02 Section II - Technical Specifications (2).pdf
PDF 1 MB Posted
- Attached to
- Laydown Yard Surface Treatment
- Solicitation number
- RFB 26-301A
- Issued by
- Orange County, Texas
About this file
This is the Technical Specifications document for the Laydown Yard Surface Treatment project issued by the Port of Corpus Christi Authority (PCCA) in Texas. The project involves surface maintenance to existing storage and laydown yards, including mill and overlay, scarifying, re-compacting, and applying new surface treatments. The scope of work encompasses crushed limestone flexible base installation, pavement rehabilitation and repair, and two-course surface treatment applications. The specifications establish comprehensive requirements across multiple divisions, including procurement policies, general project requirements, access control procedures for Port Authority property, project coordination and meeting protocols, submittal procedures, pollution prevention measures, tropical storm and hurricane preparedness, environmental management system compliance, and temporary stormwater pollution controls for construction sites exceeding five acres.
The technical specifications mandate that contractors comply with extensive administrative, environmental, and safety requirements established by PCCA. Key requirements include submission of a detailed construction schedule within ten days of the Notice to Proceed, preparation of a Stormwater Pollution Prevention Plan (SWP3) with Notice of Intent submission to the Texas Commission on Environmental Quality at least seven days before construction commencement, and submission of construction drawings to the Port's Environmental representative two days prior to work beginning. Contractors must maintain TWIC (Transportation Worker Identification Credential) compliance for secure area access, adhere to strict harassment and workplace violence policies, implement substance abuse testing protocols, comply with the Port's ISO 14001 certified Environmental Management System, and follow detailed best management practices for air emissions, water quality, spill prevention and response, and stormwater runoff management. All personnel working on PCCA property must be aware of and comply with the Port's Environmental Policy, which includes targets for emissions reduction, water quality improvement, habitat restoration, and climate action initiatives.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION II
TECHNICAL SPECIFICATIONS
Laydown Yard Surface Treatment i
TABLE OF CONTENTS
for
Technical Specifications for Laydown Yard Surface Treatment
DIVISION 00 PROCUREMENTS AND CONTRACTING REQUIREMENTS
00 73 10 PCCA Policies and Procedures
DIVISION 01 GENERAL REQUIREMENTS
01 14 13 Access to Port Authority Property 01 31 13 Project Coordination 01 31 19 Project Meetings 01 33 00 Submittals 01 35 21 Pollution Prevention
01 35 30 Tropical Storm and Hurricane Preparedness 01 35 43 Environmental Management System Requirements 01 42 00 Definitions and Standards 01 57 23.13 Temporary Stormwater Pollution Controls
(Construction Sites >5 Acres) 01 57 23.13 Stormwater Pollution Prevention Plan
01 77 00 Closeout Procedures
DIVISION 32 EXTERIOR IMPROVEMENTS
32 11 23.33 Crushed Limestone Flexible Base
32 12 33.02 Pavement Rehabilitation and Repair 32 15 50 Two-Course Surface Treatment
DIVISION 00
PROCUREMENT AND CONTRACTING
REQUIREMENTS
SECTION 00 73 10 Page 1 of 10 (Rev. 09/2022)
SECTION 00 73 10
PCCA POLICIES AND PROCEDURES
PART 1 - GENERAL
1.01 SUMMARY
A. This section specifies the policies and procedures by which the PCCA, an "at will" employer, is governed and by which the PCCA obligates the Contractor, his employees, his subcontractors and suppliers, and their employees.
B. This specification is intended to provide a minimum policy level for all personnel working on PCCA property. In addition, the Contractor may implement and enforce his own personnel policies if more stringent or encompassing than this specification.
1.02 EQUAL OPPORTUNITY EMPLOYER
The Port of Corpus Christi Authority is an equal opportunity employer. It is the policy of the PCCA not to allow discrimination against any person in job structuring, recruitment, examination, selection, appointment, placement, training, upward mobility, discipline, or any other aspect of personnel administration based on a person’s sex, race, age, religion, color, disability, citizenship, national origin, or veteran status. An occupational qualification may, however, disqualify certain persons from a particular job.
1.03 AFFIRMATIVE ACTION POLICY
The PCCA recognizes that equal employment opportunity can only be fully achieved with a firm commitment to the concept of Affirmative Action. Therefore, the PCCA has adopted an Affirmative Action Plan to continue to remove employment practices which could negatively impact an identifiable, protected group of persons and to apply good faith efforts to seek out, employ, train, and promote under-represented protected group members into and within the PCCA’s workforce.
1.04 COMPLIANCE WITH APPLICABLE LAWS
It is the policy of the PCCA to comply with applicable federal and state laws including, without limitation, the Family and Medical Leave Act, the Americans with Disabilities
Act, the Fair Labor Standards Act, and the Texas Worker’s Compensation Act.
1.05 HARRASSMENT POLICY
The PCCA is determined to maintain a work environment that is free of harassment, exploitation, and intimidation based on sex, race, age, religion, color, disability, national origin, or veteran status. All employees, whether of the PCCA or the Contractor or his subcontractors and suppliers, are expected to comply with this policy. Failure to do so
SECTION 00 73 10 Page 2 of 10 may result in termination of an individual or termination of the contract. The Contractor will adhere to the following policy and procedure with regard to any harassment incident.
A. General: The PCCA does not condone and will not tolerate harassment of employees on the basis of race, color, religion, sex, national origin, age, citizenship, veteran status, disability, or work-related injury or illness.
Harassment may include physical conduct as well as insulting remarks or jokes.
The PCCA considers harassment to be a grave act of misconduct and may subject the perpetrator to disciplinary action up to and including discharge from employment. Harassment of employees by co-workers, clients, visitors, vendors, or other third parties will also not be tolerated.
B. Sexual Harassment: The PCCA is concerned about the prevention of sexual harassment. For purposes of this policy, sexual harassment includes unwelcome sexual advances, requests for sexual favors, and other verbal, graphic or physical conduct of a sexual nature where:
1. Submission to such conduct is either an expressed or implied term or condition of an individual’s employment;
2. Submission to or rejection of such conduct by an individual is used as the basis for employment decisions affecting that individual; or
3. Such conduct has the purpose or effect of unreasonably interfering with an individual’s work performance or creating an intimidating, hostile or offensive working environment.
C. Handling of Harassment Complaints:
1. If any employee feels that he or she has been harassed in violation of the
PCCA’s policy on harassment, he or she should immediately report the alleged harassment to his or her supervisor or the Director of Human
Resources of the PCCA. An employee need not first make a report to his or her supervisor. In other words, an employee may report directly to the
PCCA Director of Human Resources. Any employee or supervisor who observes or becomes aware of possible sexual or other unlawful harassment should immediately advise the PCCA Director of Human
Resources. All complaints will be promptly and thoroughly investigated.
The PCCA will treat complaints of harassment in as confidential a manner as possible, releasing information only to those with a need or right to know.
2. No employee should assume that the PCCA is aware of a problem. Please bring complaints and concerns to the PCCA’s attention so that we may take steps to correct them.
3. No retaliation will be taken against any employee because he or she reports a problem concerning possible acts of harassment. Employees can
SECTION 00 73 10 Page 3 of 10 raise concerns and make reports without fear of reprisal. If you have any question about what constitutes harassing behavior, feel free to speak with your supervisor or the PCCA’s Director of Human Resources.
1.06 WORKPLACE VIOLENCE POLICY
The PCCA is committed to preventing workplace violence and to maintaining a safe work environment. Intimidation, harassment or other threats of (or actual) violence is prohibited during business hours or on PCCA premises. All employees, whether of the
PCCA or the Contractor or his subcontractors and suppliers, are expected to comply with this policy. Failure to do so may result in termination of an individual or termination of the contract. The Contractor will adhere to the following policy and procedure with regard to any violent workplace incident.
A. General: Given the increasing violence in society in general, the PCCA has adopted the following guidelines to deal with intimidation, harassment or other threats of (or actual) violence that may occur during business hours or on PCCA premises.
B. Prohibited Conduct:
1. All employees, including temporary employees and those of the
Contractor and his subcontractors and suppliers, will be treated with courtesy and respect at all times. Conduct that threatens, intimidates or coerces another employee, a customer, or a member of the public at any time, including off-duty periods, will not be tolerated. This prohibition includes all acts of harassment, including harassment that is based on an individual’s sex, race, age, national origin, disability, religion, veteran status, or any characteristic protected by federal, state, or local law.
2. The PCCA does not permit any employee, former employee, client or other person (excluding bona fide law enforcement personnel) to use or possess firearms, weapons, and other dangerous or hazardous devices or substances on PCCA premises. Furthermore, pursuant to Texas Penal
Code §30.06 (trespass by holder of license to carry a concealed handgun), a person licensed under Texas Revised Statutes Article 4413 (29EE)
(concealed handgun law) may not enter PCCA property with a concealed handgun.
C. Reporting Conduct:
1. All threats of (or actual) violence, both direct and indirect, should be reported immediately to a supervisor, Manager of Risk Management, or to the PCCA’s Human Resources Department. This includes threats by employees, as well as threats by customers, vendors, solicitors, or other members of the public. When reporting a threat of violence, be as specific and detailed as possible.
SECTION 00 73 10 Page 4 of 10
2. All suspicious individuals or activities should also be reported as soon as possible to the PCCA’s Manager of Risk Management or the PCCA’s
Human Resources Department. Employees are requested not to place themselves in peril. If a commotion or disturbance occurs near the work area, employees are requested not to try to intercede or see what is happening, but to report it immediately. The PCCA will promptly and thoroughly investigate all reports of threats of (or actual) violence and of suspicious individuals or activities. The identity of the individual making a report will be protected as much as practical. Anyone determined to be responsible for threats of (or actual) violence or other conduct that is in violation of these guidelines will be subject to prompt disciplinary action up to and including termination of employment.
3. The PCCA encourages employees to bring their disputes or differences with other employees to the attention of their supervisor or the PCCA’s
Director of Human Resources before the situation escalates into potential violence. The PCCA is eager to assist in the resolution of employee disputes and will not discipline employees for raising such concerns.
1.07 SUBSTANCE ABUSE POLICY
The PCCA recognizes its responsibility to implement measures necessary to ensure the safe and efficient operation of its facilities and services, not only for the protection and wellbeing of our employees and the operations of our organization, but also in the interests of the public. As a result of the growing concern about drug and alcohol use in the workplace and the potential impact with respect to the safe and secure operation of our facilities and services, the PCCA has developed a substance abuse policy. All employees, whether of the PCCA or the Contractor or his subcontractors and suppliers, are expected to comply with this policy and Section 2.10, “Drug-Free Workplace,” of the
General Conditions. Failure to do so may result in termination of an individual or termination of the contract. The Contractor will adhere to the following policy and procedure with regard to any substance abuse incident.
A. Policy Violations: The following are violations of this policy:
1. Engaging, on the job or off the job, in current illegal use, possession, consumption, exchange, delivery, manufacture, distribution, sale, or purchase of any drug;
2. Engaging in the improper use or possession of prescription drugs.
Employees may use or possess prescription drugs at work only if:
a. The drugs/medications have been prescribed by a health care provider (authorized by law to prescribe such drugs) for the person in possession of the drugs/medications.
b. The drugs/medications are kept in their original container, which identifies the drug, the dosage, the prescription date, the
SECTION 00 73 10 Page 5 of 10 prescribing health care provider, and the person for whom the drugs/medications were dispensed.
c. The drugs/medications are ingested or administered only in the prescribed or recommended therapeutic dosages, and all restrictions on the use of the prescription drugs are observed by the employee.
3. Engaging in the use of over-the-counter drugs/medications in a manner inconsistent with the instructions or warnings on the container for the drug/medication.
4. Possessing paraphernalia associated with the illegal use of drugs.
5. Engaging in current use, possession, consumption, exchange, delivery, distribution, or sale of any alcoholic beverage while at work, or on PCCA property, in PCCA vehicles, or in personal vehicles being used for PCCA purposes.
6. Engaging in off-the-job use of alcohol that adversely affects the employee’s ability to perform his/her job duties safely and/or efficiently.
This policy does not prohibit off-the-job use of alcohol by employees when that use does not adversely affect the employee’s ability to perform his/her job responsibilities safely and efficiently.
7. Reporting to work or performing job duties after having consumed drugs, including prescription or over-the-counter drugs, when that drug use may impair the employee’s ability to safely perform his/her job duties or may affect his/her safety and/or the safety of others.
8. Refusing to consent to a urinalysis and/or alcohol test as required by this policy or refusing to release the results of any such urinalysis and/or alcohol test.
9. Failure to comply or fully cooperate with any provision of this Substance
Abuse Policy.
10. Producing a positive test result on a urinalysis or alcohol test indicating a violation of this policy.
B. Penalties for Violations: Engaging in any illegal drug activity, producing a positive test result on a urinalysis test indicating the illegal use of drugs, refusal or failure to fully cooperate in testing, or any other violation of this policy will lead to discipline up to and including discharge.
C. Policy Enforcement: The PCCA reserves the right to perform urinalysis and/or alcohol testing under the following conditions:
SECTION 00 73 10 Page 6 of 10
1. Pre-Employment/Post-Offer Testing: Any applicant who has been presented with an offer of employment must submit to a urinalysis test.
An applicant who refuses to consent or submit to a urinalysis test will no longer be considered eligible for hire. Further, any offer made to an applicant who produces a positive test result for illegal drugs on a urinalysis test will be withdrawn.
2. Reasonable Suspicion Testing: When the PCCA determines that there is reasonable individualized suspicion to believe that an employee may have violated the prohibitions of this policy, the PCCA may require the employee to submit to urinalysis testing and/or alcohol testing.
Reasonable suspicion may be based upon, among other factors:
a. Observable phenomena, such as direct observation of alcohol or drug use and/or the physical symptoms of being impaired by a drug;
b. Deteriorating work performance, absenteeism, or poor personal hygiene;
c. A pattern of abnormal conduct, erratic or a marked change in personal behavior or attitude;
d. An arrest or conviction for a drug-related offense or the identification of an employee as the focus of a criminal investigation into illegal drug possession, use, or trafficking;
e. Information provided by reliable and credible or independently corroborated sources;
f. Newly discovered evidence that the employee has tampered with a previous drug/alcohol test.
g. Any supervisor who believes reasonable suspicion testing is appropriate in a particular case should immediately report that recommendation to the PCCA’s Director of Human Resources.
Before reasonable suspicion testing is administered, the PCCA’s
Director of Human Resources must substantiate the decision to test. If the decision to test is substantiated, arrangements will be made for transporting the employee to and from the sample collection site.
3. Post-Incident Testing: Any employee that management suspects may have caused, contributed to, or been involved in a job-related accident or injury is subject to urinalysis and/or alcohol testing. Post-incident testing occurs when there is reason to believe that an employee may have contributed to an injury to themselves, another employee, another person, SECTION 00 73 10 Page 7 of 10 or may have contributed to substantial damage to PCCA property or the property of another entity or individual.
4. Random Testing:
a. The PCCA may, in its sole discretion, choose to screen all employees holding safety-sensitive positions for the illegal use of drugs or improper use of alcohol in violation of this policy without a determination of reasonable suspicion that an employee is abusing alcohol and/or drugs, or may also conduct across-the-board drug screening by selecting certain job categories or departments and screening all employees holding safety-sensitive positions in those selected categories or departments. Submission to such testing is a condition of continued employment.
b. Additionally, random urinalysis testing or alcohol testing of specified percentages of the workforce holding safety-sensitive positions may be conducted. The percentage of the workforce tested and the timing and frequency of random testing is a matter within the sole discretion of management.
c. In order to ensure that any random drug screening is conducted in a nondiscriminatory manner, the PCCA will select employees by a computer program that randomly selects candidates for drug testing from a pool of all employees holding safety-sensitive positions. Employees selected to be tested on one random testing occasion will not be deleted from the pool on the next random testing occasion; all employees holding safety-sensitive positions are subject to being randomly selected for drug testing on any testing occasion.
5. Safety-Sensitive Positions: A “safety-sensitive position” includes a position that, to any extent, involves any of the following:
a. Emergency-response obligations for PCCA;
b. Functions necessary to maintaining PCCA security;
c. Driving a truck weighing more than 25,000 pounds or operating heavy mechanized equipment;
d. Inspecting, servicing, or conditioning such vehicles or equipment;
e. Directing, in any fashion, any ship or other vessel utilizing PCCA facilities or services;
f. Engaging in safety-sensitive communications with any ship or other vessel utilizing PCCA facilities or services; or
SECTION 00 73 10 Page 8 of 10
g. Any other function for which a momentary lapse by an employee could result in an accident.
6. Consent to Test: Compliance with the PCCA's Substance Abuse Policy is a condition of employment for all employees hired prior to and after the effective date of this policy. Current employees will be required to sign a written consent and release which will become part of each employee’s personnel file. Applicants will be required to sign a written consent and release before being subject to sample collection for pre-employment testing. Additionally, the PCCA will not perform a drug test or alcohol test on an applicant or employee without first obtaining the individual’s signed consent. The signed consent will also provide for the release of the test results to the PCCA.
7. Testing Requirements: Any drug test performed on applicants or employees will be performed utilizing the services of a qualified testing laboratory. Testing will consist of an initial screening (urine) test, wherein the urine specimen will be tested for the presence of drugs. If a positive test result is found, a second, more comprehensive test (Gas
Chromatograph/Mass Spectrometer test) will be conducted to confirm the results of the first test.
a. Applicants: If the results of the first test are confirmed, an applicant will be eliminated from consideration for employment.
b. Employees: If the results of the first test are confirmed, the employee will be subject to disciplinary action up to and including discharge.
c. For purposes of alcohol screening, the PCCA may employ existing methods of breath or blood testing to determine the level of intoxication. Refusal to submit to an ordered urinalysis or alcohol-screening test is a violation of PCCA policy and will result in termination.
8. Searches and Inspections: When the PCCA has good reason to suspect that there may be drug or alcohol use or possession in violation of this policy by employees or other persons on PCCA property, the PCCA reserves the right to conduct or employ specialists to conduct searches and inspections, including the use of scent-trained dogs. The Executive
Director must approve searches and inspections, which may be conducted at any time without notice. During any search, there will be at least one searcher and one observer present. In conducting such a search, management will attempt to carry it out in a confidential and discreet manner. Employee work areas, desks, lockers, briefcases, and personal vehicles parked on PCCA property may be subject to searches at any time.
The PCCA may also search any personal items brought onto PCCA
SECTION 00 73 10 Page 9 of 10 premises, and employees should have no expectation of privacy with regard to those items. In addition to drug and alcohol concerns, searches may be conducted for other legitimate reasons. Refusal to voluntarily submit to a search or inspection by a supervisor or authorized search specialist is a violation of PCCA policy and may result in disciplinary action up to and including dismissal.
9. Rehabilitation, Treatment, and Education: An employee’s decision to admit to substance abuse and seek assistance for alcohol or drug abuse/dependency will not be used against the employee for disciplinary purposes. However, where facts establish a violation of this policy or other PCCA policies, requesting assistance will not prevent the imposition of disciplinary action up to and including termination of employment. The
PCCA encourages employees to seek rehabilitation; however, rehabilitation is the responsibility of the employee. Any employee seeking medical attention for alcoholism or drug addiction may use benefits under the PCCA's group medical insurance plan, if available
(questions about coverage may be directed to the PCCA’s Director of
Human Resources). Employees completing medical treatment or formal treatment programs will be required to submit to drug and alcohol screening tests prior to being allowed to return to work and as often as management deems appropriate for a period of one year thereafter
(without prior notice to the employee). Currently, the PCCA does not offer any drug or alcohol education, training, or treatment program for employees.
10. Modification of Policy: The PCCA may amend, modify or terminate this policy at any time. Employees will be notified of such actions. This policy, alone or in conjunction with other PCCA policies, does not constitute an employment contract or agreement between any employee and the PCCA.
11. Confidentiality: The test and results of any drug or alcohol test will be kept confidential. The identity of individuals in rehabilitation programs will also be kept confidential. A testing administrator will be designated to receive test results and will notify the appropriate supervisors on a need-to-know basis.
12. Employees who have any questions regarding this policy are encouraged to speak with the PCCA’s Director of Human Resources.
1.08 CONCEALED HANDGUN POLICY
The use or possession of firearms, except by law enforcement officials or authorized security personnel, is prohibited on all PCCA property. PCCA property includes all land, parking areas, facilities, buildings, offices, open and covered cargo storage areas, sheds and docks (including their entries and exits) owned, controlled or operated by the PCCA.
SECTION 00 73 10 Page 10 of 10
In addition, prohibited areas include PCCA equipment, machinery, railroad right-of-way, and roadways that are owned, controlled, or operated by the PCCA. Contractors will adhere to this policy. Failure to do so may result in the termination of an individual or termination of the contract.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION (Not Used)
END OF SECTION
DIVISION 01
GENERAL REQUIREMENTS
SECTION 01 14 13 Page 1 of 6
SECTION 01 14 13
ACCESS TO PORT AUTHORITY PROPERTY
ITEM 669 ( C ) ( R ) 04-21-2015
PART 1 - RESTRICTED ACCESS
1.01 DEFINITIONS
A. Escort: an individual, who has been issued a TWIC, who engages in escorting, as defined in the Maritime Transportation Security Act (MTSA), 33 C.F.R. § 101- 107, and who assumes the responsibility for accompanying authorized non-TWIC holder(s) into a TWIC secure area.
B. Escorting: ensuring that the escorted individual is continuously accompanied while within a TWIC secure area in a manner sufficient to observe whether the escorted individual is engaged in activities other than those for which escorted access was granted.
C. Restricted Area: the infrastructure or locations identified in an area, vessel, or facility security assessment or by the owner/operator that require limited access and a higher degree of security protection. (1 TWIC holder for 5 non-TWIC holders)
D. TWIC Secure Area: the area over which an owner/operator has implemented security measures for access control and includes restricted areas within TWIC secure areas. (1 TWIC holder for 10 non-TWIC holders)
E. Transportation Worker Identification Credential (TWIC): a common identification credential for all personnel requiring unescorted access to secure areas of MTSA-regulated facilities and vessels, and all mariners holding Coast Guard-issued credentials. Individuals who meet TWIC eligibility requirements are issued a tamper-resistant credential containing the worker's biometric (fingerprint template) to allow for a positive link between the card and the individual.
1.02 To promote public safety and efficient operations, the Port Authority may restrict access to part of or all Terminal Facilities and other designated TWIC Secure and Restricted Areas within its jurisdiction. Users, however, are responsible for the security of any area of a Terminal Facility in which the User’s cargo or other personal property is located. The Port Authority is not responsible for providing escorts to non- TWIC holding personnel of Users. The User is responsible for providing TWIC holding escorts to accompany and/or monitor, as applicable, their non-TWIC holding personnel.
1.03 Before being authorized to escort a non-TWIC individual, the TWIC-holding escort must have prior authorization from the Port Authority to enter a Port facility (e.g. gate list, company letterhead document). Each authorized escort must complete the “Escort Agreement” form provided at the guard station. Each escort will be given a copy of the “Escort Rules.” TWIC Escorts shall comply with all rules pertaining to escorting non-TWIC individuals.
SECTION 01 14 13 Page 2 of 6
The TWIC escort and its employer assume all liability for penalties levied against the Port Authority for failure of the respective escort to comply with escorting responsibilities mandated by 33 C.F.R. §105 and other applicable U.S. Coast Guard requirements.
1.04 Docks, piers, and wharves, within secure areas, are restricted areas. Warehouses, designated open cargo storage areas adjacent to, or otherwise within the same immediate area of restricted areas, are designated TWIC secure areas. A TWIC is required for unescorted access to these TWIC secure and restricted areas at all times.
PART 2 - AUTHORIZATION REQUIRED TO ENTER UPON PORT AUTHORITY
PROPERTY
2.01 The security measures for control of access to Port Authority Property listed below are intended to fulfill the following purposes:
• Deter the unauthorized introduction of dangerous substances and devices, including any device intended to damage or destroy persons, vessels, facilities or ports.
• Secure dangerous substances and devices that are authorized by the Port Authority and the owner or operator to be on the facility; and control access to the facility.
A. TWIC/PHOTO IDENTIFICATION CARD
1. Except as otherwise noted in this paragraph, all persons requiring unescorted access to TWIC secure areas must possess, and present, a TWIC, before such access is granted. Federal officials are not required to obtain or possess a TWIC card. Except in cases of emergencies or other exigent circumstances, in order to gain unescorted access to a TWIC secure area, a federal official must present his/her agency’s official credential. Law enforcement officials, in the actual discharge of their official duty, at the State or Local level are not required to obtain or possess a TWIC to gain unescorted access to TWIC secure areas. State and local emergency responders are exempt from the requirement to have a TWIC when they are responding to an emergency.
2. At most Port Authority facilities, access to the facility is gained either through a guard manually logging the individual, or by the individual scanning their TWIC against a TWIC reader. In order to use TWIC readers, individuals must enroll their TWIC into the Port Authority Access Control System (instructions provided below). If an individual has not enrolled his or her TWIC with the Port Authority, the individual Will be required to present their TWIC, and one additional acceptable form of identification to the security guard at the access control point to the facility before access will be given. See 33 C.F.R. § 101.515. Individuals may enroll their TWIC into the Port Authority AMAG Access Control System. There is no fee for such enrollment. To enroll a TWIC with the Port Authority, the individual
SECTION 01 14 13 Page 3 of 6 must meet with the Port Access & Administrative Specialist at the Port Security Command Center, 1002 E. Port Avenue, Corpus Christi, Texas, 78401 (no appointment is needed). The individual must have a signed company letterhead document reflecting the request for authorization to enter a certain facility (or facilities), as well as the period of time (days/hours of the day) that entry will be necessary. Individuals desiring to enroll their TWIC with the Port Authority must know their TWIC Personal Identification Number (PIN) to be able to enroll their TWIC.
NOTE: If the PIN has been forgotten, the individual must request the Transportation Security Administration (TSA) TWIC Office to reset their PIN. When an individual has successfully enrolled their TWIC into the Port Authority Access Control System, the TWIC is the only identification that will be required to be presented by that individual to gain authorized and unescorted access to a Port Authority facility, in most cases. Port employees are issued Port Identification cards, in addition to their TWIC (if the employee is required to have a TWIC).
3. If an individual cannot present a TWIC because it has been lost, damaged or stolen, and he or she has previously been granted unescorted access to the facility and is known to have had a valid TWIC, the individual may be given unescorted access to TWIC secure areas for a period of no longer than seven (7) consecutive calendar days, or in accordance with the most current U.S. Coast Guard guidance, if the following requirements are met:
a. The individual has reported the TWIC as lost, damaged or stolen to TSA as required in 49 C.F.R. § 1572.19(f); and
b. The individual can present another identification credential that meets the requirements of 33C.F.R. § 101.515; and
c. There are no other suspicious circumstances associated with the individual’s claim of loss or theft.
4. If an individual cannot present his or her TWIC for any other reason, he or she may not be granted unescorted access to the TWIC secure area. The individual must be under TWIC escort, as described above, at all times when inside of a TWIC secure area.
5. With the exception of Federal, State and Local Regulatory & Law Enforcement/Emergency responders, all persons granted unescorted access to TWIC secure areas of the facility must be able to produce his or her TWIC upon request.
6. Personal vehicles that require access to TWIC secure areas of the Port Authority may be issued a decal, for a fee, that will permit them to remain within authorized areas on the facility. Vehicle decals expire, and must be
SECTION 01 14 13 Page 4 of 6 renewed, annually. See Part Four.
7. TWIC cards expire on the 5th anniversary from date of issue. Individuals must renew their TWIC enrollment in the Port Access Control System annually. Port Authority employee ID cards expire, and must be renewed, annually.
8. 33 C.F.R. § 105.257 entitled “Security Measures for newly-hired employees” applies to Port Authority personnel only. The Port Authority has an internal policy that addresses 33 C.F.R. § 105.257.
Tenant/Customer/Visitor newly-hired employees without a TWIC, require a TWIC escort in accordance with 33 C.F.R. § 105 and this Tariff Item.
PART 3 - SEAFARER ACCESS AND VISITOR PASSES
3.01 SHIPS’ CREW MEMBERS AND OTHER SEAGOING PERSONNEL
Ships’ crew members and other seagoing personnel calling at Terminal Facilities may be permitted access to Terminal Facilities, without a TWIC, for purposes of performing their assigned work on the dock immediately adjacent to the vessel. Otherwise, Ships’ crew members and other seagoing personnel must comply with TWIC regulations. The Port Authority Facility Security Officer (FSO), through his/her designated representative, will ensure the vessel Master or Vessel Security Officer (VSO), and ship’s agent be made aware of approved, no cost means of seafarer access between the vessel and the facility Access Control Point (gate).
3.02 VISITOR PASSES
Visitor passes will be issued to casual visitors at Access Control Points upon presentation of a photo ID issued by a city, state or federal agency and upon verification that the person has received Port Security authorization to enter a facility. Visitors must be escorted by a TWIC holder while in TWIC secure areas. Escorts must remain with their visitors while in TWIC secure areas. Vehicle and visitor passes must be surrendered/retrieved when the vehicle/person departs from the terminal facilities.
PART 4 - OPERATION OF MOTOR VEHICLES ON PORT AUTHORITY PROPERTY
4.01 All vehicles entering upon Port Authority property are subject to security screening at any time while on the facility. If the driver of a vehicle refuses to permit such security screening, access will be revoked and/or denied.
4.02 Only authorized vehicles may be operated in or on Terminal Facilities. If, in the judgment of the Port Authority, the use, driving, operating or parking of a motor vehicle does, or will interfere with the efficient and safe operations within Terminal Facilities, then designated Port Authority representatives, including the Port Authority’s security and police personnel, may order such vehicle(s) out of the area, or may order the removal of the vehicle from the Terminal Facility. The Port Authority may order the removal of
SECTION 01 14 13 Page 5 of 6 vehicles not in compliance with this provision, and in such event all towing and storage will be charged to the owner of the vehicle.
4.03 Certain areas have been or may be designated for parking and are so marked. Automobiles or other vehicles must be parked in these areas. Automobiles or other vehicles that are not parked in designated parking areas may be subject to removal as noted above.
4.04 Part Four is subject to Tariff Item 666 entitled Vehicles Prohibited on Docks During
Loading or Unloading
PART 5 - AUTHORIZED VEHICLES
5.01 Only the following vehicles will be permitted to drive into TWIC secure areas:
• Port Authority owned;
• Official government vehicles;
• Personal vehicles displaying a Port Authority issued decal; or
• Clearly marked contractor or vessel servicing company vehicle actively engaged in loading or unloading cargo, servicing a vessel or requiring access for some other authorized purpose.
5.02 Taxicabs and other conveyances-for-hire must display a Port Authority vehicle decal prior to being permitted access into secure areas.
5.03 For purposes of this section, “clearly marked” means company signage on the vehicle that is printed legibly, and that is of font size that would permit a reasonable person to easily read the information from at least 15’ from the side of the vehicle. Decals for personal vehicles owned by Port Authority employed personnel must be authorized by the Director of the Port department that the Port employee has been assigned to. There is no charge for decals issued to Port Authority personnel.
5.04 Registration Fee for a vehicle decal is Ten Dollars ($10.00). The fee may only be paid by cash or by a company issued check. Persons desiring a vehicle decal must present a company letterhead document that reflects the company authorization for the individual to be issued a vehicle decal. That authorization may be contained in the same company letter requesting authorization be granted for the individual(s) to enter a restricted/TWIC secure Terminal Facility. Port Security staff will require the individual to provide proof of motor vehicle liability insurance and proof of state vehicle registration, and, if applicable, state inspection, as required by the applicable laws of the State of Texas.
Failure to furnish satisfactory proof of liability insurance may result in denial of access to or upon restricted/TWIC secure Terminal Facilities.
5.05 Vehicle decals are non-transferable. Vehicle decals are valid for one year. Vehicles whose liability insurance expires within the year may obtain one renewal at no charge. Vehicle decals must be affixed to the front windshield of the authorized vehicle in a position where
SECTION 01 14 13 Page 6 of 6 it can be clearly seen. When a vehicle is sold, traded, destroyed or the owner no longer is employed or associated with the Port Authority, the decal must be removed and returned to the Port Authority Police Department.
5.06 The Port Authority may recognize vehicle access decals or “rear view mirror hangers” issued by designated Port Industries or other Texas Ports.
PART 6 - PROHIBITED ITEMS
6.01 In accordance with the Maritime Transportation Security Act of 2002 and Title 33, U.S.
Code of Federal Regulations (CFR) Part 105, the possession of firearms, ammunition, personal chemical dispensing devices, tire deflation devices, or other devices designed or adapted primarily to inflict bodily injury or serious bodily injury are prohibited within any Port of Corpus Christi Authority (PCCA) secure/restricted area, as defined in the PCCA Facility Security Plan and approved by USCG Sector Corpus Christi.
6.02 Individuals requesting access to a PCCA secure/restricted area who are in lawful possession of a firearm, or other device, will be required to secure the firearm or device in a lockable storage locker at the primary access control point to that secure/restricted area.
The firearm, or other device, shall be returned to the individual when the individual leaves the secure/restricted area.
6.03 Federal, State, and Local law enforcement officials, acting in the actual discharge of their official duties, and/or when authorized by statute, are exempt from the provisions in this Part Six.
6.04 Alcoholic Beverages, as defined by Texas Alcoholic Beverage Code, Title 1, Chapter 1, Sec. 1.04(1), are prohibited on Port property, Terminal facilities, or within Secure/restricted areas, except as provided herein;
A. Section 6.04 does not apply to vessel crewmembers provided that the
Master/Captain of the respective vessel, or their designated authorized representative has communicated authorization for crewmembers to bring alcoholic beverages aboard the respective vessel; such authorization will be provided to the Port of Corpus Christi Authority Harbormasters office, or the Port of Corpus Christi Authority Security Command Center.
B. Section 6.04 does not apply when the possession of Alcoholic Beverages has been specifically authorized by the Port of Corpus Christi Authority Executive Director, or that individual’s authorized designated representative.
6.05 Illegal drugs, narcotics, and controlled substances, as defined and as deemed unlawful by provisions Texas Health and Safety Code, and amendments thereto, are prohibited on PCCA property, Terminal facilities, or within PCCA secure/restricted areas.
SECTION 01 31 13 Page 1 of 3
SECTION 01 31 13
PROJECT COORDINATION
PART 1 – GENERAL
1.01 SUMMARY
A. This section specifies administrative and supervisory requirements necessary for project coordination including, but not necessarily limited to:
1. Coordination
2. Administrative and supervisory personnel
3. General installation provisions
B. Progress meetings, coordination meetings, and pre-installation conferences are included in Section 01 31 19 - Project Meetings.
C. Requirements for construction schedules are included in Section 01 33 00 - Submittals.
1.02 COORDINATION
A. Coordination: Coordinate construction activities (as defined in the various sections of these specifications) to assure efficient and orderly installation of each part of the work. Coordinate construction operations (as defined in the different sections of the specifications) that are dependent upon each other for proper installation, connection, and operation.
1. Where installation of one part of the work is dependent upon installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.
2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Prepare memoranda for distribution to each involved party outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings.
SECTION 01 31 13 Page 2 of 3
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progression of the work. Such administrative activities include, but are not limited to, the following:
1. Preparation of schedules
2. Installation and removal of temporary facilities
3. Delivery and processing of submittals
4. Progress meetings
5. Project closeout activities
1.03 SUBMITTALS
Within 10 days of the Notice to Proceed, the Contractor will submit a list of the Contractor’s principal staff assignments including the superintendent and other personnel in attendance at the site; provide a proposed organizational chart that identifies individuals, their duties and responsibilities; and list the proposed staff’s addresses and telephone numbers.
1.04 GENERAL INSTALLATION PROVISIONS
A. Manufacturer’s Instructions: Comply with manufacturer’s installation instructions and recommendations if those instructions and recommendations are more explicit or stringent than requirements contained in the Contract Documents.
B. Inspect materials or equipment immediately upon delivery and again prior to installation. Reject damaged and defective items.
C. Recheck measurements and dimensions before starting installation procedure.
D. Install each component during weather conditions and at the point in the project sequence that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.
E. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
1.05 CLEANING AND PROTECTION
A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration until Final Acceptance.
SECTION 01 31 13 Page 3 of 3
B. Limiting Exposures: Supervise construction activities to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Where applicable, such exposures include, but are not limited to, the following:
1. Excessive static or dynamic loading
2. Heavy traffic
3. Vibration from adjacent activity
4. Erosion
5. Damage by contact with construction equipment
PART 2 – PRODUCTS (Not Used)
SECTION 01 31 19 Page 1 of 4
SECTION 01 31 19
PROJECT MEETINGS
PART 1 – GENERAL
1.01 SUMMARY
A. This section specifies administrative and procedural requirements for project meetings including, but not limited to:
1. Pre-construction conferences
2. Pre-installation meetings
3. Coordination meetings
4. Progress meeting
B. Requirements for construction schedules are specified in Section 01 33 00 - Submittals.
1.02 PRE-CONSTRUCTION CONFERENCE
A. A pre-construction conference and organizational meeting will be scheduled by the Engineer at the Project site or other convenient location no later than 10 days after execution of the Agreement and prior to commencement of construction activities.
The meeting will be conducted to review responsibilities and personnel assignments with the Engineer and Contractor.
B. Attendees: The Engineer, Contractor, and subcontractors will each be represented at the conference by persons familiar with and authorized to conclude matters relating to the work.
C. Agenda: Discuss items of significance that could affect progress including such topics as:
1. Tentative construction schedule
2. Critical working sequencing
3. Designation of responsible personnel
4. Procedures for processing field decisions
5. Procedures for processing applications for payment
6. Distribution of Contract Documents
SECTION 01 31 19 Page 2 of 4
7. Submittal of shop drawings, product data, and samples
8. Preparation of record documents
9. Use of the premises
10. Office, work, and storage areas
11. Equipment deliveries and priorities
12. Safety procedures
13. First aid
14. Security
15. Housekeeping
16. Working hours
1.03 PRE-INSTALLATION MEETINGS
A. Pre-installation meetings may be held prior to beginning installation of critical work items. These items include:
1. Rail work
2. Traffic control plan
3. Limestone paving
4. Ditch re-grading
B. These meetings will be attended by all persons involved in the supervision, inspection, and quality control of this work. Those required to attend are as follows:
1. Engineer
2. Contractor’s project manager and superintendent
3. Subcontractor’s superintendent
4. Crew foremen
C. Agenda will include:
1. Layout, horizontal and vertical control, etc.
2. Equipment and materials required
SECTION 01 31 19 Page 3 of 4
3. Specific methods to be used for installation
4. Review of applicable specifications
1.04 COORDINATION MEETINGS
A. The Engineer reserves the right to schedule and conduct coordination meetings at his option.
B. The Contractor will conduct coordination meetings with his subcontractors; however, the Engineer will be invited to such meetings.
C. Agenda: Review and resolve operational conflicts between subcontractors, suppliers, and/or PCCA operations.
1.05 PROGRESS MEETINGS
A. The Engineer reserves the right to schedule and conduct weekly meetings at his option.
B. Agenda: Review and correct or approve minutes of the previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to the current status of the project.
C. Contractor’s Construction Schedule: Review progress since the last meeting.
Determine where each activity is in relation to the Contractor’s construction schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited and secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the contract time.
D. Review the present and future needs of each entity present including such items as:
1. Interface requirements
2. Time
3. Sequences
4. Site utilization
5. Hours of work
6. Hazards and risks
7. Housekeeping
8. Quality and work standards
SECTION 01 31 19 Page 4 of 4
9. Change orders
10. Documentation of information for payment requests
E. Schedule Updating: Revise the construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue the revised schedule concurrently with the report of each meeting.
PART 2 – PRODUCTS (Not Used)
SECTION 01 33 00 Page 1 of 4
SECTION 01 33 00
SUBMITTALS
PART 1 – GENERAL
1.01 SUMMARY
This section specifies administrative and procedural requirements for submittals requisite to the performance of the work, including:
A. Contractor’s partial payment and construction schedule
B. Submittal schedule
C. Shop drawings
D. Product data and mill certificates
1.02 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.
1. Coordinate each submittal with fabrication, purchase, testing, delivery, other submittals, and related activities that require sequential activities.
2. Processing:
a. Allow sufficient review time so that installation will not be delayed as a result of the time required to process submittals (including time for resubmittals).
b. Allow two weeks for initial review. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. The Engineer will promptly advise the Contractor when a submittal being processed must be delayed for coordination.
B. Submittal Preparation: Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.
1. Provide a space approximately 4" x 5" on the label or beside the title block on shop drawings to record the Contractor’s review and approval markings and the action taken.
2. Include the following information on the label for processing and recording action taken.
SECTION 01 33 00 Page 2 of 4
a. Project name
b. Date
c. Name of Engineer
d. Name of Contractor
e. Name of subcontractor
f. Name of supplier
g. Name of manufacturer
h. Number and title of appropriate specification section
i. Drawing number and detail references as appropriate
1.03 CONTRACTOR’S PARTIAL PAYMENT AND CONSTRUCTION SCHEDULE
Prepare a fully developed construction schedule, preferably a computer-based CPM type, but a Gantt chart at a minimum. Submit within 10 days of issuance of the Notice to Proceed.
The schedule will include the…
This is the start of the file's text. The full file is on GovTribe.