This document is an official advertisement for a state-let construction contract in Hardin, Jefferson, Jasper, Liberty, Orange, and Chambers counties in Texas. The contract is for a Hazard Elimination and Safety project on various highways including US 96, US 190, SH 61, SH 62, SH 73, SH 87, SH 105, FM 563, FM 105, FM 0777, FM 2246, FM 1003, FM 2518, and CR 109, CR 676, CR 2800, Zach Banks Rd, and Englin Rd. The total project length is 5.096 miles, and the estimated cost is $1,985,289.57. Bids will be received until 1:00 PM on March 5, 2024, and the contract has a time for completion of 119 working days.
The project has a 0.0% Disadvantaged Business Enterprise (DBE) goal. Bidders must provide a $40,000.00 guaranty. Funding for the project is through the Federal-aid Highway Program. The contract will be awarded by the Texas Department of Transportation (TxDOT).
Text of this file
******* OFFICIAL ADVERTISEMENT *******
*** STATE LET CONSTRUCTION CONTRACT ***
COUNTY: HARDIN, ETC HIGHWAY: US 96, ETC LENGTH: 5.096 MI
CONTROL NUMBER: 0065-05-158, ETC DBE GOAL: 0.0 %
PROJECT NUMBER: STP 2024(953)HES, ETC
TYPE: HAZARD ELIMINATION & SAFETY
TIME FOR COMPLETION: 119 WORKING DAYS GUARANTY: 40,000.00
BIDS RECEIVED UNTIL: 1:00 PM March 5, 2024 EST.COST: 1,985,289.57 BIDS WILL BE OPENED: 1:00 PM March 5, 2024
MAIL OR DELIVER BIDS TO: FOR QUESTIONS CALL:
TEXAS DEPARTMENT OF TRANSPORTATION DAVID COLLINS
AUSTIN HQ - STASSNEY 8350 EASTEX FREEWAY
6230 E STASSNEY LN RM M1C3.02 BEAUMONT TX 77708
AUSTIN TX 78744-3147 (409)898-5836
(512)416-2498
COUNTY CONTROL LIMITS FROM
HIGHWAY PROJECT LIMITS TO
HARDIN 0065-05-158 AT NERREN LN
US 96 STP 2024(953)HES .
LENGTH: 0.200 MILES
JASPER 0213-08-097 AT FM0777
US 190 STP 2024(953)HES .
LENGTH: 0.200 MILES
LIBERTY 0242-01-029 AT CR 109
SH 61 F 2024(952) .
JASPER 0243-01-055 AT FM2246
SH 62 STP 2024(807)HES .
LENGTH: 0.200 MILES
ORANGE 0306-01-068 FM 105, SOUTH
SH 87 STP 2024(953)HES SH 62
LENGTH: 3.056 MILES
JEFFERSON 0508-04-187 AT ENGLIN RD
SH 73 STP 2024(953)HES .
LENGTH: 0.219 MILES
LIBERTY 0593-01-138 AT CR676
SH 321 STP 2024(953)HES .
LENGTH: 0.199 MILES
HARDIN 0811-02-032 AT FM1293
FM 1003 STP 2024(807)HES .
LENGTH: 0.199 MILES
LIBERTY 0813-01-111 AT FM2518
FM 787 STP 2024(807)HES .
LENGTH: 0.282 MILES
LIBERTY 0951-01-077 AT CR 2800
SH 105 STP 2024(953)HES .
LENGTH: 0.198 MILES
CHAMBERS 1023-01-038 ZACH BANKS RD, SOUTH
FM 563 F 2024(952) 0.35 MILES NORTH OF PERCH
LENGTH: 0.343 MILES
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .