This is an Invitation for Bid (IFB) notification document issued by the State of Hawaii, Department of Hawaiian Home Lands (DHHL), Land Management Division, for the Honokoa Gulch Brush Clearing and Ungulate Fencing Installation project located in Kawaihae, South Kohala, Island of Hawaii. The project seeks bids to furnish all labor, materials, equipment, transportation, supervision, tools, and incidentals necessary to construct approximately five miles of firebreak with a minimum 20-foot width on the south side of Honokoa Gulch and install approximately 45,000 linear feet of four-foot-high woven-wire ungulate-proof fencing on both sides of the gulch, including five fenced stream crossings and one pedestrian gate. The solicitation opened November 4, 2026, with a pre-bid conference scheduled for November 18, 2026, at 9:30 a.m. Hawaii Standard Time in Waimea, Hawaii. A Notice of Intention to Bid was due by November 20, 2026, vendor questions were due by November 23, 2026, and DHHL responses were to be posted by December 1, 2026. Bid offers must be submitted electronically through the Hawaii eProcurement System (HIePRO) no later than 2:00 p.m. Hawaii Standard Time on December 10, 2026. The contractor must complete all work within 180 calendar days after receipt of the Notice to Proceed. Bids must include a surety bid bond, and the awardee must provide performance and payment bonds.
The project is subject to Chapter 103D, Hawaii Revised Statutes, and prevailing wage requirements as determined by the State of Hawaii Department of Labor and Industrial Relations, with wage rates specified in Wage Rate Schedule Bulletin No. 511 and Addendum Bulletin No. 512. Minimum prevailing wages apply to all laborers and mechanics, including overtime compensation at one and one-half times the basic hourly rate plus fringe benefits for work on Saturdays, Sundays, legal holidays, or more than eight hours per day. Weekly certified payroll submissions are required, and contractors must post wage rate schedules at the job site. The contractor is responsible for all site examination, access arrangements, equipment transportation, and staging, as DHHL will not provide transportation, equipment, fuel, storage, or facilities unless expressly stated in contract documents. Bidders and their subcontractors must hold all valid State of Hawaii licenses and specialty licenses required to perform the work. A Standard Qualification Questionnaire (SPO Form-21) must be provided within three working days of bid opening. No specific set-asides are identified in this solicitation. The IFB reserves the right to amend by addendum, reject any or all bids, or waive defects when in the State's best interest, and offerors agree to comply with HRS 11-355 prohibiting campaign contributions during the contract term.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF HAWAI‘I
DEPARTMENT OF HAWAIIAN HOME LANDS
91-5420 Kapolei Parkway, Kapolei, HI. 96707
IFB NOTIFICATION AND
INFORMATION
FOR
FURNISHING LABOR AND MATERIALS FOR
Honokoa Gulch Brush Clearing and Ungulate Fencing Installation Kawaihae, South Kohala, Island of Hawai‘i
T.M.K. (3) 6-1-001:003 (p)
IFB No.: IFB-27-HHL-006
November 2026
Honokoa Gulch Bruch Clearing and Ungulate Fencing Installation
Table of Contents
IFB-27-HHL-006
Table of Contents
1. IFB Notification and Information
No. of Pages
1.1 Table of Contents
1.2 IFB Notice to Bidders/Invitation for Bid
1.3 Chapter 104, HRS Requirements
1.4 State Wage Rate Schedules
1.5 List of Construction Trades in Registered Apprenticeship Programs
1.6 Hawaii State Holidays (2026 & 2027)
2. Bid Submittals
2.1 Instructions for Bid Submittal
2.2 Notice of Intention to Bid
2.3 Standard Qualification Questionnaire (SPO Form-21)
2.4 Bid Offer Form
3. Sample DHHL Contract
3.1 Contract for Goods or Services (Form AG-003)
3.2 Contractor’s Standard of Conduct (Form AG-010)
3.3 Scope of Services, Attachment – S-1 (Form AG-011)
3.4 Compensation & Payment Schedule, Attachment – S-2 (Form AG-012)
3.5 Time of Performance, Attachment – S-3 (Form AG-013)
3.6 Certificate of Exemption From Civil Service, Attachment – S-4 (Form AG-
014)
3.7 Special Conditions, Attachment – S-5 (AG-015)
3.8 Contract Conditions
3.8.1 General Conditions (Form AG-008 103D)
3.8.2 DHHL Construction General Conditions
4. Sample Forms
4.1 Corporate Resolution
4.2 Bid Security, Contract Performance, and Payment Bonds
4.2.1 Exhibit A – Surety Bond
4.2.2 Exhibit B – Performance Bond (Surety)
4.2.3 Exhibit C – Performance Bond
4.2.4 Exhibit D – Labor and Material Payment Bond (Surety)
4.2.5 Exhibit E – Labor and Material Payment Bond
4.2.6 Exhibit F – NOT USED
Honokoa Gulch Bruch Clearing and Ungulate Fencing Installation
Table of Contents
IFB-27-HHL-006
4.2.7 Exhibit G – Performance Bond (Surety) for Supplemental Agreement for Goods and Services
4.2.8 Exhibit H – Performance Bond for Supplemental Agreement for Goods and Services
4.2.9 Exhibit I – Contractor Acknowledgement
4.2.10 Exhibit J – Surety Acknowledgement
4.3 SPO – 38 Certification for Hawaii Product Preference
4.4 Form 1 – Certification of Bidders Participation
4.5 Form 2 – Monthly Report of Contractor’s Participation
4.6 Certification of Compliance for Employment of State Residents
NOTICE TO BIDDERS
INVITATION FOR BID
Department of Hawaiian Home Lands Land Management Division
IFB NO.: IFB-27-HHL-006
Bid offers must be submitted electronically through the Hawaiʻi eProcurement System (HIePRO) no later than 2:00 p.m., Hawaiʻi Standard Time (HST), on December 10, 2026. The Bid Offer Form must be attached to the offer submitted through HIePRO. Bids received after the deadline or submitted by any other means will not be considered.
Schedule of Key Dates
Date Event
November 4, 2026 Solicitation opens on HIePRO
November 18, 2026 Pre-bid conference
November 20, 2026 Intention to bid due. Email form to ashley.n.tabalno@hawaii.gov
November 23, 2026 Vendor questions due through HIePRO
December 1, 2026 DHHL responses to vendor questions posted on HIePRO
December 10, 2026 Deadline to submit bids through HIePRO
Bids must be submitted through the State of Hawaiʻi eProcurement System (HIePRO). The submission deadline is 2:00 p.m. Hawaiʻi Standard Time, as stated in the IFB Notification.
Scope of Work
1. Project overview and objective
The State of Hawaiʻi, Department of Hawaiian Home Lands (DHHL), Land Management Division (LMD), is seeking bids to furnish all labor, materials, equipment, transportation, supervision, tools, and incidentals necessary to construct a firebreak and install ungulate-proof fencing along Honokoa Gulch.
The project is intended to reduce erosion and the transport of sediment from DHHL lands toward Kohala’s nearshore marine environment. Feral goats in and around Honokoa Gulch consume and damage vegetation, leaving soil more susceptible to erosion. The fencing is intended to exclude feral goats from the gulch and adjoining riparian areas so vegetation can recover. The firebreak is intended to reduce wildfire risk to Kawaihae communities and the Honokoa watershed, protect vegetation that helps stabilize the land, and provide access for fence construction and long-term land management.
The work includes the installation of approximately 45,000 linear feet of four-foot-high woven-wire ungulate fencing on both sides of Honokoa Gulch; constructing approximately five miles of firebreak with a minimum width of 20 feet on the south side of the gulch; five fenced stream crossings; fence-corridor preparation; and fabrication and installation of one step-over and step-through gate at location shown in the plans. The approved plans and DHHL-marked alignments shall establish the actual work locations and construction limits.
mailto:ashley.n.tabalno@hawaii.gov mailto:ashley.n.tabalno@hawaii.gov
2. Quantities and alignment
The quantities stated in this solicitation are estimated. The Contractor shall perform only work authorized under the executed contract and DHHL’s written Notice to Proceed. Changes to the authorized work shall be made in accordance with the contract’s written change procedures. DHHL may increase or decrease authorized quantities in accordance with the contract documents, available funding, and applicable procurement requirements.
DHHL will identify the proposed fence and firebreak alignments in the plans and during the preconstruction walk-through. The Contractor shall not relocate an alignment, stream crossing, endpoint, or access structure without DHHL’s prior written approval. Any approved adjustment shall maintain the intended firebreak and ungulate-exclusion functions while avoiding unnecessary disturbance to terrain, vegetation, drainage features, and sensitive resources.
3. Access, site conditions, and weather
The Contractor shall examine the project area and become familiar with access routes, terrain, vegetation, stream channels, drainage features, existing improvements, and conditions affecting the work. Access and equipment use may be affected by weather, terrain, road conditions, and land-management activities. The firebreak will serve as the primary access route, supplemented by existing four-wheel-drive ranch roads where available. Some portions of the alignment are accessible only on foot. Some fencing materials may need to be delivered by helicopter. The Contractor shall be responsible for transporting all required fence tools, work crew, and equipment to the installation sites. DHHL will not provide transportation, equipment, fuel, storage, or staging facilities unless expressly stated in the contract documents. Equipment may be stored on-site at the Contractor’s own risk.
Before beginning fieldwork, the Contractor shall participate in a walk-through with DHHL to confirm access routes, work limits, firebreak and fence alignments, stream-crossing locations, gate location, material-staging areas, and resource-protection requirements. The Contractor shall keep roads, gates, drainage paths, and emergency access routes unobstructed.
4. Firebreak construction
The Contractor shall construct approximately five miles of firebreak on the south side of Honokoa Gulch along the alignment shown in the plans. The finished cleared corridor shall be at least 20 feet wide, measured across the approved firebreak alignment, unless otherwise directed by DHHL through a written contract modification.
Work includes cutting, mowing, trimming, mulching, or removing brush, grasses, shrubs, and other vegetative fuels necessary to establish a continuous firebreak. Heavy machinery may be used where appropriate to the terrain and approved work limits. The Contractor shall minimize soil disturbance, rutting, erosion, damage to adjacent vegetation, and the movement of sediment into gulches or drainage channels.
The firebreak shall provide access for construction and future land-management activities. Construction of an engineered road, paved surface, all-weather driving surface, or new drainage structure is not included unless expressly shown in the plans or Bid Offer Form. The Contractor shall not grade, excavate, blade, or remove soil beyond what is necessary for the authorized clearing work without DHHL’s prior written approval.
The Contractor shall remove green waste, slash, and clear debris from the site and lawfully dispose of it off-site unless DHHL approves another method in writing. Burning or leaving combustible debris piles on-site is prohibited unless specifically authorized in writing and all required approvals have been obtained.
5. Fence corridor preparation
The Contractor shall clear and prepare the approved fence corridor as necessary to install, inspect, and maintain the ungulate fence. Unless the plans specify otherwise, clearing shall not exceed four feet on either side of the final fence centerline, for a maximum total width of 8 feet.
Clearing shall be limited to vegetation that interferes with construction, fence tensioning, inspection, or maintenance. The Contractor shall avoid unnecessary cutting of native vegetation and shall not remove large healthy native trees or vegetation outside the approved limits without DHHL’s written authorization. The Contractor shall protect cultural and natural resources identified in the plans, marked in the field, or encountered during construction.
The 20-foot minimum firebreak width applies only to the designated firebreak alignment. It does not establish the clearing width for fencing elsewhere along Honokoa Gulch.
6. Fence installation The Contractor shall furnish and install approximately 45,000 linear feet total of four-foot-high woven-wire fencing along the approved alignments on both sides of Honokoa Gulch. The stated quantity is the combined total for both sides. The fencing shall be located approximately 200 to 400 feet from the edge of the gulch, as established by the approved alignments. The fence shall form a continuous barrier between the approved gate and stream-crossing locations and shall be constructed to restrict passage by feral goats.
Work includes furnishing, transporting, handling, and installing woven wire, posts, pipe posts, braces, anchors, clips, fasteners, panels, and all other components necessary for a complete fence. The Contractor shall provide appropriate reinforcement at corners, changes in grade, gates, endpoints, and stream crossings.
The Contractor shall not attach fence fabric to living trees, standing dead trees, or other natural features unless the approved plans specifically permit that method.
7. Fenced stream crossings
The Contractor shall construct five fenced stream crossings at locations shown in the approved plans. The crossings shall maintain ungulate exclusion where the fence alignment intersects streams. Because crossings may be exposed to storm flow and debris, each crossing shall be constructed to reduce the likelihood that damage to its in-channel components will pull down adjoining upland fence.
The Contractor shall install independently braced fence sections on both banks and a crossing assembly that restricts goat passage under ordinary conditions while accounting for site-specific channel geometry, storm flows, and debris. Standard upland fencing shall not be extended across a stream channel without an approved crossing detail.
Before constructing each crossing, the Contractor shall submit a site-specific detail showing the proposed posts, braces, anchors, panels or other crossing components, connections, ground clearances, maintenance access, and method for accommodating storm flow and debris. DHHL’s written approval of the detail is required before crossing work begins. Work in or near a channel is subject to applicable environmental, cultural, historic, and other approvals and work restrictions.
8. Pedestrian Gate
Furnish and install one galvanized-steel pedestrian gate, complete with a fixed mesh covered lower section and a swinging gate above it with appropriate support, anchoring, hardware, and connections to adjacent ungulate fencing at the location and in the quantity identified in the approved plans and Bid Offer Form. The structure shall permit authorized pedestrian access while maintaining the ungulate-exclusion function of the adjacent fence.
Before fabrication, the Contractor shall submit shop drawings or sketches showing dimensions, materials, hinges, latches, closures, bracing, and ground clearances for DHHL’s written approval.
9. Materials and equipment
Unless expressly stated otherwise, the Contractor shall furnish all materials, equipment, tools, supplies, labor, and transportation necessary to complete the work. Fence materials shall be new, durable, corrosion-resistant, and suitable for the project’s outdoor conditions.
The Contractor shall submit a proposed materials list identifying manufacturers, product descriptions, dimensions, gauges, and coatings for fence fabric, posts, braces, anchors, fasteners, panels, and gates.
Substitutions require DHHL’s written approval before installation.
10. Environmental and cultural protection
The Contractor shall keep clearing and equipment operations within approved limits and shall protect streams, drainage features, vegetation, cultural resources, and existing improvements. The Contractor shall not place soil, vegetation, concrete, fuel, wire, or construction debris in any stream or drainage channel.
The Contractor shall take precautions to prevent the introduction or spread of invasive plants, insects, animals, seeds, and pathogens. Vehicles, equipment, tools, footwear, and materials shall be inspected and cleaned before entering and when leaving the work area as directed by DHHL.
If human remains, bones, cultural materials, archaeological features, rare plants, protected species, or other potentially sensitive resources are discovered, the Contractor shall immediately stop work in the affected area, protect the discovery, and notify DHHL. Work in that area shall not resume until DHHL provides written directions.
The Contractor shall comply with all applicable environmental, cultural, and historic preservation requirements communicated by DHHL. Work in an affected area shall not begin until DHHL has issued a Notice to Proceed and identified any applicable clearance, monitoring, or work restrictions.
11. Communication and completion
The Contractor shall notify the DHHL Contract Administrator at least five calendar days before beginning work at the site and shall provide an updated schedule when access, weather, or other conditions affect progress. If the Contractor leaves the site and expects to be away for more than one week, it shall notify DHHL seven calendar days before departure.
This Contract shall expire on the date on which the later of the following occurs:
(a) the State makes final payment to the CONTRACTOR in accordance with (1) paragraph 17(d) of the
General Conditions (AG-008 103D General Conditions) and (2) no dispute between the parties hereto as to the Work or other obligations of the CONTRACTOR hereunder is outstanding, or
(b) the STATE issues a Final Acceptance letter to the CONTRACTOR.
The Contractor shall complete all work within one hundred eighty (180) calendar days after receipt of the Notice to Proceed. The one hundred eighty (180)-calendar-day performance period shall occur within the contract term. Any extension of the contract term or performance period shall be subject to DHHL approval and shall comply with HRS Chapter 103D.
Upon completion of each work segment, the Contractor shall remove green waste, scrap wire, damaged posts, packaging, tools, equipment, fuel containers, food waste, and other debris. Any excess materials DHHL elects to retain shall be placed where DHHL directs. DHHL will inspect the work before acceptance and payment. The Contractor shall correct nonconforming work at no additional cost to DHHL.
Specifications
1. General
The completed firebreak and fence shall conform to the approved plans, these specifications, and DHHL-approved field adjustments. The fence’s primary purpose is to exclude feral goats from the Honokoa Gulch riparian corridor. The Contractor shall construct a continuous, securely tensioned barrier between approved access structures and stream crossings, without gaps that allow goats to pass beneath, through, or around it.
The firebreak, upland fence, stream crossings, and gate are separate construction elements. Compliance with the specification for one element does not excuse incomplete or nonconforming work on another.
2. Woven-wire fence
The base fence shall consist of four-foot-high woven wire meeting the following minimum requirements:
Component Minimum specification
Woven wire 48-inch height; minimum 12.5-gauge wire; 13 horizontal wires; maximum six-inch by six-inch mesh opening
Wire coating Bezinal, XtraLife, Galfan, or DHHL-approved comparable corrosion-resistant coating
T-posts Galvanized T-133 posts, five feet long, with anchor plate
Pipe posts Galvanized Schedule 40 pipe, minimum 2⅞-inch outside diameter
Fence clips Corrosion-resistant, minimum 11 gauge; at least five per T-post
Smooth wire Minimum nine gauge with corrosion-resistant coating
Wire shall be secured to posts without damaging its protective coating. It shall be properly tensioned, with no excessive sagging or “bellying.” A 20-pound lateral pull applied midway between two posts shall not move the fence more than six inches from the fence centerline. The Contractor shall repair or replace damaged materials as directed by DHHL.
3. T-posts and ground clearance
T-posts shall be spaced no more than 10 feet apart and closer where terrain, changes in grade, drainage features, or fence tension require it. They shall be driven at least 24 inches into the ground using a method that does not bend the post or damage its coating. Posts shall be installed at high and low points along the alignment. The bottom of the woven wire shall be flush with the ground wherever practicable and no more than three inches above the ground at any point along the upland fence. Where terrain would otherwise create a larger gap, the Contractor shall use additional posts, secure anchors, approved skirting, or another DHHL-approved treatment.
Loose rocks or temporary weights shall not be used to hold the fence down.
At least five clips shall secure the wire to each T-post: one at the top horizontal wire, one at the bottom horizontal wire, and three spaced between them. Clips shall be tightened sufficiently to prevent movement without breaking the clip or damaging the wire.
4. Pipe posts and bracing
Pipe posts shall be placed at fence corners, endpoints, gates, stream crossings, significant changes in grade, and intervals not exceeding 100 feet along the upland fence, unless the plans specify a different spacing. Pipe posts shall be set or driven at least 30 inches into the ground and capped to prevent water accumulation.
H-braces shall be installed at fence-section endpoints, gate openings, stream-crossing approaches, and fence-line changes in direction greater than 30 degrees. Additional bracing shall be provided where needed to maintain wire tension and resist expected animal pressure. Braces shall consist of galvanized pipe posts and rails with appropriate tensioning wire or approved welded connections. Welds, cuts, and areas of damaged galvanized coating shall be protected with cold-galvanizing compound or an equivalent approved treatment.
5. Stream-crossing assemblies
Each of the five stream crossings shall follow a DHHL-approved, site-specific detail. At a minimum, the detail shall address:
• Channel and bank geometry, fence alignment, and crossing location.
• Independent bracing and anchoring of upland fence on each bank.
• The proposed in-channel barrier and its connections to the bank-supported fence.
• How the crossing restricts goat passage under ordinary conditions.
• How storm flow and accumulated debris will pass through, over, under, or around the assembly without unnecessarily damaging adjoining fence.
• Inspection, repair, and replacement of components after storm events.
• Required construction access, limits of disturbance, and erosion- and sediment-control measures.
The Contractor shall construct each crossing in accordance with its approved detail. A change that materially affects the crossing’s design, construction cost, or schedule shall be addressed under the contract-change provisions before the changed work is performed.
6. Gate and access structure Pedestrian gate will need to be fabricated (and materials provided by the Contractor). Gates will be a minimum of 75” working height with additional six (6”) inch stub-outs on bottom. Total length of vertical pipes will be 81” minimum, 96” maximum – single piece pipe (not welded). Total width is 36” with a swinging gate 28” W by 36” H. There should be a 32” high fixed step over. Square steel dipped galvanized paneling will be used for fixed gate mesh portions. Perimeter pipe will be 2 3/8” OD Schedule 40 galvanized steel pipe. The gate will be designed as a self-closing gate, using heavy duty weather resistant Tru-close hinges or equivalent. All hardware will be galvanized, including any screws, bolts or mounting hardware. The gate will swing in only one direction and have a gate stop. The step over must allow human traffic while preventing ungulates from crossing (See the Pedestrian Gate Diagram and picture example, below). The gate will be braced in two directions on hinge side, one to the vertical pipes of an H-brace, the other perpendicular to the hinge side upright of the gate. The perpendicular brace pipe will be set on the inside of the fence.
7. Firebreak acceptance
The completed firebreak shall be continuous along the authorized alignment and at least 20 feet wide, measured horizontally across the approved clearing limits. Vegetation and debris left within the corridor shall not defeat its intended fuel-reduction function or obstruct approved construction and management access. The Contractor shall stabilize or repair ruts, disturbed drainage paths, or other damage caused by its operations as directed by DHHL. DHHL shall inspect the cleared limits, debris removal, and affected access areas before accepting the firebreak work.
8. Final inspection
DHHL shall inspect completed fence sections, gates, stream crossings, firebreak segments, and cleanup. Work found incomplete or nonconforming shall be corrected before acceptance. Acceptance of an individual segment does not waive the Contractor’s responsibility for other work or for deficiencies covered by the contract.
Bidder requirements, bid documents, and pre-bid conference To be eligible to bid, bidders and/or their subcontractors must hold all valid State of Hawaiʻi licenses and specialty licenses required to perform the work. A surety bid bond is required with or before bid submittal. The awardee must also provide performance and payment bonds to ensure completion of the work in accordance with the contract specifications and payment for labor and materials.
This project is subject to Chapter 103D, Hawaiʻi Revised Statutes (HRS), and the payment of no less than the prevailing wages promulgated by the State of Hawaiʻi Department of Labor and Industrial Relations.
Bid documents may be examined or obtained through HIePRO. Interested bidders are responsible for checking HIePRO for addenda issued by DHHL.
All prospective bidders and offerors are invited to a pre-bid conference at 9:30 a.m. HST on November 18, 2026, at 61-3240 Maluokalani Street, Waimea, Hawaii 96743. Subcontractors and union representatives are also invited. The conference will provide an opportunity to ask questions about the contractual requirements and technical aspects of the project.
A written Notice of Intention to Bid must be received by DHHL’s Land Management Division no later than November 20, 2026. Email the notice to ashley.n.tabalno@hawaii.gov.
A properly executed and notarized Standard Qualification Questionnaire for Offerors, SPO Form-21, is required and must be made available within 3 working days of bid opening as provided in the Instructions for Bid Submittal. The questionnaire is available from State Forms Central.
Bids must comply with the IFB requirements. Noncompliant bids may be disqualified. DHHL reserves the right to amend the IFB by written addendum, reject any or all bids, or waive defects in bids when DHHL determines that doing so is in the State’s best interest.
Campaign contributions by State and county contractors prohibited. An offeror awarded a contract under this solicitation agrees to comply with HRS § 11-355, which prohibits campaign contributions by a State or county government contractor during the term of a contract paid with funds appropriated by a legislative body, from execution through completion of the contract.
Questions concerning the scope of work, specifications, bid requirements, or other terms of this solicitation shall be submitted through HIePRO by November 23, 2026. DHHL’s responses will be posted on HIePRO. Any clarification or revision that changes the solicitation requirements will be issued by written addendum through HIePRO. Oral statements or individual email communications shall not modify the solicitation.
Dated at Kapolei, Hawaiʻi, this 4th day of November 2026.
DEPARTMENT OF HAWAIIAN HOME LANDS
Kali Watson, Chairperson Hawaiian Homes Commission
Posted on the internet at: https://hiepro.ehawaii.gov/sav-search.html https://hiepro.ehawaii.gov/sav-search.html mailto:ashley.n.tabalno@hawaii.gov http://spo.hawaii.gov/wp-content/uploads/2013/12/spo-021.pdf https://hiepro.ehawaii.gov/sav-search.html https://hiepro.ehawaii.gov/sav-search.html mailto:ashley.n.tabalno@hawaii.gov http://spo.hawaii.gov/wp-content/uploads/2013/12/spo-021.pdf https://hiepro.ehawaii.gov/sav-search.html https://stateofhawaii.na1.adobesign.com/verifier?tx=CBJCHBCAABAAOZepRKUf2Eco_jjDR71SKO8Tbo0pujRi
Requirements of Chapter 104, HRS Wages and Hours of Employees on Public Works Law
Chapter 104, HRS, applies to every public works construction project over $2,000, regardless of the method of procurement or financing (purchase order, voucher, bid, contract, lease arrangement, warranty).
Rate of Wages for Laborers and Mechanics
• Minimum prevailing wages (basic hourly rate plus fringe benefits), as determined by the Director of Labor and Industrial Relations and published in wage rate schedules, shall be paid to the various classes of laborers and mechanics working on the job site.
[§104-2(a), (b), Hawaii Revised Statutes (HRS)]
• If the Director of Labor determines that prevailing wages have increased during the performance of a public works contract, the rate of pay of laborers and mechanics shall be raised accordingly. [§104-2(a) and (b), HRS; §12-22-3(d) Hawaii Administrative Rules (HAR)]
Overtime
• Laborers and mechanics working on a Saturday, Sunday, or a legal holiday of the State or more than eight hours a day on any other day shall be paid overtime compensation at one and one-half times the basic hourly rate plus the cost of fringe benefits for all hours worked. [§§104-1(5), 104-2(c), HRS]
Weekly Pay
• Laborers and mechanics employed on the job site shall be paid their full wages at least once a week, without deduction or rebate, except for legal deductions, within five working days after the cutoff date. [§104-2(d), HRS]
Posting of Wage Rate Schedules
• Wage rate schedules shall be posted by the contractor in a prominent and easily accessible place at the job site. A copy of the entire wage rate schedule shall be given to each laborer and mechanic employed under the contract, except when the employee is covered by a collective bargaining agreement. [§104-2(d), HRS]
Withholding of Accrued Payments
• If necessary, the contracting agency may withhold accrued payments to the contractor to pay to laborers and mechanics employed by the contractor or subcontractor on the job site any difference between the wages required by the public works contract or specifications and the wages received. [§104-2(e), HRS]
Certified Weekly Payrolls and Payroll Records
• A certified copy of all payrolls shall be submitted weekly to the contracting agency.
• The contractor is responsible for the submission of certified copies of the payrolls of all subcontractors. The certification shall affirm that the payrolls are correct and complete, that the wage rates listed are not less than the applicable rates contained in the applicable wage rate schedule, and that the classifications for each laborer or mechanic conform with the work the laborer or mechanic performed. [§104-3(a), HRS]
• Payroll records shall be maintained by the contractor and subcontractors for three years after completion of construction.
The records shall contain:
• the name and home address of each employee
• the employee's correct classification
• rate of pay (basic hourly rate+ fringe benefits)
• daily and weekly hours worked
• weekly straight time and overtime earnings
• amount and type of deductions
• actual wages paid
• date of payment
• Records shall be made available for inspection by the contracting agency, the Department of Labor and Industrial Relations, and any of its authorized representatives, who may also interview employees during working hours on the job. [§104- 3(b), HRS]
-1-eH I 04-3 (Replaces Attachment I) I 1/03
Termination of Work on Failure to Pay Wages
• If the contracting agency finds that any laborer or mechanic employed on the job site by the contractor or any subcontractor has not been paid prevailing wages or overtime, the contracting agency may, by written notice to the contractor, terminate the contractor's or subcontractor's right to proceed with the work or with the part of the work in which the required wages or overtime compensation have not been paid. The contracting agency may complete this work by contract or otherwise, and the contractor or contractor's sureties shall be liable to the contracting agency for any excess costs incurred. [§104-4, HRS]
Apprentices and Trainees
• In order to be paid apprentice or trainee rates, apprentices and trainees must be parties to an agreement either registered with or recognized as a USDOL nationally approved apprenticeship program by the Department of Labor and Industrial Relations, Workforce Development Division. [§12-22-6(1), HAR]
• The number of apprentices or trainees on any public work in relation to the number of journeyworkers in the same craft classification as the apprentices or trainees employed by the same employer on the same public work may not exceed the ratio allowed under the apprenticeship or trainee standards registered with or recognized by the Department of Labor and Industrial Relations. A registered or recognized apprentice receiving the joumeyworker rate will not be considered a joumeyworker for the purpose of meeting the ratio requirement. [§12-22-6(2), HAR]
Enforcement
• To ensure compliance with the law, DLIR and the contracting agency will conduct investigations of contractors and subcontractors. If a contractor or subcontractor violates the law, the penalties are:
■ First Violation
■ Second Violation
■ Third Violation
Equal to 10% of back wages found due or $25 per offense, whichever is greater.
Equal to amount of back wages found due or $100 for each offense, whichever is greater.
Equal to two times the amount of back wages found due or $200 for each offense, whichever is greater; and Suspension from doing any new work on any public work of a governmental contracting agency for three years.
"EEFOEVN /P. 1,
"UUBDINFOU 3
State ofHawai'i
DEPARTMENT OF LABOR AND INDUSTRIAL RELATIONS
Princess Ruth Ke'elikolani Building 830 Punchbowl Street
Honolulu, Hawai'i 96813
September 15, 2026
WAGE RATE SCHEDULE BULLETIN NO. 512
Addendum to Wage Rate Schedule Bulletin No. 511
This addendum lists changes in wage rates to Wage Rate Schedule (WRS) Bulletin No. 51I. The rates contained herein are recognized by the Director of Labor and Industrial Relations to be prevailing on public construction work for the purposes of Chapter 104, Hawai'i Revised Statutes. Wage rates listed on WRS Bulletin No.
511 are still in effect, except for the changes noted in this addendum.
For addenda or additional wage rate schedules, please consult the Internet at http://labor.hawaii.gov/rs/wage-rate-schedule/.
Questions on the schedules should be referred to the Research and Statistics Office at (808) 586-8799.
The next wage rate schedule will be issued on or about February
15, 2027.
JADE T. BUTAY
Director
STATE OF HAWAI'I
JOSH GREEN, M.D., Governor
JADE T. BUTAY, Director
WILLIAM G. KUNSTMAN, Deputy Director
RESEARCH AND STATISTICS OFFICE
ASCENCION LOPEZ, Research Statistician
SCOTT S. WHEELER, Supervisor
In cooperation with:
WAGE STANDARDS DIVISION
SHERYL LEE, Administrator MARI IMAMURA, Staff Supervisor http://labor.hawaii.gov/rs/wage-rate-schedule/ http://labor.hawaii.gov/rs/wage-rate-schedule/
This Page Intentionally Left Blank
511 I 16
Dredges]
WAGE RATE SCHEDULE - Bulletin No. 512 Addendum to Wage Rate Schedule Bulletin No. 511 i ICARPENTER: 2 Journeyman Carpenter {Form/Framer/Rough/Finish) 08/31/2026 $87.24 $56.75 $30.49 1,13 511 2 Journeyman Carpenter {Form/Framer/Rough/Finish) 08/30/2027 $89.29 $58.00 $31.29 1,12,13 511 2 Journeyman Carpenter (Form/Framer/Rough/Finish) 09/04/2028 $91.34 $59.50 $31.84 1,12,13 511 3 Millwright and Machine Erector 08/31/2026 $87.49 $57.00 $30.49 1,13 511 3 Millwright and Machine Erector 08/30/2027 $89.54 $58.25 $31.29 1,12,13 511 3 Millwright and Machine Erector 09/04/2028 $91.59 $59.75 $31.84 1,12,13 511 4 Power Saw Operator {2 h.p. & over) 08/31/2026 $87.39 $56.90 $30.49 1,13 511 4 Power Saw Operator (2 h.p. & over) 08/30/2027 $89.44 $58.15 $31.29 1,12,13 511 4 Power Saw Operator (2 h.p. & over) 09/04/2028 $91.49 $59.65 $31.84 1,12,13 511 CEMENT FINISHER: 5 Journeyperson Cement Finisher 09/14/2026 $85.88 $46.85 $39.03 2,13 511 5 Journeyperson Cement Finisher 09/05/2027 $85.93 $46.90 $39.03 2,12,13 511 5 Journeyperson Cement Finisher 09/04/2028 $93.10 $53.67 $39.43 2,12,13 511 6 Trowel Machine Operator 09/14/2026 $86.03 $47.00 $39.03 2,13 511 6 Trowel Machine Operator 09/05/2027 $86.08 $47.05 $39.03 2,12,13 511 6 Trowel Machine Operator 09/04/2028 $93.25 $53.82 $39.43 2,12,13 511 CHAIN-LINK FENCE ERECTOR: 7 Chain-Link Fence Erector 09/29/2025 $50.70 $29.75 $20.95 10,13 511 7 Chain-Link Fence Erector 10/05/2026 $52.90 $30.90 $22.00 10,13 511 7 Chain-Link Fence Erector 10/04/2027 $55.20 $32.10 $23.10 10,13 511 7 Chain-Link Fence Erector 10/02/2028 $57.50 $33.30 $24.20 10,13
1lorinator 09/14/2026 $44.38 $40.43 $3.95
511 I DIVER - AQUA LUNG DIVING (Scuba Diver): 9 Stand-By Diver 09/14/2026 $101.87 $65.16 $36.71 12,13 511 I I 511 I I DIVER - DIVING OTHER THAN AQUA LUNG (Surface
Supplied Diving):
12 Tender 09/14/2026 $98.84 $62.13 $36.71 12,13
511 I I 13 Stand-By Diver 09/14/2026 $101.87 $65.16 $36.71 I 3,12,13
511 I I 14 Diver 09/14/2026 $120.62 $83.91
512 I *IDRAPERY INSTALLER: 15 Drapery Installer 09/14/2026 $52.05 $45.92
$36.71 I 3,12,13
$6.13
I DREDGING - CLAMSHELL AND HYDRAULIC SUCTION -
CLAMSHELL OR DIPPER DREDGES:
Clamshell or Dipper Operator 09/14/2026 $99.56 $62.85 $36.71 I 11,12,13
511 I I 17 Mechanic or Welder, Watch Engineer [Clamshell or Dipper 09/14/2026 $98.90 $62.19
$36.71 I 12,13
511 18 IDeckmate, Barge Mate [Clamshell or Dipper Dredges] 09/14/2026 $98.50 $61.79 $36.71 I 12,13
511 19 I Bargeman, Deckhand, Fireman and Oiler [Clamshell or 09/14/2026 $96.84 $60.13 $36.71 12,13 Dipper Dredges]
10 Scuba Diver (Wet) (up to 30 feet) 09/14/2026 $111.25 $74.54 $36.71 12,13 11 Scuba Diver (Wet) (over 30 feet) 09/14/2026 $120.62 $83.91 $36.71 12,13
* Indicates a wage, fringe benefit, remark, or title change from the previous bulletin. Page 1
State of Hawai'i
Princess Ruth Ke'elikolani Building 830 Punchbowl Street
Honolulu, Hawai'i 96813
September 14, 2026
WAGE RATE SCHEDULE BULLETIN NO. 511
This schedule of wage rates contained herein is recognized by the Director of Labor and Industrial Relations to be prevailing on public construction work for the purposes of Chapter 104, Hawai'i Revised Statutes. The schedule of wage rates determines the applicable wage determination for each classification and does not impose any staffing requirements for any classification.
As required by law, future wage rates for laborers and mechanics are incorporated into this bulletin based on available information and are subject to change. Whenever the Director determines that the prevailing wage has increased as shown in the wage rate schedule, the contractor must increase the wages accordingly during the performance of the contract. For addenda or additional wage rate schedules, please consult the Internet at http://labor.hawaii.gov/wsd.
The Apprentice Schedule is available on the Internet or upon request from the Wage Standards Division. Pursuant to Section 12-22-6, Hawai'i Administrative Rules, the Apprentice Schedule is applicable only to apprentices who are parties to apprenticeship agreements registered with or recognized by the Department of Labor and Industrial Relations.
Questions on the schedules should be referred to the Research and Statistics Office at (808) 586-8799.
STATE OF HAWAI'I
JOSH GREEN, M.D., Governor
JADE T. BUTAY, Director
WILLIAM G. KUNSTMAN, Deputy Director
RESEARCH AND STATISTICS OFFICE
ASCENCION LOPEZ, Research Statistician
SCOTT S. WHEELER, Supervisor
In cooperation with:
WAGE STANDARDS DIVISION
SHERYL LEE, Administrator
MARI IMAMURA, Staff Supervisor
The next wage rate schedule will be issued on or about February 15, 2027.
/4vr�
JADE T. BUTAY
Director http://labor.hawaii.gov/wsd http://labor.hawaii.gov/wsd
This Page Intentionally Left Blank
WAGE RATE SCHEDULE - Bulletin No. 511
511 I *IDRAPERY INSTALLER: 15 Drapery Installer 09/14/2026 $78.19 $75.00
$3.19
DGES:
511 19 I Bargeman, Deckhand, Fireman and Oiler [Clamshell or 09/14/2026 $96.84 $60.13 $36.71 Dipper Dredges]
I 12,13
BOILERMAKER: 1 Boilermaker/ Blacksmith 02/16/2026 $76.33 $42.64 $33.69 13 511 * CARPENTER: 2 Journeyman Carpenter (Form/Framer/Rough/Finish) 08/31/2026 $87.24 $56.75 $30.49 1,13 511 2 Journeyman Carpenter (Form/Framer/Rough/Finish) 08/30/2027 $89.29 $58.00 $31.29 1,12,13 511 2 Journeyman Carpenter (Form/Framer/Rough/Finish) 09/04/2028 $91.34 $59.50 $31.84 1,12,13 511 3 Millwright and Machine Erector 08/31/2026 $87.49 $57.00 $30.49 1,13 511 3 Millwright and Machine Erector 08/30/2027 $89.54 $58.25 $31.29 1,12,13 511 3 Millwright and Machine Erector 09/04/2028 $91.59 $59.75 $31.84 1,12,13 511 4 Power Saw Operator (2 h.p. & over) 08/31/2026 $87.39 $56.90 $30.49 1,13 511 4 Power Saw Operator (2 h.p. & over) 08/30/2027 $89.44 $58.15 $31.29 1,12,13 511 4 Power Saw Operator (2 h.p. & over) 09/04/2028 $91.49 $59.65 $31.84 1,12,13 511 * CEMENT FINISHER: 5 Journeyperson Cement Finisher 09/14/2026 $85.88 $46.85 $39.03 2,13 511 5 Journeyperson Cement Finisher 09/05/2027 $85.93 $46.90 $39.03 2,12,13 511 5 Journeyperson Cement Finisher 09/04/2028 $93.10 $53.67 $39.43 2,12,13 511 6 Trowel Machine Operator 09/14/2026 $86.03 $47.00 $39.03 2,13 511 6 Trowel Machine Operator 09/05/2027 $86.08 $47.05 $39.03 2,12,13 511 6 Trowel Machine Operator 09/04/2028 $93.25 $53.82 $39.43 2,12,13 511 CHAIN-LINK FENCE ERECTOR: 7 Chain-Link Fence Erector 09/29/2025 $50.70 $29.75 $20.95 10,13 511 7 Chain-Link Fence Erector 10/05/2026 $52.90 $30.90 $22.00 10,13 511 7 Chain-Link Fence Erector 10/04/2027 $55.20 $32.10 $23.10 10,13 511 7 Chain-Link Fence Erector 10/02/2028 $57.50 $33.30 $24.20 10,13 511 * CHLORINATOR: 8 Chlorinator 09/14/2026 $44.38 $40.43 $3.95
511 * DIVER - AQUA LUNG DIVING (Scuba Diver): 9 Stand-By Diver 09/14/2026 $101.87 $65.16 $36.71 12,13 511 10 Scuba Diver (Wet) (up to 30 feet) 09/14/2026 $111.25 $74.54 $36.71 12,13 511 11 Scuba Diver (Wet) (over 30 feet) 09/14/2026 $120.62 $83.91 $36.71 12,13
511 I * DIVER - DIVING OTHER THAN AQUA LUNG (Surfa ce 12 Tender 09/14/2026 $98.84 $62.13 $36.71 12,13
Supplied Diving):
511 I I
13 Stand-By Diver 09/14/2026 $101.87 $65.16 $36.71 I 3,12,13
511 I I I 14 Diver 09/14/2026 $120.62 $83.91 $36.71 I 3,12,13
511 I *I DREDGING - CLAMSHELL A
CLAMSHELL OR DIPPER DRE
D HYDRAULIC SUCTION - 16 Clamshell or Dipper Operator 09/14/2026 $99.56 $62.85 $36.71 I 11,12,13
511 I I 17 Mechanic or Welder, Watch Engineer [Clamshell or Dipper Dredges] 09/14/2026 $98.90 $62.19 $36.71 I 12,13
18 IDeckmate, Barge Mate [Clamshell or Dipper Dredges] 09/14/2026 $98.50 $61.79 $36.71
12,13
• Indicates a wage, fringe benefit, remark, or title change from the previous bulletin. Page 2
I
*I DREDGING - CLAMSHELL AND HYDRAULIC SUCTION -
HYDRAULIC SUCTION DREDGES:
511 I
511 *I DREDGING - CLAMSHELL AND HYDRAULIC SUCTION -
DERRICKS:
*I DREDGING - CLAMSHELL AND HYDRAULIC SUCTION -
BOAT OPERATORS:
511 * DRYWALL & ACOUSTICAL WORKER AND LATHER:
511 * DRYWALL TAPER/FINISHER:
511 I I I 35 Journeyman Taper 01/01/2029 $92.65 511 * ELECTRICIAN: Inside 36 Cable Splicer [Inside] 09/14/2026 $103.07 511 I I I 37 Journeyman Wireman [Inside] 09/14/2026 $94.06
$57.00 $67.80 $60.00
$35.65 $35.27 I 4,13 $34.06 I 4,13
Leverman 09/14/2026 $99.20 $62.49
$36.71
Watch Engineer (Steam or Electric) 09/14/2026 $99.05 $62.34
I 22
I Mechanic or Welder [Hydraulic Suction Dredges] 09/14/2026 $98.90 $62.19
I 23
I Dozer Operator 09/14/2026 $98.84 $62.13
I 24
I Deckmate [Hydraulic Suction Dredges] 09/14/2026 $98.50 $61.79
I 25
/Winchman (Stern Winch on Dredge) 09/14/2026 $98.39 $61.68
Deckhand (can operate Anchor Scow under direction of
26 IDeckmate), Fireman, Leveeman, Oiler [Hydraulic Suction 09/14/2026 $96.84 $60.13 $36.71 12,13 Dredges]
Operators (Derricks, Piledrivers, and Cranes) 09/14/2026 $99.56 $62.85
Saurman Type Dragline (over five [5] cubic yards) 09/14/2026 $98.90 $62.19
29 Deckmate, Saurman Type Dragline (up to and including five [5] cubic yards) [Derricks]
09/14/2026 $98.50 $61.79 $36.71 12,13
Deckhand, Fireman, Oiler [Derricks] 09/14/2026 $96.84 $60.13
Master Boat Operator 09/14/2026 $99.20 $62.49
Boat Operator 09/14/2026 $99.05 $62.34
Boat Deckhand 09/14/2026 $96.84 $60.13
Journeyman [Drywall & Acoustical Worker and Lather] 08/31/2026 $87.49 $57.00 $30.49 1,13
34 Journeyman [Drywall & Acoustical Worker and Lather] 08/30/2027 $89.54 $58.25 $31.29 1,12,13 34 Journeyman [Drywall & Acoustical Worker and Lather] 09/04/2028 $91.59 $59.75 $31.84 1,12,13 35 Journeyman Taper 01/01/2026 $83.84 $49.54 $34.30
35 Journeyman Taper 01/01/2027 $86.70 $51.90 $34.80 35 Journeyman Taper 01/01/2028 $89.63 $54.58 $35.05
* Indicates a wage, fringe benefit, remark, or title change from the previous bulletin. Page 3
38 Cable Splicer [Outside] 09/14/2026 $103.07 $67.80 $35.27 4,13
511 39 Journeyman Wireman [Outside] 09/14/2026 $94.06 $60.00 $34.06 4,13 511 40 Journeyman Lineman 09/14/2026 $108.77 $74.28 $34.49 4,13 511 41 Heavy Equipment Operator 09/14/2026 $85.59 $54.00 $31.59 4,13 511 42 Groundman 09/14/2026 $72.88 $45.00 $27.88 4,13 511 * ELEVATOR CONSTRUCTOR: 43 Mechanic (5 years and over) [Elevator Constructor] 09/14/2026 $122.07 $76.93 $45.14 13,14 511 43 Mechanic (under 5 years) [Elevator Constructor] 09/14/2026 $120.53 $76.93 $43.60 13,14 511 * EQUIPMENT OPERATOR: 44 Group 1 09/14/2026 $96.56 $59.85 $36.71 5,12,13 511 45 Group 2 09/14/2026 $96.67 $59.96 $36.71 5,12,13 511 46 Group 3 09/14/2026 $96.84 $60.13 $36.71 5,12,13 511 47 Group 4 09/14/2026 $97.11 $60.40 $36.71 5,12,13 511 48 Group 5 09/14/2026 $97.42 $60.71 $36.71 5,12,13 511 49 Group 6 09/14/2026 $98.07 $61.36 $36.71 5,12,13 511 50 Group 7 09/14/2026 $98.39 $61.68 $36.71 5,12,13 511 51 Group 8 09/14/2026 $98.50 $61.79 $36.71 5,12,13 511 52 Group 9 09/14/2026 $98.61 $61.90 $36.71 5,12,13 511 53 Group 9A 09/14/2026 $98.84 $62.13 $36.71 5,12,13 511 54 Group 10 09/14/2026 $98.90 $62.19 $36.71 5,12,13 511 55 Group lOA 09/14/2026 $99.05 $62.34 $36.71 5,12,13 511 56 Group 11 09/14/2026 $99.20 $62.49 $36.71 5,12,13 511 57 Group 12 09/14/2026 $99.56 $62.85 $36.71 5,12,13 511 58 Group 12A 09/14/2026 $99.92 $63.21 $36.71 5,12,13 511 59 Group 13 09/14/2026 $96.84 $60.13 $36.71 12,13 511 60 Group 13A 09/14/2026 $97.11 $60.40 $36.71 12,13 511 61 Group 13B 09/14/2026 $97.42 $60.71 $36.71 12,13 511 62 Group 13C 09/14/2026 $98.07 $61.36 $36.71 12,13 511 63 Group 13D 09/14/2026 $98.39 $61.68 $36.71 12,13 511 64 Group 13E 09/14/2026 $98.50 $61.79 $36.71 12,13 511 * FLOOR LAYER (CARPET, LINOLEUM & SOFT TILE): 65 Journeyperson [Floor Layer] 03/01/2026 $81.05 $45.30 $35.75 13 511 65 Journeyperson [Floor Layer] 02/28/2027 $84.30 $47.65 $36.65 13 511 65 Journeyperson [Floor Layer] 03/05/2028 $87.40 $50.00 $37.40 12,13 511 * GLAZIER: 66 Journeyperson [Glazier] 09/14/2026 $93.45 $52.50 $40.95 6,13 511 HEAT AND FROST INSULATOR: 67 Mechanic [Heat and Frost Insulator] 09/07/2025 $76.65 $46.90 $29.75 7,13 511 * HELICOPTER WORK: 68 Pilot 09/14/2026 $100.73 $64.02 $36.71 12,13 511 69 Co-Pilot 09/14/2026 $100.56 $63.85 $36.71 12,13 511 70 Airborne Hoist Operator 09/14/2026 $100.42 $63.71 $36.71 12,13 511 * IRON WORKER: 71 Journeyman [Iron Worker] 09/14/2026 $95.25 $53.00 $42.25 8,13 511 * LABORER - LABORER: 72 Laborer I 08/31/2026 $71.66 $43.95 $27.71 1,13 511 72 Laborer I 08/30/2027 $73.61 $45.05 $28.56 1,13 511 72 Laborer I 09/04/2028 $75.56 $46.15 $29.41 1,13 511 * LABORER - LABORER: 73 Laborer II 08/31/2026 $69.06 $41.35 $27.71 1,13 511 73 Laborer II 08/30/2027 $71.01 $42.45 $28.56 1,13 511 73 Laborer II 09/04/2028 $72.96 $43.55 $29.41 1,13
• Indicates a wage, fringe benefit, remark, or title change from the previous bulletin. Page 4
511 * LABORER - LABORER: 74 Licensed Powderman 08/31/2026 $72.66 $44.95 $27.71 1,13 511 74 Licensed Powderman 08/30/2027 $74.61 $46.05 $28.56 1,13 511 74 Licensed Powderman 09/04/2028 $76.56 $47.15 $29.41 1,13
511 * LABORER - LABORER: 75 Driller 08/31/2026 $74.66 $46.95 $27.71 1,13 511 75 Driller 08/30/2027 $76.61 $48.05 $28.56 1,13 511 75 Driller 09/04/2028 $78.56 $49.15 $29.41 1,13 511 * LABORER- LABORER: 76 Gunite or Shotcrete Operator 08/31/2026 $72.16 $44.45 $27.71 1,13 511 76 Gunite or Shotcrete Operator 08/30/2027 $74.11 $45.55 $28.56 1,13 511 76 Gunite or Shotcrete Operator 09/04/2028 $76.06 $46.65 $29.41 1,13
511 * LABORER - LABORER: 77 Mason Tender/Hod Carrier 08/31/2026 $72.16 $44.45 $27.71 1,13 511 77 Mason Tender/Hod Carrier 08/30/2027 $74.11 $45.55 $28.56 1,13 511 77 Mason Tender/Hod Carrier 09/04/2028 $76.06 $46.65 $29.41 1,13 511 * LABORER - LABORER: 78 High Scaler (Working Suspended) 08/31/2026 $72.16 $44.45 $27.71 13 511 78 High Scaler (Working Suspended) 08/30/2027 $74.11 $45.55 $28.56 13
511 *
511 I LABORER - LABORER: 79
and/or cable-suspended scaffold or work platform)
511 79 I Window Washer (Outside-Working from bosun's chair and/or cable-suspended scaffold or work platform)
511 I I
511 I * LABORER - LABORER:
511 I
511 I
* LABORER - UNDERGROUND WORK {Worker in a raise, shaft, or tunnel):
I I
* jLABORER - UNDERGROUND WORK (Worker in a raise, shaft, or tunnel): I
I I I
I I I
78 High Scaler (Working Suspended) 09/04/2028 $76.06 $46.65 $29.41 13 Window Washer (Outside-Working from bosun's chair
Window Washer (Outside-Working from bosun's chair and/or cable-suspended scaffold or work platform) 09/04/2028 $75.06 $45.65
$29.41
80 Light/Final Clean-up (Janitorial) Laborer 08/31/2026 $55.82 $32.50 $23.32 1,13 80 Light/Final Clean-up (Janitorial) Laborer 08/30/2027 $57.32 $33.05 $24.27 1,13 80 Light/Final Clean-up (Janitorial) Laborer 09/04/2028 $58.82 $33.60 $25.22 1,13
81 Group 1 08/31/2026 $72.26 $44.55 $27.71 13
81 Group 1 08/30/2027 $74.21 $45.65
$28.56
81 Group 1 09/04/2028 $76.16 $46.75
82 Group 2 08/31/2026 $73.76 $46.05
$27.71
82 Group 2 08/30/2027 $75.71 $47.15
82 Group 2 09/04/2028 $77.66 $48.25
511 I
511 I
08/31/2026 $71.16 $43.45 $27.71 I 13
I 08/30/2021 I $73.11 I $44.55 I $28.56 I 13
* Indicates a wage, fringe benefit, remark, or title change from the previous bulletin. Page 5
* LABORER - UNDERGROUND WORK (Worker in a raise,I
IGroup 3
Group 3
08/31/2026
08/30/2027
$74.26
$76.21
$46.55
$47.65
83 Group 3 09/04/2028
$78.16
$48.75
$29.41 I 13
511 I * LABORER - UNDERGROUND WORK (Worker in a raise, 84 Group 4 08/31/2026
$75.26
$47.55
I $27.71
84 Group 4 08/30/2027
$77.21
$48.65
84 Group 4 09/04/2028
$79.16
$49.75
511 * LABORER - UNDERGROUND WORK (Worker in a raise, 85 Group 5 08/31/2026 $75.51 $47.80 $27.71 13
85 Group 5 08/30/2027
$77.46
$48.90
85 Group 5 09/04/2028
$79.41
$50.00
*I LABORER - UNDERGROUND WORK (Worker in a raise, 86 Group 6 08/31/2026
$75.61
$47.90
13.
86 Group 6 08/30/2027
$77.56
$49.00
86 Group 6 09/04/2028
$79.51
$50.10
511 * LABORER - UNDERGROUND WORK (Worker in a raise, 87 Group 7 08/31/2026 $75.86 $48.15 $27.71 13
87 Group 7 08/30/2027
$77.81
$49.25
87 Group 7 09/04/2028
$79.76
$50.35
* LABORER - UNDERGROUND WORK {Worker in a raise, 88 Group 8 08/31/2026
$76.31
$48.60
88 Group 8 08/30/2027
$78.26
$49.70
88 \Group 8 09/04/2028
$80.21
$50.80
* Indicates a wage, fringe benefit, remark, or title change from the previous bulletin. Page 6
511 I * [LANDSCAPE & IRRIGATION LABORER: I 89
Landscape & Irrigation Laborer A 08/31/2026 08/30/2027 09/04/2028 09/03/2029 08/31/2026 08/30/2027 09/04/2028 09/03/2029 08/31/2026 08/30/2027 08/30/2027 09/03/2029 09/14/2026 08/30/2027 09/04/2028 09/14/2026 08/30/2027
$48.95 $50.80 $52.65 $54.50 $49.95 $51.80 $53.65 $55.50 $43.55 $45.40 $47.25 $49.10 $95.67 $96.66 $96.87 $95.92 $96.91
$30.40 $31.45 $32.50 $33.55 $31.40 $32.45 $33.50 $34.55 $25.00 $26.05 $27.10 $28.15 $59.03 $60.02 $60.02 $59.28 $60.27
$18.55 $19.35 $20.15 $20.95 $18.55 $19.35 $20.15 $20.95 $18.55 $19.35 $20.15 $20.95
511 I I I Landscape & Irrigation Laborer A
Landscape & Irrigation Laborer A Landscape & Irrigation Laborer A Landscape & Irrigation Laborer B Landscape & Irrigation Laborer B Landscape & Irrigation Laborer B Landscape & Irrigation Laborer B Landscape & Irrigation Maintenance Laborer Landscape & Irrigation Maintenance Laborer Landscape & Irrigation Maintenance Laborer Landscape & Irrigation Maintenance Laborer Bricklayer Stonemason Blocksetter Bricklayer Stonemason Blocksetter Bricklayer Stonemason Blocksetter Pointer/Caulker Weatherproofer Pointer/Caulker Weatherproofer
511 I I I
511 I I I
511 * MASON (Bricklayer): $36.64 2,13 511 $36.64 2,12,13 511 $36.85 2,12,13 511 $36.64 2,13 511 $36.64 2,12,13 511 93 Pointer/Caulker…