02_DWA Intake Gate Refurbishment PWS - Sources sought.docx
DOCX document 105 KB Posted
- Attached to
- DWA Intake Gate Refurbishment Federal contract opportunity
- Solicitation number
- W912EF24RSS07
About this file
This document outlines the technical specifications for refurbishing two penstock emergency gates at Dworshak Dam. The scope of work includes removing the existing coating, inspecting the gates for defects, and applying a new multi-layer coating system. Transportation of the gates from the dam to the contractor's facility and back is also required. Surface preparation must be in accordance with SSPC SP5 and coatings must meet the specifications of Army Corps of Engineers system No. 5-E-Z. Inspection reports are required along with certified inspectors. The contractor must be an SSPC QP3 certified painting contractor. Retrieval of the gates is between April and June 2024 with return by August 15, 2024. A one-year warranty on all workmanship and materials is also required.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTICE: SOURCES SOUGHT ONLY
This is not a solicitation. A formal solicitation may be posted if deemed viable at a later date and is contingent on the findings of this sources sought.
Technical specifications attached are to be informative only for the purpose of gauging market interest and potential sources.
TECHNICAL SPECIFICATIONS
DWORSHAK DAM PENSTOCK EMERGENCY GATE REFURBISHMENT
SCOPE
The following specification pertains to the transportation, inspection, and refurbishment of penstock emergency gates. The refurbishment includes existing coating removal and new coating application in accordance with the specifications below. The contractor shall perform all duties as assigned in the specification below for both penstock emergency gates.
2.0 PENSTOCK EMERGENCY GATE REFURBISHMENT– GENERAL REQUIREMENTS
· The Scope of work for this project shall not be modified without prior approval from the contracting officer. The contractor shall not deviate from the specifications listed herein without prior approval from the contracting officer.
· All work conducted in accordance with this contract shall be comply with Federal, State, and local regulations.
· The Government (GOVT) reserves the right to travel to contractor’s facility for quality assurance inspections at any point during the progression of this contract.
3.0 Penstock Emergency Gate Transportation
The critical defining elements for the transportation of the penstock emergency gates are as defined below:
· The contractor shall be responsible for transportation from Dworshak Dam to the repair facility and back to Dworshak Dam from the repair facility for the emergency gates. The contractor shall transport the emergency gates in a manner that does not damage the integrity of any structural members or the newly applied coating upon return.
· GOVT personnel will assist the contractor in loading and unloading the emergency gates at Dworshak Dam. The GOVT will load and unload the emergency gates utilizing a crane and the emergency gates will be oriented in a manner that it is in the flat, horizontal position with the skin plate facing down. The GOVT will not be responsible for the loading and unloading of the emergency gates at the contractor’s repair facility. The responsibility of loading and unloading at the contractor’s repair facility shall be borne entirely by the contractor.
· All load securement responsibility shall be borne by the contractor. The GOVT will not be responsible in any manner for load securement.
· All damage that is caused to the emergency gates by the contractor shall be repaired at the contractor’s expense. If structural or coatings damage is to occur, the repair procedure must be submitted and approved by the contracting officer before any repairs are made.
· The 19’ Diameter Penstock Emergency Gate has an approximate weight of 51000 pounds with approximate dimensions of 25 ft tall x 17 ft wide x 3 ft 6 in thick. (Please reference attached drawings DWD-1-5-19/9&10). Each 19’ Diameter Penstock Emergency gate has an estimated value of $850,000.
· The 12’ Diameter Penstock Emergency Gate has an approximate weight of 30000 pounds with approximate dimensions of 16 ft tall x 12 ft wide x 3 ft thick. (Please reference attached drawings DWD-1-5-19/4&5) Each 12’ Diameter Penstock Emergency gate has an estimated value of $500,000.
· All transportation must comply with local, state, and federal regulations. All fees and permits associated with transportation are the responsibility of the contractor.
· The emergency gates will be stripped of the roller chains, seals, and guides by Dworshak personnel before transportation.
4.0 Penstock Emergency Gate Refurbishment
The critical defining elements for the refurbishment of the penstock emergency gates are as defined below:
4.1 Existing Coatings Removal
· The existence of heavy metal-based coatings system is unknown. We are currently getting the sample tested.
· All fastener locations shall be plugged before coatings removal to protect existing threads.
· The Contractor shall dry-blast clean all surfaces to white metal in accordance with SSPC SP 5/ NACE No. 1. The blast profile must be angular with a minimum profile height of 1.5 mils. Select appropriate abrasive size and equipment operating parameters to limit maximum surface profile to 2.5 mils. Steel shot or other abrasives that do not produce an angular profile shall not be used. After blast cleaning, and before the first coat of paint, and in any case prior to the deposition of moisture, contaminants, or corrosion, clean all surfaces of dust and abrasive particles by brush, vacuum cleaner, and/or blown down with clean, dry, compressed air.
· If pinpoint or general rusting appears, the affected areas must be re-blasted and repainted at no additional cost to the government.
4.2 Inspection and Reporting
· For the 19’ Diameter Emergency Gate and the 12’ Diameter Emergency Gate, inspect one hundred (100) percent of all welds in accordance with AWS D1.1/D1.1M utilizing Visual Testing (VT) and Magnetic Particle Testing (MT) methods.
· No Inspections shall be conducted until existing coatings have been fully removed in accordance with Specification Section 4.1 Existing Coatings Removal
· All inspectors performing structural steel visual inspections must be qualified and certified in conformance with AWS CQ1. All inspectors performing (MT) inspections must be qualified in accordance with ASNT CP-189 NDT Levell II. Submit Inspector qualifications to Contracting Officer a minimum of three business days (MONDAY-FRIDAY) in advance of any inspection.
· An inspection report must be generated for each of the gates. Include in the inspection report all welded connections that have any indication of cracks, undercuts, craters, porosity, lack of fusion, missing weld, and any areas of corrosion that have removed more than approximately 25 percent of the base metal when compared to the original member thickness.
· All welded connections included in the inspection report must include a closeup picture showing the defect, a picture or drawing of the connections from a distance to be able to accurately identify its location in the structure, a verbal description of the defect and verbal description of the connection. The report shall include approximate length of defect, weld type, and approximate existing size of weld.
· The contractor shall visually inspect the entirety of the Hydraulic Steel Structure and any defects such as corrosion or cracks shall be included in the inspection reports. If corrosion is present, estimate on the report the percent of material lost in comparison to original base metal thickness.
· The inspection report shall be provided to the Contracting Officer within 5 days of the initial inspection. The GOVT may require the contractor to withhold the painting system from areas identified in the inspection report to perform repairs in these areas. In this event, the contractor will withhold coating these areas a minimum of three inches in any direction from the identified deficiency. The contractor shall allow five (5) business days (MONDAY-FRIDAY) for GOVT review of the inspection report after acknowledged receipt.
· The GOVT intends to travel to the Contractor’s facility to conduct an internal inspection of the Hydraulic Steel Structure in conjunction with other inspections. This inspection will be conducted after the existing coatings system has been completely removed. The contractor shall inform the Contracting Officer a minimum of two (2) weeks in advance of the coatings systems being removed. The GOVT will coordinate with the Contractor a maximum of 5 business days in advance of inspection. The contractor is to provide adequate means of egress and access for the internal GOVT inspection at the contractor’s facility.
4.3 Coating System
· The contractor shall utilize Army Corps of Engineers coating system No. 5-E-Z for this contract. This coating system is available from various commercial paint suppliers. See the figure below for Painting Schedule:Figure 1: Painting Schedule
· The contractor shall utilize formula VZ-108D for the first coat. The formula for the Vinyl-Type Zinc Rich Impacted Immersion coating is attached in Figure 2 below.Figure 2: Formula VZ-108D
· The contractor shall utilize formula V-766E for coats two through four (2-4). The formula for the Vinyl-Type White (Or Gray) Impacted Immersion Coating is shown in Figure 3 below.
Figure 3: Formula V-766E
4.4 Coating Application
· The painting contractor must be a certified SSPC QP 3 painting contractor for all surface preparation and coatings application. The contractor shall provide applicable SSPC certificates with the pre-award submittal package. The contractor must be certified prior to the award of this contract and must remain certified for the duration of contract work. Provide the contracting officer all renewals if they occur during the contract performance period.
· The finished coating shall be free from holidays, pinholes, bubbles, runs, drops, ridges, waves, laps, excessive or unsightly brush marks, and variations in color, texture, and gloss. Each coat of paint shall be spray applied in a manner that will produce an even, continuous film of uniform thickness.
· The contractor shall not initiate the application of the initial or subsequent coatings until the coatings inspector has verified that atmospheric conditions and surfaces to be coated are satisfactory.
· The contractor shall ensure that all paint products to be utilized under this contract are stored in accordance with the manufacturers direction and that all paints are paints are at the manufactures recommended application temperature before commencing coatings applications.
· The contractor shall allow sufficient time between successive coats to permit them to dry properly for recoating in accordance with the manufacturer’s product data.
· Apply paint by spray, unless access is limited for spray operations, to an average dry film thickness of a minimum of 7.0 mils for the completed system, with the thickness at any spot not being less than 6.0 mils. The dry film thickness of the zinc rich primer must be approximately 2.5 mils with the thickness at any spot being not less than 2.0 mils. The above specified film thickness must be attained in any event, and any extra coats needed to attain the specified thickness must be applied at no additional cost to the GOVT.
4.5 Coating Inspection
· The contractor shall provide a certified coatings inspector, either in-house or third party, who is listed as either SSPC-PCI Level 2 or NACE CIP Level 2 for all surface preparation and painting activities.
· The contractor’s inspector shall inspect, and document all work phases and operations on a daily basis while actively performing work and submit the inspection reports to the contracting officer at a minimum of once a week during the contract performance period. The inspection reports shall include at a minimum the following items:
· Inspections performed, including the area of the structure involved and the results of the inspection.
· Surface preparation operations performed, including the area of the structure involved, the mode of preparation, the kinds of solvent, abrasives or power tools employed, and whether the contract requirements were met.
· Thinning operations performed, including thinners used, batch numbers, and thinner/paint volume ratios.
· Application operations performed: Including the area of the structure involved, mode of application employed, ambient temperature, substrate temperature, dew point, relative humidity, type of paint with batch numbers, elapsed time between surface preparation and application, elapsed time for recoat, condition of the underlying coat of paint, number of coats applied, and measured dry film thickness.
4.6 Supplied Materials
· The contractor shall Provide one (1) Kit of the Formula VZ-108D that when combined has a total volume of 5 gallons. All components of the kit shall be new and unopened.
· The contractor shall provide one (1) 5-gallon container of the Formula V-766E in the gray color. The container shall be new and unopened.
· The contractor shall provide one (1) 5-gallon container of the Formula V-766E in the White color. The container shall be new and unopened.
6.0 SUBMITTALS
6.1 Pre-Award Submittals
The offeror shall submit with their quote copies of manufacturer catalog cuts, specification sheets, initial drawings, warranty information for the products offered, and contractor qualification records. Documents submitted must clearly demonstrate that the offered items meet the requirements of this specification, or the offer will be considered non-responsive. Options not pertinent to the offer should be crossed out or otherwise redacted.
6.2 Delivery Submittals – Comprehensive Reports
The Contractor shall provide one complete digital copy of a comprehensive inspection report for each gate. The reports shall include the following sections:
· Complete Weld Inspection Report
· Complete Coatings Inspection Reports
· Complete warranty information
7.0 SHIPMENT, DELIVERY, AND PRODUCT ORIENTATION
7.1 Shipment and Delivery
All items shall be retrieved from the Dworshak Project between April 1st,2024 and June 1, 2024 and returned to the Dworshak Project No later than August 15th, 2024. The Contractor shall be responsible for packing and shipping the components in a manner that will ensure undamaged and complete arrival to Dworshak Project. Retrievals and deliveries shall only be conducted during normal Dworshak Project business hours, Monday–Thursday 7:30 a.m. – 2:30 p.m., excluding federal holidays. All transportation activities shall be coordinated with the Contracting Officer a minimum of four weeks in advance.
All shipments shall be delivered to:
USACE Dworshak Project - Bruce’s Eddy Boat Launch Attn: Contract Performance Specialist 1682 A Road Ahsahka, ID 83520
8.0 WARRANTY
The painting system shall be covered by a minimum one-year warranty on all parts, labor, and workmanship from factory defects. All warranty work will be done without delivery or shipment fees (including travel or on-site work). All parts and components covered by a manufacturer’s warranty greater than one (1) year shall prevail.