03_P2699011_Sample_Contract_Exhibits.pdf

PDF 1 MB Posted

Attached to
P2699011 - WINDOW REPLACEMENT
Solicitation number
0000040984
Issued by
Fresno County, Fort Washington CDP, California

About this file

Summary of Contract Exhibits for Window Replacement Project P2699011

This file comprises sample contract exhibits for a construction project administered by the California Department of Fish and Wildlife (CDFW) under Agreement Number P2699011. The project involves retrofitting six state-owned residences at San Joaquin Hatchery in Fresno County with replacement windows, an ADA-compliant ramp, and associated work. The scope includes removal and installation of seventy vinyl sliding windows across residences R4-48, R4-49, R4-52, R4-53, and R4-55; installation of an ADA-compliant modular aluminum ramp with detectable warning surfacing at residence R4-49; and contingency work for unforeseen items. The contract requires a General Engineering Contractor or General Building Contractor license. Construction shall be completed within sixty working days following the official notice to commence work, with the contract term extending from approval through December 30, 2027. The project is located at 12373 Brooktrout Drive, Friant, California 93626. The contractor must submit a detailed work schedule three days prior to beginning work and obtain approval of all shop drawings and material submittals before proceeding.

The contract specifies lump-sum pricing for the three primary line items: window replacement, ADA ramp installation, and contingencies, with a maximum agreement amount not yet specified in this sample document. Payment will be made by warrant from the California State Controller's Office following invoice submission and approval by the CDFW Contract Manager. Five percent retention is held from each progress payment for thirty days after project completion before release. The contractor must maintain comprehensive insurance including Commercial General Liability ($1,000,000 per occurrence), Automobile Liability ($1,000,000 combined single limit), and Workers' Compensation with Employer's Liability ($1,000,000), all naming the State as additional insured. Performance and Payment Bonds are required if the contract cost exceeds $10,000 and $25,000 respectively. The work must comply with 2022 California Building Code, California Residential Code, and ADA accessibility standards. A Disabled Veteran Business Enterprise (DVBE) subcontracting provision requires completion of Form STD 817 before final payment is released, with the state withholding up to $10,000 until compliance is certified.

View the file

Other files

File Type Posted
02_P2699011_Section-F_Bidding_Documents.pdf PDF
01_P2699011_Bid_Specs.pdf PDF
04_P2699011_Drawing_.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF CALIFORNIA - DEPARTMENT OF GENERAL SERVICES

STANDARD AGREEMENT

STD 213 (Rev. 04/2020)

AGREEMENT NUMBER

P2699011 PURCHASING AUTHORITY NUMBER (If Applicable)

SCO ID: 3600-P2699011

1. This Agreement is entered into between the Contracting Agency and the Contractor named below:

CONTRACTING AGENCY NAME

California Department of Fish and Wildlife

CONTRACTOR NAME

TBD

2. The term of this Agreement is:

START DATE

Upon DGS Approval

THROUGH END DATE

December 30, 2027

3. The maximum amount of this Agreement is:

Written Dollars and Cents ($XX,XXX.XX)

4. The parties agree to comply with the terms and conditions of the following exhibits, which are by this reference made a part of the Agreement.

Exhibits Title Pages

Exhibit A Scope of Work 6

Exhibit A1 Scope of Work Continued 22

Exhibit B Budget Detail and Payment Provisions 4

Exhibit C * General Terms and Conditions *

Exhibit G Additional Provisions (Public Works) 20

STD 18 Standard California Nondiscrimination Construction Contract Specifications 2

Drawing Dated: 05/01/2025Drawing: H08-2024-003 2 Sheet(s) Items shownwith anasterisk (*), are hereby incorporated by reference andmadepart of this agreement as if attachedhereto.

These documents can be viewed at https://www.dgs.ca.gov/OLS/Resources

INWITNESSWHEREOF, THIS AGREEMENTHAS BEENEXECUTEDBY THE PARTIES HERETO.

CONTRACTOR

CONTRACTOR NAME (if other than an individual, state whether a corporation, partnership, etc.)

TBD

CONTRACTOR BUSINESS ADDRESS CITY STATE ZIP

PRINTED NAME OF PERSON SIGNING TITLE

CONTRACTOR AUTHORIZED SIGNATURE DATE SIGNEDSAM

PLE

STATE OF CALIFORNIA - DEPARTMENT OF GENERAL SERVICES

STANDARD AGREEMENT

STD 213 (Rev. 04/2020)

AGREEMENT NUMBER

P2699011 PURCHASING AUTHORITY NUMBER (If Applicable)

SCO ID: 3600-P2699011

STATE OF CALIFORNIA

CONTRACTING AGENCY NAME

California Department of Fish and Wildlife

CONTRACTING AGENCY ADDRESS

1010 Riverside Parkway

CITY

West Sacramento

STATE

CA

ZIP

95605

PRINTED NAME OF PERSON SIGNING

Yujie Jin

TITLE

Branch Chief, Land and Facilities Engineering Branch

CONTRACTING AGENCY AUTHORIZED SIGNATURE DATE SIGNED

CALIFORNIA DEPARTMENT OF GENERAL SERVICES APPROVAL EXEMPTION (If Applicable)

SAM

WINDOW REPLACEMENT P2699011

CONTRACTOR

EXHIBIT A – SCOPE OF WORK

08/05/2026 A1 of A6 LFEB-Engineering-PW

1. Description:

The Contractor shall furnish all labor, tools, equipment, materials, incidentals, permits, taxes and incidentals necessary to replace seventy (70) retrofit windows, install one Americans with Disabilities Act (ADA) compliant ramp, and other miscellaneous work on six state-owned-residences located at San Joaquin Hatchery.

2. Location of Services:

San Joaquin Hatchery, 12373 Brooktrout Drive, Friant, CA 93626, Fresno County

3. Contract Term Date:

Upon DGS approval through December 30, 2027

4. Time of Completion:

Construction shall be completed within SIXTY (60) WORKING DAYS following the official “Notice of Start Date” from CDFW to the Contractor to commence construction. CDFW may approve additional working days for delays caused by unexpected events or circumstances including but not limited to supply chain disruption and inclement weather. Contractor must advise Contract Manager IN WRITING of any unexpected events or circumstances and obtain CDFW approval for any time extension.

5. License Required:

A – General Engineering Contractor, OR B – General Building Contractor

6. Items of Work:

All items of work on the contract form are to be complete in place. In addition, the specified items shall be in accordance with the following and shall include as well as furnish all labor, tools, equipment, materials, permits and taxes necessary to:

Item 1 - Replace Seventy (70) Retrofit Windows

Item 2 - Install ADA Ramp at Residence R4-48

Item 3 - Contingencies are for changes due to unforeseen items of work, and/or adjustments in the quantities of items bid on a unit price basis, as may be determined, and allowed by the Contract Manager. The total amount to be paid under this item may be from zero (if no changes are allowed) to the full amount, as determined by the Contract Manager.

08/05/2026 A2 of A6 LFEB-Engineering-PW

7. The Project Officials during the term of this agreement will be:

CDFW Project Officials Contractor Project Official(s) Contract Manager Project Director Name: Brytanni Parrett Name: XXX Contractor Phone: (916) 838-4880 Phone: (XXX) XXX-XXXX Email: Brytanni.Parrett@wildlife.ca.gov Email: XXXXXXXXXX

Address: 1010 Riverside Parkway West Sacramento, CA 95605 Address: XXXXX

XXXXX

Either party may make changes to the Project Officials by giving written notice to the other party.

Said changes will not require an amendment to this Agreement

8. General:

The Contractor shall visit and determine the actual condition of the site prior to submitting the quote and shall familiarize themselves of the work in place. The Contractor shall investigate conditions character, quality and quantity of surface, and sub-surface materials of obstacles to be encountered. Failure by the Contractor to acquaint himself/herself with site conditions and available information will not relieve him/her from the responsibility for assessing properly the difficulty or cost of successfully performing the work. The submission of a quote will be considered as conclusive evidence that the Contractor has made such examination. No claim of the Contractor shall be made as a result of different physical conditions of any item or exposed work if such condition is exposed and present at the time of inspection. If any unknown physical condition exists or is not exposed at the time of site inspection, unless noted in these specifications, an equitable adjustment will be made.

All work is to be performed in accordance with the Standard Specifications as stated below, except as provided in the General Conditions, Technical Specifications, and any applicable drawings.

State and Federal Codes:

A. 2022 California Code of Regulations (CCR) B. 2022 California Administrative Code (CAR), [California Code of Regulations (CCR), Title 24, Part 1] C. 2022 California Building Code (CBC), Volumes 1, and 2, (CCR, Title 24, Part 2)

(Based on 2021 International Building Code with 2022 California Amendments) D. 2022 California Residential Code (CRC), (CCR, Title 24, Part 2.5), (Based on 2021

International Residential Code)

08/05/2026 A3 of A6 LFEB-Engineering-PW

E. 2022 California Electrical Code (CEC), (CCR, Title 24, Part 3) (2020 National Electric Code (NEC))

F. 2022 California Mechanical Code (CMC), (CCR, Title 24, Part 4) (Based on 2021 Uniform Mechanical Code with 2022 California Amendments)

G. 2022 California Plumbing Code (CPC), (CCR, Title 24, Part 5) (Based on 2021 Uniform Plumbing Code)

H. 2022 California Energy Code, (CCR, Title 24, Part 6) I. 2022 California Wildland – Urban Interface (WUI) Code (CCR, Title 24, Part 7) J. 2022 California Historical Building Code, (CCR, Title 24, Part 8) K. 2022 California Fire Code (CFC), (CCR, Title 24, Part 9) (Based on 2021 International

Fire Code) L. 2022 California Existing Building Code, (CCR, Title 24, Part 10), (Based on the 2021

International Existing Building Code) M. 2022 California Green Building Standards Code, (CCR, Title 24, Part 11) N. 2022 California Referenced Standards Code, (CCR, Title 24, Part 12);

NFPA 13 - Automatic Sprinkler Systems w/ CA Amendments 2022 Edition NFPA 14 - Standpipe Systems w/ CA Amendments 2019 Edition NFPA17a - Wet Chemical Systems 2021 Edition NFPA 20 - Stationary Pumps 2022 Edition NFPA 24 - Private Fire Mains w/ CA Amendments 2022 Edition NFPA 72 - National Fire Alarm Code w/ CA Amendments 2022 Edition NFPA 2001 - Clean Agent Fire Extinguishing Systems 2022 Edition w/ CA Amendments Reference code section for NFPA standards is in 2022 CBC Chapter 35 or 2022 CFC Chapter 80. See Chapter 35 for State California amendments to NFPA standards

O. Reference Code Sections for Applicable Standards:

2022 CBC, Chapter 35 2022 CFC, Chapter 80

P. Title 8 California Code of Regulations (CCR), CAL/OSHA Regulations-Safety Orders issued by Division of Industrial Safety of the State of California

Q. Title 19 CCR., Public Safety, State Fire Marshall (SFM) Regulations, List of Federal Codes & Standards (if applicable)

R. American with Disabilities Act (ADA), Title II or Title III S. 2022 California Access Compliance Advisory Reference Manual (As prepared by the

Division of the State Architect Office, published on January 1, 2021, effective July 1, 2021)

T. Department of Transportation (DOT) Standard Specifications and/or Plans; State of California, DOT, 2022

U. Underwriters Laboratories, Inc. (UL Standards)

Additional Codes:

A. American Concrete Institute (ACI), Latest Edition B. American Society for Testing and Materials (ASTM), Latest Edition

08/05/2026 A4 of A6 LFEB-Engineering-PW

C. Steel Construction Manual, American Institute of Steel Construction, (AISC), 15th Edition D. American Welding Society, AWS E. Sheet Metal and Air Conditioning Contractors National Association (SMACNA)

Additional Documents which are attached hereto and made a part of this agreement;

A. Drawing: H08-2024-003 Dated: 5/01/2025 Sheet(s): Two (2)

9. Insurance Requirements:

The Contractor will be required to supply proof of and maintain liability coverage as outlined in Exhibit G, Insurance, Item 12B – Insurance Requirements of this agreement. These policy types include:

Commercial General Liability Automobile Liability Worker’s Compensation and Employer’s Liability

The above policies must each be endorsed to include “The State of California, its officers, agents and employees as additional insured but only with respect to work performed under the Contract”.

10. Bond Requirements:

Contractor will be required to supply bonds as outlined in Exhibit G, Item 13 – Contract Bonds which is attached hereto and will be part of the resulting agreement. The bond(s) required for this Agreement include:

Payment Bond required if contract cost is $25,000 or more Performance Bond required if contract cost is $10,000 or more AND progress payments are made

11. Quality Control:

The Contractor will be responsible for the completeness of the contract work. The Contractor will be responsible for the progress of the contract work until final completion and acceptance of same by the State and will make such checks on the work as may be necessary to assure conformance with these specifications.

12. Work Schedule:

The Contractor shall furnish the Contract Manager a proposed work schedule THREE (3) DAYS PRIOR TO BEGINNING WORK and The Contractor shall submit at such times as may be requested by the Contract Manager, schedules which shall show the order in which the Contractor

08/05/2026 A5 of A6 LFEB-Engineering-PW proposes to carry on the work with dates at which the Contractor will start the several parts of the work and estimated dates of completion of the several parts.

13. Submittal Process:

The Contractor shall submit shop drawing(s), manufacturer’s data for all equipment and materials proposed for use on this job, complete with descriptions, information, and performance data to the Engineer for approval in Portable Document Format (PDF).

The electronic submittal process is not intended for physical material samples.

Submittals must be approved prior to start of the work identified in the respective submittals.

The Engineer will prepare a Letter of Transmittal indicating one of the three (3) actions by item number:

A. If review and comment indicates “APPROVED”, work may begin immediately on incorporating the material and equipment covered by the submittal into the work.

B. If review and comment indicates “APPROVED AS NOTED”, limited corrections are required. Corrections shall be made before work may begin on incorporating the material and equipment covered by the submittal into the work.

C. If review and comment indicates “NOT APPROVED”, the material and equipment is unacceptable. The Contractor is not authorized to begin incorporating the material and equipment covered by this submittal into the work until new submittal is made, resubmitted, and returned marked either “APPROVED” or “APPROVED AS NOTED”.

Designation of submittal documents “For Information Only” does not preclude the Engineer from reviewing or commenting on the submittal contents. Information only submittals returned to the Contractor marked “AMEND AND RESUBMIT” or “REJECTED –SEE REMARKS” shall be revised and resubmitted by the Contractor.

14. Clean Up and Disposal of Refuse:

Upon completion of each maintenance/service activity under this contract, the Contractor must remove all remaining excess materials, waste, rubbish, debris, temporary facilities, and other equipment from the site. Final approval of the work done under these specifications will not be given until the final cleanup meets approval of the CDFW Facility Manager or CDFW designee.

15. Restoration of Improvements:

Any damage to existing facilities, structures or improvements caused by the Contractor, the Contractor’s equipment, or the Contractor’s staff during the term of this contract, will be repaired

08/05/2026 A6 of A6 LFEB-Engineering-PW and restored to as good a condition as existed at the time work commenced at the Contractor’s own expense.

16. Inability to Provide Services:

If the Contractor is temporarily unable to provide services as required, CDFW reserves the right to accomplish the work by other means during the period of the Contractor’s inability to provide services and will be reimbursed by the Contractor for any costs.

17. Accidents/Damages:

Damage caused to the equipment covered herein due to fire, abuse, act of God, accident, unauthorized alterations, disasters, the elements, failure of electrical power, misuse, use of unauthorized agents, vandalism or negligence by the State or its officers, agents, or employees are not covered by this agreement except on a time and material basis. Such repairs will be performed by the Contractor at the Contractor’s current, published rates at the time service is required, but only after the Contractor has made an estimate of all costs involved and written documentation has been provided to the Institution Contract Liaison or designee.

18. Exclusions:

Excluded are painting or refinishing of equipment, and the furnishing of supplies, accessories, or devices of any nature, except such items or equipment as may be necessary for the maintenance of the equipment. This agreement does not include service, repair, or replacement of parts required as a result of accident, neglect, abuse, misuse, alteration of equipment, or other improper operation, including but not limited to operation of equipment outside of its specified environmental conditions.

19. Guarantee:

See Exhibit G, (Additional Provisions, Public Works) Item 54, Guarantee.

EXHIBIT A1 – SCOPE OF WORK CONT.

07/07/2025 A1-1 of A1-22 LFEB - PW

TABLE OF CONTENTS

Section Page Numbers

DIVISION 1 – GENERAL REQUIREMENTS

01 00 00 General Requirements.................................................................................. 2-8

DIVISION 5 – MODULAR ALUMINUM RAMPS

05 51 20 Modular Aluminum Ramps............................................................................. 9-13

DIVISION 8 – OPENINGS

08 51 00 Vinyl Sliding Windows................................................................................... 14-15

DIVISION 9 – FINISHES

09 90 00 Painting......................................................................................................... 16-19

31 00 00 Site Clearing……………...………………………………………………………… 20

DIVISION 33 – DETECTABLE WARNING

32 17 26 Detectable Warning Surfacing...................................................................... 21-23

07/07/2025 A1-2 of A1-22 LFEB - PW

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

The Contractor shall visit and determine the actual condition of the site prior to submitting the bid and shall familiarize themselves of the work in place. Contractor shall investigate conditions character, quality and quantity of surface, and sub-surface materials of obstacles to be encountered. Failure by the Contractor to acquaint himself/herself with site conditions and available information will not relieve him/her from the responsibility for estimating properly the difficulty or cost of successfully performing the work. The submission of a bid will be considered as conclusive evidence that the Contractor has made such examination. No claim of the Contractor shall be made as a result of different physical conditions of any item or exposed work if such condition is exposed and present at the time of inspection. If any unknown physical condition exists or is not exposed at the time of site inspection, unless noted in these specifications, an equitable adjustment will be made.

All work is to be performed in accordance with the Standard Specifications as stated below, except as provided in the General Conditions, Technical Specifications, and any applicable drawings. The provisions of Section 12-1.04, DOT Standard Specifications, regarding flagging costs shall not apply. The contractor shall be solely responsible for all flagging costs.

All materials and workmanship shall comply with the following:

State and Federal Codes:

A. 2022 California Code of Regulations (CCR) B. 2022 California Administrative Code (CAR), [California Code of Regulations (CCR), Title 24, Part 1] C. 2022 California Building Code (CBC), Volumes 1, and 2, (CCR, Title 24, Part 2)

(Based on 2021 International Building Code) D. 2022 California Residential Code (CRC), (CCR, Title 24, Part 2.5), (Based on 2021

International Residential Code) E. 2022 California Electrical Code (CEC), (CCR, Title 24, Part 3) (2020 National Electric

Code (NEC) with 2025 California Amendments) F. 2022 California Mechanical Code (CMC), (CCR, Title 24, Part 4) (Based on 2021

Uniform Mechanical Code with 2025 California Amendments) G. 2022 California Plumbing Code (CPC), (CCR, Title 24, Part 5) (Based on 2021

Uniform Plumbing Code) H. 2022 California Energy Code, (CCR, Title 24, Part 6) I. 2022 California Historical Building Code, (CCR, Title 24, Part 8) J. 2022 California Fire Code (CFC), (CCR, Title 24, Part 9) (Based on 2021

International Fire Code)

07/07/2025 A1-3 of A1-22 LFEB - PW

K. 2022 California Existing Building Code, (CCR, Title 24, Part 10), (Based on the 2021 International Existing Building Code)

L. 2022 California Green Building Standards Code, (CCR, Title 24, Part 11) M. 2022 California Referenced Standards Code, (CCR, Title 24, Part 12);

NFPA 13 - Automatic Sprinkler Systems w/ CA Amendments 2022 Edition NFPA 14 - Standpipe Systems w/ CA Amendments 2019 Edition NFPA17a - Wet Chemical Systems 2021 Edition NFPA 20 - Stationary Pumps 2022 Edition NFPA 24 - Private Fire Mains w/ CA Amendments 2022 Edition NFPA 72 - National Fire Alarm Code w/ CA Amendments 2022 Edition

NFPA 2001 - Clean Agent Fire Extinguishing Systems 2022 Edition w/ CA Amendments Reference code section for NFPA standards is in 2022 CBC Chapter 35 or 2022 CFC Chapter 80. See Chapter 35 for State California amendments to NFPA standards

N. Reference Code Sections for Applicable Standards:

2022 CBC, Chapter 35 2022 CFC, Chapter 80

O. Title 8 California Code of Regulations (CCR), CAL/OSHA Regulations-Safety Orders issued by Division of Industrial Safety of the State of California

P. Title 19 CCR., Public Safety, State Fire Marshall (SFM) Regulations, List of Federal Codes & Standards (if applicable)

Q. American with Disabilities Act (ADA), Title II or Title III R. 2022 California Access Compliance Advisory Reference Manual (As prepared by the

Division of the State Architect Office, published on January 1, 2021, effective July 1, 2021)

S. Department of Transportation (DOT) Standard Specifications and/or Plans; State of California, DOT, 2025

T. Underwriters Laboratories, Inc. (UL Standards)

Additional Codes:

A. American Concrete Institute (ACI), Latest Edition B. American Society for Testing and Materials (ASTM), Latest Edition C. Steel Construction Manual, American Institute of Steel Construction, (AISC), 15th Edition D. American Welding Society, AWS E. Sheet Metal and Air Conditioning Contractors National Association (SMACNA)

Additional Documents which are attached hereto and made a part of this agreement;

A. Drawing: H08-2024-003 Dated: 5/01/2025 Sheet(s): Two (2)

07/07/2025 A1-4 of A1-22 LFEB - PW

INSURANCE REQUIREMENTS

The Contractor will be required to supply proof of, and maintain, liability coverage as outlined in Exhibit G, Insurance, Item 12B – Insurance Requirements which is attached hereto and will be part of the resulting agreement. These policy types include:

Commercial General Liability Automobile Liability Worker’s Compensation and Employer’s Liability

The above policies must each be endorsed to include “The State of California, its officers, agents and employees as additional insured but only with respect to work performed under the Contract”.

QUALITY CONTROL

The Contractor shall be responsible for the completeness of his/her work. He/she shall be responsible for the progress of his/her work until final completion and acceptance of same by the State, and shall make such checks on the work as may be necessary to assure conformance with these specifications.

WORK SCHEDULE

The Contractor shall furnish the Engineer a proposed work schedule THREE (3) DAYS PRIOR TO BEGINNING WORK and The Contractor shall submit at such times as may be requested by the Engineer, schedules which shall show the order in which the Contractor proposes to carry on the work with dates at which the Contractor will start the several parts of the work and estimated dates of completion of the several parts.

SUBMITTAL PROCESS

The Contractor shall submit shop drawing(s), manufacturer’s data for all equipment and materials proposed for use on this job, complete with descriptions, information, and performance data to the Engineer for approval in Portable Document Format (PDF).

The electronic submittal process is not intended for physical material samples.

Submittals must be approved prior to start of the work identified in the respective submittals.

The Engineer will prepare a Letter of Transmittal indicating one of the three (3) actions by item number:

A. If review and comment indicates “APPROVED”, work may begin immediately on incorporating the material and equipment covered by the submittal into the work.

07/07/2025 A1-5 of A1-22 LFEB - PW

B. If review and comment indicates “APPROVED AS NOTED”, limited corrections are required.

Corrections shall be made before work may begin on incorporating the material and equipment covered by the submittal into the work.

C. If review and comment indicates “NOT APPROVED”, the material and equipment is unacceptable. The Contractor is not authorized to begin incorporating the material and equipment covered by this submittal into the work until new submittal is made, resubmitted, and returned marked either “APPROVED” or “APPROVED AS NOTED”.

Designation of submittal documents “For Information Only” does not preclude the Engineer from reviewing or commenting on the submittal contents. Information only submittals returned to the Contractor marked “AMEND AND RESUBMIT” or “REJECTED –SEE REMARKS” shall be revised and resubmitted by the Contractor.

MATERIAL OR EQUIPMENT SPECIFIED BY NAME

When any material or equipment is indicated or specified by patent or proprietary name or by the manufacturer’s name of one or more designations, it shall be considered as used for convenience in describing the material or equipment desired. The use of an alternative material or equipment which is of equal quality, operability, maintenance history, and reliability, and of the required characteristics for the purpose intended will be permitted. The Contractor may offer substitutions of products considered to be equal to that specified. The burden of proof as to the quality and suitability of the alternative shall be upon the Contractor. The Engineer shall be the sole judge as to the quality and suitability of the alternative materials or equipments.

CLEAN UP AND DISPOSAL OF REFUSE

Upon completion of the work under this contract, the Contractor shall remove all remaining excess materials, waste, rubbish, debris, temporary facilities and other equipment from the site. Final approval of the work done under these specifications will not be given until the final cleanup shall have met with the approval of the Engineer.

All material that results from clearing, grubbing, stripping, demolition/removal, excavation, and is not to be incorporated in the work shall become the property of the Contractor and shall be removed from the site and lawfully disposed of by the Contractor at his/her expense.

Surplus materials, resulting from excavations or trenching operations that are not required for backfill construction are the property of the Contractor.

The State has the right to salvage any items scheduled for removal as shown on the drawings. The State shall mark items to be salvaged. The Contractor shall be responsible for such items to be disconnected at flanged connections, bolted connections or wire terminals, where practical, removed from their foundations, flushed, and stored at a location as directed by the State.

07/07/2025 A1-6 of A1-22 LFEB - PW

RESTORATION OF IMPROVEMENTS

Any damage to existing facilities, structures or improvements caused by the Contractor, his/her equipment or workmen, during the term of this contract, shall be repaired and the damaged item(s) restored to as good a condition as existed at the time work commenced at the Contractor’s own expense.

DVBE VERIFICATION & CERTIFICATION

Final retention will not be released until the Prime Contactor’s DVBE Subcontracting Report (Form 817) has been completed and returned to the State Engineer.

At the end of the contract, the Contractor will be required to complete the Prime Contractor’s DVBE Subcontracting Report (Form 817) to certify that he/she has met all of their DVBE Obligations as identified in their Bid.

1. Use of Subcontractor(s)

The Contractor shall be responsible for all work performed. All persons engaged in the work will be considered employees of the Contractor. When any subcontractor fails to execute a portion of the work in a manner satisfactory to the State, the Contractor shall immediately remove such subcontractor upon written request of the State and the subcontractor shall not be employed for any portion of the contract. The State will not entertain requests to arbitrate disputes among subcontracts concerning responsibility for performing any part of the work.

2. Prime Contractor DVBE Subcontracting Form (STD 817)

If the Contractor enters into a subcontract with a Disabled Veteran Business Enterprise (DVBE), the CDFW and the Contractor are required to follow Military and Veterans Code Section 999.5, 999.55 and 999.7. Upon request by CDFW, the Contractor shall provide proof of payment for the DVBE work.

Pursuant to the Military and Veterans Code (M&VC) Section 999.5, if the Contractor has entered into a subcontract with a DVBE, then the Contractor must certify to CDFW through the Contractor DVBE Subcontracting Form (STD 817), before releasing final retention payment, all of the following:

a. The total bid amount and the total final contract amount including contingencies the contractor received under the contract.

b. The name and address of the disabled veteran business enterprise that participated in the performance of the contract and the contract number.

c. The amount and percentage of work the Contractor committed to provide to one or more disabled veteran business enterprises under the requirements of the contract

07/07/2025 A1-7 of A1-22 LFEB - PW and the amount each disabled veteran business enterprise received from the prime contractor.

d. That all payments under the contract have been made to the disabled veteran business enterprise. Upon request by the CDFW, the Contractor shall provide proof of payment for the work. A person or entity that knowingly provides false information shall be subject to a civil penalty for each violation in the minimum amount of two thousand five hundred dollars ($2,500) and the maximum amount of twenty-five thousand dollars ($25,000). An action for a civil penalty under this subdivision may be brought by any public prosecutor in the name of the people of the State of California and the penalty imposed shall be enforceable as a civil judgment.

Pursuant to the M&VC Section 999.7, the CDFW will withhold ten thousand dollars ($10,000) from the final payment, or the full final retention payment if less than ten thousand dollars ($10,000), until the Contractor complies with the certification requirements of Military and Veterans Code Section 999.5. Contractors that fail to comply with the certification requirements shall be given notice and allowed to cure the defect. If after 15 calendar days but not more than 30 calendar days from the date of the notice, the Contractor fails to comply with the certification requirements, the CDFW shall permanently deduct ten thousand dollars ($10,000) from the final payment, or the full final retention payment if less than ten thousand dollars ($10,000). The withholding applies to all procurement approaches with a DVBE subcontractor, as defined by M&VC Section 999(b)(4). Notwithstanding any other law, the CDFW shall not withhold more than the amount specified or the full final retention payment of any disabled veteran business enterprise contract for the purposes of ensuring compliance with the certification requirements of M&VC 999.5.

Scope of Work

The Contractor shall preform and complete the following work:

1. Remove all existing windows from six state owned residences: R4-48, R4-49, R4-52, R4- 53, and R4-55

2. Install new windows in the same location as old windows sized based on improvement drawings. Adjust framing if necessary.

3. Paint windows to match the existing house. Paint colors will be discussed during the pre-construction meeting.

4. Install an ADA compliant ramp and detectable warning at the R4-49 residence.

07/07/2025 A1-8 of A1-22 LFEB - PW

SECTION 05 51 20

MODULAR ALUMINUM RAMPS

PART 1 - GENERAL

1.01 DESCRIPTION

A. Work Included: Install ADA compliant ramp.

1.02 SUBMITTALS

A. Product Data: Manufacturer’s Data sheets on each product to be used, including:

1. Preparation instructions and recommendations.

2. Storage and handling requirements and recommendations.

3. Installation methods.

B. Shop drawings: Drawings showing plans, elevations, sections and details of components.

Show member sizes and part identification, fasteners, anchor requirements, fittings and evidence of compliance with structural performance requirements.

PART 2 – PRODUCTS

2.01 DESIGN/PERFORMANCE REQUIREMENTS

A. Design shall conform to ADA Standards for Accessibility Design and applicable local codes and standards

B. Design landings and ramps for a minimum uniform live load of 100 lbs/sf and a concentrated vertical load of 400 lbs distributed uniformly over an area of 1 sf.

C. Handrails and Guardrails: Provide handrails and railings capable of withstanding the following structural loads without exceeding allowable design working stress of materials for handrails, railings, anchors and connections:

1. Handrails and guardrails shall be designed and constructed to resist a single concentrated load of 200 lbs applied at any point and in any direction at the top of the handrail or guardrail.

2. Handrails and guardrails shall be designed and constructed for a load of 50 lbs/lf applied horizontally at the required guardrail height and a simultaneous load of 100 lbs/lf applied vertically downward at the top of the guardrail.

D. Corrosion Resistance: Separate incompatible materials to prevent galvanic Corrosion.

07/07/2025 A1-9 of A1-22 LFEB - PW

2.02 MANUFACTURERS

A. American Access, Inc., which is located at:

3150 Stage Post Dr., Suite 101 Bartlett, TN 38133 Tel: 901-584-0252 Email: sales@aaramps.com Web: http://www.aaramps.com

B. Approved equal

2.03 MATERIALS

A. Extruded aluminum Bars, Rods, Wire, Shapes and Tubes shall be 6063-T6 alloy and temper with a minimum ultimate tensile strength of 22,000 psi. Comply with

ASTM B 221.

B. Sheet and Plate Aluminum: ASTM B 209; 5005 alloy.

C. Extruded Aluminum-Alloy Structural Pipe and Tube. Comply with ASTM B 429.

D. Mechanical Fasteners: Aluminum, stainless steel or other non-corrosive materials compatible with aluminum members, trim, hardware, anchors and other components of the modular system.

2.04 MODULAR RAMP SYSTEM

A. All components shall be universal so that system can be easily relocated and assembled into many different configurations.

B. Ramp sections: Ramp sections are prefabricated aluminum shapes.

1. Length: 24 feet

2. Width: 3 feet

3. Heigh: Variable as indicate

4. Walking surface shall be continuous, without gaps and aluminum deck with Extruded slip resistant surface.

5. Ramp sections have a wheelchair guard 3 inches plus or minus 1 inch from decking Surface.

C. Landings: Fabricated of aluminum shapes and deck.

1. Prefabricated in typical 63 inch by 63 inch or 63 inch by 78 inch sections.

Larger sizes will be fabricated as required by local codes and for specific applications as indicated on the Drawings.

2. Landings shall be designed for variable heights

3. Walking surface of the landing shall be continuous, without gaps, knurled or cross-hatched, aluminum deck with extruded slip resistant surface.

07/07/2025 A1-10 of A1-22 LFEB - PW

D. Legs: Fabricated of aluminum shapes and plate.

1. Lengths as required to fit site conditions.

2. Provide with 4 inch by 4 inch foot pads.

3. Legs telescope into the ramps and landing and shall allow for height and slope adjustments.

4. Design to be independent each side, perpendicular to the ground and allow for adjustment without additional foundation systems.

5. Legs shall not protrude outside the footprint of the walking surface, eliminating tripping hazards.

E. Handrail and Guardrail: Fabricated of aluminum tubing and fittings.

1. Handrail shall have outside diameter of 1.5 inches.

2. Handrail gripping surface shall be smooth and continuous throughout ramp sections, steps and landings.

3. Guardrails shall form a protective barrier of a minimum of 42 inches high and designed such that a 4 inch sphere can not pass through any opening.

4. Pickets, balusters will be minimum aluminum 3/4 inch by 3/4 inch, 4 inches o.c.

5. Inside handrail to be attached to guardrail 34 inches to 38 inches above walking surface.

2.05 FINISHES

A. Shop finish ramp components as follows

1. Preparation: Brush Off Blast SSPC-SP10.

a. Remove all oil, grease, dirt, mill scale, corrosion products, oxides or other foreign from the surface by abrasive blasting, except for very light shadows, very slight streaks or slight discolorations caused by mill scale oxides.

b. At least 95 percent of each square inch of surface area shall be free of all visible residues, and the remainder shall be limited to the light discolorations.

Final blast profile should not exceed 0.7mils.

2. Powder Coat:

a. Electrostatically applied Thermosetting Powder Coating, Polyester Powder

Coating, meeting performance requirements of AAMA 2603.

b. Color: Los Gloss Sandstone

2.06 FABRICATION

A. Fit and shop assemble components in largest practical sizes for delivery to site.

B. Fabricate components with joints tightly fitted and secured. Furnish spigots and sleeves to accommodate site assembly and installation.

C. Exposed Mechanical Fastenings: Screws or bolts; unobtrusively located;

consistent with design of component, except where specifically noted otherwise.

07/07/2025 A1-11 of A1-22 LFEB - PW

D. Grind exposed joints flush and smooth with adjacent finish surface. Make exposed joints butt tight, and flush. Ease exposed edges to small uniform radius.

E. Accurately form components to suit stairs and landings, to each other and to building structure as applicable.

PART 3 - EXECUTION

3.01 EXAMINATION

A. Do not begin installation until substrates have been properly prepared.

B. Verify field conditions are acceptable and are ready to receive work.

C. If substrate preparation is the responsibility of another installer, notify engineer of unsatisfactory preparation before proceeding.

3.02 PREPARATION

A. Clean surfaces thoroughly prior to installation.

B. Prepare surfaces using the methods recommended by the manufacturer for achieving the best result for the substrate under the project conditions.

3.03 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to the job site in good condition and adequately protected against damage as handrails are a finished product.

B. Inspect ramp and rail sections for damage before signing the receipt from the trucking company. Truck driver must note damaged goods on the bill of lading if damaged product is found.

C. Store products in manufacturer's unopened packaging until ready for installation.

3.04 INSTALLATION

A. Install in accordance with manufacturer’s instructions.

B. Install components plumb and level, accurately fitted, free from distortion or defects.

C. Conceal bolts and screws whenever possible.

D. All legs should land on a solid surface or a concrete paver. Minimum dimensions of

Paver must be equal to or greater than 2 inches H by 6 inches W by 9 inches.

E. Anchor assembly as specified by manufacturer.

07/07/2025 A1-12 of A1-22 LFEB - PW

3.05 PROTECTION

A. Protect installed products until completion of project.

B. Touch-up, repair or replace damaged products before Substantial Completion.

- End of Section –

07/07/2025 A1-13 of A1-22 LFEB - PW

SECTION 08 51 00

VINYL SLIDING WINDOWS

PART 1 - GENERAL 1.01 QUALITY

A. Windows shall be of vinyl in accordance with AAMA 101. Windows shall be horizontal sliding type, furnished complete with operating and locking hardware, glazing, screened panels, weatherstripping, and framing and fasteners to properly install the windows.

A. Product Data: Manufacturer’s Data sheets on each product to be used, including:

3. Installation methods.

PART 2 - PRODUCTS 2.01 VINYL WINDOWS

A. Windows shall be insulated, single hung aluminum sliding window; Windows shall be vinyl “Retrofit”, Milgard V300 or approved equal or approved equal. Frame components shall be contemporary vinyl.

2.02 GLASS

A. Insulation glass units: formed of two pieces of Type 1, Quality Q3, 1/4-inch thick glass, separated by 1/4-inch dehydrated air space, hermetically sealed. Outside facing glass shall be bronzed tinted, interior glass shall be clear.

2.03 INSECT SCREENS

A. Each window shall include a removable insect screen; roll formed 0.025 inch minimum, not less than 7/16 inch by 1 inch. Cloth shall be fiberglass.

PART 3 - EXECUTION 3.01 WINDOWS

A. Set straight, plumb, level, in true alignment and securely anchor in place. Adjust vent sash for weather tightness and proper operation. Leave finished installation free from dents, twists, and other defects.

3.02 SEALANT

A. Thoroughly seal perimeter of window openings. Remove lacquer from aluminum surfaces in contact with sealant. Tool exposed joints slightly concave.

07/07/2025 A1-14 of A1-22 LFEB - PW

3.03 FINAL CLEANING

A. Clean exposed aluminum surfaces with soap and clean water. Abrasive cleaning agents and laquer thinner are not permitted. Leave exposed surfaces free from stains, marks or other defects.

- End of Section –

07/07/2025 A1-15 of A1-22 LFEB - PW

SECTION 09 90 00

PAINTING

1.01 WORK INCLUDED

A. All labor, material, transportation and shop services required for interior and exterior painting as described herein, and for all interior and exterior surfaces not specifically mentioned herein, but shown on the drawings.

B. Paint only windows.

1.02 QUALITY ASSURANCE

A. Manufacturers Direction: Follow manufacturers printed directions for application of paints and finishes. Do not add materials to paints, except as recommended by the manufacturer.

B. Certifications and Affidavits: When requested by Engineers, submit manufacturers affidavits certifying compliance of materials with Engineers specifications.

C. Paints shall comply with State of California Air Resources Board Rule 1113. Paints containing lead in excess of 0.06 percent by weight of the total nonvolatile content shall not be used. Paints containing zinc chromate or strontium chromate shall not be used. Interior latex paints are not permitted in toilet rooms.

1.03 SUBMITTALS

A. Materials List: Submit complete list of proposed manufacturers materials for Engineer approval. Completely describe all materials.

B. Colors and Samples: Submit samples of each color and type of finish for Engineers approval. Samples shall be completely finished will all coats specified and over same materials as those in the work.

1.04 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Identifications: Deliver materials to job site in manufacturers original labeled unopened containers, printed with all information necessary for complete identification.

B. Handling: Protect materials against rain, dust and drying in container.

07/07/2025 A1-16 of A1-22 LFEB - PW

1.05 JOB CONDITIONS

A. Environmental Requirements: Do not paint in wet or dusty conditions or in temperatures below 65 F.

B. Ventilation: In interior work, provide fan ventilation to remove paint fumes, especially when spray application is employed. Use spark proof fans.

C. Spray painting: Employ spray painting only in accordance with the requirements of the State Division of Industrial Safety and other jurisdictions.

D. Lighting: See that areas requiring painting work have been provided with adequate artificial lighting where day lighting is insufficient. Do not proceed otherwise.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Paints shall be best quality as regularly manufactured by recognized paint and varnish manufacturers. Material not bearing manufacturer’s identification as standard best grade of regular line are not acceptable. Materials shall be delivered to jobsite in original containers bearing manufacturer’s name. Paint application shall comply with manufacturer’s recommendation and standards.

2.02 PAINT SCHEDULE

A. Paint windows to match existing home.

3.01 EXAMINATION

A. See that the following conditions are obtained before proceeding with painting and finishing.

Do not proceed otherwise. Start of work will indicate acceptance of conditions as being satisfactory.

1. Surfaces are complete, dry, clean with nails set, and are in good condition to receive finish.

2. Surfaces are not coated with material that would reduce or impair adhesion of paint finishes.

3.02 PREPARTATION

A. Cleaning: Sweep and vacuum clean floors: Damp mop in addition, if necessary.

B. Protection:

07/07/2025 A1-17 of A1-22 LFEB - PW

1. Protect floors, equipment, furnishings, and adjoining work from paint spots or overlaps.

2. Protect aluminum, or other surfaces from which removal of paint would cause injury, by covering with masking tape, paper or other approved means, and remove when directed.

3. Protect painted or finished surfaces until dry and not tacky.

3.03 FIELD QUALITY CONTROL

A. Use good quality brushes adaptable for each type of work.

B. There shall not be sags, laps, runs, skips, heavy brush marks, or other defects in the finished work.

C. Cut in true to line.

D. Allow 24 hours minimum between coats, or longer dried hard Coats specified here in are in addition to shop coats.

E. Paints and finishes are to cover well. When undercoats, stains, or discolorations show through final coat, apply additional coats at Contractor’s expense until paint is of uniform color and coverage is complete.

F. Repaint or finish any damaged finished work to match new undamaged work.

3.05 WORKMANSHIP

A. All materials shall be applied and cut in neatly so as to dry uniformly to the color and sheen specified and shall be free from excessive runs, sags, wrinkles, shiners, streaks and brush marks.

B. All materials shall be applied in accordance with manufacturers directions as printed on container. Any thinning required shall be done in the manner and exclusively with the type of reducer recommended.

C. Vary each coat of paint in shade from the preceding coat in a manner that will make each coat readily distinguishable without affecting finish color. Touch up all blemishes.

D. In enclosed spaces, application and drying of paint shall be performed only:

1. When temperature is 65 F or above, maintained constantly to prevent condensation.

2. When ventilation is adequate to maintain humidity lower than the dew point of the coldest wall.

07/07/2025 A1-18 of A1-22 LFEB - PW

E. No exterior painting shall be undertaken at temperatures under 50 F, or immediately following rain, frost or dew. Safe levels for painting shall be determined by use of an electronic moisture meter.

F. The areas in which Contractor has been conducting his/her work shall be left in a clean and orderly condition with all paint spots, rags, and discarded equipment removed.

G. Do not paint finish hardware.

H. Paint rough hardware same color as trim to which it is attached.

3.08 CLEANING

A. Surfaces: remove all paint spots and stains from surfaces that were not to be painted, taking care not to damage such surfaces in so doing. Repair, replace or refinish damaged work as directed.

B. Glass Cleaning: Remove paint spots.

- End of Section -

07/07/2025 A1-19 of A1-22 LFEB - PW

SECTION 31 10 00

SITE CLEARING

1.01 PROTECTION OF EXISTING IMPROVEMENTS

A. Provide barricades, coverings, or other types of protection necessary to prevent damage to existing facilities and improvements indicated to remain in place. Protect improvements on State Property. Any improvements damaged by this work shall be restored to original condition as approved by authority having jurisdiction.

B. The limits of construction shall be as identified on the drawing and shall not interfere with the operations of the Grizzly Island Wildlife Area.

PART 2 – PRODUCTS

2.01 DISPOSAL OF MATERIALS

A. Remove rubbish and other undesirable materials resulting from site clearing operations;

dispose of same off State property. Burning of materials not permitted. Upon completion of site clearing work, premises shall be neat, clean and in condition to receive subsequent work.

PART 3 – EXECUTION

3.01 GENERAL

A. Remove trees, shrubs, grass weeds, other vegetation, improvements, or obstructions that interfere with installation of new construction. Carefully and cleanly cut roots of trees indicated to remain in place, where such roots obstruct new construction.

B. All obstructions, both and below ground shall be removed as necessary for the construction of the proposed improvements.

- End of Section

07/07/2025 A1-20 of A1-22 LFEB - PW

SECTION 32 17 26

DETECTABLE WARNING SURFACING

PART 1 – GENERAL

1.01 SUMMARY

A. This Section requires Applicators trained, certified, and authorized by the manufacturer.

B. This Section requires Applicator's Superintendent approval of substrate integrity and extent of substrate repair is required prior to mobilization.

C. Performance-type specification for: On-site, surface-applied, extruded polymer in shape of Detectable Warning Surfacing (DWS) applied as Tactile Walking Surface Indicator (TWSI).

A. Provide Product Data: Manufacturer’s Data sheets on each product to be used, including:

3. Manufacturer’s written application instructions.

4. Drawings

5. Maintenance Requirements

1.03 DELIVERY, STORAGE, AND HANDLING

A. Store in environment meeting a temperature range between 25 degrees F and 90 degrees F.

B. Remove and replace components at no additional cost which are delivered to site damaged or otherwise not suitable for application.

PART 2 - PRODUCTS

2.01 DETECTABLE WARNING COMPONENTS - PERFORMANCE

A. Products require certified compatibility with asphalt for a warrantable application of the designed condition.

07/07/2025 A1-21 of A1-22 LFEB - PW

B. Basis of Design: Self-Adhesive Detectable Warning (Truncated Dome) by ADA Sign Depot or approved equal

1. Salient Features:

a. Application method: Self Adhesive

b. Shape: Raised truncated domes.

c. Size:

Extruded DWS (Truncated) Dome Size (nominal):

(a) Height: 0.2 inch.

(b) Base Diameter: 0.9 inches minimum to 1.4 inches maximum.

(c) Truncation Ratio: Top Diameter to be 50 percent minimum to 65 percent maximum of base diameter.

d. Extruded DWS (Truncated) Dome Spacing:

(a) Center-to-Center Spacing: 1.6 inches minimum to 2.4 inches maximum.

(b) Minimum Base-to-Base Spacing: 0.65 inches, measured between most adjacent domes on square grid.

(c) Width of DWS Application: Nine (9) feet

(d) Depth of DWA Application: Twelve (12) feet depth across by width of opening

(e) Remove six (6) feet by five (5) feet rectangle to match landing in drawing

e. Color: LI-B35 Yellow

2.02 DETECTABLE WARNING COMPONENTS - APPLICATION

A. Detectable warning shall be applied by self-adhesion

3.01 EXAMINATION AND VERIFICATION

A. Verify existing conditions meet Manufacturer's and Applicator's requirements before starting Work.

1. Assess CSP existing substrate profile to determine extent of surface preparation required.

2. Verify surface is clean and dry, and free of surface applied sealers, coloring agents, or other materials detrimental to surface bond.

3. Verify surface temperature is between 35 degrees F and 88 degrees F.

4. Verify moisture content of asphalt substrate does not exceed six (6) percent.

3.02 PREPARATION

A. Protection of In-Place Conditions: Applicator to protect applied work areas required by until work is complete to maintain product performance, design criteria and warranty.

07/07/2025 A1-22 of A1-22 LFEB - PW

B. Surface Preparation: Prepare surfaces to receive work in accordance with manufacturer's instructions.

1. Grind clean or abrade to remove surface applied sealers, coloring agents, oils, bond breakers, or any surface applied or infused materials that will cause reaction of adhesion and provide required surface profile.

2. If seal-coated, grind to remove sealer with walk-behind or handheld grinder to CSP 3 - 5.

3. Fill large holes or crevices resulting from the grinding process with manufacturer's recommended materials.

4. Broom or air sweep clean surfaces free of dust and debris, vegetation and material impacting adhesion, prior to installation of liquid-polymer extrusion materials.

5. Measure, layout, and mask Work area.

3.04 CLEANING

A. Dispose of all waste material in compliance with project’s Waste Management Plan in accordance with 01 74 19 - Construction Waste Management and…