This document is a Summary of Work section (Section 01110) for a construction project located in the Yolo Bypass, Yolo County, California, involving the California Department of Transportation. The project focuses on infrastructure improvements at Agricultural Road Crossing 4 (ARC4), including installing and removing environmental exclusion fencing, installing a turbidity curtain, placing temporary surcharge material at future bridge abutment areas, and installing settlement devices to monitor ground settlement. The work is scheduled to begin within 5 days of receiving a notice to proceed, with installation of surcharge and removal of fencing to be completed by October 31, 2025, and settlement instrumentation monitoring to be finished by May 31, 2026. The project has specific work restrictions, including a work window from April 16 to October 31, an in-water work window from June 1 to October 31, and considerations for Giant Garter Snake active season.

The contract includes liquidated damages of $1,000 per day for failure to complete work, and requires the contractor to obtain necessary permits, including transportation and hauling permits and county roadway encroachment permits. The project involves coordination with the Swanston Ranch Landowner Project, with an estimated completion date of September 3, 2025. The contractor must verify existing facility dimensions and cooperate with other ongoing projects. The contract prices are intended to include full compensation for all costs incurred, with specific environmental and operational constraints such as ground disturbance limitations, weather considerations, and requirements for maintaining aquatic life during construction activities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary of Work

01110-1 S-25

SECTION 01110

SUMMARY OF WORK

PART 1 GENERAL

1.01 DESCRIPTION

A. The term project is defined in Document 00700 – Abbreviations and Definitions, Paragraph 2. This project includes the following principal features:

1. Install and remove Environmental Exclusion Fencing.

2. Install and remove Turbidity Curtain.

3. Install Temporary Surcharge Material (RSP) at future bridge abutment areas.

4. Install Settlement Devices and monitor settlement rate of the surcharge material during the surcharge period.

1.02 RELATED SECTIONS

A. Supplementary General Conditions, General Conditions, other Division 1 sections, and Drawings apply to this section.

1.03 LOCATION AND ACCESS

A. The Project is located in the northern portion of the Yolo Bypass, near the Sacramento Bypass and between the towns of Davis and West Sacramento in Yolo County, California. The Project area includes the Tule Canal north of Interstate 80 (I-80) and Agricultural Road Crossing 4 (ARC4), which provides access for vehicles and agricultural equipment from the east side of the Tule Canal to agricultural fields on the west side of Tule Canal. The Agricultural Crossing 4 is located west of Sacramento, California in the Tule Canal, within the Yolo Bypass at

38.589 degrees latitude and -121.586 degrees longitude. It is approximately 13 miles south of Fremont Weir.

01110-2 S-25

1.04 TIME OF COMPLETION

A. Pursuant to Document 00705 – Prosecution of Work, Paragraph 1.A, the Contractor shall begin work within

5 DAYS

from date of receipt of notice to begin work.

B. The Contractor shall complete installation of the surcharge, removal of the environmental exclusion fencing and the turbidity curtain, before the expiration of:

October 31, 2025

C. The Contractor shall complete the settlement instrumentation monitoring and maintenance before the expiration of

May 31, 2026.

D. The above completion date is based on the Contractor receiving the notice to begin work within 10 days from the date of the bid opening.

The Department will extend the completion date by the number of days after the 10 days specified above that the Contractor receives the notice to begin work, except to the extent that the delay in issuance of the notice to begin work results from the failure of the Contractor to perform obligations specified in Document 00200 – Instructions to Bidders. Notwithstanding the provisions of Document 00705 – Prosecution of Work, Paragraph 6, the Contractor shall not be entitled to adjustment in compensation for such extension of the completion date.

1.05 LIQUIDATED DAMAGES

A. Pursuant to Document 00705 – Prosecution of Work Paragraph 2:

1. Liquidated damages for failure to complete the balance of the work will be $1,000 per day.

1.06 RESTRICTIONS

A. Work Window: April 16 – October 31, 7 am – 7 pm.

1. In-water work window: June 1 – October 31.

2. Giant Garter Snake (GGS) active season: June 1 – October 31.

01110-3 S-25

3. Low Rainfall/ Dry Weather: Less than one half of one inch per 24 hour period (less than 50 percent chance of rain) in 72 hour forecast.

a. No work during a dry-out period of 24 hours after above referenced wet weather.

4. Ground Disturbance: May 1 – October 1, unless otherwise directed by the Engineer.

a. Ground disturbance extension from October 2 – October 31 if air temps exceed 75 degrees Fahrenheit during work and max daily air temp have exceeded 75 degrees Fahrenheit for at least three consecutive days.

5. Flood Season: November 1 – April 15.

B. Ground Disturbing Activities include, but are not limited to:

1. Installing exclusion fencing.

2. Placement of temporary surcharge material (RSP).

3. Installing Settlement Devices.

C. Contractor shall install environmental exclusion fencing as shown prior to staging and the initiation of clearing and grubbing and/or ground disturbing construction activities.

D. When the temporary surcharge fill, environmental exclusion fencing, and turbidity curtain is installed, maintained, or placed in operation;

sufficient aquatic water must be allowed to pass downstream to maintain aquatic life below the obstruction at all times. The Contractor shall remove the environmental exclusion fencing and turbidity curtain after installation of the temporary surcharge fill and prior to the beginning of flood season (October 31).

1.07 PERMITS AND LICENSES

A. Pursuant to Document 00703 – Applicable Laws and Regulations, Contractor shall obtain necessary permits and licenses including, but not limited to, the following:

1. The Contractor shall obtain transportation and hauling permits as required.

01110-4 S-25

2. The Contractor shall obtain such permits and licenses and pay charges and fees, except as specified in Section 01570 – Environmental Protection. Permits and licenses shall be obtained in sufficient time to prevent delay to the project. Such permits shall become a part of these specifications by reference.

3. County roadway encroachment permits from Sacramento County as required for work on county roads.

1.08 COOPERATION WITH OTHERS

A. Pursuant to Document 00706 – Control of Work, Paragraph 3.E, the Contractor shall cooperate with others. Other contracts under construction during the period of the contract include but are not limited to:

SUMMARY OF CONTRACTS

Contract Estimated

Award Date Estimated

Completion Date

Swanston Ranch Landowner Project N/A 9/3/2025

B. The Contractor shall meet regularly with the Upper Swanston Ranch, Irrigation and Fish Passage Improvement Project (Swanston Project) owner and contractor throughout construction to maximize coordination, minimize conflicts and develop schedules that address the following:

1. The Contractor shall coordinate with the Swanston Project owner and contractor to connect the water pipelines as shown.

1.09 VERIFICATION OF EXISTING FACILITIES

A. The Contractor shall verify the applicable structural dimensions, the location, elevations, and dimensions of existing facilities, and other dimensions and data required to complete the project.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

01110-5 S-25

PART 4 PAYMENT

4.01 PAYMENT

A. The contract prices shall include full compensation for all costs incurred under this section.

END OF SECTION