01-0M1204 Excavate and Construct Roadway_ Widen Shoulders and Install Guardrail.pdf
PDF 691 KB Posted
- Solicitation number
- 01-0M1204, Fed #HSNHQ-101 (466)
- Issued by
- Del Norte County, California
About this file
This is a Scope of Work document for a California state and local contract opportunity involving roadway excavation and construction work. The project requires excavation and construction of roadway, widening of shoulders, and installation of guardrail. The contract is identified as 01-0M1204 and falls under general highway infrastructure improvement work. Specific details regarding project quantities, timelines, site visit requirements, bidders' conferences, response deadlines, award dates, and contract term duration with any renewal options are not detailed in the available file information provided.
Pricing terms, set-aside classifications, incumbent contractor information, funding sources, and financial amounts associated with this project are not specified in the file materials reviewed. Additional contract documentation would be required to determine the complete scope including budget allocation, funding mechanisms, and any small business or disadvantaged business enterprise set-asides that may apply to this California Department of Transportation or related state agency project.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Thursday, December 17, 2026 Dated November 16, 2026
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN DEL NORTE COUNTY ABOUT
5 MILES SOUTH OF CRESCENT CITY FROM 1.9 MILES SOUTH TO 1.0 MILE
SOUTH OF MILL CREEK PARK ENTRANCE
In District 01 On Route 101
Under Bid book dated November 16, 2026 Standard Specifications dated 2026
Project plans approved October 1, 2026 Standard Plans dated 2026
Identified by Contract No. 01-0M1204
01-DN-101-18.4/19.3
Project ID 0122000105
Federal-Aid Project
HSNHQ-101 (466)
SPECIAL NOTICES
• See sections 2 and 3 for contractors' registration requirements.
• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
• See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
• The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
• See section 14-11.14 for changes to the management of treated wood waste.
• See sections 6-1.01 and 6-1.04 of these Special Provisions for the Buy America requirements applicable to iron, steel, construction materials, and manufactured products.
Contract No. 01-0M1204 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
1 GENERAL
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
10 GENERAL
12 TEMPORARY TRAFFIC CONTROL
14 ENVIRONMENTAL STEWARDSHIP
DIVISION III EARTHWORK AND LANDSCAPE
19 EARTHWORK
20 LANDSCAPE
21 EROSION CONTROL
DIVISION V SURFACINGS AND PAVEMENTS
36 GENERAL
37 SEAL COATS
39 ASPHALT CONCRETE
DIVISION IX TRAFFIC CONTROL DEVICES
83 RAILINGS AND BARRIERS
84 MARKINGS
DIVISION X ELECTRICAL WORK
86 GENERAL
87 ELECTRICAL SYSTEMS
ii iii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
A3A Abbreviations (Sheet 1 of 3)
A3B Abbreviations (Sheet 2 of 3)
A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
A20D Pavement Markers and Traffic Lines - Typical Details
A20F Pavement Markers and Traffic Lines - Typical Details
A24A Pavement Markings - Arrows
A40D Center Line Rumble Strip Details - Ground-In Indentations
A40G Sinusoidal Rumble Strip Details - Ground-In Indentations
A62A Excavation and Backfill - Miscellaneous Details
A73A Object Markers
A73B Markers
A77L2 Midwest Guardrail System - Standard Railing Section (Steel Post with Notched Wood or Notched Recycled Plastic Block)
A77M1 Midwest Guardrail System - Standard Hardware
A77N2 Midwest Guardrail System - Steel Post and Block Details
A77N3 Midwest Guardrail System - Typical Line Post Embedment and Hinge Point Offset Details
A77N4 Midwest Guardrail System - Typical Height Measurement, Dike Positioning, and Delineation Details
A77N5 Minor Concrete Vegetation Control - Guardrail System
A77N5A Minor Concrete Vegetation Control - Guardrail System - Narrow Vegetation Control Installation
A77N10 Minor Concrete Vegetation Control - Guardrail System at Fixed Object
A77N11 Minor Concrete Vegetation Control - Guardrail System - Miscellaneous Details
A77P1 Midwest Guardrail System - Typical Layouts for Embankments
A77R4 Midwest Guardrail System - Typical Layouts for Roadside Fixed Objects
A77R5 Midwest Guardrail System - Typical Layouts for Roadside Fixed Objects iv
A77T3 Midwest Guardrail System - Buried Post End Anchor (Type B-S)
A87B Hot Mix Asphalt Dikes
P75 Pavement Edge Treatments - Overlays
P76 Pavement Edge Treatments - New Construction
D75A Steel Pipe Inlets
D75B Concrete Pipe Inlets
D77A Grate Details No. 1
D77B Grate Details No. 2
D87A Corrugated Metal Pipe Downdrain Details
D87D Overside Drains
D88 Construction Loads on Culverts
D89A Pipe Culvert Headwalls - Straight and "L"
D89B Pipe Culvert Headwalls - Straight and "L"
D97A Corrugated Metal Pipe Coupling Details No. 1 - Annular Coupling Band, Bar and Strap, and Angle Connections
D97C Corrugated Metal Pipe Coupling Details No. 3 - Helical and Universal Couplers
D97D Corrugated Metal Pipe Coupling Details No. 4 - Hugger Coupling Bands
D97E Corrugated Metal Pipe Coupling Details No. 5 - Standard Joint
D97F Corrugated Metal Pipe Coupling Details No. 6 - Positive Joint
D97G Corrugated Metal Pipe Coupling Details No. 7 - Downdrain
H1 Landscape and Erosion Control Symbols
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
T3C Temporary Barrier System (Cross Bolt)
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
T9 Traffic Control System Tables for Lane and Ramp Closures
T10 Traffic Control System for Lane Closure on Freeways and Expressways
T12 Traffic Control System for Half Road Closure on Multilane Conventional Highways and Expressways v
T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways
T13A Traffic Control System - Two Lane Conventional Highways
T15 Traffic Control System for Moving Lane Closure on Multilane Highways
T17 Traffic Control System for Moving Lane Closure on Two Lane Highways
T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on Freeways and Expressways
T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details
T22 Traffic Control System for Construction Work Zone Speed Limit Reduction on Two Lane Conventional Highways
T51 Temporary Water Pollution Control Details (Temporary Silt Fence)
T53 Temporary Water Pollution Control Details (Temporary Cover)
T54 Temporary Water Pollution Control Details (Temporary Erosion Control Blanket)
T55 Temporary Water Pollution Control Details (Temporary Erosion Control Blanket)
T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)
T57 Temporary Water Pollution Control Details (Temporary Check Dam)
T58 Temporary Water Pollution Control Details (Temporary Construction Entrance)
T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)
T60 Temporary Water Pollution Control Details (Temporary Reinforced Silt Fence)
T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T65 Temporary Water Pollution Control Details (Temporary High-Visibility Fence)
B3-1A Retaining Wall Type 1 (Case 1)
RS1 Roadside Signs - Typical Installation Details
RS2 Roadside Signs - Wood Post - Typical Installation Details
RS4 Roadside Signs - Typical Installation - Miscellaneous Details
RS5 Roadside Sign - PSST Post - Typical Installation Details No. 1
RS6 Roadside Sign - PSST Post - Typical Installation Details No. 2
ES-1A Electrical Systems (Legend)
ES-1B Electrical Systems (Legend)
ES-1C Electrical Systems (Legend)
ES-5C Electrical Systems (Accessible Pedestrian Signal and Push Button Assemblies)
ES-7J Electrical Systems (Flashing Beacon on a Type 1, Type 15-FBS, and Type 40 Standard)
ES-7K Electrical Systems (Flashing Beacon with Type 9, 9A, and 9B Sign)
ES-7L Electrical Systems (Flashing Beacon with Type 9, 9A, and 9B Sign) vi
ES-8A Electrical Systems (Non-Traffic Pull Box)
ES-9F Electrical Systems (Flush-Mounted Soffit Luminaire Details)
ES-10B Electrical Systems (Isofootcandle Curves)
ES-13A Electrical Systems (Splice Insulation Methods Details)
ES-13B Electrical Systems (Kinking and Banding Detail)
CANCELED STANDARD PLANS LIST
The standard plan sheets listed below are canceled and not applicable to this contract.
Plan No. Date Canceled Plan No. Date
Canceled Plan No. Date Canceled
No Canceled Standard Plans
NOTICE TO BIDDERS
Bids open Thursday, December 17, 2026
Dated November 16, 2026
General work description: Excavate and construct roadway, widen shoulders and install guardrail.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN DEL NORTE COUNTY ABOUT 5 MILES SOUTH OF CRESCENT CITY FROM 1.9
MILES SOUTH TO 1.0 MILE SOUTH OF MILL CREEK PARK ENTRANCE.
District-County-Route-Post Mile: 01-DN-101-18.4/19.3
Contract No. 01-0M1204
The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-12.
Federal-aid project no.:
HSNHQ-101 (466)
Bids must be on a cost+time basis.
Complete the work within the number of working days bid.
Do not bid less than 75 working days and not more than 105 working days.
The estimated cost of the project is $4,370,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.
The federal minimum wage rates for this Contract as determined by the United States Secretary of Labor are available at https://sam.gov/content/home.
If the minimum wage rates as determined by the United States Secretary of Labor differs from the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors must not pay less than the higher wage rate. The Department does not accept lower State wage rates not specifically included in the federal minimum wage determinations. This includes helper, or other classifications based on hours of experience, or any other classification not appearing in the federal wage determinations. Where federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors must not pay less than the federal minimum wage rate that most closely approximates the duties of the employees in question.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 080060 LEVEL 2 CRITICAL PATH METHOD SCHEDULE LS LUMP SUM
0003 090105 TIME-RELATED OVERHEAD (LS) LS LUMP SUM
0004 090200 DISPUTE RESOLUTION ADVISOR ON-SITE
MEETING
EA 4
0005 090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-
ADVISOR-RELATED TASKS
HR 20
0006 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0007 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0008 013804 STATIONARY IMPACT ATTENUATOR VEHICLE
(LS)
LS LUMP SUM
0009 120120 TYPE III BARRICADE EA 12
0010 120149 TEMPORARY PAVEMENT MARKING (PAINT) SQFT 48
0011 120159 TEMPORARY TRAFFIC STRIPE (PAINT) LF 960
0012 120165 CHANNELIZER (SURFACE MOUNTED) EA 120
0013 010413 PORTABLE RADAR SPEED FEEDBACK SIGN
SYSTEMS (LS)
LS LUMP SUM
0014 120320 TEMPORARY BARRIER SYSTEM LF 3,000
0015 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM
0016 129108 TEMPORARY CRASH CUSHION TL-3 EA 4
0017 013357 AUTOMATED FLAGGER ASSISTANCE DEVICE LS LUMP SUM
0018 130100 JOB SITE MANAGEMENT LS LUMP SUM
0019 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM
0020 130505 MOVE-IN/MOVE-OUT (TEMPORARY EROSION
CONTROL)
EA 6
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 130530 TEMPORARY HYDRAULIC MULCH (BONDED
FIBER MATRIX)
SQYD 680
0022 130570 TEMPORARY COVER SQYD 680
0023 130610 TEMPORARY CHECK DAM LF 200
0024 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 3
0025 130640 TEMPORARY FIBER ROLL LF 1,000
0026 130650 TEMPORARY GRAVEL BAG BERM LF 96
0027 130680 TEMPORARY SILT FENCE LF 1,000
0028 130710 TEMPORARY CONSTRUCTION ENTRANCE EA 1
0029 130730 STREET SWEEPING LS LUMP SUM
0030 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0031 141120 TREATED WOOD WASTE LB 4,260
0032 146002 CONTRACTOR-SUPPLIED BIOLOGIST (LS) LS LUMP SUM
0033 146007 INVASIVE SPECIES CONTROL LS LUMP SUM
0034 013843 CONTRACTOR SUPPLIED ARBORIST LS LUMP SUM
0035 160110 TEMPORARY HIGH-VISIBILITY FENCE LF 130
0036 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM
0037 190101 ROADWAY EXCAVATION CY 2,190
0038 190105 ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY
DEPOSITED LEAD)
CY 130
0039 017985 ROADWAY EXCAVATION (HANDWORK) CY 5
0040 190185 SHOULDER BACKING TON 200
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0041 198010 IMPORTED BORROW (CY) CY 190
0042 200002 ROADSIDE CLEARING LS LUMP SUM
0043 210120 DUFF (SQFT) SQFT 33,100
0044 260203 CLASS 2 AGGREGATE BASE (CY) CY 210
0045 270014 CEMENT TREATED BASE (PLANT-MIXED, CLASS
A) (CY)
CY 450
0046 037164 HIGH FRICTION SURFACE TREATMENT SQYD 10,400
0047 390132 HOT MIX ASPHALT (TYPE A) TON 3,050
0048 390137 RUBBERIZED HOT MIX ASPHALT (GAP GRADED) TON 1,020
0049 391006 ASPHALT BINDER (GEOSYNTHETIC PAVEMENT
INTERLAYER)
TON 0.5
0050 393004 GEOSYNTHETIC PAVEMENT INTERLAYER
(PAVING FABRIC)
SQYD 510
0051 394060 DATA CORE LS LUMP SUM
0052 394075 PLACE HOT MIX ASPHALT DIKE (TYPE D) LF 210
0053 394090 PLACE HOT MIX ASPHALT (MISCELLANEOUS
AREA)
SQYD 11
0054 397005 TACK COAT TON 11
0055 398100 REMOVE ASPHALT CONCRETE DIKE LF 240
0056 398200 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 4,990
0057 510092 (F) - STRUCTURAL CONCRETE, HEADWALL CY 3
0058 510502 (F) - MINOR CONCRETE (MINOR STRUCTURE) CY 1.5
0059 690112 12" CORRUGATED STEEL PIPE DOWNDRAIN
(.079" THICK)
LF 16
0060 692005 12" ENTRANCE TAPER EA 1
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0061 710138 REMOVE DOWNDRAIN (EA) EA 1
0062 710152 REMOVE HEADWALL EA 1
0063 710196 ADJUST INLET EA 1
0064 810120 REMOVE PAVEMENT MARKER EA 18
0065 810190 GUARD RAILING DELINEATOR EA 35
0066 810250 PAVEMENT MARKER (RETROREFLECTIVE-
RECESSED)
EA 310
0067 820112 MARKER (CULVERT) EA 4
0068 820220 REMOVE MARKER EA 4
0069 820250 REMOVE ROADSIDE SIGN EA 14
0070 820750 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.063"-UNFRAMED)
SQFT 120
0071 820760 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.080"-UNFRAMED)
SQFT 16
0072 820840 ROADSIDE SIGN - ONE POST EA 14
0073 832018 MIDWEST GUARDRAIL SYSTEM (8' STEEL POST) LF 240
0074 832070 VEGETATION CONTROL (MINOR CONCRETE) SQYD 340
0075 839521 (F) - CABLE RAILING LF 4
0076 839589 BURIED POST END ANCHOR (TYPE B-S) EA 2
0077 839752 REMOVE GUARDRAIL LF 340
0078 840516 THERMOPLASTIC PAVEMENT MARKING
(ENHANCED WET NIGHT VISIBILITY)
SQFT 130
0079 840529 6" THERMOPLASTIC TRAFFIC STRIPE (BROKEN
36-12)
LF 2,240
0080 846007 6" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 11,700
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0081 846030 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 1,370
0082 846053 12" RUMBLE STRIP (ASPHALT CONCRETE
PAVEMENT-SINUSOIDAL)
STA 31
0083 872002 TEMPORARY SIGNAL SYSTEMS LS LUMP SUM
0084 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to section 1-1.01:
Bid Items and Applicable Sections Item code
Item description Applicable section
090200 DISPUTE RESOLUTION ADVISOR ON-SITE MEETING 5
090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-ADVISOR-RELATED
TASKS
013804 STATIONARY IMPACT ATTENUATOR VEHICLE (LS) 12
010413 PORTABLE RADAR SPEED FEEDBACK SIGN SYSTEMS (LS) 12
013357 AUTOMATED FLAGGER ASSISTANCE DEVICE 12
013843 CONTRACTOR SUPPLIED ARBORIST 14
017985 ROADWAY EXCAVATION (HANDWORK) 19
037164 HIGH FRICTION SURFACE TREATMENT 37
Add to section 1-1.09:
This project is in a freeze-thaw area.
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information Means Description
Included in the Information Handout 1. PLAC U.S. Fish and Wildlife Service, Arcata Fish and Wildlife Office, Letter of Concurrence, Ref. No.
AFWO-2023-003821, dated August 03, 2026
2. Aerially Deposited Lead Sie Investigation Report, dated June 2024
Available as specified in the Standard Specifications
1. Digital terrain model in 3D DGN or LandXML format
2. Alignments and profiles in LandXML format
3. Cross sections in 2D DGN and PDF format
4. Digital design model in LandXML format
5. Pavement smoothness data (.ppf)
Add to the end of section 2-1.10:
Failing to adequately provide this information may require the bidder to self-perform the work, consistent with Public Contract Code § 4106.
Delete section 2-1.20.
Delete section 2-1.33B(2)(b).
5 CONTROL OF WORK
Replace the 2nd and 3rd paragraphs of section 5-1.09A with:
Professionally facilitated project partnering is required.
Delete section 5-1.13B.
Replace section 5-1.13E with:
5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Add to the end of section 5-1.20A:
During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:
Coincident or Adjacent Contracts
Contract no. County–Route–Post Mile Location Type of work 01-0J2104 DN-101-R3.9/23.6 Near Klamath Place overlay 01-0K9504 DN-101-15.6/16.2 Near Crescent City Reconstruct Roadway
Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.
Add to the end of section 5-1.20B(1):
The Department will communicate with PLAC agencies unless communication between you and the PLAC agency is authorized.
Add to the end of section 5-1.32:
Personal vehicles of your employees must not be parked on the traveled way or shoulders, including sections closed to traffic.
Do not cast precast concrete members within the right-of-way of Route 101.
Temporary parking of vehicles, and storage of equipment and materials is not allowed on vegetated areas.
6 CONTROL OF MATERIALS
Add to end of section 6-1.01:
If you fail to submit the form for materials subject to Buy America, the Department may:
1. Withhold from the next progress payment
2. Reject your request for a De Minimis Costs waiver for non-compliant construction materials or manufactured products
Replace section 6-1.04 with:
6-1.04 BUY AMERICA
6-1.04A General Buy America requirements do not apply to the following:
1. Tools and construction equipment used in performing the work
2. Temporary work that is not incorporated into the finished project
3. Excluded materials
An article, material, or supply to be permanently incorporated in the project should only be classified into one of the following categories based on its status at the time it is brought to the work site:
1. Iron or steel products
2. Manufactured products
3. Construction materials
4. Excluded materials
Excluded materials include:
1. Cement and cementitious materials
2. Aggregates such as stone, sand, or gravel
3. Aggregate binding agents or additives
4. Other materials that do not meet the definition of iron or steel products, manufactured products or construction materials
6-1.04B Crumb Rubber (Pub Res Code § 42703(d)) Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:
1. Produced in the United States
2. Derived from waste tires taken from vehicles owned and operated in the United States
6-1.04C Iron or Steel Products Iron or steel products, as defined in 23 CFR 635.410, must be melted and manufactured in the United States except:
1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials
2. The total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total bid or $2,500, the material may be used if authorized
Furnish iron or steel products to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured.
All melting and manufacturing processes for these materials, including an application of a coating, must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.
6-1.04D Manufactured Products Manufactured products mean articles, materials, or supplies that have been:
1. Processed into a specific form and shape; or
2. Combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies
Per 23 CFR 635.410, Manufactured Products must:
1. Be manufactured in the United States; and
2. The cost of the components that are mined, produced, or manufactured in the United States, as defined in 2 CFR 184.5, is greater than 55 percent of the total cost of all components of the manufactured product.
Manufacturer, in the case of manufactured products, means the entity that performs the final manufacturing process by bringing individual elements together that produces a manufactured product.
If an item is classified as an iron or steel product, a construction material, or an excluded material under the definitions set forth under this Buy America section, then it is not a manufactured product. However, an article, material, or supply classified as a manufactured product under this Buy America section may include components that are construction materials, iron or steel products, or excluded materials.
If the cost of iron and steel components of a product is more than 50 percent of the cost of the product, then the product would be classified as iron or steel products, not a manufactured product and only need to meet the requirements of section 6-1.04C except as noted below.
Iron or steel used in precast concrete manufactured products or enclosures for Intelligent Transportation Systems (ITS) and other electronic hardware systems must meet the requirements of section 6-1.04C regardless of the amount used.
Furnish manufactured products to be incorporated into the work with certificates of compliance with each project delivery. The manufacturer's certificate of compliance must identify where the manufacturing occurred and attest to compliance with the 23 CFR 635.410 standard.
6-1.04E Construction Materials The following construction materials must be produced in the United States under standards in 2 CFR 184.6:
1. Non-ferrous metals
2. Plastic and polymer-based products such as:
2.1. Polyvinylchloride
2.2. Composite building materials
3. Glass
4. Fiber optic cable including drop cable
5. Optical fiber
6. Lumber
7. Engineered wood
8. Drywall
All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United States.
Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where the construction material was manufactured and attest to compliance with the 2 CFR 184.6 standard.
Minor additions of articles, materials, supplies, or binding agents to construction materials do not change the categorization of the construction material.
6-1.04F Buy America Waiver for the De Minimis Costs for Manufactured Products and Construction Materials A De Minimis Costs waiver can waive the application of FHWA's Buy America requirements for manufactured products and construction materials under a single project when the total cost of non-compliant manufactured products and construction materials is no more than the lesser of $1,000,000 or 5 percent of the total applicable costs for the project.
The percentage threshold is calculated based on the following formula:
X = NC / TA
where:
X = percent threshold NC = total cost of non-compliant construction materials and manufactured products TA = total applicable project costs (steel, iron, construction materials and manufactured products;
does not include excluded materials)
This threshold is based on the actual cost of the steel, iron, construction materials, and manufactured products, not the anticipated cost of those materials. The contractor must account for compliant and non-compliant Department-Furnished Materials for the project in the De Minimis Costs Waiver Worksheet calculation if provided by the Department as supplemental project information.
See further instructions for the De Minimis Costs waiver request in the Notice of Materials to be Used form.
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Replace Section 7-1.02K(6)(j)(iii) with:
7-1.02K(6)(j)(iii) Unregulated Earth Material Containing Lead Section 7-1.02K(6)(j)(iii) includes specifications for handling, removing, and disposing of unregulated earth material containing lead. Management of this material must be addressed in your lead compliance plan. This material contains average lead concentrations below 80 mg/kg total lead and below 5 mg/L soluble lead and is not regulated by DTSC as a hazardous substance or a hazardous waste. This material does not require disposal at a permitted landfill or solid waste disposal facility. The RWQCB has jurisdiction over reuse of this material at locations outside the job site limits.
Manage regulated earth material containing lead under sections 14-11.08 and 14-11.09.
Unregulated earth material containing lead is present on the job site at the following locations:
Location Element of work Depth Sta "A" 100+00.00 Lt to Sta "A" 106+72.00 Lt
Excavation 0 to 2 feet
Sta "A" 106+72.00 Lt to
Sta "A" 107+88.00 Lt
Excavation 1 to 2 feet
Sta "A" 107+88.00 Lt to
Sta "A" 141+97.00 Lt
Excavation 0 to 2 feet
Sta "A" 100+00.00 Rt to
Sta "A" 106+88.00 Rt
Excavation 0 to 2 feet
Sta "A" 106+88.00 Rt to
Sta "A" 108+75.00 Rt
Excavation 1 to 2 feet
Sta "A" 108+75.00 Rt to
Sta "A" 141+97.00 Rt
Excavation 0 to 2 feet
Unregulated earth material containing lead has been detected to a depth of 2.0 feet within the job site.
Unregulated levels of lead found range from less than 0.99 to 73 mg/kg total lead with an average concentration of 24.55 mg/kg total lead as analyzed by EPA test method 6010 or EPA test method 7000 series and based upon a 95 percent upper confidence limit. Unregulated levels of lead on the job site have a predicted average soluble concentration of less than 5.0 mg/L as analyzed by the California Waste Extraction Test and based upon a 95 percent upper confidence limit.
Handle the material under all applicable laws, rules, and regulations, including those of the following agencies:
1. Cal/OSHA
2. CA RWQCB, Region - 1, North Coast
If unregulated material is disposed of:
1. Submit at least 15 days before disposal, the form titled "Agreement between a Contractor Working on State Facilities and a Real Property Owner for Disposing Construction-related Material Suitable for Use on Residential Zoned Property" which discloses the lead concentration of the material to the receiving property owner and obtains authorization for disposal on the property. Give a copy of the signed form to the property owner.
2. You are responsible for any additional sampling and analysis required by the receiving property owner.
If you choose to dispose of unregulated material at a commercial landfill:
1. Transport it to a Class III or Class II landfill appropriately permitted to receive the material
2. You are responsible for identifying the appropriately permitted landfill to receive the material and for all associated trucking and disposal costs, including any additional sampling and analysis required by the receiving landfill
8 PROSECUTION AND PROGRESS
Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:
Schedule Baseline schedule and weekly statement of working days report
Replace section 8-1.04C with:
8-1.04C Delayed Start Section 8-1.04B does not apply.
Start job site activities within 55 days after receiving notice that the Contract has been approved by the Attorney General or the attorney appointed and authorized to represent the Department.
Do not start job site activities until the Department authorizes or accepts your submittal for:
1. Contractor-supplied biologist
2. WPCP or SWPPP, whichever applies
3. Notification of DRA or DRB nominee and disclosure statement
4. CPM baseline schedule
5. Contingency plan for opening closures to traffic
If the submittals for Contractor-supplied biologist, natural resource protection plan, and biological resource information program are authorized, you may enter the job site only to measure controlling field dimensions, locate utilities, and survey for NSO/MAMU.
Do not start other job site activities until all submittals from the above list are authorized or accepted and the following information is received by the Engineer:
1. Notice of Materials To Be Used form.
2. Written statement from the vendor that the order for sign panels has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.
3. Written statement from the vendor that the order for electrical material has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.
You may start job site activities before the 55th day after Contract approval if you:
1. Obtain specified authorization or acceptance for each submittal before the 55th day
2. Receive authorization to start
Submit a notice 72 hours before starting job site activities. If the project has more than 1 location of work, submit a separate notice for each location.
Replace the 4th and 5th paragraphs of section 8-1.05 with:
The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.
The weekly statement of working days report shows:
1. Working days and non–working days during the reporting week
2. Time adjustments
3. Calculations of work completion dates, including working days remaining
4. Controlling activities
Delete the 6th paragraph of section 8-1.05.
9 PAYMENT
Replace the 1st paragraph of section 9-1.11D with:
For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.
Replace item 2 in the list in the paragraph of section 9-1.16C with:
2. Material cost exceeds either of the following:
2.1. $50,000
2.2. $25,000 if the requestor is certified as one or more of the following:
2.2.1. DVBE
2.2.2. Small business as certified by Department of General Services, Office of Small
Business and Disabled Veteran Business Enterprise Services
DIVISION II GENERAL CONSTRUCTION
10 GENERAL
Replace section 10-1.03 with:
10-1.03 TIME CONSTRAINTS
Complete Stage 1 Traffic Handling as shown by March 15, 2027, Conduct protocol nesting bird surveys twice weekly on non-consecutive days between March 15th, 2027 and July 1, 2027.
Replace the 1st sentence in the 3rd paragraph of section 10-6 with:
Water must be nonpotable.
12 TEMPORARY TRAFFIC CONTROL
Add to section 12-3.11B(5)(b):
Provide 2 C50D(CA) construction project funding identification signs.
Legend for the type of project must read as follows:
HIGHWAY IMPROVEMENT
Legend for the year of completion on project funding sign must read as follows:
YEAR OF COMPLETION: 2028
Add between the 2nd and 3rd paragraphs of section 12-3.20A(1):
Value engineering change proposals for the use of Type K temporary railing are not allowed.
Replace item 2 of the list in paragraph 1 of section 12-3.20A(3) with:
2. Manufacturer's installation instructions and Department approved manufacturer’s drawings from the
Department’s Division of Safety Programs website, except for temporary concrete barriers Cross Bolt, and CAL F-23.
Replace the 3rd and 4th paragraphs of section 12-3.20B(1) with:
Temporary barrier systems must comply with a minimum MASH Test Level 3.
Except for Cross Bolt, and CAL F-23, temporary barrier systems must:
1. Be on the Authorized Materials List for highway safety features
2. Comply with the manufacturer's drawings shown on the Department's Division of Safety Programs website and the manufacturer's installation instructions
Delete section 12-3.20B(2)(c):
Replace the tables in paragraph 2 of section 12-3.20C(1) with:
Minimum Clear Area Width
Temporary barrier system Configuration
Height differentials 3 feet or less
(ft)
Height differentials greater than 3 feet up to 8 feet
(ft)
Edge of deck or height differentials greater than
8 feet (ft)
Fixed objects, falsework members, or temporary supportsa
(ft) Cross Bolt 10-foot & 30-foot
Freestanding 1 2 5 5 3 stakes or anchor bolts per segment traffic side
1 1 2 3
Cross Bolt 20-foot
Freestanding 1 2 5 5 4 stakes or anchor bolts per segment traffic side
1 1 2 3
CAL F-23
12-foot
Freestanding 4 5 8 8 3 stakes or anchor bolts per segment traffic side
1 1 2 3
CAL F-23
20-foot
Freestanding 4 5 8 8 4 stakes or anchor bolts per segment traffic side
1 1 2 3
J-J hooks 12.5-foot
Freestanding 3 4 8 7 3 stakes per segment traffic side
1 1 2 3
2 anchor bolts per segment traffic side
1 1 2 3
J-J hooks 20-foot
Freestanding 3 4 8 7 4 stakes per segment traffic side
1 1 2 3
3 anchor bolts per segment traffic side
1 1 2 3
ProMASH 30-foot
Freestanding 1 2 4 4 4 stakes on traffic side 1 1 1 2
4 stakes each side (total 8) 1 1 1 2
ProMASH 20-foot
Freestanding 1 2 5 5 3 stakes on traffic side 1 1 2 3
3 stakes each side (total 6) 1 1 1 2
ProMASH 10-foot
Freestanding 2 3 6 6 2 stakes on traffic side 1 1 3 4
2 stakes each side (total 4) 1 1 2 3
REBLOC
39.33-foot
SDS
Freestanding 4 4 7 7
MDS
Staked or
Anchored every
6.5 feet
1 1 2 4
Zoneguard 50-foot
Freestanding Staked or anchored at both ends only
6 7 9 10
SDS
Staked or anchored every 250 feet
5 6 8 9
MDS
Staked or anchored every 33 feet
1 1 3 4
HV2
19-foot Freestanding 4 5 7 8
Defender 12-3/4-foot
Staked every 30 feet 1 2 4 5
HighwayGuard 19.8-foot
SDS
Staked or
Anchored every 190 feet
4 5 7 8
LDS
Staked or
Anchored every 40 feet
1 2 5 5
MDS
Staked or
Anchored every
6.5 feet
1 1 1 2 aThe minimum clear area width to a falsework or temporary support footing can be 2 feet less than the clear area width shown. Measure clear area width to the footing edge closest to traffic.
Minimum System Length, Curve Radius, and Setback
Temporary barrier system
Barrier segment length
(ft)
Minimum system length
(ft) Minimum curve radius (ft)
Minimum setback
(ft) Posted speed greater than
45mph
Posted speed 45mph or less
Cross Bolt 10
160 120
CAL F-23 12
20 160 120 100
165 1
J-J hooks 12.5
165 1
ProMASH 10
REBLOC
SDS
MDS 39.33 354
197 853 6
Zoneguard
Freestanding
SDS
MDS 50 250 250 800
NAa NAa
HV2 19 323 323 262 5
Defender 12.75 260 260 755 2 HighwayGuard SDS 19.8 393 393 NAa 7 HighwayGuard LDS 19.8 200 200 NAa 2 HighwayGuard
MDS 19.8 160 120 NAa NAa a Not approved.
Delete section 12-3.20C(2)(c):
Replace section 12-3.22 with:
12-3.22 TEMPORARY CRASH CUSHIONS
12-3.22A General 12-3.22A(1) Summary Section 12-3.22 includes specifications for temporary crash cushions.
Type 3 marker panels must comply with section 82.
12-3.22A(2) Definitions Not Used
12-3.22A(3) Submittals At least 10 days before installation, submit as informational submittal for each temporary crash cushion model:
1. Certificate of compliance
2. Two copies of the following:
2.1. Manufacturer’s installation and maintenance manual
2.2 Department approved manufacturer’s drawings from the Department’s Division of Safety
Programs website
3. Record of training provided by manufacturer for each person installing the temporary crash cushion
12-3.22A(4) Quality Assurance 12-3.22A(4)(a) General Not Used
12-3.22A(4)(b) Quality Control Temporary crash cushion must be installed by personnel trained by the manufacturer.
Keep a copy of the manufacturer’s drawings, and installation and maintenance manual for each temporary crash cushion model at the job site during installation.
12-3.22B Materials 12-3.22B(1) General Temporary crash cushion must be on the Authorized Materials List for highway safety features.
12-3.22B(2) In-Line Temporary Crash Cushions 12-3.22B(2)(a) General In-line temporary crash cushion must:
1. Include all components required for attachment to temporary barrier or protected obstacle
2. Comply with the manufacturer's drawings shown on the Department’s Division of Safety Programs website
12-3.22B(2)(b) Temporary Crash Cushions TL-3 Temporary crash cushion TL-3 must comply with MASH TL-3 for a posted speed limit of 45 mph or greater.
12-3.22B(2)(c) Temporary Crash Cushions TL-2 Temporary crash cushion TL-2 must comply with MASH TL-2 for a posted speed limit of less than 45 mph.
12-3.22B(3) Temporary Crash Cushion Modules Temporary crash cushion module array must comply with MASH:
1. Test Level 3 (TL-3) for a posted speed limit of 45 mph or greater
2. Test Level 2 (TL-2) for a posted speed limit of less than 45 mph
Each temporary crash cushion module must be:
1. Colored standard yellow with a black lid
2. Free from structural flaws and objectionable surface defects
Sand must:
1. Be commercial quality, washed concrete sand
2. Contain no more than 5 percent water under California Test 226, when placed in the module
12-3.22C Construction 12-3.22C(1) General When activities expose traffic to fixed obstacles, protect traffic from the obstacles with temporary crash cushions.
Install temporary crash cushions under the manufacturer's instructions before:
1. Starting activities requiring temporary crash cushions
2. Opening lanes to traffic
Temporary crash cushions must not impede the flow of traffic or encroach on the traveled way.
Attach a Type 3 marker panel to the front of temporary crash cushions if the closest point to the traveled way is within 15 feet of the traveled way. Fasten marker panels firmly to crash cushions with commercial quality hardware or by other authorized methods.
Maintain temporary crash cushions in place at each location, including when work is not in progress.
Keep the area on the non-traffic side of the temporary crash cushions clear of obstructions.
Repair or replace damaged temporary crash cushions immediately. Repair and replacement of temporary crash cushions damaged by traffic is change order work.
12-3.22C(2) In-Line Temporary Crash Cushions When in-line temporary crash cushions are placed with temporary barrier systems, comply with the following tables:
Authorized Temporary Crash Cushions for Temporary Barrier Systems Temporary barrier system ABSORB M ABSORB RZ ArmorBuffa QUASH SLED
Cross bolt X -- X X X
CAL F-23 X -- X X X
J-J hooks X -- X X X ProMASH X -- X X X Zoneguard X -- -- -- X
HV2 -- -- -- -- X
Defender X -- -- -- -- HighwayGuard -- -- X -- --
REBLOC X -- X X X
Authorized Temporary Crash Cushions for Movable Barrier Systems Moveable barrier system ABSORB M ABSORB RZ ArmorBuffa QUASH SLED
Quickchange moveable barrier concrete reactive tension system
-- X -- -- --
TALL 42 -- -- -- X --
When temporary crash cushions are used with temporary barrier systems:
1, Place temporary crash cushion parallel to the traveled way
2. Offset temporary crash cushion 2 feet from the edge of traveled way, when practicable
3. Place a minimum 20 feet temporary barrier system in alignment with the temporary crash cushion
Offset temporary crash cushions placed adjacent to a:
1. Barrier, a distance 1 to 2 feet or 7 feet or greater from the barrier
2. Dike or curb, a distance 0 to 4 feet or 7-1/2 feet or greater from the dike or curb
A lateral move of a temporary crash cushion is change order work if ordered and the repositioning is not shown.
12-3.22C(3) Temporary Crash Cushion Modules You may use NCHRP Report 350 compliant sand-filled temporary crash cushion modules before December 31, 2026.
Use the same type of temporary crash cushion module for each array. Fill each module with sand under the manufacturer's instructions.
Securely fasten the top edge of a seal to the wall of the temporary crash cushion module with a continuous strip of heavy-duty tape, when a seal is required.
You may place temporary crash cushion modules on movable pallets or frames complying with the dimensions shown. The pallets or frames must provide a full-bearing base beneath the modules. Do not move the modules and supporting pallets or frames by sliding or skidding along the pavement or bridge deck.
Attach OM3-R or OM3-L marker panel such that the top of the panel is 1 inch below the module lid.
Attach OM3-C marker panel such that the bottom of the panel rests upon the roadway surface or pallet surface when used.
You may remove temporary crash cushion modules during the work shift for access to the work area if the exposed fixed obstacle is 15 feet or more from the nearest lane carrying traffic. Reset the modules before the end of the work shift.
12-3.22D Payment Not Used
Add to the beginning of section 12-3.32C:
Place PCMSs at the locations shown and in advance of the 1st warning sign for each stationary lane closure.
Replace the 5th paragraph of section 12-3.32C with:
When in operation, place the bottom of a PCMS at least 7 feet above the roadway. Place the top of the PCMS no more than 14.5 feet above the roadway.
Add between the 9th and 10th paragraphs of section 12-3.32C:
Start displaying the message on the sign 15 minutes before closing the lane or when directed by the Engineer.
Replace section 12-3.37 with:
12-3.37 PORTABLE RADAR SPEED FEEDBACK SIGN SYSTEMS
12-3.37A General Section 12-3.37 includes specifications for placing, maintaining, and removing portable radar speed feedback sign systems.
The system must be able to operate on a continuous, 24- hour basis.
12-3.37B Materials A portable radar speed feedback sign system consists of a vehicle speed feedback sign, a power source, and signs R2-1 and G20-5aP.
The portable radar speed feedback sign system must comply with section 87-14, except:
1. System must be mounted on a trailer
2. LED character display must remain blank when no vehicles are detected or when the detected vehicle speed is 10 miles less than the preset speed
Sign panels must comply with section 82-2.
12-3.37C Construction Configure the portable radar speed feedback sign system to detect traffic only in the approach direction of travel.
Place the portable radar speed feedback sign system.
1. As far from the traveled way as practicable where it is visible and legible to approaching traffic. Where practicable, place the sign behind a barrier or guardrail.
2. At or before the crest of roadway vertical curvatures that restrict sight distance.
3. At or before the curve of horizontal roadway curvatures that restrict sight distance.
12-3.37D Payment
Add between the 1st and 2nd paragraphs of section 12-4.02A(3)(c):
Submit a contingency plan for each of the following activities:
1. Roadway excavations encroaching on the traveled way not protected by temporary barrier system
2. Cold-planing asphalt concrete for depths of 2 inches or greater
3. HMA paving
4. Striping
5. Temporary signal system
Add to section 12-4.02A(3):
12-4.02A(3)(e) Emergency Responder Access Plan Submit an emergency responder access plan.
The emergency responder access plan must include:
1. Procedures and location of a path for emergency responder access through the work zone.
2. The estimated time to clear the path and provide access.
3. List of workers trained in the emergency responder access plan procedures.
4. Primary and alternate contact information and methods for:
4.1. Traffic control technician.
4.2. On-site representatives responsible for implementing the emergency responder access plan.
4.3. Emergency responder agencies. Obtain list of emergency responders from the Engineer.
5. Written confirmation from the emergency responder agencies they will provide advance notification each time they need access through the work zone.
Retain a printed copy of the approved plan at the jobsite. Provide a copy of the emergency response access plan to the emergency responder agencies.
Add to the end of section 12-4.02C(1):
Keep the full width of the traveled way open to traffic when no active construction activities are occurring in the traveled way or within 6 feet of the traveled way.
Replace section 12-4.02C(3)(f) with:
12-4.02C(3)(f) Closure Restrictions for Designated Holidays and Special Days Closure restrictions for designated holidays are shown in the following table:
Lane Closure Restrictions For Designated Holidays Thu Fri Sat Sun Mon Tues Wed Thu Fri Sat Sun Mon xx
H
Legend:
Refer to lane requirement charts.
xx Except during the use of temporary signal systems, the full width of the traveled way must be open for use by traffic.
H Designated holiday
Replace section 12-4.02C(3)(k) with:
12-4.02C(3)(k) Conventional Highway Lane Requirement Charts Comply with the requirements for the conventional highway lane closures shown in the following charts:
Chart No. K1 Multilane Conventional Highway Lane Requirements
County: Del Norte Route/Direction:101/NB
101/SB
Post Mile:18.3/18.7 18.9/19.9
Closure limits:
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Mon– Thu
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Fri 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Sat 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Sun 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Legend:
1 Provide at least 1 through traffic lane and adjacent space with a minimum width equal to the existing shoulder open in the direction of travel.
REMARKS:…
This is the start of the file's text. The full file is on GovTribe.