01 33 16 AM-0001.pdf
PDF 72 KB Posted
- Solicitation number
- w912hv
About this file
This document outlines design requirements for a federal construction project in Okinawa, Japan. The project involves repair of Army facilities and includes civil, architectural, structural, mechanical, and electrical design work. Design submittals are required at 35%, 65%, 95%, and 100% completion with a 21-day government review period for each. Deliverables include drawings, specifications, analyses, cost estimates, and quality control documentation. Drawings must comply with CAD standards and be delivered electronically in AutoCAD or MicroStation format. Specifications use Unified Facilities Guide Specifications and SpecsIntact. The construction budget and completion dates are to be determined. The Army Corps of Engineers is the contracting agency managing the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01 11 00-A AM-0001.pdf | ||
| IFB W912HV20B0011 AM 01.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY20 OMA ARMY MUNS FACILITIES REPAIR (PHASE I), KAB 19SF0011
SECTION 01 33 16
DESIGN AFTER AWARD
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
MIL-STD 3007 Standard Practice For Unified Facilities Criteria And Unified Facilities Guide Specifications
UFC 1-200-01 (2019) DoD Building Code
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-345-700 (1997) Design Analysis, Drawings and Specifications
1.2 GENERAL DESCRIPTION
This section lists items that must be submitted for review at various milestones following award of a Design-Build Contract.
Design submittals are required at the Intermediate stage, Final stage, and Final Backcheck stage. The requirements for each design stage are listed hereinafter.
1.3 DESIGNER
1.3.1 Designer Of Record (DOR) Identification
Identify a DOR for each design area. Minimum requirements of the DORs shall be as indicated in following experience matrix. Submit a list of DORs to the Contracting Officer's Representative.
Experience Matrix
Area Qualifications
Civil Graduate of an accredited university with a Civil Engineering degree. Two years of work experience as either a U.S. Licensed Professional Civil Engineer or 1 Kyu Doboku Sekou Kanrigishi (1st Class Civil Engineering Works Management Engineer).
W912HV-20-B-0011 SECTION 01 33 16 Page 1
(AM-0001)
Experience Matrix
Area Qualifications
Mechanical Graduate of an accredited university with a Mechanical Engineering degree. Two years of work experience as either a U.S. Licensed Professional Mechanical Engineer or 1 Kyu Kankouji Sekou Kanrigishi (1st Class Building Mechanical and Electrical Engineer).
Electrical Graduate of an accredited university with an Electrical Engineering degree. Two years of work experience as either a U.S. Licensed Professional Electrical Engineer or 1 Kyu Kankouji Sekou Kanrigishi (1st Class Building Mechanical and Electrical Engineer).
Structural Graduate of an accredited university with a Structural Engineering degree. Two years of work experience as either a U.S. Licensed Professional Structural Engineer or 1 Kyu Kenchikushi (1st Class Qualified Architect).
Architectural Graduate of an accredited university with an Architectural degree. Two years of work experience as either a U.S. Licensed Architect or 1 Kyu Kenchikushi (1st Class Qualified Architect).
For Architecture and Structural Engineering, the highest level of qualification is specified. For Mechanical Engineering, qualification of Kenchiku Setsubishi is higher than 1st class Kankouji Sekou Kanrigishi, and therefore acceptable. For Civil and Geotechnical Engineering, Gijutsushi is higher in qualifications than RCCM, and therefore acceptable
1.3.2 DOR Responsibilities
Each DOR shall be responsible for ensuring integrity of their design and design integration in all construction submittals and extensions to design developed by others, such as the Contractor, subcontractors, or suppliers.
All construction drawings and design calculations of the Contractor and any changes to these documents shall be affixed with the registration stamp (seal) of the DOR and that of all consultants, as appropriate, (i.e.
structural, civil, mechanical and fire protection engineers) before submittal for review. Approval shall be indicated on all documents by having the professional stamp/seal of the architect or engineer with personal signature over same appearing on all sheets as applicable to their specialties.
Each DOR shall review and approve all construction submittals and extensions to design, in accordance with the procedures described in Section 01 33 00 SUBMITTAL PROCEDURES. Each DOR shall be responsible for reviewing Requests for Information (RFI), applicable to their area of design responsibility, prior to submission to the Government
W912HV-20-B-0011 SECTION 01 33 16 Page 2
1.4 SEQUENCE OF DESIGN AND CONSTRUCTION
a. After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply with all design submission requirements as covered under Division 01 General Requirements, and obtain Government review of each submission. No construction shall be started until the Government reviews the Final Backcheck Design submission and determines it satisfactory for purposes of beginning construction. The COR shall notify the Contractor when the design is cleared for construction. The Government shall not grant any time extension for any design resubmittal required when, in the opinion of the ACO or COR, the initial submission failed to meet the minimum quality requirements as set forth in the Contract.
b. If the Government allows the Contractor to proceed with limited construction based on pending minor revisions to the reviewed Final Backcheck Design submission, no payment shall be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.
c. No payment shall be made for any in-place construction until all required submittals have been made, reviewed and are satisfactory to the Government.
1.5 CONTRACTOR'S ROLE DURING DESIGN
The Contractor's construction management key personnel shall be actively involved during the design process to effectively integrate the design and construction requirements of this Contract. In addition to the typical required construction activities, the Contractor's involvement includes, but is not limited to actions such as: integrating the design schedule into the Master Schedule to maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the contract), ensuring constructability and economy of the design, integrating the shop drawing and installation drawing process into the design, executing the material and equipment acquisition programs to meet critical schedules, effectively interfacing the construction QC program with the design QC program, and maintaining and providing the design team with accurate, up-to-date redline and as-built documentation. The Contractor shall require and manage the active involvement of key trade subcontractors in the above activities.
1.6 DESIGN TIMELINE
As indicated in Section 01 32 16.00 20 SMALL PROJECT CONSTRUCTION SCHEDULES, the Contractor shall submit for approval, a complete design schedule with all submittals and review times indicated in calendar dates. Update this schedule in accordance with 01 32 16.00 20 SMALL PROJECT CONSTRUCTION SCHEDULES. No design submittals shall be reviewed or evaluated until after receipt and acceptance of the proposed design/review schedule.
1.7 DEVIATING FROM THE ACCEPTED DESIGN
The Contractor must obtain the approval of the Designer of Record and the Government's concurrence for any Contractor proposed revision to the professionally stamped and sealed and Government reviewed and concurred design, before proceeding with the revision.
W912HV-20-B-0011 SECTION 01 33 16 Page 3
a. The Government reserves the right to non-concur with any revisions to the design, which may impact furniture, furnishings or equipment selections or operations decisions that were made, based on the reviewed and concurred design.
b. Any revisions to the design, which deviates from the Contract requirements (i.e., the RFP and the accepted proposal), will require a modification, pursuant to the Changes clause, in addition to Government concurrence. The Government reserves the right to disapprove such a revision.
c. Unless the Government initiates a change to the Contract requirements, or the Government determines that the Government furnished design criteria are incorrect and must be revised, any Contractor initiated proposed change to the Contract requirements, resulting in additional cost, shall strictly be at the Contractor's expense.
d. The Contractor shall track all approved revisions to the reviewed and accepted design and shall incorporate them into the as-built design documentation, in accordance with agreed procedures. The Designer of Record shall document its professional concurrence on the as-builts for any revisions to the stamped and sealed drawings and specifications.
1.8 DESIGN CONFERENCES
1.8.1 Pre-Performance
As part of the Pre-Performance Conference conducted after the Contract award, key representatives of the Government and the Contractor shall review the design submission and review procedures specified herein, discuss the preliminary design schedule and provisions for phase completion of the D-B documents with construction activities (fast tracking), as appropriate, meet with Corps of Engineers Design Review personnel and key Using Agency points of contact and any other appropriate pre-design discussion items.
1.8.2 Design Charrette
After award of the Contract, the Contractor shall visit the site and conduct interviews and problem solving discussions with the individual users and the Corps of Engineers personnel to acquire all necessary site information, review user options, and discuss user needs. The Contractor shall document all discussions. Additionally, the Contractor shall schedule and perform a Design Charrette which is a condensed design meeting with the Corps of Engineers personnel The design scope shall be finalized as direct result of these meetings.
1.8.3 Design Review Conferences
Review conferences shall be held either on-base or Corps of Engineer's Office for each design submittal. The Contractor shall bring the personnel that developed the design submittal to the review conference.
The conferences shall take place approximately one week after the review is complete.
1.9 POST REVIEW CONFERENCE ACTION
Copies of comments, annotated with comment action agreed on, shall be made
W912HV-20-B-0011 SECTION 01 33 16 Page 4 available to all parties before the conference adjourns. Unresolved problems shall be resolved by immediate follow-on action at the end of conferences. Valid comments shall be incorporated. After receipt of Final Backcheck design documents upon incorporation of backcheck comments, the Contractor may proceed with site and building development activities within the parameters set forth in the Contract and accepted design submittal. The Government, however, reserves the right to reject design document submittals if comments are significant (in the opinion of the Government, it does not comply with the Contract documents nor the level of quality implied).
1.10 CONFERENCE RECORDS
The Contractor shall within three (3) working days after each conference or discussion, prepare a written record of the meeting and/or discussions and submit to the Japan Engineer District Resident Engineer/Contracting Officer Representative identified in the Contract. The written report shall include the project name, Contract number, subject, the name of the participants, an outline of discussions, the recommendations, and conclusions. All meetings, site visits, review conferences, and telephonic discussions require written records. The Contractor shall also provide copies of conference records to the designated Administrative Contracting Officer identified for the Contract. Number each written record for the particular project under design in consecutive order.
1.11 DESIGN SUBMITTALS
The Contractor shall follow the requirements outlined below for all submittals.
1.11.1 Guidance, References, and Precedence
The design shall comply with Department of Defense Uniform Facilities Criteria (UFC), Component Service (Air Force, Army, Navy) Design Standards, the appropriate Installation Design Guide, and the US Army Corps of Engineers planning, design, and construction directive. In the event of conflict between documents and references, precedence shall be given to the following in descending order.
a. Unified Facilities Criteria (UFC) system prescribed by MIL-STD 3007 , which provides planning, design, construction, operations, and maintenance criteria, and applies to all Department of Defense (DoD) commands. UFC are distributed in electronic media from the Whole Building Design Guide (WBDG) website:
http://www.wbdg.org/ccb/browse_cat.php?c=4. UFC 1-200-01 provides guidance for the use of model building codes for design and construction of DoD facilities. Public Law 104-113, National Technology Transfer and Advancement Act of 1995, requires federal use of private sector consensus standards wherever practicable. The goal of the law is to reduce reliance on Federal standards by using industry standards when there is potential to simplify contracting, increase timeliness and cost effectiveness, and promote the safety and welfare of users.
b. The Service Component Design Standards provide common facility and infrastructure standards for the relevant Service Component installations. The appropriate installation design standards in conjunction with mission requirements and technical designs and specifications, define requirements for installation maintenance, W912HV-20-B-0011 SECTION 01 33 16 Page 5 repair, and construction projects. The Installation Design Standards and Installation Design Guides improve the functional and visual aspects of the installation. The Installation Design Standards follow the concept established in the Joint Service Unified Facilities Criteria Installation Design Manual.
c. Federal and Industry Standards. All applicable Federal and local industry standards referenced in the scope of work, including those not referenced or listed, constitute criteria for the design of this project, unless otherwise indicated. Applicable Japanese standards may apply.
1.11.2 Quantity of Design Submittals
Submit the documents listed and generally described hereinafter to the Government. Each submittal shall be accompanied by one (1) electronic copies of all documentation and drawings to be provided. The electronic copies shall consist of standard type word processing, spreadsheet, and CAD (AutoCAD or MicroStation) files. The delivery address, quantity and type of the required hardcopy submittals are identified in the table below.
Activity and Address Drawing set (Size A1)
Design Analysis
Specs Other Documents
Okinawa Area Office (OAO) Attn: Michael L. Farris USAED-J, Unit 35132
APO, AP 96374-5132
DSN: 315-645-9353
Email: Michael.L.Farris.civ@usace.army.mil
3 1 3 1
CEPOJ-CD-OZ Zukeran Resident Office Attn: Keith Howard USAED-J, Unit 35132
APO, AP 96376
DSN: 315-645-9533
Email:
Keith.D.Howard@usace.army.mil
1 0 1 1
1.11.3 Delivery of Design Submittals
Mail all design submittals to the Government during design and construction. For mail delivery use an overnight mailing service. The Government shall furnish the Contractor addresses where each copy shall be delivered after Contract award.
1.11.4 Transmittal Letter
Each design submittal shall have a transmittal letter accompanying it indicating the date, design percentage, type of submittal, list of items submitted, transmittal number, and point of contact with telephone number.
W912HV-20-B-0011 SECTION 01 33 16 Page 6
1.11.5 Late Design Submittal
If a design submittal is over one (1) day late in accordance with the latest design schedule, the Government review period may be extended 7 calendar days. The review conference shall be held the week after the new period. Submittal date revisions must be made in writing at least one (1) week prior to the affected submittal schedules.
1.12 GOVERNMENT REVIEW
After receipt of submittals, the Government shall be allowed twenty-one
(21) calendar days to review and comment on each Intermediate and Final Design submittal, except as noted below. The Final Backcheck design submittal shall permit the Government fourteen (14) calendar days to review and ensure the Final Design submittal was updated. For each design submittal, the COR shall furnish the Contractor comments from the various design sections and from other concerned agencies involved in the review process. The review shall be for conformance with the technical requirements of the Contract RFP and the Contractor's proposal. If the Contractor disagrees technically with any comment or comments and does not intend to comply with the comment, he must clearly outline, with ample justification, the reasons for noncompliance within five (5) working days after receipt of these comments in order that the comment can be resolved. All comments must be mutually resolved by the Government and the Contractor. The Contractor shall furnish disposition of all comments, in writing, with the next scheduled submittal. The Contractor is cautioned in that if he believes the action required by any comment exceeds the requirements of this Contract, that he should take no action and notify the COR in writing immediately. Review conferences shall be held for each design submittal at the project's location. The Contractor shall bring the personnel that developed the design submittal to the review conference. These conferences shall take place approximately one week after the twenty-one (21) day review period.
1.12.1 ProjNet (DrChecks)
Although the Contractor may use its own internal system for overall design configuration management, the Government and the Contractor shall use the DrChecks Design Review and Checking System to initiate, respond to, resolve and track Government design compliance review comments. This system may be useful for other data which needs to be interactive or otherwise available for shared use and retrieval. See Attachment 01 33 16-A for details on how to establish an account and set-up the DrChecks system for use on the project. The Contractor shall check the Design Quality Lessons learned (DQLL) through DrChecks and incorporate any applicable Lessons Learned into the design of this project.
1.12.2 Contractor Actions
The disposition of each Government review comment must be clearly annotated. Merely stating "concur" or "will comply" is not considered an adequate indication of actions taken. Not-in-scope comments annotated by the Contractor must be discussed with the Government within five (5) working days.
1.12.3 Design Responsibility and Compliance
Regardless of Government review and comment on design submittals, the
W912HV-20-B-0011 SECTION 01 33 16 Page 7
Contractor shall be responsible for compliance with all requirements of the RFP and accepted Proposal. Should any non-compliance be discovered during design and/or construction, the Contractor shall be responsible for providing corrective action at no additional cost and/or time impact to the Government in order to comply with the requirements of the Contract.
PART 2 PRODUCTS
2.1 DESIGN ANALYSIS
2.1.1 General
Design Analysis format shall follow guidance from ER 1110-345-700 , Appendix B located on Corps of Engineers website:
http://www.publications.usace.army.mil/Portals/76/Publications/ EngineerRegulations/ER_1110-345-700.pdf.
This shall exclude part 6 "Exceptions to Appendix B, Requirements."
2.1.2 Format
Use standard 8.5 inch by 11 inch paper except that larger sheets may be used when required for graphs or other special calculation forms. All sheets shall be in reproducible form. The material may be typewritten, hand lettered, handwritten, or a combination thereof, provided it is legible. Side margins shall be 1 inch minimum to permit side binding and head to head printing. Bottom margins shall be a minimum of 1 inch with page numbers centered.
2.1.3 Organization
The design analysis shall be sequentially numbered and bound under a cover indicating the name of the facility and project number. The design analysis shall be further classified by the submittal stage. All portions of the design analysis shall be organized and bound by relevant topics.
2.1.4 Design Computations
Calculations are a part of the design analysis. When they are voluminous, bind them separately from the narrative part of the design analysis.
Present the design calculations in a clean and legible form incorporating a title page and index for each volume. Furnish a table of contents which shall be an index of the indices, when there is more than one volume.
Identify the source of loading conditions, supplementary sketches, graphs, formulae, and references. Explain all assumptions and conclusions.
Calculation sheets shall carry the names or initials of the computer and the checker and the dates of calculations and checking. As part of the Contractor's Quality Control System, no portion of the calculations shall be computed and checked by the same person.
When ADPS are used to perform design calculations, the design analysis shall include descriptions of the computer programs used and copies of the ADPS input data and output summaries. When the computer output is large, it may be divided into volumes at logical division points. Precede each set of computer printouts by an index and by a description of the computation performed. If several sets of computations are submitted;
they shall be accompanied by a general table of contents in addition to the individual indices. Include the following in the description accompanying each set of ADPS printouts:
W912HV-20-B-0011 SECTION 01 33 16 Page 8
a. Explain the design method, including assumptions, theories and formulae.
b. Include applicable diagrams, adequately identified.
c. State exactly the computation performed by the computer.
d. Provide all necessary explanations of the computer printout format, symbols and abbreviations.
e. Use adequate and consistent notation.
f. Provide sufficient information to permit manual checks of the results.
2.2 DRAWINGS
2.2.1 General
Prepare all drawings utilizing Computer-Aided Design and Drafting (CADD) software so that they are well arranged, placed for ready reference and they present complete information. The Contractor shall prepare all CADD files drawings in compliance with the A/E/C CADD Standards (rel 6.0) dated August 2015 (referred to as the "CADD standard") unless otherwise specified. Drawings shall be complete, unnecessary work such as duplicate views, notes and lettering, and repetition of details shall not be permitted. Do not show standard details that are not applicable to the project, and minimize unnecessary wasted space. Do not include details of standard products or items, which are adequately covered by specifications on the drawings. The cover sheet shall be signed and stamped by a principal of the firm who is a registered professional engineer/architect. Each design discipline shall provide a complete list of abbreviations and symbols used in their respective drawings. Do not use shop drawings as design drawings. The design documents shall consist of drawings utilizing metric drawing sheets A1 (594 x 841 mm) or A2 (420 x 594 mm) format unless otherwise specified. The Contractor shall use standard Corps of Engineers title blocks and borders on all drawings. The Contractor shall submit all CADD files for A/E/C compliance verification and a description of all drawings and drawing file names with each required design submittal.
2.2.2 Methods and Format
Create all drawings utilizing metric units. All CADD files shall utilize one of the following software applications and the version specified (or the latest version):
a. AutoCAD 2013 (.dwg)
b. MicroStation V8 (.dgn)
2.2.3 Use of Records Management Directory Structure
a. The main (root) folder shall be named after the P2 number of the project.
b. The folder names (under the root folder) are shown on table 2-1, page 13 of the CADD standard. CADD files shall then be properly organized in the applicable folder structure as described. Table 2-1 shall also serve as the sequence or order of drawings.
W912HV-20-B-0011 SECTION 01 33 16 Page 9
c. Model files shall be organized in a sub-folder (in each applicable discipline) called "resource".
d. Sheet files shall be organized in the applicable discipline folder.
e. A subfolder called "PDF" shall be created under each applicable discipline folder to store design .pdf files of each submittal percentage phase.
f. Only English language characters shall be used in the folder names.
g. The Contractor at their prerogative may delete folders that are not applicable to the design.
2.2.4 Use of A/E/C CADD File Naming System
For the purposes of simplicity model files and sheet files shall be named as described below:
a. Model files names shall have a minimum of ten characters (reference the CADD standard, figure 2-4, page 12). The first six characters shall be the project P2 number, followed by two characters for the discipline designator, and the last two characters the model file type. The last four characters of the model file name is user definable and may be used at the Contractor's prerogative. Only English alphabet and numerical characters shall be used in file names (no kanji).
b. The sheet file name shall have a minimum of ten characters (reference the CADD Standard, figure 2-5, page 18). The first six characters shall be the project P2 number, followed by one character for the discipline designator (the level 2 designator shall be used only when more than 99 sheets are needed to subdivide the applicable discipline), and the last two characters the sheet sequence number.
The last three characters of the sheet file name is user definable and shall be used in the event of an amendment or modification.
2.2.5 Use of Reference or Xref Files
The use of reference or xrefs files during the design stage is at the discretion of the designers.
2.2.6 Drawing Sheet Assembly
CADD drawings shall utilize model and sheet files (modelspace and paperspace) and shall be drawn in real world units. The drawings shall be Xref'd or referenced to a scale (see table 3-7, page 35 of the CADD standard) that fits into the Government provided border sheet. The Contractor shall utilize "Option 1" of a drawing sheet assembly (see figure 2-2, page 10 of the CADD standard). The border sheet shall remain at its original scale and only one bordersheet (paperspace) per design file is allowed.
2.2.7 Use of True Type Fonts and Sizes
For file conversion purposes the standard font shall be Arial.ttf and simplex.ttf. Fonts created by third parties or the designers are not permitted. Standard text sizes that may be used are 1.5 mm, 3 mm, 6 mm
W912HV-20-B-0011 SECTION 01 33 16 Page 10 and 12 mm (text height and width).
2.2.8 Use of Standard Dimensioning and Terminator Symbols
All dimensioning shall be in millimeters (see figure 3-7 through 3-10, pages 38 and 39 of the CADD standard). The preferred terminator for dimensioning shall be the architectural slash. In the event that filled arrowheads are selected ensure that the size of the arrowheads are at a ratio of 3:1 (see page 37 of the CADD standard).
2.2.9 Use of Standard Abbreviations
The use of abbreviations are for use when space is limited within a drawing sheet, otherwise it is recommended the all the words are spelled out versus using abbreviations. Approved abbreviations are available from the National CADD Standard (NCS version 3.1)
2.2.10 Use of Standard Symbols, Patterns, and Line Styles
General symbols such as a two part detail, section and elevation bubbles are to be used. Other approved symbols, patterns, and line styles are located in Appendix D of the CADD Standards.
2.2.11 Government Provided Files
The use of these files is free. The U.S. Army Corps of Engineers (USACE) makes no warranty, impressed or implied, with regards to the use of these files. USACE shall not be liable for any errors or for incidental or consequential damages in connection with the furnishing and performance of these files. The COR shall furnish the Contractor with the following:
a. A/E/C CADD Standards rel. 6.0 (Main text, Appendix A in pdf format)
b. Japan Engineer District Title and border sheets (Size A1 and A2 in .dgn and .dwg format)
c. AutoCAD drawing template and MicroStation library files (.dwt and .dgnlib)
d. A/E/C Cell and Block Libraries (.cel and .dwg)
e. A/E/C Line Style Libraries (.rsc and .shx)
f. A/E/C Pattern Libraries (.cel and .pat)
2.2.12 Submittal Delivery Media and Format
Submit all Design Complete CADD files on the following media.
a. Before a CADD file is copied on the delivery digital media, the following procedures shall be performed:
(1) Remove all extraneous graphics outside the border area of the sheet file. Set the active parameters to a standard setting or those in the Government-furnished template or seed file.
(2) Include all files, both graphic and non-graphic, required for the project (i.e., color tables, pen tables, font libraries, cell libraries, user command files, plot files, etc.). All cells/blocks not provided as Government-furnished materials must
W912HV-20-B-0011 SECTION 01 33 16 Page 11 be provided to the Government as a part of the electronic digital deliverables.
(3) Make sure that all support files such as those listed above are in the resource directory and that model files do not include device or directory specifications.
(4) Document any fonts, tables, etc., developed by the Contractor or not provided among the Government-furnished materials. The Contractor shall obtain Government approval before using anything other than the Government's standard fonts, line styles, patterns, cells/blocks.
b. A copy of all CADD data and files developed under this Contract shall be submitted to the Government on electronic digital CAD media for approval by the Government at the Intermediate Design submittal phase, the Final Design submittal stage, and at the Final Backcheck Design submittal phase as required unless otherwise directed by the Contracting Officer.
c. The external label for each electronic digital media shall contain, as a minimum, the following information:
(1) The Project title, design submittal stage, and date.
(2) The format and version of operating system software.
(3) The name and version of utility software used for preparation (e.g., compression/decompression) and copying files to the media.
(4) The A/E name and address.
2.3 SPECIFICATIONS
2.3.1 General
Specifications can be either on the design drawings or provided as a separate document as noted below.
The latest version of Unified Facilities Guide Specifications (UFGS), as established by CSI Manual of Practice, shall be utilized, and can be obtained from the Whole Building Design Guide website http://www.wbdg.org/ccb/browse_cat.php?c=3.
SpecsIntact is an automated specification processing system for use in preparing construction project specifications from the UFGS. The use of SpecsIntact is mandatory. SpecsIntact can be downloaded at http://specsintact.ksc.nasa.gov/. The Contractor shall submit SpecsIntact (.sec) files for marked-up and final specifications as required in the Contract.
Federal Specs and MIL Specs have been phased out with a few exceptions.
Only those Federal and MIL specs in the current editions of the UFGS may be used. Industry standards (e.g. ASTM, ANSI) shall be used to the greatest extent practicable for description of materials. Japanese Industry Standards (e.g. JIS, JAS) are acceptable, provided that the A-E can provide adequate documentation for COR's approval proving that the Japanese Industry Standards are equivalent to the US Industry Standards.
A limited set of modified UFGS incorporating previously identified and
W912HV-20-B-0011 SECTION 01 33 16 Page 12 accepted Japanese standards and methods (also known as Japan Edited Specifications, or JES) can be found at https://www.poj.usace.army.mil/Business-With-Us/References/.
When standards are not available for an item, specify by performance criteria instead. Proprietary items are not allowed.
At the Intermediate and Final Design submittal stages, submit edited specifications in marked-up or redlined format. At the Final Backcheck Design submittal stage, execute all previous revisions.
2.3.2 Submittal Register
A Submittal Register indicating the submittal requirements during the construction phase must be prepared by the A-E using SpecsIntact during the design phase of the Contract. The A-E shall be responsible for listing all required submittals necessary to insure the project requirements are complied with. The Register shall identify submittal items such as shop drawings, manufacturer's literature, certificates of compliance, material samples, guarantees, test results, etc. that the Contractor shall submit for review and/or approval action during the life of the construction Contract. The A-E shall include the Submittal Register as an attachment to Section 01 33 00 SUBMITTAL PROCEDURES with the specifications.
PART 3 EXECUTION
3.1 CONCEPT (35%) DESIGN SUBMITTAL
The A-E shall prepare the Concept Design based on the discussions and decisions made at the design charrette.
The Concept Design goal is to demonstrate that the A-E has a thorough understanding of the scope of the project and the owner's requirements, as discussed at the design charrette. At the Concept Design stage, the A-E shall confirm all CADD requirements (i.e.: sheet numbering, sheet size, A/E/C CADD & USACE standards) with the POJ CADD center.
Concept Design submittal shall consist of, but not limited to, the following:
3.1.1 Design Drawings
a. Title and general sheets with preliminary haul route.
b. Project site plan & area site plan.
c. Construction notes and legend pages (all disciplines); Phasing plan, if required.
d. Preliminary Building Life Safety Code Analysis.
e. Civil
(1) Project site plan..
(2) Area site plan.
(3) General Preliminary Exterior Utility Plans.
W912HV-20-B-0011 SECTION 01 33 16 Page 13 j2ee9nf9 Line
f. Architectural
(1) Architectural Plans that consider functional relationships, work area use, security requirements and traffic flow patterns.
(2) Exterior elevations showing principal shapes, fenestrations and exterior finishes.
(3) Building sections.
(4) General interior finish selections.
h. Mechanical
(1) General Preliminary HVAC, equipment capacities and sizes.
3.1.2 Specifications
List of Technical Specification sections that will be included in the intermediate submittal.
3.1.3 Design Analysis
a. Concept Design Analysis
(1) Include a discussion of existing conditions and project goals.
(2) List design assumptions, design calculations referenced criteria, and show initial calculations.
(3) Include placeholder sections for topics not required in the concept submittal, but needed for the intermediate submittal.
(4) Discussion of types and capacities of primary electrical power, conduit, information systems, lighting, and other systems considered, including a description of the selected systems.
(5) Site analysis that discusses the opportunities and constraints of the site and include the recommendations from the IDG/Installation.
(6) Hazard analysis (lead based paint, asbestos, etc., if required).
(7) Preliminary erosion control analysis.
(8) Preliminary plant material analysis that reflects the selection of plant material native to the project area, if required.
(9) Life cycle cost analysis.
(10)Corrosion mitigation plan, if required.
(11)Site specific traffic analysis.
(12)List of materials and methods of construction to be used.
3.1.4 Cost Estimate
Current working estimate.
W912HV-20-B-0011 SECTION 01 33 16 Page 14
(AM-0001)
3.1 INTERMEDIATE (65%) DESIGN SUBMITTAL
Prepare the Intermediate Design and technical specifications based on scope of wor k i n pr ovi ded i n 01 11 00- A ( r ef er r ed t o her ei n as Concept Design ) , project criteria and general instructions.
The Intermediate Design effort shall be a continuation of the Concept Design. The Intermediate Design goals are to show the project is on schedule and at an acceptable level of quality and completeness and demonstrate that A-E's QC process is functioning properly. Submit all QC documentation with the Intermediate Design submittal. Complete coordination amongst design disciplines shall be conducted to review and resolve design conflicts.
Intermediate Design shall consist of, but not limited to, the following:
3.1.1 Design Drawings
a. Title and general sheets with haul route.
b. Project site plan & area site plan.
c. Construction notes and legend pages (all disciplines); Phasing plan, if required.
d. Complete Discipline coordination of the design.
e. Civil
(1) Existing conditions (topography).
(2) Demolition plan.
(3) Site plan.
(4) Grading plan , i f r equi r ed.
(5) Road sections, plans, and profiles , i f r equi r ed.
(6) Utility plans and profiles , i f r equi r ed.
(7) Civil and site profiles.
f. Architectural
(1) Architectural Floor Plans.
(2) Reflected Ceiling Plans , i f r equi r ed.
(3) Roof Plans , i f r equi r ed.
(4) Exterior elevations , i f r equi r ed.
(5) Building sections , i f r equi r ed.
(6) Wall sections , i f r equi r ed.
(7) Interior elevations.
W912HV-20-B-0011 SECTION 01 33 16 Page 15
(AM-0001)
j2ee9nf9 Line j2ee9nf9 Line
(8) Door & window types/schedules and details.
(9) Room Finish Materials and Schedule.
(10)Miscellaneous Details.
(11)Signage Plans and Schedules.
g. Structural
(1) Foundation plans , i f r equi r ed.
(2) Slab Schedules and details , i f r equi r ed.
(3) Building sections.
h. Mechanical
(1) Equipment Schedules.
(2) Isometrics.
(3) Riser Diagrams NOT USED.
(4) Schematics.
(5) Details.
i. Electrical
(1) Electrical Legend.
(2) Existing Electrical Site plan, indicating power, lighting.
(3) Exterior Demolition Plan.
(4) Plan view, indicating the interior electrical power plan, including receptacles, HVAC equipment, and specialty items needing power , i f r equi r ed.
(5) Plan view, indicating the interior light fixture layout , i f required .
(6) Preliminary Light fixture schedule.
(7) Preliminary Electrical one line diagram.
(8) Preliminary one line diagram for any auxiliary systems.
3.1.2 Technical Specifications
a. Full red-lined mark-ups of Technical Specifications.
3.1.3 Design Analysis
a. Intermediate Design Analysis
(1) Include a discussion of existing conditions and project goals.
W912HV-20-B-0011 SECTION 01 33 16 Page 16 j2ee9nf9 Line j2ee9nf9 Line
(2) List design assumptions, design calculations referenced criteria, and show initial calculations and manufacturer's material and equipment information.
(3) Designed primary electrical power types and capacities, conduit, information systems, lighting, and other systems considered, including a description of the selected systems.
(4) Designed information systems requirements.
(5) Hazard analysis, if required.
(6) Erosion control analysis.
(7) Corrosion mitigation plan (as required).
(8) Economic analyses.
(9)Justification for use of all U.S. materials/equipment specified in the design to be used in construction when local materials/equipment are excluded.
c. Provide a copy of the project's authorization.
3.1.4 Cost Estimate
Current working estimate for budget purposes and back-up cost data and price quotes.
3.1.5 Quality Control
Submit completed Detail Check Review (DCR) and Independent Technical Review (ITR) documents to include: Completed DCR checklists, completed ITR annotated comment sheets in accordance with the project's Scope of Work.
3.2 FINAL (95%) DESIGN SUBMITTAL
The A-E shall prepare the Final Design based on the Intermediate Design, project criteria and general instructions.
The Final Design effort shall be a complete design incorporating and resolving all previous review comments. Complete coordination amongst design disciplines shall be conducted to review and resolve any and all design conflicts. A-E shall conduct a full Quality Control review prior to the submittal of the Final Design. A-E QC review shall consist of a full Detail Check and Independent Technical Review. The Final Design submittal is the last full review of the Contract documents by the Government. Any significant new information included in this submittal that is not a direct result of a review comment shall be brought to the attention of the reviewer(s) and USACE Project Manager. Provide a brief description of the new information. The design shall be within the project's programmed amount.
All disciplines and specialty systems shall be designed and detailed to provide clear design intent. Design analysis shall include representative sample manufacturer's product information.
Final Design shall consist of, but not limited, to the following:
W912HV-20-B-0011 SECTION 01 33 16 Page 17
3.2.1 Design Drawings
a. Title and general sheets with haul route.
b. Project site plan & area site plan.
c. Construction notes and legend pages (all disciplines); Phasing plan (as required).
d. Complete Discipline Coordinate of the design.
e. Civil
(1) Completed set of Civil drawings.
f. Architectural
(1) Completed set of Architectural drawings.
g. Structural
(1) Completed set of Structural drawings.
h. Mechanical
(1) Completed set of Mechanical.
i. Electrical & Telecommunication
(1) Completed set of Electrical and Telecommunication drawings.
3.2.2 Technical Specifications
a. Completed set of Technical Specifications.
(1) Technical specifications shall incorporate all comments and revisions from the previous submission.
b. Specifications shall include the submittal register (ENG Form 4288) in .csv and .pdf format in this and all subsequent submittals.
c. Draft 1354 property form shall be submitted for review.
3.2.3 Design Analysis
a. Final Design Analysis
(1) Completed Design Analysis incorporating all comments and revisions from the previous submission.
c. Provide a copy of the project authorization.
3.2.4 Cost Estimate
a. Final working cost estimate with all back-up data, vendor estimates, etc.
W912HV-20-B-0011 SECTION 01 33 16 Page 18
3.2.5 Quality Control
a. Submit Detail Check Review (DCR) and Independent Technical Review (ITR) documents to include: Completed DCR checklists, completed ITR annotated comment sheets in accordance with the project Scope of Work.
3.3 FINAL BACKCHECK (100%) DESIGN SUBMITTAL
The A-E shall prepare the Final Backcheck Design submittal based on the Final Design, project criteria and general instructions.
The Final Backcheck Design submittal shall be complete in every respect, from the Government's perspective. The drawings shall show the name of the reviewer and signature of the Principal of the firm responsible for the design as testimony that this submittal has been reviewed. The submittal shall incorporate all previous review comments. A-E shall provide a response indicating the reason for not incorporating any non-concurred comments. The A-E shall submit a complete response to all previous review comments in DrChecks with the submission.
Final Backcheck Design shall consist of, but not limited to, the following:
3.3.1 Design Drawings
Complete final design construction drawings.
3.3.2 Technical Specifications
Completed set of final technical specifications.
3.3.3 Design Analysis
Complete final design analysis.
3.3.4 Cost Estimate
Complete final working cost estimate.
-- End of Section --