Culvert Repair and Replacement Project Summary
This is a project specification document issued by the State of California for culvert repair and replacement work. The project, identified as 02-1J3504, involves the assessment and remediation of culvert infrastructure. The document outlines the scope of work required to repair existing culverts and replace those deemed beyond repair. Specific details regarding project location, quantities of culverts to be addressed, site inspection requirements, bidder conferences, submission deadlines, and contract award timelines should be detailed within the project specifications. The contract term and any provisions for renewal or additional phases would be established based on the scope complexity and funding allocation.
Pricing for the project will be determined through the competitive bidding process, with costs structured according to the itemized work breakdown provided in the specifications. Funding sources and total project budgeting information, along with any applicable set-asides for small businesses or other targeted contractors, would be specified in the procurement documents. The incumbent contractor, if applicable, and current environmental considerations affecting the work would influence project execution and timeline requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Thursday, December 10, 2026 Dated November 2, 2026
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN SHASTA COUNTY AT
VARIOUS LOCATIONS FROM 0.5 MILE WEST OF SEAMANS GULCH ROAD TO
0.1 MILE WEST OF FENDERS FERRY ROAD
In District 02 On Route 299 Under
Bid book dated November 2, 2026 Standard Specifications dated 2025
Project plans approved January 15, 2026 Standard Plans dated 2025
Identified by Contract No. 02-1J3504
02-Sha-299-41.1/55.3 Project ID 0220000061
SPECIAL NOTICES
• See sections 2 and 3 for contractors' registration requirements.
• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
• See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
• The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
• See sections 1-1.06, 1-1.07B, 2-1.23, 2-1.24, 2-1.33B(3), 5-1.13D, and 5-1.13F for “Small
Business Enterprise Participation Goal Requirement” and “Small Business and Non-Small Business Subcontractor Preferences.”
• See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.
Contract No. 02-1J3504 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
1 GENERAL
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
10 GENERAL
12 TEMPORARY TRAFFIC CONTROL
13 WATER POLLUTION CONTROL
14 ENVIRONMENTAL STEWARDSHIP
15 EXISTING FACILITIES
DIVISION III EARTHWORK AND LANDSCAPE
19 EARTHWORK
21 EROSION CONTROL
DIVISION V SURFACINGS AND PAVEMENTS
39 ASPHALT CONCRETE
DIVISION VII DRAINAGE FACILITIES
70 MISCELLANEOUS DRAINAGE FACILITIES
71 EXISTING DRAINAGE FACILITIES
DIVISION IX TRAFFIC CONTROL DEVICES
84 MARKINGS
DIVISION XI MATERIALS
90 CONCRETE
ii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
RSP A3A Abbreviations (Sheet 1 of 3)
RSP A3B Abbreviations (Sheet 2 of 3)
RSP A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
A62D Excavation and Backfill - Concrete Pipe Culverts
A62DA Excavation and Backfill - Concrete Pipe Culverts - Indirect Design Method
A62E Excavation and Backfill - Cast-In-Place Reinforced Concrete Box and Arch Culverts
A62F Excavation and Backfill - Metal and Plastic Culverts
A73B Markers
A77M1 Midwest Guardrail System - Standard Hardware
A77N1 Midwest Guardrail System - Wood Post and Wood Block Details
A77N2 Midwest Guardrail System - Steel Post and Block Details
A77N3 Midwest Guardrail System - Typical Line Post Embedment and Hinge Point Offset Details
A87B Hot Mix Asphalt Dikes
D72A CIP Drainage Inlets - Types OS, OL and GOL
D72B CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D72C CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D72D CIP Drainage Inlets - Types GT1, GT2, GT3 and GT4
D72E CIP Drainage Inlets - Types GO and GDO
D72F CIP Drainage Inlet Notes
D72G CIP Drainage Inlet Tables
D73A Precast Drainage Inlets - Types OS, OL and GOL
D73B Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D73C Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D73D Precast Drainage Inlets - Types GT1, GT2, GT3 and GT4 iii
D73E Precast Drainage Inlets - Types GO and GDO
D73F Precast Drainage Inlet Notes
D73G Precast Drainage Inlet Tables
D74 Drainage Inlet Details
D75B Concrete Pipe Inlets
D75C Pipe Inlets - Ladder and Trash Rack Details
D77A Grate Details No. 1
D77B Grate Details No. 2
D87A Corrugated Metal Pipe Downdrain Details
D89A Pipe Culvert Headwalls - Straight and "L"
D89B Pipe Culvert Headwalls - Straight and "L"
D93A Pipe Riser Connections
D94A Metal and Plastic Flared End Sections
D97A Corrugated Metal Pipe Coupling Details No. 1 - Annular Coupling Band, Bar and Strap, and Angle Connections
D97C Corrugated Metal Pipe Coupling Details No. 3 - Helical and Universal Couplers
D97D Corrugated Metal Pipe Coupling Details No. 4 - Hugger Coupling Bands
D97E Corrugated Metal Pipe Coupling Details No. 5 - Standard Joint
D97F Corrugated Metal Pipe Coupling Details No. 6 - Positive Joint
D97G Corrugated Metal Pipe Coupling Details No. 7 - Downdrain
D97H Reinforced Concrete Pipe or Non-Reinforced Concrete Pipe - Standard and Positive Joints
H1 Landscape and Erosion Control Symbols
H52 Rolled Erosion Control Product
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
T3C Temporary Barrier System (Cross Bolt)
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
T9 Traffic Control System Tables for Lane and Ramp Closures iv
RSP T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways
T17 Traffic Control System for Moving Lane Closure on Two Lane Highways
T22 Traffic Control System for Construction Work Zone Speed Limit Reduction on Two Lane Conventional Highways
T53 Temporary Water Pollution Control Details (Temporary Cover)
T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)
T58 Temporary Water Pollution Control Details (Temporary Construction Entrance)
T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)
T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
B11-47 Cable Railing
RS1 Roadside Signs - Typical Installation Details No. 1
RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2
RS4 Roadside Signs - Typical Installation Details No. 4
CANCELED STANDARD PLANS LIST
The standard plan sheets listed below are canceled and not applicable to this contract.
Plan No. Date Canceled Plan No. Date
Canceled Plan No. Date Canceled
No Canceled Standard Plans
NOTICE TO BIDDERS
Bids open Thursday, December 10, 2026
Dated November 2, 2026
General work description: Culvert repair and replacement.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN SHASTA COUNTY AT VARIOUS LOCATIONS FROM 0.5 MILE WEST OF
SEAMANS GULCH ROAD TO 0.1 MILE WEST OF FENDERS FERRY ROAD.
District-County-Route-Post Mile: 02-Sha-299-41.1/55.3
Contract No. 02-1J3504
The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-42.
The DVBE Contract goal is 3 percent.
The SBE Contract goal is 5 percent.
Bids must be on a cost+time basis.
Complete the work within the number of working days bid.
Do not bid less than 55 working days and not more than 70 working days.
The estimated cost of the project is $3,580,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq., the Department gives preference to certified small businesses and non–small businesses who commit to 25 percent certified small business participation.
Under Pub Cont Code § 6107, the Department gives preference to a "California company," as defined, for bid comparison purposes over a nonresident contractor from any state that gives or requires a preference to be given to contractors from that state on its public entity construction contracts.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 090105 TIME-RELATED OVERHEAD (LS) LS LUMP SUM
0003 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0004 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0005 010413 PORTABLE RADAR SPEED FEEDBACK SIGN
SYSTEMS (LS)
LS LUMP SUM
0006 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM
0007 013357 AUTOMATED FLAGGER ASSISTANCE DEVICE LS LUMP SUM
0008 130100 JOB SITE MANAGEMENT LS LUMP SUM
0009 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM
0010 130312 PRE-STORM EVENT INSPECTION REPORT EA 10
0011 130323 DURING-AND POST-STORM EVENT INSPECTION
REPORT
DAY 10
0012 130331 STORMWATER ANNUAL REPORT EA 1
0013 130530 TEMPORARY HYDRAULIC MULCH (BONDED
FIBER MATRIX)
SQYD 5,000
0014 130570 TEMPORARY COVER SQYD 250
0015 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 37
0016 130640 TEMPORARY FIBER ROLL LF 200
0017 130710 TEMPORARY CONSTRUCTION ENTRANCE EA 2
0018 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0019 131103 WATER QUALITY SAMPLING AND ANALYSIS DAY EA 10
0020 131104 WATER QUALITY MONITORING REPORT EA 10
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 131105 WATER QUALITY ANNUAL REPORT EA 1
0022 146002 CONTRACTOR-SUPPLIED BIOLOGIST (LS) LS LUMP SUM
0023 160110 TEMPORARY HIGH-VISIBILITY FENCE LF 220
0024 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM
0025 190101 ROADWAY EXCAVATION CY 770
0026 194001 DITCH EXCAVATION CY 15
0027 198010 IMPORTED BORROW (CY) CY 84
0028 210212 DRY SEED (SQFT) SQFT 13,200
0029 210252 BONDED FIBER MATRIX (SQFT) SQFT 13,900
0030 210280 ROLLED EROSION CONTROL PRODUCT
(BLANKET)
SQFT 13,200
0031 260203 CLASS 2 AGGREGATE BASE (CY) CY 350
0032 390132 HOT MIX ASPHALT (TYPE A) TON 90
0033 394073 PLACE HOT MIX ASPHALT DIKE (TYPE A) LF 170
0034 394090 PLACE HOT MIX ASPHALT (MISCELLANEOUS
AREA)
SQYD 250
0035 510092 (F) - STRUCTURAL CONCRETE, HEADWALL CY 58
0036 510094 (F) - STRUCTURAL CONCRETE, DRAINAGE
INLET
CY 36
0037 610300 (F) - CONCRETE BACKFILL (PIPE TRENCH) CY 63
0038 665012 12" CORRUGATED STEEL PIPE (.079" THICK) LF 22
0039 665018 18" CORRUGATED STEEL PIPE (.109" THICK) LF 24
0040 665025 24" CORRUGATED STEEL PIPE (.138" THICK) LF 1,080
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0041 665033 30" CORRUGATED STEEL PIPE (.138" THICK) LF 77
0042 665038 36" CORRUGATED STEEL PIPE (.138" THICK) LF 160
0043 665043 42" CORRUGATED STEEL PIPE (.138" THICK) LF 23
0044 665048 48" CORRUGATED STEEL PIPE (.138" THICK) LF 48
0045 667025 42" X 29" CORRUGATED STEEL PIPE ARCH (.138"
THICK)
LF 180
0046 667030 49" X 33" CORRUGATED STEEL PIPE ARCH (.138"
THICK)
LF 68
0047 690124 24" CORRUGATED STEEL PIPE DOWNDRAIN
(.109" THICK)
LF 84
0048 692309 24" ANCHOR ASSEMBLY EA 11
0049 703240 36" CORRUGATED STEEL PIPE RISER (.138"
THICK)
LF 2.4
0050 016831 48" WELDED STEEL PIPE (.750" THICK)
(TRENCHLESS)
LF 210
0051 705015 24" STEEL FLARED END SECTION EA 2
0052 705019 30" STEEL FLARED END SECTION EA 1
0053 705411 42" X 29" STEEL FLARED END PIPE ARCH
SECTION
EA 2
0054 705413 49" X 33" STEEL FLARED END PIPE ARCH
SECTION
EA 1
0055 707117 36" PRECAST CONCRETE PIPE INLET LF 18
0056 710102 ABANDON CULVERT (LF) LF 570
0057 710132 REMOVE CULVERT (LF) LF 1,330
0058 710150 REMOVE INLET EA 14
0059 710152 REMOVE HEADWALL EA 13
0060 710167 REMOVE FLARED END SECTION (EA) EA 4
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0061 710360 CLEANING, INSPECTING, AND PREPARING
CULVERT (LF)
LF 180
0062 710370 SAND BACKFILL CY 41
0063 710380 18" CURED-IN-PLACE PIPELINER LF 91
0064 710384 24" CURED-IN-PLACE PIPELINER LF 89
0065 723070 ROCK SLOPE PROTECTION (150 LB, CLASS III,
METHOD B) (CY)
CY 23
0066 729011 ROCK SLOPE PROTECTION FABRIC (CLASS 8) SQYD 58
0067 750001 (F) - MISCELLANEOUS IRON AND STEEL LB 9,698
0068 820112 MARKER (CULVERT) EA 74
0069 839521 (F) - CABLE RAILING LF 133
0070 839765 RECONSTRUCT GUARDRAIL LF 50
0071 870009 MAINTAINING EXISTING TRAFFIC MANAGEMENT
SYSTEM ELEMENTS DURING CONSTRUCTION
LS LUMP SUM
0072 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to section 1-1.01:
Bid Items and Applicable Sections Item code
Item description Applicable section
010413 PORTABLE RADAR SPEED FEEDBACK SIGN SYSTEMS (LS) 12
013357 AUTOMATED FLAGGER ASSISTANCE DEVICE 12
016831 48" WELDED STEEL PIPE (.750" THICK) (TRENCHLESS) 70
Add to the table in the 1st paragraph of section 1-1.06:
SBE Small Business Enterprise
Add to section 1-1.07B:
small business enterprise: Small business or small business for the purpose of public works, as certified by the Department of General Services, Office of Small Business and DVBE Services, and as defined in Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.
Add to section 1-1.09:
This project is in a freeze-thaw area.
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information Means Description
Included in the Information Handout 1. PLAC - United States Army Corps of Engineers, Sacramento District, Non-Reporting Nationwide Permit No.14, dated February 25, 2022
2. PLAC - California Regional Water Quality Control Board, Central Valley Region, Water Quality Certification, Board Order No. 2003-0017-DWQ, WDID No. 5A45CR00675, dated September 24,
3. PLAC - California Department of Fish and Wildlife, Northern Region, 1602 Streambed Alteration Agreement, No. EPIMS-SHA-57864-R1, dated November 17, 2025
4. Geotechnical Design Report for Diddy Roost Culverts Drainage Rehabilitation Project, dated June 23, 2025
5. Department of Industrial Relations, Division of Occupational Safety and Health, Mining and Tunneling Unit, Project: 26009 - Diddy Roost Culverts, Shasta County, Classification: Potentially Gassy with Special Conditions
6. California Department of Fish and Wildlife Aquatic Invasive Species Decontamination Protocol
7. TMS Element Operational Status Certified List
8. DOT OCR-0003 Final Report - Utilization of Small
Business Enterprises (NEW 04/2024) Available as specified in the Standard Specifications
1. Alignments and profiles in LandXML format
Replace section 2-1.23 with:
2-1.23 SMALL BUSINESS ENTERPRISE PARTICIPATION GOAL REQUIREMENT
2-1.23A General Section 2-1.23 applies if an SBE participation goal requirement is shown on the Notice to Bidders.
The SBE participation goal requirement is in addition to any DVBE goal shown on the Notice to Bidders and the DVBE requirements in section 2-1.22.
Make work available to SBEs and select work parts consistent with the available SBEs, including subcontractors, suppliers, service providers, and truckers.
Meet the SBE participation goal requirement shown on the Notice to Bidders. A bid that demonstrates an SBE participation commitment less than the SBE participation goal requirement is nonresponsive.
Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
The Department of General Services determines whether an SBE was certified on the bid opening date.
The Department of Transportation confirms an SBE’s certification status.
2-1.23B SBE Submittals Submit SBE information under section 2-1.33.
For the SBE participation goal requirement, submit the following:
1. Completed Small Business Enterprise – Commitment form. Failure to submit the completed form by 4 p.m. on the 4th business day after bid opening may result in a nonresponsive bid.
2. Copy of the quote for each SBE shown on the Small Business Enterprise – Commitment form that describes the type and dollar amount of work shown on the form. Quotes are not required for work that will be completed by SBE prime bidders. Failure to submit a copy of the quote for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.
3. Completed Small Business Enterprise – Confirmation form from each SBE listed on the Commitment form. The form for each SBE is required to establish that the SBE will be participating in the Contract for the type and dollar amount of work shown on the form. Failure to submit completed Confirmation forms for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.
4. If an SBE is participating as a joint venture partner, submit a copy of the joint venture agreement.
The Department may contact you and SBEs to clarify quotes and supporting documentation.
If you elect, at time of bid, to pursue the optional small business or non-small business preference, see section 2-1.24 for the requirements arising from your request for the preference. SBE participation listed to meet the SBE participation goal requirement should not be listed for the preference.
Replace section 2-1.24 with:
2-1.24 SMALL BUSINESS AND NON–SMALL BUSINESS SUBCONTRACTOR PREFERENCES
2-1.24A General Section 2-1.24 applies to a non-federal-aid contract.
The Department applies small business preferences and non–small business preferences under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.
Any contractor, subcontractor, supplier, or service provider who qualifies as a small business or small business for the purpose of public works is encouraged to apply for certification as an SBE by submitting its application to the Department of General Services, Office of Small Business and DVBE Services.
The Department of General Services determines whether an SBE was certified on the bid opening date.
The Department of Transportation confirms an SBE’s certification status before applying the small business or non-small business preference.
Contract award is based on the total bid, not the reduced bid.
Pursuant to Govt Code § 14838, SBE participation listed on the Small Business Enterprise – Commitment form used to meet the SBE participation goal requirement should not be listed on the Certified Small Business Listing for the Non-Small Business Preference form. Listing the same SBE participation on both the Small Business Enterprise – Commitment form and on the Certified Small Business Listing for the Non-Small Business Preference form may result in disallowance of the SBE’s participation toward the small business or non-small business preference.
2-1.24B Small Business Preference The Department allows a bidder certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, a preference if:
1. Bidder submitted a completed Request for Small Business Preference or Non–Small Business Preference form with its bid
2. Low bidder did not request the preference or is not certified as a small business
The Bidder's signature on the Request for Small Business Preference or Non–Small Business Preference form certifies that the Bidder is certified as an SBE at the date and time of bid or has submitted a complete application to the Department of General Services. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
The small business preference is a reduction for bid comparison in the total bid submitted by the small business contractor by the lesser of the following amounts:
1. 5 percent of the verified total bid of the low bidder
2. $50,000
If the Department determines that a certified small business bidder is the low bidder after the application of the small business preference, the Department does not consider a request for non–small business preference.
2-1.24C Non–Small Business Subcontractor Preference At time of bid, the Department allows a bidder not certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, the option of requesting the non-small business subcontractor preference. If a bidder elects to pursue that option at the time of bid, the bidder is required to meet the corresponding commitment.
For the non-small business subcontractor preference, submit the following:
1. Completed Request for Small Business Preference or Non–Small Business Preference form with your bid
2. Completed Certified Small Business Listing for the Non–Small Business Preference form which shows you are subcontracting at least 25 percent to certified SBEs
Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
Failure to submit a completed Certified Small Business Listing for the Non–Small Business Preference form by 4 p.m. on the 4th business day after bid opening will result in a nonresponsive bid.
The non–small business subcontractor preference is a reduction for bid comparison in the total bid submitted by the non–small business contractor requesting the preference by the lesser of the following amounts:
1. 5 percent of the verified total bid of the low bidder
2. $50,000
Replace the table in the 1st paragraph of section 2-1.33B(3)(b)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract with a DVBE Goal
Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa Time of bid
Certified DVBE Summary No later than 4 p.m. on the 4th business day after bid opening
California Company Preference Time of bid
Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
Replace the table in the 1st paragraph of section 2-1.33B(3)(c)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract without a DVBE Goal
Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa Time of bid
California Company Preference Time of bid
Certified DVBE Summaryb No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
bSubmit only if you obtain DVBE participation or you are the apparent low bidder, 2nd low bidder, or 3rd low bidder and you choose to receive the specified incentive.
5 CONTROL OF WORK
Replace the 2nd and 3rd paragraphs of section 5-1.09A with:
Professionally facilitated project partnering is required.
Replace section 5-1.13D with:
5-1.13D Non-Small Business Preference 5-1.13D(1) General Section 5-1.13D applies to a non-federal-aid contract when you have obtained a non-small business subcontractor preference under section 2-1.24.
Use each SBE as shown on the Certified Small Business Listing for the Non-Small Business Preference form unless you receive authorization for a substitution under section 5-1.13D(3).
Maintain records of subcontracts and agreements made with each SBE. Include in the records:
1. SBE subcontract or agreement
2. Name and business address of each business
3. Proof of each payment made to an SBE
Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:
1. Interviewing employees.
2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.
Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.
5-1.13D(2) Commercially Useful Function SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Certified Small Business Listing for the Non-Small Business Preference form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the non-small business preference if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.
Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.
Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:
1. Subcontract or agreement with the SBE
2. Purchase orders
3. Bills of lading
4. Invoices
5. Proof of payment
You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:
1. Proof of ownership or lease and rental agreements for equipment
2. Tax records
3. Employee rosters
4. Certified payroll records
5. Inventory rosters
Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.
Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
5-1.13D(3) Substitutions Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.
The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.
Include in your substitution request:
1. Copy of the written notice issued to the SBE with proof of delivery
2. Copy of the SBE response to the notice
3. Your explanation of the reason for the substitution request
4. Names and certification numbers of the listed SBE and the proposed substitute SBE
5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform
6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that non-small business preference portion of the Contract will be fulfilled
Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.
If the Department authorizes your SBE substitution request, it will do so in writing.
Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
Replace section 5-1.13E with:
5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Replace section 5-1.13F with:
5-1.13F Small Business Enterprise Participation Goal Requirement 5-1.13F(1) General Section 5-1.13F applies to a non-federal-aid contract if an SBE participation goal requirement is shown on the Notice to Bidders.
Use each SBE as shown on the Small Business Enterprise – Commitment form unless you receive authorization for a substitution under section 5-1.13F(3).
Maintain records of subcontracts and agreements made with each SBE. Include in the records:
1. SBE subcontract or agreement
2. Name and business address of each business
3. Proof of each payment made to an SBE
Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:
1. Interviewing employees.
2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.
Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.
5-1.13F(2) Commercially Useful Function SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Small Business Enterprise – Commitment form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the SBE participation goal requirement if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.
Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.
Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:
1. Subcontract or agreement with the SBE
2. Purchase orders
3. Bills of lading
4. Invoices
5. Proof of payment
You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:
1. Proof of ownership or lease and rental agreements for equipment
2. Tax records
3. Employee rosters
4. Certified payroll records
5. Inventory rosters
Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.
Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
5-1.13F(3) Substitutions Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.
The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.
Include in your substitution request:
1. Copy of the written notice issued to the SBE with proof of delivery
2. Copy of the SBE response to the notice
3. Your explanation of the reason for the substitution request
4. Names and certification numbers of the listed SBE and the proposed substitute SBE
5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform
6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that SBE participation goal requirement portion of the Contract will be fulfilled
Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.
If the Department authorizes your SBE substitution request, it will do so in writing.
Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
Add to the end of section 5-1.20A:
During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:
Coincident or Adjacent Contracts
Contract no. County–Route–Post Mile Location Type of work 02-0J71U4 SHA-299-57.5/59.0 Shasta County near
Montgomery Creek Asphalt Concrete Overlay
Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.
Add to the end of section 5-1.20B(1):
The Department will communicate with PLAC agencies unless communication between you and the PLAC agency is authorized.
Add to the end of section 5-1.32:
Personal vehicles of your employees must not be parked on the traveled way or shoulders, including sections closed to traffic.
Temporary parking of vehicles, and storage of equipment and materials is not allowed on vegetated areas.
Replace section 5-1.36C(2) with:
5-1.36C(2) Nonhighway Facility Protection The utilities shown in the following table may interfere with the work and must be exposed or protected in place. Make arrangements with the utility owner (1) to conduct or witness all exposures or (2) to request temporary deactivation of the utility.
Utilities to Be Exposed and/or Protected in Place During Construction Utility Location
Sprint Cogent Fiber Optic 2" Conduit PM 42.39 Sprint Cogent Fiber Optic 2" Conduit PM 44.97 Sprint Cogent Fiber Optic 2" Conduit PM 46.25 Frontier Telecom 2" Conduit PM 46.34 Frontier Telecom 2" Conduit PM 46.41 Frontier Telecom 2" Conduit PM 48.71 Frontier Telecom 2" Conduit PM 48.98 Sprint Cogent Fiber Optic 2" Conduit PM 49.15 Sprint Cogent Fiber Optic 2" Conduit PM 49.24 Sprint Cogent Fiber Optic 2" Conduit PM 49.63 Sprint Cogent Fiber Optic 2" Conduit PM 52.02 PG&E Fiber Optic 2" Conduit Zayo Telecom 2" Conduit
PM 52.20
6 CONTROL OF MATERIALS
Replace section 6-1.03B with:
6-1.03B Submittals 6-1.03B(1) General Not Used
6-1.03B(2) Work Plan For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:
1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the
Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).
2. Land use history of the local material location and surrounding property
3. Sampling protocol
4. Number of samples per volume of local material
5. QA and QC requirements and procedures
6. Qualifications of sampling personnel
7. Stockpile history
8. Name and address of the analytical laboratory that will perform the chemical analyses
9. Analyses that will be performed for lead and pH
10. Other analyses that will be performed for possible hazardous constituents based on:
10.1. Source property history
10.2. Land use adjacent to source property
10.3. Constituents of concern in the ground water basin where the job site is located
The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.
If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.
6-1.03B(3) Analytical Test Results At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:
1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.
2. Chain of custody of samples
3. Analytical results no older than 1 year
4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit
5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location
6-1.03B(4) Sample and Analysis Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:
1. Before bringing the local material to the job site
2. As described in the local material plan
3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)
The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.
Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:
Minimum Number of Samples and Analytical Tests for Local Material Maximum volume of imported borrow
(cu yd) Minimum number of samples and analytical tests
< 5,000 8
5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof
10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof
20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof
40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof
> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof
Do not collect composite samples or mix individual samples to form a composite sample.
Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).
The analytical test results must demonstrate that the local material:
1. Is not a hazardous waste
2. Has a pH above 5.0
3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg
4. Is free of possible contaminants identified in the local material plan
5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location
6-1.03C Local Material Management Do not place local material until authorized.
If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).
Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.
Add to section 6-1:
6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE
Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.
See section 6-1.06B for definitions.
For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:
Material or product Material specifications Hot mix asphalta Section 39-2, "Hot Mix Asphalt"
Excludes RHMA, OGFC, and BWC materials.
Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid
Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."
Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.
aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.
bFor each concrete plant providing 250 cubic yards or more on the project by mix design.
The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.
The requirements in section 6-1.08 do not apply to informal-bid contracts.
For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:
1. Applicable product category rule has expired without replacement as of the bid opening date.
2. Applicable product category rule was issued less than 50 days before the bid opening date.
Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer.