02-0J81U4 RHMA_ Concrete Barrier_ and Corrugated Steel Pipe Culvert.pdf

PDF 1 MB Posted

Attached to
02-0J81U4 RHMA, Concrete Barrier, and Corrugated Steel Pipe Culvert
Solicitation number
02-0J81U4, Fed #NH-0058(647)
Issued by
Shasta County, California

About this file

This Notice to Bidders and Special Provisions document is issued by the California Department of Transportation (Caltrans) for construction work on State Highway 5 in Shasta and Siskiyou Counties near Dunsmuir. The project involves RHMA (hot mix asphalt), concrete barrier installation, and corrugated steel pipe culvert work, extending from 0.6 mile north of Sims Road Undercrossing to 0.2 mile south of Siskiyou Avenue Overcrossing. Bids are scheduled to open on Thursday, January 7, 2027, with the contract identified as 02-0J81U4 under Project ID 0226000122, a Federal-Aid Project (NH-0058(647)). The bid book is dated November 9, 2026, with project plans approved on June 17, 2026. The document references 2025 Standard Specifications and Standard Plans, and includes detailed bid item listings and special provisions for construction management.

The special provisions address multiple regulatory and operational requirements including contractors' registration, potential claim submissions via the Department's Internet system, DVBE quotes and Non-Small Business Subcontractor Preference submissions, diesel-fueled vehicle compliance documentation, Buy America/Build America requirements for manufactured products, environmental product declarations for materials, certified payroll record submissions using LCPtracker Pro, and revised flagging and temporary traffic control requirements. The document contains extensive standard plans for various construction elements including concrete barriers (Types 60K, 60M, 60MP, 60MC, 60MS, 60MG, 60MGF), drainage facilities, guardrail systems, traffic control systems, and erosion control measures. Additional provisions address water pollution control, environmental stewardship, earthwork, dust palliatives, erosion control, asphalt concrete work, concrete structures, reinforcement, electrical work, and traffic control devices. No specific pricing, award date, or contract term information is provided in this notice document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bids open Thursday, January 7, 2027 Dated November 9, 2026 OSD

STATE OF CALIFORNIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

AND

SPECIAL PROVISIONS

FOR CONSTRUCTION ON STATE HIGHWAY IN SHASTA AND SISKIYOU

COUNTIES AT AND NEAR DUNSMUIR FROM 0.6 MILE NORTH OF SIMS ROAD

UNDERCROSSING TO 0.2 MILE SOUTH OF SISKIYOU AVENUE

OVERCROSSING

In District 02 On Route 5

Under Bid book dated November 9, 2026 Standard Specifications dated 2025

Project plans approved June 17, 2026 Standard Plans dated 2025

Identified by Contract No. 02-0J81U4

02-Sha,Sis-5-58.0/67.0,0.0/2.7 Project ID 0226000122

Federal-Aid Project

NH-0058(647)

SPECIAL NOTICES

• See sections 2 and 3 for contractors' registration requirements.

• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.

• See section 2 for submittal requirements for DVBE quotes and Non–Small Business

Subcontractor Preference.

• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.

• See section 6-1.01 and 6-1.04 of these Special Provisions for the requirements of Buy

America/Build America for manufactured products.

• See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.

• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).

• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.

• The flagging and temporary traffic control requirements have been revised. See sections 7-

1.03, 7-1.04, and 12.

• See section 14-11.14 for changes to the management of treated wood waste.

Contract No. 02-0J81U4 i

TABLE OF CONTENTS

NOTICE TO BIDDERS

BID ITEM LIST

SPECIAL PROVISIONS

ORGANIZATION

DIVISION I GENERAL PROVISIONS

1 GENERAL

2 BIDDING

5 CONTROL OF WORK

6 CONTROL OF MATERIALS

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

8 PROSECUTION AND PROGRESS

9 PAYMENT

DIVISION II GENERAL CONSTRUCTION

10 GENERAL

11 WELDING

12 TEMPORARY TRAFFIC CONTROL

13 WATER POLLUTION CONTROL

14 ENVIRONMENTAL STEWARDSHIP

15 EXISTING FACILITIES

DIVISION III EARTHWORK AND LANDSCAPE

18 DUST PALLIATIVES

19 EARTHWORK

21 EROSION CONTROL

DIVISION V SURFACINGS AND PAVEMENTS

36 GENERAL

39 ASPHALT CONCRETE

DIVISION VI STRUCTURES

51 CONCRETE STRUCTURES

52 REINFORCEMENT

56 OVERHEAD SIGN STRUCTURES, STANDARDS, AND POLES

60 EXISTING STRUCTURES

DIVISION VII DRAINAGE FACILITIES

71 EXISTING DRAINAGE FACILITIES

DIVISION VIII MISCELLANEOUS CONSTRUCTION

80 FENCES

DIVISION IX TRAFFIC CONTROL DEVICES

83 RAILINGS AND BARRIERS

ii

84 MARKINGS

DIVISION X ELECTRICAL WORK

86 GENERAL

87 ELECTRICAL SYSTEMS

DIVISION XI MATERIALS

90 CONCRETE

iii

STANDARD PLANS LIST

The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.

RSP A3A Abbreviations (Sheet 1 of 3)

RSP A3B Abbreviations (Sheet 2 of 3)

RSP A3C Abbreviations (Sheet 3 of 3)

A10A Legend - Lines and Symbols (Sheet 1 of 5)

A10B Legend - Lines and Symbols (Sheet 2 of 5)

A10C Legend - Lines and Symbols (Sheet 3 of 5)

A10D Legend - Lines and Symbols (Sheet 4 of 5)

A10E Legend - Lines and Symbols (Sheet 5 of 5)

A20A Pavement Markers and Traffic Lines - Typical Details

A20B Pavement Markers and Traffic Lines - Typical Details

A20C Pavement Markers and Traffic Lines - Typical Details

A20D Pavement Markers and Traffic Lines - Typical Details

A20E Traffic Lines - Typical Details for Contrast Striping

A20F Pavement Markers and Traffic Lines - Typical Details

A20G Exit Ramp with Enhanced Pavement Markers for Wrong Way Details

A24A Pavement Markings - Arrows

A24B Pavement Markings - Arrows and Symbols

A24C Pavement Markings - Symbols and Numerals

A24D Pavement Markings - Words

A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details

A40B Shoulder Rumble Strip Details - Ground-In Indentations

A40E Rumble Strip Placement at Freeway Exit Ramps, Freeway Entrance Ramps, and Intersections

A40J Combined Recessed Traffic Stripe and Rumble Strip Details

A40K Rumble Strip Placement for Paved Medians

A62A Excavation and Backfill - Miscellaneous Details

A62C Limits of Payment for Excavation and Backfill - Bridge

A62F Excavation and Backfill - Metal and Plastic Culverts

A62G Excavation and Backfill - Precast Reinforced Concrete Box Culvert

A63A Portable Concrete Barrier (Type 60K)

A63B Portable Concrete Barrier (Type 60K)

A73A Object Markers iv

A73B Markers

A73C Delineators, Channelizers and Barricades

RSP A76A Concrete Barrier Type 60M

RSP A76AB Concrete Barrier Type 60M Details

A76AC Concrete Barrier Type 60M Transition to Concrete Barrier Type 50

RSP A76BA Concrete Barrier Type 60MP

A76BM Concrete Barrier Type 60M with Small Pole

A76BO Concrete Barrier Types 60M and 60MS with Small Pole Transition Details

A76BP Concrete Barrier Type 60MC with Small Pole

A76BR Concrete Barrier Types 60MC and 60MSC with Small Pole Transition Details

A76D Concrete Barrier Type 60MG

A76E Concrete Barrier Type 60MG

A76F Concrete Barrier Type 60MGF

A76G Concrete Barrier Type 60MS

A76HB Concrete Barrier Type 60MS to Transition Railing (Type AGT)

A76K Concrete Barrier - Wildlife Passageway (Type MM)

A77N5 Minor Concrete Vegetation Control - Guardrail System

A77N5A Minor Concrete Vegetation Control - Guardrail System - Narrow Vegetation Control Installation

A77N6 Minor Concrete Vegetation Control - Guardrail System for Terminal System End Treatments

A77N7 Minor Concrete Vegetation Control - Guardrail System at Structure Approach

A77P1 Midwest Guardrail System - Typical Layouts for Embankments

A77P2 Midwest Guardrail System - Typical Layouts for Embankments

A77P3 Midwest Guardrail System - Typical Layouts for Embankments

A77P4 Midwest Guardrail System - Typical Layouts for Embankments

A77P5 Midwest Guardrail System - Typical Layouts for Embankments

A77P6 Midwest Guardrail System - Typical Layouts for Embankments

RSP A77Q1 Midwest Guardrail System - Typical Layouts for Structure Approach

A77Q3 Midwest Guardrail System - Typical Layouts for Structure Approach

A77Q4 Midwest Guardrail System - Typical Layouts for Structure Departure

A77Q5 Midwest Guardrail System - Typical Layouts for Structure Departure

RSP A77S1 Midwest Guardrail System - End Anchor Assembly (Type SFT - M)

A77S2 Midwest Guardrail System - Rail Tensioning Assembly

A77S3 Metal Railing Anchor Cable and Anchor Plate Details

A77T1 Metal Railing End Anchor Assembly (Type CA) v

A77T2 Midwest Guardrail System - Buried Post End Anchor (Type B-F)

A77T3 Midwest Guardrail System - Buried Post End Anchor (Type B-S)

RSP A79A1 Transition Railing (Type AGT)

A79A3 Transition Railing (Type AGT) Details

A79B1 Transition Railing (Type AGT) to Bridge Railings without Sidewalks

A87B Hot Mix Asphalt Dikes

D71 Drainage Inlet Markers

D72E CIP Drainage Inlets - Types GO and GDO

D72F CIP Drainage Inlet Notes

D72G CIP Drainage Inlet Tables

D73B Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6

D73C Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6

D73E Precast Drainage Inlets - Types GO and GDO

D73F Precast Drainage Inlet Notes

D73G Precast Drainage Inlet Tables

D74 Drainage Inlet Details

D75A Steel Pipe Inlets

D75B Concrete Pipe Inlets

D75C Pipe Inlets - Ladder and Trash Rack Details

D77A Grate Details No. 1

D77B Grate Details No. 2

D78C Inlet Depressions - Hot Mix Asphalt Shoulders

D83A Precast Reinforced Concrete Box Culvert

D83B Precast Reinforced Concrete Box Culvert - Miscellaneous Details

D84 Box Culvert Wingwalls - Types A, B and C

D87A Corrugated Metal Pipe Downdrain Details

D87C Cable Anchorage System

D87D Overside Drains

D89A Pipe Culvert Headwalls - Straight and "L"

D89B Pipe Culvert Headwalls - Straight and "L"

D94A Metal and Plastic Flared End Sections

D97A Corrugated Metal Pipe Coupling Details No. 1 - Annular Coupling Band, Bar and Strap, and Angle Connections

D97C Corrugated Metal Pipe Coupling Details No. 3 - Helical and Universal Couplers

D97D Corrugated Metal Pipe Coupling Details No. 4 - Hugger Coupling Bands vi

D97E Corrugated Metal Pipe Coupling Details No. 5 - Standard Joint

D97F Corrugated Metal Pipe Coupling Details No. 6 - Positive Joint

D97G Corrugated Metal Pipe Coupling Details No. 7 - Downdrain

D97I Corrugated Polyvinyl Chloride Pipe with Smooth Interior - Standard and Positive Joints

D98A Slotted Corrugated Steel Pipe Drain Details

D98B Slotted Corrugated Steel Pipe Drain Details

D98D Slotted Plastic Pipe Drain Details

D98F Slotted Pipe Grate Extension Details

D98G Grated Line Drain Details No. 1 - Polymer Concrete, 4" Nominal Width

RSP D98J Grated Line Drain Details No. 4 - Connection to Existing Drainage Structure

H52 Rolled Erosion Control Product

T1A Temporary Crash Cushion - Sand Filled (Unidirectional)

T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)

T1B Temporary Crash Cushion - Sand Filled (Bidirectional)

T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)

T3C Temporary Barrier System (Cross Bolt)

T3D Temporary Barrier System (Cross Bolt)

T3E Temporary Barrier System (Cross Bolt)

T3F Temporary Barrier System (Cal F-23)

T3F2 Temporary Barrier System (Cal F-23)

T3G Temporary Barrier System (Staking or Anchoring)

T3G2 Temporary Barrier System (Staking or Anchoring)

T4 Temporary Traffic Screen

T4A Temporary Traffic Screen (Cross Bolt)

T4B Temporary Traffic Screen (Cal F-23)

T9 Traffic Control System Tables for Lane and Ramp Closures

T10 Traffic Control System for Lane Closure on Freeways and Expressways

T10A Traffic Control System for Lane Closure on Freeways and Expressways

T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional Highways and Expressways

RSP T12 Traffic Control System for Half Road Closure on Multilane Conventional Highways and Expressways

RSP T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways

RSP T13B Traffic Control System - Two Lane Conventional Highways

RSP T13C Traffic Control System - Two Lane Conventional Highways

T14 Traffic Control System for Ramp Closure vii

T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on Freeways and Expressways

RSP T24 Mobile Barrier System

RSP T25 Mobile Barrier System

T26 Temporary Automated End of Queue Warning System Type 1 (Queue <= 3.5 Miles)

T27 Temporary Automated End of Queue Warning System Type 2 (Queue <= 7.5 Miles)

T51 Temporary Water Pollution Control Details (Temporary Silt Fence)

T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)

T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)

T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

B0-5 Bridge Details

B6-21 Joint Seals (Maximum Movement Range = 2")

B7-8 Deck Drainage Details

B9-2 Structure Approach - Type R (30)

B11-47 Cable Railing

B11-81 Concrete Barrier Type 842 Details No. 1

RSP B11-82 Concrete Barrier Type 842 Details No. 2

B11-82A Concrete Barrier Type 842 Details No. 3

RS1 Roadside Signs - Typical Installation Details No. 1

RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2

RS4 Roadside Signs - Typical Installation Details No. 4

S82 Roadside Laminated Sign - Single or Multiple Panel (Type B, 1" Thick)

S83 Roadside Laminated Sign - Single or Multiple Panel (Type B, 2-1/2" Thick)

S86 Laminated Panel Details (Extrusions for Type A, B, and H Panels)

S89 Roadside Sign - Formed Single Sheet Aluminum Panel

S93 Framing Details for Framed Single Sheet Aluminum Signs, Rectangular Shape

S94 Roadside Framed Single Sheet Aluminum Signs, Rectangular Shape

S95 Roadside Single Sheet Aluminum Signs, Diamond Shape

ES-1A Electrical Systems (Legend)

ES-1B Electrical Systems (Legend)

ES-1C Electrical Systems (Legend)

ES-2D Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - A Series) viii

ES-5A Electrical Systems (Loop Detectors)

ES-5B Electrical Systems (Detectors)

ES-5D Electrical Systems (Curb and Shoulder Termination, Trench, and Handhole Details)

ES-6E Electrical Systems (Lighting Standard, Types 30 and 31)

ES-6F Electrical Systems (Lighting Standard, Slip Base Plate)

ES-7M Electrical Systems (Signal and Lighting Standard, Details No. 1)

ES-7N Electrical Systems (Signal and Lighting Standard, Details No. 2)

RSP ES-7O Electrical Systems (Signal and Lighting Standard, Details No. 3)

ES-8A Electrical Systems (Non-Traffic Pull Box)

ES-8B Electrical Systems (Traffic Pull Box)

ES-9A Electrical Systems (Structure Pull Box Installations)

ES-9C Electrical Systems (Structure Pull Box)

ES-9D Electrical Systems (Structure Pull Box Installations)

ES-11 Electrical Systems (Foundation Installations)

ES-13A Electrical Systems (Splice Insulation Methods Details)

ES-13B Electrical Systems (Kinking and Banding Detail)

CANCELED STANDARD PLANS LIST

The 2025 standard plan sheets listed below are canceled and not applicable to this contract.

Plan No. Date Canceled Plan No. Date

Canceled Plan No. Date Canceled

P8 04-20-26

NOTICE TO BIDDERS

Bids open Thursday, January 7, 2027

Dated November 9, 2026

General work description: RHMA, concrete barrier, and corrugated steel pipe culvert.

The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON

STATE HIGHWAY IN SHASTA AND SISKIYOU COUNTIES AT AND NEAR DUNSMUIR FROM 0.6

MILE NORTH OF SIMS ROAD UNDERCROSSING TO 0.2 MILE SOUTH OF SISKIYOU AVENUE

OVERCROSSING.

District-County-Route-Post Mile: 02-Sha,Sis-5-58.0/67.0,0.0/2.7

Contract No. 02-0J81U4

The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-8, C-12.

Federal-aid project no.:

NH-0058(647)

For the Federal training program, the number of trainees or apprentices is 14.

Bids must be on a cost+time basis.

Complete the work within the number of working days bid.

Do not bid less than 255 working days and not more than 360 working days.

The estimated cost of the project is $67,000,000.

The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.

The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.

For bid results go to:

https://ppmoe.dot.ca.gov/cc

Select Electronic Bidding under the Bidding tab.

District office addresses are provided in the Standard Specifications.

Present bidders' inquiries to the Department and view the Department's responses at:

https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries

Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.

Submit your bid with bidder's security equal to at least 10 percent of the bid.

Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.

The federal minimum wage rates for this Contract as determined by the United States Secretary of Labor are available at https://sam.gov/content/home.

If the minimum wage rates as determined by the United States Secretary of Labor differs from the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors must not pay less than the higher wage rate. The Department does not accept lower State wage rates not specifically included in the federal minimum wage determinations. This includes helper, or other classifications based on hours of experience, or any other classification not appearing in the federal wage determinations. Where federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors must not pay less than the federal minimum wage rate that most closely approximates the duties of the employees in question.

The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.

Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.

Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.

Department of Transportation

BID ITEM LIST

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM LUMP SUM

0002 080060 LEVEL 2 CRITICAL PATH METHOD

SCHEDULE

LS LUMP SUM LUMP SUM

0003 090105 TIME-RELATED OVERHEAD (LS) LS LUMP SUM LUMP SUM

0004 090205 DISPUTE RESOLUTION BOARD ON-SITE

MEETING

EA 6 7,500.00 45,000.00

0005 090210 HOURLY OFF-SITE DISPUTE-

RESOLUTION-BOARD-RELATED TASKS

HR 120 250.00 30,000.00

0006 100100 DEVELOP WATER SUPPLY LS LUMP SUM LUMP SUM

0007 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM LUMP SUM

0008 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM LUMP SUM

0009 120101 TRAFFIC CONTROL SUPERVISOR DAY 180

0010 120105 AUTOMATED WORK ZONE INFORMATION

SYSTEM

LS LUMP SUM LUMP SUM

0011 013804 STATIONARY IMPACT ATTENUATOR

VEHICLE (LS)

LS LUMP SUM LUMP SUM

0012 120120 TYPE III BARRICADE EA 21

0013 120149 TEMPORARY PAVEMENT MARKING

(PAINT)

SQFT 1,370

0014 120159 TEMPORARY TRAFFIC STRIPE (PAINT) LF 268,000

0015 120165 CHANNELIZER (SURFACE MOUNTED) EA 2,780

0016 010413 PORTABLE RADAR SPEED FEEDBACK

SIGN SYSTEMS (LS)

LS LUMP SUM LUMP SUM

0017 120300 TEMPORARY PAVEMENT MARKER EA 2,280

0018 120320 TEMPORARY BARRIER SYSTEM LF 89,000

0019 124010 TEMPORARY SHUTTLE SERVICE LS LUMP SUM LUMP SUM

0020 128652 PORTABLE CHANGEABLE MESSAGE

SIGN (LS)

LS LUMP SUM LUMP SUM

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0021 129108 TEMPORARY CRASH CUSHION TL-3 EA 40

0022 129150 TEMPORARY TRAFFIC SCREEN LF 2,030

0023 130100 JOB SITE MANAGEMENT LS LUMP SUM LUMP SUM

0024 130301 STORMWATER POLLUTION PREVENTION

PLAN

LS LUMP SUM LUMP SUM

0025 130312 PRE-STORM EVENT INSPECTION

REPORT

EA 15

0026 130323 DURING-AND POST-STORM EVENT

INSPECTION REPORT

DAY 50

0027 130331 STORMWATER ANNUAL REPORT EA 4 3,000.00 12,000.00

0028 130530 TEMPORARY HYDRAULIC MULCH

(BONDED FIBER MATRIX)

SQYD 18,000

0029 130620 TEMPORARY DRAINAGE INLET

PROTECTION

EA 50

0030 130640 TEMPORARY FIBER ROLL LF 6,500

0031 130680 TEMPORARY SILT FENCE LF 600

0032 130730 STREET SWEEPING LS LUMP SUM LUMP SUM

0033 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM LUMP SUM

0034 131103 WATER QUALITY SAMPLING AND

ANALYSIS DAY

EA 36

0035 131104 WATER QUALITY MONITORING REPORT EA 12

0036 131105 WATER QUALITY ANNUAL REPORT EA 3

0037 141120 TREATED WOOD WASTE LB 893,000

0038 146002 CONTRACTOR-SUPPLIED BIOLOGIST

(LS)

LS LUMP SUM LUMP SUM

0039 146007 INVASIVE SPECIES CONTROL LS LUMP SUM LUMP SUM

0040 018788 SALVAGE FLASHING ARROW SIGN (EA) EA 7

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0041 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM LUMP SUM

0042 190101 ROADWAY EXCAVATION CY 2,960

0043 190112 ROADWAY EXCAVATION (TYPE A) CY 800

0044 190185 SHOULDER BACKING TON 4,260

0045 192001 (F) - STRUCTURE EXCAVATION CY 405

0046 192025 (F) - STRUCTURE EXCAVATION

(CULVERT)

CY 1,402

0047 193001 (F) - STRUCTURE BACKFILL CY 316

0048 193004 (F) - STRUCTURE BACKFILL (CULVERT) CY 336

0049 193030 (F) - PERVIOUS BACKFILL MATERIAL CY 29

0050 014626 NATIVE BACKFILL CY 35

0051 194001 DITCH EXCAVATION CY 200

0052 198010 IMPORTED BORROW (CY) CY 490

0053 198230 GEOSYNTHETIC REINFORCEMENT,

PR1000

SQYD 4,510

0054 210010 MOVE-IN/MOVE-OUT (EROSION

CONTROL)

EA 2

0055 210212 DRY SEED (SQFT) SQFT 119,000

0056 037634 HYDRAULIC BIOTIC GROWTH MEDIUM SQFT 24,100

0057 210255 FIBER REINFORCED MATRIX (SQFT) SQFT 24,100

0058 210270 ROLLED EROSION CONTROL PRODUCT

(NETTING)

SQFT 17,900

0059 210280 ROLLED EROSION CONTROL PRODUCT

(BLANKET)

SQFT 119,000

0060 220101 FINISHING ROADWAY LS LUMP SUM LUMP SUM

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0061 260203 CLASS 2 AGGREGATE BASE (CY) CY 660

0062 375020 PARKING AREA SEAL TON 6

0063 390095 REPLACE ASPHALT CONCRETE

SURFACING

CY 3,600

0064 390132 HOT MIX ASPHALT (TYPE A) TON 8,220

0065 390137 RUBBERIZED HOT MIX ASPHALT (GAP

GRADED)

TON 73,300

0066 394060 DATA CORE LS LUMP SUM LUMP SUM

0067 394073 PLACE HOT MIX ASPHALT DIKE (TYPE A) LF 240

0068 394074 PLACE HOT MIX ASPHALT DIKE (TYPE C) LF 1,040

0069 394076 PLACE HOT MIX ASPHALT DIKE (TYPE E) LF 15,800

0070 394077 PLACE HOT MIX ASPHALT DIKE (TYPE F) LF 29,400

0071 394090 PLACE HOT MIX ASPHALT

(MISCELLANEOUS AREA)

SQYD 180

0072 397005 TACK COAT TON 140

0073 398100 REMOVE ASPHALT CONCRETE DIKE LF 44,100

0074 398200 COLD PLANE ASPHALT CONCRETE

PAVEMENT

SQYD 84,500

0075 420203 GRIND EXISTING BRIDGE DECK SQYD 3,607

0076 510054 STRUCTURAL CONCRETE, BRIDGE

(POLYMER FIBER)

CY 447

0077 015318 STRUCTURAL CONCRETE, WINGWALL

(TYPE A)

CY 85

0078 510081 AGGREGATE BASE (APPROACH SLAB) CY 38

0079 510090 STRUCTURAL CONCRETE, BOX

CULVERT

CY 220

0080 510092 (F) - STRUCTURAL CONCRETE,

HEADWALL

CY 46

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0081 510094 (F) - STRUCTURAL CONCRETE,

DRAINAGE INLET

CY 323

0082 036910 STRUCTURAL CONCRETE, APPROACH

SLAB (TYPE R MODIFIED)

CY 376

0083 510502 (F) - MINOR CONCRETE (MINOR

STRUCTURE)

CY 2.2

0084 048717 PAVING NOTCH EXTENSION (MODIFIED) CF 268

0085 511111 DRILL AND BOND DOWEL (CHEMICAL

ADHESIVE) (LF)

LF 6,270

0086 511118 CLEAN EXPANSION JOINT LF 168

0087 519081 JOINT SEAL (MR 1/2") LF 332

0088 519091 JOINT SEAL (MR 1 1/2") LF 168

0089 520107 (F) - BAR REINFORCING STEEL (BOX

CULVERT)

LB 30,629

0090 048205 (F) - BAR REINFORCING STEEL (BRIDGE,

STAINLESS STEEL)

LB 118,500

0091 010124 (F) - BAR REINFORCING STEEL

(WINGWALL)

LB 14,815

0092 039112 (F) - BAR REINFORCING STEEL

(HEADWALL)

LB 337

0093 600001 PUBLIC SAFETY PLAN LS LUMP SUM LUMP SUM

0094 015978 REPAIR CULVERT JOINT EA 1

0095 600033 REMOVE UNSOUND CONCRETE CF 1,895

0096 600034 REMOVE POLYESTER CONCRETE

OVERLAY

SQFT 30,397

0097 600037 PREPARE CONCRETE BRIDGE DECK

SURFACE

SQFT 72,594

0098 600041 FURNISH POLYESTER CONCRETE

OVERLAY

CF 4,014

0099 600043 (F) - PLACE POLYESTER CONCRETE

OVERLAY

SQFT 40,137

0100 600115 BRIDGE REMOVAL (PORTION), LOCATION

A

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0101 600116 BRIDGE REMOVAL (PORTION), LOCATION

B

LS LUMP SUM LUMP SUM

0102 604100 GALVANIC ANODES EA 1,420

0103 610112 24" ALTERNATIVE PIPE CULVERT LF 7,880

0104 610201 18" ALTERNATIVE SLOTTED PIPE LF 61

0105 610300 (F) - CONCRETE BACKFILL (PIPE

TRENCH)

CY 14

0106 665012 12" CORRUGATED STEEL PIPE (.079"

THICK)

LF 20

0107 665018 18" CORRUGATED STEEL PIPE (.109"

THICK)

LF 300

0108 665025 24" CORRUGATED STEEL PIPE (.138"

THICK)

LF 7,400

0109 665033 30" CORRUGATED STEEL PIPE (.138"

THICK)

LF 120

0110 665038 36" CORRUGATED STEEL PIPE (.138"

THICK)

LF 640

0111 016787 18" X 30" CORRUGATED STEEL PIPE

ARCH (.109" THICK)

LF 90

0112 681132 GEOCOMPOSITE DRAIN SQFT 350

0113 690118 18" CORRUGATED STEEL PIPE

DOWNDRAIN (.109" THICK)

LF 73

0114 690125 24" CORRUGATED STEEL PIPE

DOWNDRAIN (.138" THICK)

LF 790

0115 692307 18" ANCHOR ASSEMBLY EA 2

0116 692309 24" ANCHOR ASSEMBLY EA 30

0117 702123 24" TO 18" CORRUGATED STEEL

ECCENTRIC REDUCER (.079" THICK)

EA 5

0118 703233 GRATED LINE DRAIN LF 47

0119 705015 24" STEEL FLARED END SECTION EA 11

0120 710102 ABANDON CULVERT (LF) LF 2,030

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0121 710110 ABANDON INLET EA 2

0122 710132 REMOVE CULVERT (LF) LF 10,500

0123 017113 REMOVE SLOTTED DRAIN (LF) LF 940

0124 018790 REMOVE DOWNDRAIN (LF) LF 610

0125 710150 REMOVE INLET EA 130

0126 710152 REMOVE HEADWALL EA 7

0127 710190 RELOCATE OVERSIDE DRAIN LF 80

0128 710196 ADJUST INLET EA 52

0129 710206 ADJUST OVERSIDE DRAIN EA 39

0130 710230 ADJUST SLOTTED DRAIN TO GRADE LF 970

0131 710240 MODIFY INLET EA 26

0132 710360 CLEANING, INSPECTING, AND

PREPARING CULVERT (LF)

LF 3,770

0133 710370 SAND BACKFILL CY 160

0134 710384 24" CURED-IN-PLACE PIPELINER LF 1,980

0135 710388 30" CURED-IN-PLACE PIPELINER LF 580

0136 710390 36" CURED-IN-PLACE PIPELINER LF 760

0137 721431 CONCRETE (CONCRETE APRON) CY 1

0138 723040 ROCK SLOPE PROTECTION (3/8 T, CLASS

VI, METHOD B) (CY)

CY 27

0139 723080 ROCK SLOPE PROTECTION (60 LB,

CLASS II, METHOD B) (CY)

CY 56

0140 723110 ROCK SLOPE PROTECTION (1/2 T, CLASS

VII, METHOD B) (CY)

CY 36

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0141 729011 ROCK SLOPE PROTECTION FABRIC

(CLASS 8)

SQYD 300

0142 750001 (F) - MISCELLANEOUS IRON AND STEEL LB 51,980

0143 801110 4' WIRE MESH GATE EA 1

0144 801230 16' WIRE MESH GATE EA 1

0145 803100 RECONSTRUCT FENCE LF 50

0146 036950 WILDLIFE FENCE LF 2,130

0147 810180 DELINEATOR (CLASS 2) EA 890

0148 810190 GUARD RAILING DELINEATOR EA 410

0149 810250 PAVEMENT MARKER

(RETROREFLECTIVE-RECESSED)

EA 11,000

0150 038419 REMOVE MARKER (CULVERT) EA 160

0151 820110 MILEPOST MARKER EA 48

0152 820112 MARKER (CULVERT) EA 190

0153 037137 CONCRETE BARRIER MARKER EA 340

0154 015247 MARKER (DRAINAGE INLET) BARRIER EA 300

0155 820270 REMOVE ROADSIDE SIGN (WOOD POST) EA 120

0156 820300 REMOVE ROADSIDE SIGN (STRAP AND

SADDLE BRACKET METHOD)

EA 15

0157 820310 REMOVE ROADSIDE SIGN PANEL EA 86

0158 820320 REMOVE METAL POST EA 24

0159 820330 REMOVE ROADSIDE SIGN (STEEL POST) EA 56

0160 037363 SALVAGE ROADSIDE SIGN (TURNABLE

METAL POST)

EA 2

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0161 820620 RELOCATE ROADSIDE SIGN (METAL

POST)

EA 8

0162 820720 FURNISH LAMINATED PANEL SIGN (1"-

TYPE B)

SQFT 710

0163 820730 FURNISH LAMINATED PANEL SIGN (2 1/2"-

TYPE B)

SQFT 3,470

0164 820760 FURNISH SINGLE SHEET ALUMINUM

SIGN (0.080"-UNFRAMED)

SQFT 2,120

0165 820780 FURNISH SINGLE SHEET ALUMINUM

SIGN (0.063"-FRAMED)

SQFT 450

0166 820790 FURNISH SINGLE SHEET ALUMINUM

SIGN (0.080"-FRAMED)

SQFT 1,560

0167 820820 METAL (BARRIER MOUNTED SIGN) LB 2,970

0168 820840 ROADSIDE SIGN - ONE POST EA 120

0169 820850 ROADSIDE SIGN - TWO POST EA 13

0170 820860 INSTALL SIGN (STRAP AND SADDLE

BRACKET METHOD)

EA 21

0171 820900 INSTALL ROADSIDE SIGN PANEL ON

EXISTING POST

EA 83

0172 820920 INSTALL ROADSIDE SIGN (LAMINATED

WOOD BOX POST)

EA 25

0173 832006 MIDWEST GUARDRAIL SYSTEM (STEEL

POST)

LF 16,300

0174 832018 MIDWEST GUARDRAIL SYSTEM (8' STEEL

POST)

LF 34,000

0175 832070 VEGETATION CONTROL (MINOR

CONCRETE)

SQYD 2,970

0176 010160 CONCRETE BARRIER WILDLIFE

PASSAGEWAY (TYPE MM)

EA 14

0177 010609 CONCRETE BARRIER (TYPE 60MP

MODIFIED)

LF 1,120

0178 038223 CONCRETE BARRIER (TYPE 60MD

MODIFIED)

LF 375

0179 018789 REMOVE CONCRETE BARRIER (TYPE 50

MOD)

LF 3,950

0180 839521 (F) - CABLE RAILING LF 105

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0181 839544 TRANSITION RAILING (TYPE AGT) EA 25

0182 839576 END CAP (TYPE A) EA 18

0183 839580 END ANCHOR ASSEMBLY (TYPE SFT-M) EA 55

0184 015299 ALTERNATIVE IN-LINE TERMINAL TL-3 EA 46

0185 839588 BURIED POST END ANCHOR (TYPE B-F) EA 6

0186 839589 BURIED POST END ANCHOR (TYPE B-S) EA 16

0187 839640 CONCRETE BARRIER (TYPE 60M) LF 24,700

0188 839641 CONCRETE BARRIER (TYPE 60MA) LF 120

0189 839642 CONCRETE BARRIER (TYPE 60MC) LF 29,500

0190 839645 CONCRETE BARRIER (TYPE 60MG) LF 50

0191 839648 CONCRETE BARRIER (TYPE 60MGF) LF 160

0192 839649 CONCRETE BARRIER (TYPE 60MS) LF 85

0193 839653 CONCRETE BARRIER (TYPE 60MP) LF 66

0194 017970 CONCRETE BARRIER (TYPE 60M W/

SMALL POLE)

LF 120

0195 018792 RESET PORTABLE 60K BARRIER LF 1,540

0196 839745 (F) - CONCRETE BARRIER TRANSITION LF 320

0197 839746 (F) - CONCRETE BARRIER (TYPE 842) LF 94

0198 839749 (F) - CONCRETE BARRIER (TYPE 842

MODIFIED)

LF 749

0199 839752 REMOVE GUARDRAIL LF 49,300

0200 839761 SALVAGE GUARDRAIL LF 2,210

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0201 839765 RECONSTRUCT GUARDRAIL LF 2,760

0202 018791 REMOVE STEEL BARRIER LF 290

0203 839774 REMOVE CONCRETE BARRIER LF 51,900

0204 840515 THERMOPLASTIC PAVEMENT MARKING SQFT 1,820

0205 846030 REMOVE THERMOPLASTIC TRAFFIC

STRIPE

LF 243,000

0206 846051 12" RUMBLE STRIP (ASPHALT

CONCRETE PAVEMENT)

STA 2,230

0207 847104 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

(RECESSED)

LF 283,000

0208 847110 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

(RECESSED, BROKEN 36-12)

LF 120,000

0209 847112 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

(RECESSED, BROKEN 17-7)

LF 2,480

0210 847118 8" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

(RECESSED)

LF 460

0211 847123 12" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

(RECESSED)

LF 14,700

0212 847124 THERMOPLASTIC PAVEMENT MARKING

(ENHANCED WET NIGHT VISIBILITY)

(RECESSED)

SQFT 4,850

0213 847128 6" METHYL METHACRYLATE PAINT

TRAFFIC STRIPE

LF 6,650

0214 847138 6" METHYL METHACRYLATE PAINT

TRAFFIC STRIPE (BROKEN 36-12)

LF 3,330

0215 847196 CONTRAST STRIPE PAINT (2-COAT) LF 9,980

0216 870009 MAINTAINING EXISTING TRAFFIC

MANAGEMENT SYSTEM ELEMENTS

DURING CONSTRUCTION

LS LUMP SUM LUMP SUM

0217 870600 TRAFFIC MONITORING STATION SYSTEM LS LUMP SUM LUMP SUM

0218 018793 MODIFYING FLASHING ARROW SIGN

SYSTEMS

LS LUMP SUM LUMP SUM

0219 013863 MODIFYING ROADSIDE WEATHER

INFORMATION SYSTEMS

0220 872131 MODIFYING LIGHTING SYSTEMS LS LUMP SUM LUMP SUM

Item No.

Item Code

Item Description Unit of Measure

Estimated Quantity

Unit Price Item Total

0221 872135 MODIFYING TRAFFIC MONITORING

STATIONS

0222 999990 MOBILIZATION LS LUMP SUM LUMP SUM

SPECIAL PROVISIONS

ORGANIZATION

Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.

Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.

Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.

DIVISION I GENERAL PROVISIONS

1 GENERAL

Add to section 1-1.01:

Bid Items and Applicable Sections Item code

Item description Applicable section

090205 DISPUTE RESOLUTION BOARD ON-SITE MEETING 5

090210 HOURLY OFF-SITE DISPUTE-RESOLUTION-BOARD-RELATED

TASKS

010124 BAR REINFORCING STEEL (WINGWALL) 52

010160 CONCRETE BARRIER WILDLIFE PASSAGE (TYPE MM) 83

010413 PORTABLE RADAR SPEED FEEDBACK SIGN SYSTEMS (LS) 12

010526 TEMPORARY ALTERNATIVE CRASH CUSHION (TL-3) 12

010609 CONCRETE BARRIER (TYPE 60 MP MODIFIED) 83

013804 STATIONARY IMPACT ATTENUATOR VEHICLE (LS) 12

013863 MODIFYING ROADSIDE WEATHER INFORMATION SYSTEMS 87

014626 NATIVE BACKFILL 19

015247 MARKER (DRAINAGE INLET) BARRIER 82

015299 ALTERNATIVE IN-LINE TERMINAL TL-3 83

015318 STRUCTURAL CONCRETE, WINGWALL (TYPE A) 51

015978 REPAIR CULVERT JOINT 60

016787 18" x 30" CORRUGATED STEEL PIP ARCH (0.109" THICK) 66

017113 REMOVE SLOTTED DRAIN (LF) 71

036910 STRUCTURAL CONCRETE, APPROACH SLAB (TYPE R MODIFIED) 51

036950 WILDLIFE FENCE 80

037137 CONCRETE BARRIER MARKERS 82

037363 SALVAGE ROADSIDE SIGN (TURNABLE METAL POST) 82

037634 HYDRAULIC BIOTIC GROWTH MEDIUM 21

038223 CONCRETE BARRIER (TYPE 60MD MODIFIED) 83

038419 REMOVE MARKER (CULVERT) 82

039042 12' X 12' PRECAST REINFORCED CONCRETE BOX CULVERT 51

039112 BAR REINFORCING STEEL (HEADWALL) 52

048205 BAR REINFORCING STEEL (BRIDGE, STAINLESS STEEL) 52

048717 PAVING NOTCH EXTENSION (MODIFIED) 51

018793 MODIFYING FLASHING ARROW SIGN SYSTEM 87

018791 REMOVE STEEL BARRIER 83

999990 MOBILIZATION 9

Add to section 1-1.09:

This project is in a freeze-thaw area.

2 BIDDING

Add between the 1st and 2nd paragraphs of section 2-1.06B:

The Department makes the following supplemental project information available:

Supplemental Project Information Means Description

Included in the Information Handout 1. PLAC - U.S. Army Corps of Engineers, 33 CFR Part 330, Nationwide Permit No.404, dated February 25,

2. PLAC - California Department of Fish and Wildlife

3. PLAC - California Regional Water Quality Control Board, Central Valley Region, Water Quality Certification, WDID No. 5A45CR00681, dated December 11, 2025

4. Tunnel Safety Order - Siskiyou County

5. Tunnel Safety Order - Shasta County

6. Longitudinal Pipeline Agreement-UPRR Project No.

0805564 (Railroad Coordination Requirements)

7. Longitudinal Pipeline Agreement-UPRR Project No.

0798309 (Railroad Coordination Requirements)

8. Longitudinal Pipeline Agreement-UPRR Project No.

0805568 (Railroad Coordination Requirements)

9. Work Plan Form

10. Project and Billing Form

11. RailPros Rates 2026 (cost summary sheet)

12. UPRR Guidelines for Track Monitoring (Railroad

Coordination Requirements)

13. UPRR Guidelines for Utility Potholing(Railroad

Coordination Requirements)

14. Geotechnical Design Report

15. TMS Element Operational Status Certified List

Available as specified in the Standard Specifications

1. Digital terrain model in 3D DGN or LandXML format

2. Alignments and profiles in LandXML format

3. Cross sections in 2D DGN and PDF format

4. Digital design model in LandXML format

5. Pavement smoothness data (.ppf)

6. Bridge as built drawings

Delete section 2-1.20.

Delete section 2-1.33B(2)(b).

5 CONTROL OF WORK

Delete section 5-1.13B.

Replace section 5-1.13E with:

5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.

Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.

Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:

1. Subcontractor’s or entity’s business name

2. Description of work performed

2.1. Bid item numbers or change order numbers

2.2. Written narrative of work performed

3. Value of work performed

4. Amount paid to subcontractor or entity

5. Withhold amount, if applicable

6. Explanation of withhold reasoning, if applicable

Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.

If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:

1. Value of the disputed work

2. Amount of the withhold being taken

3. Bid item numbers or change order numbers associated with the disputed work

4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated

5. Corrective actions to be taken for release of withheld amount

The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.

The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:

1. Withhold was not applied in good faith

2. Requested additional withhold documentation records were not provided

3. Payment information was not submitted through the prompt payment monitoring system

4. Required withhold notification was not provided

The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.

Replace section 5-1.15 with:

5-1.15 SAFETY REPRESENTATIVE

5-1.15A General Designate an on-site safety representative to superintend project safety for the duration of this Contract.

The safety representative may perform other non-safety related work if safety responsibilities are fulfilled.

The safety representative must be available after work hours as needed. The safety representative is not required to be on-site during plant establishment period, erosion control establishment period, or temporary suspensions when no other Contract work is being performed.

Develop a written site-specific safety program (SSSP) that incorporates known hazards associated with the project.

5-1.15B Submittals Submit a resume of the safety representative before starting work on the project, including education, completed safety training, and safety experience in heavy construction, heavy industrial, or oil and energy industry.

Submit a copy of the safety representative's certificate for the Cal/OSHA 30-hour – Cal/OSHA Standards for the Construction Industry or OSHA 510 - OSHA Standards for the Construction Industry training course as an informational submittal. The certificate must include:

1. Name of the entity providing certification

2. Name of the individual receiving certification

3. Date when the certification was provided

4. Expiration date, if applicable

Submit a copy of the SSSP as an informational submittal:

1. At least 15 days before starting work

2. At least 48 hours before starting work whenever a revision is made to the SSSP

5-1.15C Certifications The safety representative must have completed training and received a certificate of completion for the Cal/OSHA 30-hour - Cal/OSHA Standards for the Construction Industry or OSHA 510 – OSHA Standards for the Construction Industry training course.

The safety representative must have one of the following certifications:

1. Certified Safety Professional from the Board of Certified Safety Professionals

2. Construction Health and Safety Technician from the Board of Certified Safety Professionals

3. Occupational Hygiene and Safety Technician from the Board of Certified Safety Professionals

4. Safety Trained Supervisor from the Board of Certified Safety Professionals

5. Safety Trained Supervisor Construction from the Board of Certified Safety Professionals

6. Associate Safety Professional from the Board of Certified Safety Professionals

7. Master Safety Professional from the National Association of Safety Professionals

8. Certified Safety Director from the National Association of Safety Professionals

5-1.15D Qualifications The safety representative must be a competent and qualified person, as defined by Cal/OSHA, and must provide safety oversight on the project. The safety representative must have:

1. At least 3 years of safety experience in heavy construction, heavy industrial, or oil and energy industry

2. Knowledge in the area of safety procedure for all types of work being performed on this project

3. Knowledge of Department specifications and plans, Cal/OSHA policy and procedures, and 8 CA

Code of Regs safety requirements

The safety representative must have completed safety training and maintain valid certifications for:

1. First aid

2. Cardiopulmonary resuscitation

5-1.15E Duties and Responsibilities The safety representative must be available by:

1. Cellular telephone

2. Two-way radio

3. Mobile internet access

The safety representative must:

1. Develop the SSSP

2. Conduct the on-site new project orientation for each worker assigned to the project

3. Review the construction work plans for each subcontractor before starting work

4. Conduct or attend pre-planning sessions for high hazard work such as excavations, demolition, confined space entry, falsework, crane hoisting, high-risk utilities such as high-pressure pipelines with fuel or natural gas, and tunneling or boring

5. Conduct weekly job site safety meetings

6. Review work schedules, including subcontractors' work schedules, to ensure adequacy of job hazard analyses and address all safety concerns and issues

7. Ensure safety data sheets are available on-site for all materials and have a hazard communication program for informing workers of material hazards

8. Verify compliance with hazardous waste requirements under section 14-11, including spill prevention and control measures

9. Conduct daily safety inspections of the job site for hazards and compliance with safety requirements in the specifications and 8 CA Code of Regs

10. Report all incidents to the Engineer immediately, including the investigation of any close calls

When monitoring the job site, including work zones with certified flaggers or traffic control technicians, take immediate corrective action and notify the Engineer if an imminent danger is identified.

If the Engineer determines the safety representative is not meeting the intended duties and responsibilities, you must replace the safety representative within 30 days of written notice from the Engineer. If you need to replace the safety representative, notify the Engineer and provide replacement safety representative resume and required certifications at least 15 days before the replacement.

You may submit a secondary safety representative to act on behalf of the designated safety representative during extended shifts, continuous operations, or short-term absences that will not exceed 14 days in duration. The secondary safety representative must meet the same required qualifications and certifications as the designated safety representative.

Add to the end of section 5-1.20A:

During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:

Coincident or Adjacent Contracts

Contract no. County–Route–Post Mile Type of work

02-2J8404 SHA-005-45.85/57.87 ITS

02-3J5704 SHA-005-56.70/66.50 Drainage Culverts

02-2J8604 SHA-005-61.75 Bridge Deck Replacement

02-2J7704 SIS-005-0.00/69.29 Curve Warning Signs

Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.

Add to the end of section 5-1.20B(1):

The Department will communicate with PLAC agencies unless communication between you and the PLAC agency is authorized.

Replace section 5-1.20H with:

5-1.20H Railroad Flagging 5-1.20H(1) General 5-1.20H(1)(a) Summary Section 5-1.20H includes specifications for providing railroad flagging services at the railroad location shown. The project involves work on or in the near vicinity of railroad property between RMP 312.0- 322.87, Valley subdivision, involving the Union Pacific Railroad Company (UPRR) Project number 0805564, 0798309, 0805568.

Comply with the documents titled “Railroad Coordination Requirements” in the Informational Handout.

See section 5-1.20C for any additional railroad requirements.

5-1.20H(1)(b) Definitions Not Used

5-1.20H(1)(c) Submittals Submit weekly logs identifying railroad flaggers’ names, hours flagged and date of flagging. Submit each week’s log by the following Monday. The Department will notify you within 5 business days if there is disagreement with the weekly log information

Submit copies of the railroad flagging company’s invoices and proof of your payments. The Department will not compensate you without receiving the required documentation.

Prior to requesting Contract acceptance, submit a notarized confirmation statement from each flagging service company used that states they have no outstanding billing due and have received payment for their services on this project. The Department does not provide Contract acceptance when there are unpaid flagging services remaining.

5-1.20H(1)(d) Quality Assurance Not Used

5-1.20H(2) Materials Not Used

5-1.20H(3) Construction 5-1.20H(3)(a) General Notify the Engineer and UPRR representative of the following:

1. The date and time of mandatory preconstruction meeting

2. Your notice to proceed with the work, provided a minimum of 30 days in advance of work to be performed within the railroad right of way

3. Work or equipment to be located within 25 feet of or above a railroad track, a minimum of 45 days in advance of such work

The contact information for the UPRR representative for this project is found in the Information Handout.

Meet with the Engineer and UPRR representative at a mandatory preconstruction meeting to be held a minimum of 21 days prior to the start of jobsite activities. Discuss the work to be performed including your means and methods. Discuss requirements for coordination and scheduling railroad flagging, including notifications of potential changes in scheduled work.

Within the notification of work in proximity of the railroad, include the type of work to be performed and equipment to used. You will be notified by the railroad representative of flagging requirements, including number of flaggers required within 30 days of your notification. You are responsible to notify the Engineer, UPRR representative and railroad flagging company of changes in your work to be performed that may change flagging needs. These notifications must be made a minimum of 10 days in advance of the changed work.

Comply with the railroad’s published policy found at https://www.up.com/cs/groups/public/@uprr/@realestate for scheduling railroad flagging.

Securing flagging services will not relieve you of your responsibilities or liabilities pertaining to UPRR.

Comply with the Railroad Coordination Requirements of the Information Handout.

5-1.20H(3)(b) Flagging Services Unless otherwise provided in writing by the UPRR representative, railroad flagging services will be required when your personnel or equipment will be:

1. Within 25 feet of a railroad track

2. Operating above a railroad track

3. Operating in the vicinity of the railroad track that may affect railroad operations, such as crane usage

4. Creating an intrusion into the track zone that creates an extraordinary hazard to railroad traffic

5. Operating in proximity to the railroad, as described in your notice to the railroad representative, that requires assigned flagging services as deemed necessary by the UPRR representative

You must coordinate flagging services with the UPRR representative, flagging services subcontractor, and the Engineer, for your work that may require railroad flagging. Include the following information on each notification, submittal or written correspondence with UPRR:

1. Railroad or highway DOT #

2. Railroad milepost

3. Railroad subdivision

4. UPRR folder number

The railroad representative will make the final decision of flagging needs based on your description of your work activities, personnel and equipment in your notification and actual field operations. If your operations are delayed because an insufficient number of flagging personnel are scheduled due to description of work in the notification not aligning with actual field operations, you will be responsible for your delay costs.

You must comply with requirements for flagging services as identified within the Contractor’s Right of Entry Agreement issued by UPRR. You are responsible for any costs associated with failure to comply with these requirements. If UPRR or the flagging service bills you for expenses incurred for your failure to comply, you must pay such bills within 30 days of bill receipt. The Department does not reimburse those costs incurred for your failure to comply.

You are responsible for direct and timely payment of undisputed flagging services provided by the UPRR approved railroad flagging subcontractor. The Department reimburses you these costs upon your submittal of required documentation and proof of your payment.

The Engineer and UPRR representative will monitor your operations for compliance with required flagging services. Failure to comply with flagging service requirements may result in your removal from railroad property until you demonstrate compliance intent. If additional flagging requirements are instituted by UPRR due to your noncompliance, you will bear responsibility for compliance with the additional requirements including additional direct cost and indirect cost impacts. The Department does not reimburse your additional costs.

It is anticipated this project will require approximately 5 days of railroad flagging service.

Select a flagging service subcontractor from the following list of UPRR approved railroad flagging companies:

1. RailPros, email: mail:UP.info@railpros.com, phone: (877) 315-0513, ext. 116

2. National Railroad Safety Services, email: UP.request@nrssinc.net, phone: (877) 984-6777

5-1.20H(3)(c) Railroad Operations Normal train operations over the crossing or through the project consists of 11 freight trains and 2 passenger trains daily with a maximum timetable speed of 25 mph. Specific details regarding train operations may be obtained by consulting with the UPRR Manager of Track Maintenance (MTM) Guy Holleman by phone at 530-604-7656, gdhollem@up.com.

5-1.20H(4) Payment Payment for flagging services will be compensated under section 9-1.05.

6 CONTROL OF MATERIALS

Add to end of section 6-1.01:

If you fail to submit the form for materials subject to Buy America, the Department may:

1. Withhold from the next progress payment

2. Reject your request for a De Minimis Costs waiver for non-compliant construction materials or manufactured products

Replace section 6-1.03B with:

6-1.03B Submittals 6-1.03B(1) General Not Used

6-1.03B(2) Work Plan For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:

1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under…