shutdown period and shall be protected by mulching.

All seeding and mulching shall be completed in accordance with the seeding plan and Iowa Construction

Specification IA-6, Seeding and Mulching for Protective Cover.

The following works may be temporary. If they are installed as a temporary measure, they shall be removed and the area restored to its original state when they are no longer needed or when permanent measures are installed.

Diversions: Diversions may be required to divert clean runoff water away from work areas and to collect runoff from work areas for treatment and safe disposition.

Stream Crossings: Culverts or bridges may be required where construction equipment must cross streams.

Sediment Basins: Sediment basins may be required to settle and filter out sediment from eroding areas to protect properties and streams below the construction site.

Sediment Filters: Straw bale filters, geotextile sediment fences, or other equivalent methods may be used to trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under them.

Waterways: Waterways may be required for the safe removal of runoff from fields, diversions, and other structures or measures.

4. CHEMICAL POLLUTION

The Contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to be used to dispose of chemical pollutants, such as drained lubricating or transmission oils, greases, soaps, concrete mixer wash water, asphalt, etc., produced as a by-product of the construction work.

At the completion of the construction work, sumps shall be removed and the area restored without causing pollution.

NRCS, IA SPECIFICATION - Page 2 of 3 February 2011

Sanitary facilities such as chemical toilets or septic tanks shall not be placed adjacent to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water sources. At the completion of construction work, facilities shall be disposed of without causing pollution.

5. AIR POLLUTION

The burning of brush or trash or disposal of other materials shall adhere to local and state regulations.

Fire prevention measures shall be taken to prevent the start or the spreading of wild fires, which result from project work. Fire breaks or guards shall be constructed at locations shown on the drawings.

All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall insure safe operations at all times. If chemical dust suppressants are used, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer’s requirements and recommendations. A copy of the product data sheet and manufacturer’s recommended application procedures shall be provided to the Engineer five working days before use.

6. MAINTENANCE, REMOVAL, AND RESTORATION

All pollution control measures and works shall be adequately maintained in a functional condition as long as needed during the construction operation. All temporary measures shall be removed and the site restored to as near original conditions as practical.

NRCS, IA SPECIFICATION - Page 3 of 3 February 2011

A. Measurement and Payment

1. Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary.

Such items and bid items to which they are made subsidiary are identified in the Items of Work and Construction Details section of the Special Specification. For any item described in the bid documents, not included in any bid item, or not made subsidiary to any bid item in the Items of Work, shall be made subsidiary to the Mobilization bid item.

2. Quantities used for progress payments shall be considered as only approximate and provisional and shall be subject to recalculation, adjustment, and correction by the engineer in subsequent payment applications. Inclusion of any quantities in a progress payment, or failure to disapprove the work at the time of any progress payment, shall not be construed as acceptance of the corresponding work or materials.

3. For items of work which lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for each item will be made at the contract lump sum prices and will constitute full compensation for completion of the work.

B. Items of Work and Construction Details

1. Items of work to be performed in conformance with the specification and the construction details therefore are:

a. Subsidiary Item, Sediment Filters

(1) This item consists of all work to install, maintain, and remove sediment filters for the project. Sediment filters to be removed once vegetation is established.

(2) No separate payment will be made for sediment filters. Compensation for this item will be incidental to other items of work.

(3) Contractor shall perform all construction activities in a manner that will minimize water pollution, air pollution, and soil erosion. Sediment filters shall be placed as needed where off-site erosion could occur or as directed by the engineer.

(4) Contractor is responsible to limit discharge of sediment off site.

(5) Sediment filters are subsidiary to Bid item 5.

b. Subsidiary Item, Pollution Control

(1) This item will consist of performing all construction activities in a manner that will minimize water pollution, air pollution and soil erosion.

(2) Contractor shall comply with all local and federal laws.

(3) No separate payment will be made for Pollution Control.

Compensation for this item will be incidental to other items of work.

(4) Pollution Control is subsidiary to Bid item 5.

000 IA-6 Seeding and Mulching for Protective Cover

NRCS, IA SPECIFICATION IA CS-006, Page 1 of 5 February 2011

The work shall consist of seeding, mulching, and fertilizing all disturbed areas and other areas as indicated on the drawings or otherwise designated.

2. SEEDBED PREPARATION AND APPLICATION

The entire area to be seeded shall be reasonably smooth and all washes and gullies shall be filled to conform to the desired cross-section before actual seedbed preparation is begun. At this stage of the operation, the required fertilizer and lime shall be applied uniformly and incorporated into the top 3 inches of the soil with suitable tillage equipment. The seedbed preparation operation shall be suspended when the soil is too wet or too dry. The seedbed shall be loosened to a depth of at least three inches.

On side slopes steeper than 2-1/2 horizontal to1 vertical, the 3 inch minimum depth of seedbed preparation is not required, but the soil shall be worked enough to insure sufficient loose soil to provide adequate seed cover.

Unless otherwise specified, the seeding operation shall be performed immediately after preparation of the seedbed. The seed shall be drilled or broadcast by equipment that will insure uniform distribution of the seed.

3. MATERIALS

The seeding, fertilizing, and mulching requirements are as specified on Form IA-CPA-4.

Straw from cereal grains or hay will be used as mulching material. It shall be relatively free of weeds.

4. MULCH APPLICATION

The required mulching shall be performed as soon as possible after seeding unless otherwise specified.

The mulch shall be applied uniformly over the area. The type and rate shall be as specified. When mulching is required, all areas seeded during any one day shall be mulched within 24 hours. The mulch may be spread by any means that results in a uniform cover.

The mulch shall be anchored. Anchoring of the mulch may be performed by a mulch anchoring tool or regular farm disk weighted and set nearly straight, by installation of mulch netting, or by other methods approved by NRCS.

5. SPECIFIC SITE REQUIREMENTS

A. Measurement and Payment

Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and bid items to which they are made subsidiary are identified in Items of Work and

Construction Details section of this specification.

NRCS, IA SPECIFICATION IA CS-006, Page 2 of 5 February 2011

For items of work which lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for each item will be made at the contract lump sum price and will constitute full compensation for completion of the work.

For items of work for which specific unit prices are established in the contract, the payment will be made based on the approved quantity measured by the engineer or weight tickets. Payment will constitute full compensation of the work completed as defined by each work item.

1. Bid Item No. 4 – Structure Seeding

This item will consist of seeding the dike except the upstream side slope below the weir elevation, auxiliary spillway, the tile outlet channel side slopes and any other disturbed areas noted on the plans or as determined by engineer.

All seed must be clean and weed free. Seeding rates are expressed in bulk pounds per acre.

Seed quality shall not drop below 70% Pure Live Seed (PLS) where PLS = (percent germination plus percent dormant seed) times percent purity.

Seeding rates are as follows:

Smooth Brome grass 25 pounds/acre

Seed shall be applied with a drill and placed at ¼ to ½ inch deep.

Fertilizer shall be applied on the entire seeding area at the following rate:

Nitrogen (N) 30 pound/acre

Phosphorus (P2O5) 30 pounds/acre

Potassium (K2O) 40 pounds/acre

Straw mulch shall be applied at a rate of 2 tons per acre on all areas receiving structure and channel seeding.

Seeding shall be completed during the following seeding periods:

Spring March 1 to May 15

Summer August 1 to September 15

Fall November 15 to Freeze-up

If construction is completed during any other time of the year, the seeding shall be performed at the next seeding period.

If seeding is completed during the spring seeding period, a companion crop of oats shall be seeded at a rate of 1-1/2 bushels per acre.

Measurement will be based on the areas successfully seeded to the nearest 0.1 acre.

NRCS, IA SPECIFICATION IA CS-006, Page 3 of 5 February 2011

2. Bid Item No. 2 – Buffer Seeding

This item will consist of seeding the areas designated on the plans as buffer seeding and include borrow areas, disturbed areas not seeded as part of structural seeding, and other areas within the easement. Buffer seeding is not required in area below normal pool elevation established by the weir elevation.

Some areas of the site may have existing CRP vegetation or steep slopes with existing vegetation. Local NRCS personnel will determine if these areas will be included as part of the buffer seeding areas for this project or will be left as is. This may affect the bid quantity and Contractor will verify with Engineer the number of acres that will require buffer seeding.

All seed must be clean and weed free. Seeding rates are expressed in pounds of pure live seed per acre. All seed must be yellow-tagged Iowa ecotype unless approved otherwise by

IDALS-DSCWQ.

Seeding mixture shall include a minimum of 5 native grasses and 10 native forbs. The mixture shall provide a minimum of 30 grass seeds per square foot and 10 forbs seeds per square foot. Number of seeds will be based on Iowa Conservation Practice 327 “Native

Species for Wildlife”. Contractor’s proposed seed mix shall be submitted to Engineer and local NRCS office for approval at least 2 weeks before seed is to be applied.

Seeding shall be completed during the following seeding periods:

Spring April 1 to June 30

Fall November 15 to Freeze-up

The seed bed shall be properly prepared prior to seeding:

(a) Any weed control measures shall be completed prior to seeding. If spraying is used, then a span of two weeks shall be allowed between spraying and seeding.

(b) If the land was in soybeans, no additional tillage is required. If the land was in corn or other vegetation, areas to be seeded shall be disked to thoroughly loosen and pulverize the soil to a depth of 3 inches. This may require multiple passes of equipment. If the land was used for pasture and has a smooth surface, the preparation in non-disturbed areas to be seeded shall include mowing any vegetation taller than 12 inches and applying an appropriate herbicide at the labeled rates to emergent growth 2 to 4 weeks after mowing. After the vegetation has died, the area shall be disked thoroughly loosen and pulverize the soil depth of 3 inches. If emergent growth occurs prior to seeding, the areas shall receive a second application of herbicide. Seeding shall not occur until the existing vegetation has died (about 1 week).

(c) If deeper disking is used at the site, a lighter disk or spring harrow shall be used to remove deep furrows.

(d) After disking operations and prior to seed application, the seedbed shall be firmed with a cultipacker or similar piece of equipment.

(e) No lime or fertilizer is to be applied.

Sow seed with contour using a grassland or rangeland drill set for the specified seeding rates. The drill shall be equipped with double coulter furrow openers. The drill shall be

NRCS, IA SPECIFICATION IA CS-006, Page 4 of 5 February 2011 subject to acceptance by Engineer. Overlap each successive seeding pass to ensure complete coverage.

Plant seed not more than 1/4 inch deep; some seed may be seen on the surface after seeding.

Broadcasting by centrifugal-type or hydroseeder broadcasters, or by hand shall be allowed in areas not accessible to drills or other equipment. Once broadcast, the seed must be covered with soil to a depth no greater than 1/4 inch by means of hand rakes or other approved methods.

Upon completion of the seeding operation, cultipack the seedbed to provide a positive seed-soil contact. If the drill seeder is equipped with an approved cultipacker or press wheels, separate operations shall not be necessary. The type of cultipacker/seeder to be used shall be subject to acceptance by Engineer.

No mulch shall be required.

Measurement will be based on the area successfully seeded and measured to the nearest

0.1 acre.

3. Bid Item No. 3 – Switch Grass Seeding

This item will consist of seeding the areas designated on the plans as switch grass seeding within the easement.

All seed must be cleaned and weed free. Seeding rates are expressed in bulk pounds per acre. Seed quality shall not drop below 70% Pure Life Seed (PLS) where PLS = (% germination + % dormant seed) times % purity.

Seeding rates are as follows:

Winter Cover- Switch Grass 10 lbs. / acre

Seed shall be applied with a drill and placed at ¼ inch deep.

Fertilizer shall be applied on the entire seeding area at the following rate.

Nitrogen 30 lbs. / acre

Phosphorus (P2O5) 30 lbs. / acre

Potassium (K2O) 40 lbs. / acre

Straw mulch shall be applied at the rate of 2 tons per acre on all seeded areas.

Seeding will be completed during the following seeding periods:

Spring March 1 to May 15

Summer August 1 to September 15

Fall November 15 to freeze-up

If construction is completed during any other time of the year, the seeding shall be performed at the next seeding period.

NRCS, IA SPECIFICATION IA CS-006, Page 5 of 5 February 2011

If seeding is completed during the spring or summer seeding period, a companion crop of oats shall be seeded at a rate of one and one-half bushels per acre. If seeding is completed during the fall seeding period a companion crop of winter wheat shall be seeded at 30lbs/ac.

Measurement and payment will be based on the area successfully seeded calculated to the nearest one-tenth acre

4. Weed Control (Not a Bid item)

Weed control may be needed in portions of this site depending upon the start date of the contract, the initiation of grading, and the seeding dates.

Weed control will be added to the contract with a change order to be negotiated between

Contractor and Division based on conditions observed and the type of weed control used and will be paid only once. If delays require additional weed control, this will be paid for at

Contractor’s own expense.

Weed control may include placement of a cover crop such as oats or rye, spraying with appropriate chemicals, or disking. If thistles are present, only spraying is allowed for weed control and shall include appropriate chemicals designed to control thistles.

CS-8-1 3/22

CONSTRUCTION SPECIFICATION

Construction Specification 8—Mobilization and Demobilization

1. SCOPE

The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

2. EQUIPMENT AND MATERIAL

Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.

Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.

This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.

3. PAYMENT

Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.

Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.

CS-8-2 3/22

4. ITEMS OF WORK AND CONSTRUCTION DETAILS

A. Measurement and Payment

Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and bid items to which they are made subsidiary are identified in Items of Work and Construction Details section of this specification.

For items of work which lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for each item will be made at the contract lump sum price and will constitute full compensation for completion of the work.

For items of work for which specific unit prices are established in the contract, the payment will be made based on the approved quantity measured by the engineer or weight tickets. Payment will constitute full compensation of the work completed as defined by each work item.

B. Items of Work and Construction Details

1. Bid Item No. 5 - Mobilization/Demobilzation

This item shall consist of mobilizing and demobilizing personnel and equipment in preparation to perform the work within the scope of this contract.

Any work that is necessary to provide access to the site including, but not limited to, grading, temporary culverts, and clearing will be included in this item. When construction is completed access areas will be restored, as close as practical, to its original condition.

Any fence removed for access and /or to provide work area shall be replaced with same or like materials as approved by the engineer.

The Contractor shall exercise caution to minimize the amount of damage caused by the grading and clearing operations.

Portable toilets shall be provided at the construction site and used for the sanitary facilities.

This item shall not include transportation of personnel, equipment and operating supplies within the work limits areas of this contract.

Payment will constitute full compensation for related subsidiary item, Pollution Control.

Payment will be made as the work proceeds and will paid out on the percent of the project complete as the work progresses. Payment of the

CS-8-3 3/22

lump sum contract price for mobilization and demobilization will constitute full compensation for the completion of the work.

Payment will not be made under this item for the purchase costs of materials having a residual value, the cost of materials to be incorporated in the project, or the purchase costs of operating supplies.

Contractor is to contact “Iowa One Call” for utility locations a minimum of two (2) days prior to any excavation/construction. The ticket number must be provided to Engineer.

2. Subsidiary Item – Sign Installation

This item shall include all labor, materials, equipment and Iowa One Call notifications to install sign provided by Iowa Department of Agriculture and Land Stewardship, as shown on the plans or on next page.

This item is subsidiary to bid item 5.

NRCS, IA SPECIFICATION IA CS-009, Page 1 of 4 December 2014

CONSTRUCTION SPECIFICATION

IA-9 SUBSURFACE DRAIN INVESTIGATION,

REMOVAL, AND REPAIR

1. SCOPE

The work shall consist of investigation, location, repair, and/or removal of subsurface drains (tile) near new or existing animal waste storage facilities or in wetland restoration, enhancement, or creation project areas, or other situations where subsurface drains may be present.

2. INVESTIGATION AND LOCATION

An inspection trench at least 10 inches wide shall be dug at the location shown on the drawings or as directed by the engineer or his representative. The trench shall be at least 6 feet deep measured from the original ground line, unless otherwise shown on the plans. The Engineer or his representative shall examine the trench and excavated material to identify tile lines.

Size, material, operating condition and direction of flow of each conduit shall be documented. Location and flow line elevation of each conduit shall be surveyed with horizontal and vertical control based on benchmarks shown on the plans.

The inspection trench shall be documented by surveying the natural ground and trench bottom location and elevations at the beginning, end, and every 50 feet for trenches longer than 50 feet.

Backfilling shall not be started without approval of the Engineer. See Section 5 for backfill specifications.

Trench shields, shoring and bracing, or other methods necessary to safeguard the workers and work, and to prevent damage to the existing improvements shall be furnished, placed, and subsequently removed by the contractor.

3. TILE REPAIR

Unless designated for removal, replace damaged conduit with new conduit having equal or greater capacity using material specified in Section 6 or 7. When replacing short sections of clay or concrete tile with single-wall corrugated polyethylene pipe, use the next larger nominal size.

Make connections with manufactured fittings and tight joints. Where joints have gaps that would allow soil to enter, cover the joint with a permanent type material such as coal tar pitch treated roofing paper, fiber glass sheet or mat, or plastic sheet.

If the investigation trench has been excavated below the existing drain grade, backfill the trench with gravel or well-pulverized soil in layers not over four (4) inches thick and tamp by hand or manually directed power tamper to provide a firm foundation for the conduit at the existing grade. Do not backfill with any soil containing broken tile fragments.

Using selected soil free of hard clods, rocks, or frozen soil, hand tamp the backfill material around the haunch of the pipe in layers not over four (4) inches thick to provide support. Hold the conduit in place

NRCS, IA SPECIFICATION IA CS-009, Page 2 of 4 December 2014 mechanically while placing excavated material around and over the conduit to ensure proper alignment and grade is maintained. Complete the backfill operation according to Section 5.

4. TILE REMOVAL

Remove conduits as shown on the plans or directed by the Engineer or his representative, including envelope filter material or other flow enhancing material when present.

Cap or plug the open ends of the disconnected conduit to prevent soil entry when the conduit will continue to function downstream, or otherwise shown on the plans. For a minimum distance of two feet around each sealed conduit end, backfill in layers not over four (4) inches thick and tamp by hand or manually directed power tamper to a density equal to or greater than the surrounding undisturbed soil. Do not backfill with any soil containing broken tile fragments, large stones, frozen material, or large dry clods.

Where tile are located beneath an existing animal waste facility, remove the tile or fill the entire length of tile with concrete or Portland cement grout as shown on the plans. When tile removal is specified, the owner shall contact the Iowa Department of Natural Resources (IDNR) for permission to remove the drainage tile under the structure. The structure shall be emptied of waste or lowered to a point below the tile prior to its removal. The structure must be retested for percolation and the results submitted to IDNR and approval received prior to reusing the structure.

If shown on the plans or directed by the engineer, reroute upstream drain lines so the capacity of the upstream drainage system is maintained. Install conduit in accordance with Iowa Construction Specification IA-46, Tile Drains for Land Drainage.

5. BACKFILL

Compact soil around disturbed tile as specified in Section 3 (Tile Repair) and Section 4 (Tile Removal).

Keep the backfill within 5 feet of the conduit free from large stones, frozen material, and large dry clods.

Unless otherwise shown on the plans, backfill the remainder of the trench as follows:

For trenches located under or near structures, backfill in 12-inch layers and compact each layer to a density equal to or greater than the surrounding undisturbed soil.

For other locations, backfill the remainder of each trench with the excavated soil material which shall extend above the ground surface and be well rounded over the trench.

6. MATERIALS

Unless otherwise shown on the plans, conduit and fittings used for repair shall conform to the specifications listed in Table 1. Perforated pipe shall have a water inlet area of at least 1 square inch per foot, provided by perforations spaced uniformly along the long axis of the pipe. The perforations shall be circular or slots. Circular perforations shall not exceed 3/16 inch in diameter. Slots shall not be more than 1/8 inch wide.

NRCS, IA SPECIFICATION IA CS-009, Page 3 of 4 December 2014

Table 1. Acceptable pipe for subsurface drain repair

Kind of Pipe# Specification

Corrugated Polyethylene (PE) Pipe and Fittings, 3 to 6 inch ASTM F 405

Corrugated Polyethylene (PE) Pipe and Fittings, 3 to 24 inch ASTM F 667

Corrugated Profile Wall (Dual Wall) Polyethylene (PE) pipe, 2 to 60 inch ASTM F 2648$

Corrugated Profile Wall (Dual Wall) Polyethylene (PE) pipe, 12 to 60 inch ASTM F 2306$

Polyvinyl Chloride (PVC) Plastic Pipe, Schedules 40, 80 and 120 ASTM D 1785

PVC Pressure-Rated Pipe (SDR Series) ASTM D 2241

Clay drain tile ASTM C 4

Concrete drain tile ASTM C 412

#Pipe sizes are nominal and the ranges are inclusive $Pipe conforming to AASHTO M 252 (3 to 10 inch), or AASHTO M 294 (12 to 60 inch) is acceptable.

7. SPECIFIC SITE REQUIREMENTS

A. Measurement and Payment

Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and bid items to which they are made subsidiary are identified in Items of Work and Construction Details section of this specification.

For items of work which lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for each item will be made at the contract lump sum price and will constitute full compensation for completion of the work.

For items of work for which specific unit prices are established in the contract, the payment will be made based on the approved quantity measured by the engineer or weight tickets. Payment will constitute full compensation of the work completed as defined by each work item.

B. Items of Work and Construction Details

1. Bid Item No. 6 - DRAIN TILE INVESTIGATION & REMOVAL

This item will consist of the excavation necessary to locate and remove all tile under the embankment and to locate and determine the tie-in locations for the tile locations shown on the plans. This item shall also include backfilling of the trenches.

This item does not include the additional excavation required to excavate the embankment core trench, if included in the project. Excavation of the core trench is covered under Specification IA-21, Excavation.

NRCS, IA SPECIFICATION IA CS-009, Page 4 of 4 December 2014

The extent of the tile investigation shall be as shown on the drawings. If extra work is required to locate additional tile not shown on the drawings, the Contractor can request additional compensation, but it must be first approved by the Division.

The investigation should reveal where the tile crosses the embankment footprint or where it is located if it does not cross the embankment footprint

Payment for Drainage Tile Investigation and removal shall be made as noted in the plans.

Construction Specification

000 IA-11 Removal of Water

1. SCOPE

The work shall consist of the removal of surface water and ground water as needed to perform the required construction in accordance with the plans and specifications.

2. DIVERTING SURFACE WATER

The Contractor shall build, maintain and operate all cofferdams, channels, diversions, flumes, sumps, and other temporary protective works needed to divert surface water away from the construction site while construction is in progress.

3. DEWATERING THE CONSTRUCTION SITE

Foundations, cutoff trenches, borrow areas and other parts of the construction site shall be dewatered as needed for proper execution of the construction work. The Contractor shall furnish, install, operate and maintain all works and equipment needed to perform the dewatering.

4. EROSION AND POLLUTION CONTROL

Removal of water from the construction site, including the borrow areas shall be accomplished in such a manner that erosion and the transmission of sediment and other pollutants are minimized.

5. REMOVAL OF TEMPORARY WORKS

After temporary works have served their purposes and before the Contractor leaves the site, they shall be removed.

A. Measurement and Payment

1. Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary.

Such items and bid items to which they are made subsidiary are identified in the Items of Work and Construction Details section of the Special Specification. For any item described in the bid documents, not included in any bid item, or not made subsidiary to any bid item in the Items of Work, shall be made subsidiary to the Mobilization bid item.

2. Quantities used for progress payments shall be considered as only approximate and provisional and shall be subject to recalculation, adjustment, and correction by the engineer in subsequent payment applications. Inclusion of any quantities in a progress payment, or failure to disapprove the work at the time of any progress payment, shall not be construed as acceptance of the corresponding work or materials.

B. Items of Work and Construction Details

1. Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Subsidiary Item, Dewatering

(1) This item shall include all costs to divert, pump, dam or other means to dewater the site as needed to complete construction activities.

(2) No separate payment will be made for removal of water. Compensation for this item shall be made subsidiary to Bid Item 5.

NRCS, IA SPECIFICATION - Page 1 of 3 February 2011

Construction Specification

000 IA-13 Sheet Piling

1. SCOPE

The work shall consist of furnishing and driving the specified sheet piling at the location shown on the drawings.

2. MATERIALS

Sheet piling shall conform to the requirements of ASTM A328 (Steel Sheet Piling), A572 (High- Strength

Low-Alloy Columbium-Vanadium Structural Steel), or A690 (High-Strength Low-Alloy steel H-Piles and

Sheet Piling for Use in Marine Environments). The sheet piling provided shall meet the required cross-section, section modulus, thickness, and steel grade shown on the drawings. Fabrication of sheet piles from shorter lengths of pile stock is not permitted.

3. DRIVING SHEET PILE

The piling shall be driven in a manner so as to insure perfect interlocking throughout the entire length of each pile. The piles shall be held in proper alignment during driving by means of suitable temporary guide structures which shall be removed when they have served their purpose.

Piling shall be driven to the full depth shown on the drawings unless otherwise approved by the engineer.

4. CUTTING OFF PILES

The contractor shall cut the piling off at the specified elevations. Piling length shall be sufficient to permit removal of all materials damaged by driving.

5. DEFECTIVE PILING

Any piling damaged in driving, driven out of its proper location, driven below the specified cut off elevation, or inaccurately cut off shall be pulled and replaced or re-driven. Any piling ruptured in the interlock or otherwise damaged during driving shall be pulled and replaced.

NRCS, IA SPECIFICATION - Page 2 of 3 February 2011

A. Measurement and Payment

1. Compensation for any work item described in the contract documents but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary.

Such items and bid items to which they are made subsidiary are identified in the Items of Work and Construction Details section of the Special Specification. For any item described in the bid documents, not included in any bid item, or not made subsidiary to any bid item in the Items of Work, shall be made subsidiary to the Mobilization bid item.

2. Quantities used for progress payments shall be considered as only approximate and provisional and shall be subject to recalculation, adjustment, and correction by the engineer in subsequent payment applications. Inclusion of any quantities in a progress payment, or failure to disapprove the work at the time of any progress payment, shall not be construed as acceptance of the corresponding work or materials.

3. For items of work which Unit Prices are established in the contract, the quantity of work will be measured, estimated, or based on plan quantity. The determination of quantities of work performed under the contract will be made by the Engineer with the assistance of the contractor and will be based on lines and grades shown on the plans and as given during the progress of work or as evidenced by approved tickets for weight or liquid measure or by measurements made or approved by the engineer. The contractor will be paid based on the actual quantity of work completed and accepted.

B. Items of Work and Construction Details

1. Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 10, SHEET PILE WEIR

(1) This item shall consist of furnishing and installing the steel sheet piling shown on the drawings. This item shall include steel channel, bolts, and field cutting the side slopes of the sheet piling to the specified slope shown on the drawings.

(2) The sheet piling will be installed starting from the center of the weir section and progressing away from centerline.

Bends and deflections shall be made with prefabricated pieces specifically made for a location.

(3) Sheet piling shall have the minimum following requirements

a. Minimum section modulus of 14.36 cubic inch per foot of wall.

b. Minimum grade of steel shall be 50 ksi.

c. Minimum moment of inertia of 71.82 in4 per foot of wall.

d. Minimum thickness of 0.250’’.

e. Meet ASTM A-572 GR50.

(4) All holes shall be field drilled. Torch, plasma cutting, or other methods resulting in imperfect holes will not be permitted.

(5) Payment will be based on actual square feet of sheet pile installed after trimming and will constitute full compensation for related subsidiary items such as tie-back anchors, structure excavation, backfill, and removal of water.

(6) Refer to IA-81 for fabrication and installation specifications.

NRCS, IA SPECIFICATION - Page 3 of 3 February 2011

b. Subsidiary Item, Steel Channel, plate and Angle

(1) This item will consist of furnishing and installing the steel channel, a n g l e , a n d p l a t e pieces used to form the crest of the sheet pile weir (waler). Steel channel shall be A36 structural steel.

(2) Refer to IA-81 for fabrication and installation specifications

(3) No separate payment will be made for Steel Channel.

Payment for this item will be considered subsidiary to Bid Item 10.

c. Subsidiary Item, Bolts, Nuts, and Washers

(1) This item will consist of furnishing and installing the bolts, nuts and washers used to construct the sheet pile as shown on the plans.

(2) Bolts shall meet ASTM A307 Grade A.

(3) Washers shall meet ASTM F436.

(4) Nuts shall meet ASTM A563.

(5) Refer to IA-81 for fabrication and installation specifications

(6) No separate payment will be made for bolts, nuts, or washers. Payment for this item will be considered subsidiary to Bid Item 10.

NRCS, IA SPECIFICATION - Page 1 of 2 July 2013

000 IA-21 Excavation

The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials. The cutoff trench and any other required excavations shall be dug to the lines and grades shown on the drawings or as staked in the field. Structure or trench excavations will conform to all safety requirements of OSHA.

2. USE OF EXCAVATED MATERIALS

Suitable materials from the specified excavations shall be used in the construction of required permanent earth fill. The suitability of materials for specific purposes shall be determined by the NRCS Inspector.

3. DISPOSAL OF WASTE MATERIAL

All surplus or waste material shall be disposed of in areas shown on the drawings or as approved by the

NRCS Inspector. The waste material shall be smoothed and sloped to provide drainage.

4. STRUCTURE AND TRENCH EXCAVATION

Structure or trench excavations will conform to all safety requirements of OSHA.

5. BORROW EXCAVATION

When the quantities of suitable materials obtained from specified excavations are insufficient to construct the specified fills, additional materials shall be obtained from the designated borrow areas as shown on the drawings or as approved by NRCS and the landowner. On wetland projects, borrow shall not be taken from the wetland area within 10 feet of the embankment or as shown on the drawings.

Borrow areas shall be excavated and grading completed in a manner to eliminate steep or unstable side slopes or hazardous or unsightly conditions.

6. OVER-EXCAVATION

Excavation beyond the specified lines and grades shall be corrected by filling the resulting voids with compacted earthfill, except that if the earth is to become…