STATEMENT OF WORK (SOW)

Project Number, Title: VGLZ202014/5 RPR West Apron & ADAL Access Roads 26 Feb 2020

The Selfridge Design Standards apply to this Statement of Work (SOW). The work shall be in strict compliance with those specifications and the requirements identified in this SOW and its attachments. Sections of this SOW may supersede the requirements of the specifications, in which case the more stringent/higher quality requirements shall apply.

1. This SOW provides for construction of (4) asphalt roads, Phase I, and for the repair of a pavement transition, Phase II, on the west ramp at Selfridge ANGB, work is as follows but is not limited to:

I. Phase I - West ramp lighting pad access roads

A. Prior to beginning work the contractor shall contact Selfridge Environmental Management Office to obtain most recent soil and/or groundwater analytical data for determining contractor personnel risk exposures and personal protective equipment, if required

B. Prepare site as necessary to insure a properly graded road.

During earth work operations of this work contractor shall adhere to the following guidance:

If impacted soil controls cannot be maintained (excavated, stockpiled, reused, graded and seeded, and/or placed back at excavation area as fill or discharged to adjacent grassy area for infiltration, not allowed into storm water or sanitary sewers) within the contaminated delineated boundaries, follow General Specs 02 61 00 Removal and Disposal of Contaminated Soil.

Soil erosion permit and approved plan required as soil disturbance activities within 500 feet of wetlands.

Soil erosion plan in accordance with Selfridge Design Standards (2017).

Soil erosion best management practices must be established and maintained in accordance with Macomb County Macomb County Soil Erosion and Sedimentation Control Ordinance, adopted 16 August 2007 and Selfridge Design Standards (2017).

Catch basin and/or storm water conveyance temporary measures may be required.

Dust control for fugitive emissions must be included in soil erosion BMPs.

Any dewatering of non-contaminated/impacted groundwater or surface water infiltration will be discharged by pumping through a filter sock/dewatering bag and allowed to infiltrate into the surface vegetation and soils, in accordance with Selfridge Design Standards (2017).

Groundwater activities must be in accordance with Crock Wells and Groundwater Wells Guidance for SANGB (dated 2002-05-03).

Excess soil can be managed by backfilling native material or berming and seeding in the local vicinity or transported to one of the onsite excess soil stockpile areas, Non-contaminated excess soils may be transported to onset excess soil stockpile areas, in accordance with Soil Relocation Guidance for SANGB (dated 2018-10-24) and Selfridge Design Standards (2017)

Elevated noise levels in the area will exist as worksite with in noise contours of aircraft.

C. Road crown shall run along length of road centerline and be sloped so that the water is shed to the grass and away from the apron.

D. Install (4) 10’ wide asphalt path comprised of the following:

i. Compacted subgrade, four passes

ii. 6” of 3/4”crushed stone / Road Base. Compacted to 98%

iii. Bituminous paving, binding course, 2” thick

iv. Bituminous paving, wear course, 2” thick

v. Thermoplastic edging, 4” wide striping, Color TBD Refer to West Apron – General Specifications, Section xxx

During execution of this work contractor shall adhere to the following guidance:

Contractors using Hazardous Materials, as defined in Selfridge Design Standards (2017), must report the types and quantities used while located at Selfridge ANGB.

SANGB Form 23 and Safety Data Sheets (SDS) for each material must accompany the form prior to materials brought on base

All non-hazardous solid waste materials including demolition and construction debris (concrete, piping, etc.) transferred off the installation must be accounted.

AF Form 72 (Solid Waste Disposal and Diversion Tracking) must be completed in accordance with DoD Pollution Prevention Measure of Merit Memorandum (dated 1998-08-06)

E. Refer to attached drawing for location of roads. Roads are to be approximately 75’ Long x 10’ Wide. Actual dimensions to be verified in field.

F. Any ground coverings damaged during the execution of this work needs to be reseeded. Seed vegetation shall be compatible with air field operation. Refer to West Ramp – General Specifications, Section 32 92 19.

G. Provide final clean up.

H. Stamped drawings by a Professional Engineer (P.E.) or a Registered Architect (R.A.) are not required for this project.

I. Warranty: Contractor shall provide a one-year warranty on workmanship of the entire project in addition to any manufacturer’s warranty on materials installed. The contractor will provide any commercial warranty on materials or equipment included in the construction that exceeds this one-year, all-inclusive warranty. The commercial warranty will be issued to the Government.

II. Phase II - Pavement Transition Repair

APPLICABLE STANDARDS: Latest published versions shall be used

A. UFC-3-270-01

a. Chapter 13 Partial-Depth Repair of Concrete Pavements

B. International Building Code (IBC).

C. Occupational Safety and Health Administration standards

D. Michigan Occupational Safety and Health Administration standards

A. Contractor shall sound concrete slabs, to either side of the pavement transition, to determine the extent of the damage.

B. The Contractor shall mark continuous lines parallel to the transition joint, 3 inches wider than the widest visibly distressed area.

C. Contractor shall saw cut 2 inches deep, along this parallel line.

D. Contractor shall remove concrete within perimeter of saw cut lines, down 2 inches or until concrete is sound, whichever is deeper. Dispose of millings on base where directed.

If concrete is removed more than 1/3 depth or if dowel joints are exposed this will be required to be a full-depth repair.

E. Ensure repair area is cleaned and free from debris.

F. Prepare the joints for patch placement. Maintain location of all current joints.

G. Place cement-based patch materials.

H. Finish patch, flush to adjacent, existing pavements.

I. Allow appropriate cure time based on patch material. Reseal the repaired joints

J. Pavement marking disturbed during the execution of this work need to be repainted as required.

Refer to West Apron – General Specifications, Section 32 17 23

K. Any ground coverings damaged during the execution of this work needs to be reseeded. Seed vegetation shall be compatible with air field operation. Refer to West Ramp – General Specifications, Section 32 92 19.

L. Provide final clean up.

M. Stamped drawings by a Professional Engineer (P.E.) or a Registered Architect (R.A.) are not required for this project.

N. Warranty: Contractor shall provide a one-year warranty on workmanship of the entire project in addition to any manufacturer’s warranty on materials installed. The contractor will provide any commercial warranty on materials or equipment included in the construction that exceeds this one-year, all-inclusive warranty. The commercial warranty will be issued to the Government.

2. Additional specifications for materials or requirements not included in the Statement of Work:

A. See Selfridge Design Standards.

B. West Apron – General Specifications

3. The following attachments are included in this SOW:

1. West Ramp Concrete Light Cart Pads

2. West Ramp Pavement Transition

3. CETSC PCI 2012 report

File details come from the government source that posted it. Updated .