SOW

Ver. 2/8/2017RESPONSIBLE
NOT RESPONSIBLE
NOT AVAILABLE
Project Information (Will populate into Contact Cost tab)
NAME:MISSION COMMAND CENTER- 807 Harrison DrMTUF1-Fiber Ready - All floors (30 Day Activation)
ADDRESS:807 Harrison Dr, Fort Leavenworth, KS, 66027STUF3-Fiber in Buiding (60 Day Activation)
LOB:COAX COMMERCIAL NEW BUILDTYPE:STANDARD COAXNEXF4-Fiber at Curb (60 Day Activation)
DOCKID:1581746CONST#:878482SITE SURVEY#:3247727STREETVIEWRACK MOUNTF5-Fiber Port Access Available (60 Day Activation)
POC:WALL MOUNTF6-Fiber in Building - Non Conventional - (90 Day Activation)
NODE/HUB:Y9C/LVMAP:2670-1162FS-Fiber Serviceable (90 Day Activation)
OU:KCYESFN-Fiber Serviceable NYC/LA (120 Day Activation)
REC'D DATE:1/25/18 0:00WALKED BY:HarvalaNONS-Non Serviceable (Cold, Off-Net)
Serviceability CodeC2-Coax in Building, typically Home Run(30 Day Activation)B1-Fiber and Coax Ready All Floors (30 Day Activation)
MTU, STU or NEXSTUActive Agg Switch-Lateral DropB3-Fiber & Coax in Building (60 Day Activation)
BUILD TYPESTU (Single Tenant Unit)ColocationB4-Fiber & Coax at Curb (60 Day Activation)
TENANT COUNT1Home RunB5-Fiber Port Access Available & Coax in Bulding (60 Day Act)
LENGTH OF BLDG110MTU Conv w/ConstrB6-Fiber & Coax in Building NYC & LA (90 Day Activation)
WIDTH OF BLDG115MTU Conv w/o ConstrC1-Coax Ready All Floors, ROE obtained, Coax to MPOE (30 Day Activation)
NUMBER OF STORIES1MTU New BuildC2-Coax in Building, typically Home Run(30 Day Activation)
BUILDING EXTERIOR FINISHBlockNEX (Network Expansion)C3-Coax in Building, NYC & LA (60 Day Activation)
COMMON MPOE AVAILABLEyesStrip MallC4-Coax Coil at the Curb (60 Day Activation)
COMMON MPOE LOCATIONMechanical RoomSTU (Single Tenant Unit)C7-Coax Drop, Serviceable No Construction Required (30 Day Activation)
COMMON MPOE ROOM ACCESS SPECIFICSmech room in bsmt. Enter from W side outdoor stairway
PRIVATE NON-MPOE EQUIPMENT LOCATION
POWER IS IT AVAILABLE & WHEREna
RACK or WALL MOUNTwall mount
SPACE AVAILABILTY FOR RACK/WALL MOUNTyes
CORES REQUIRED TO ENTER BLDGnoBUILDING ACCESSNAMEPHONE #
PREBURY DROPnoNORMAL BUSINESS HOURS
FIBER VERIFICATION COMPLETED BYnaAFTER HOURS
FIBER VERIFICATION COMPLETE DATEnaEMERGENCY
Project Description: Detail from Right Of Way to Interior D-Marc in or at the Venue.
*IF MTU, detailed description MUST contain Entire Building Layout, Rack, and Power Locations*
1. From the tie in point in bldg 465. room 009, Comms Closet, enter into the existing conduit.

2. Back feed and pull coax W 145' to the grass area next to the old Prison wall. Dig up and expose the exisitng conduit and install a pull box.

3. Asphalt bore coax E 19'. Concrete bore coax E 12' to the S side of bldg 465. (4x4 concrete cut and replace section next to the bldg)

4. Attach new EMT 2" conduit between the bldg wall and concrete slab and pull coax 30' E. (Install LB's on both ends)

5. Bore coax E 9', then 25' S to an existing customer pull box.

6. Pull coax 30' W and enter into the Mechanical room. Mount a 2x2 plywood board on the S wall and terminate equipment. Coax end point.

Detail from Right Of Way to Interior D-Marc in or at the Venue.
Insert Field Map
*First 3 pages are for field map. Followed by 3 more pages for interior, exterior, rack/wall mount pictures.*

CHARTER COMMUNICATIONS SCOPE OF WORK

SOW OVERALLDetail from Right Of Way to Interior D-Marc in or at the Venue.
DOCK #1581746Insert Field Map

CHARTER COMMUNICATIONS SCOPE OF WORK

SOW OVERALLDetail from Right Of Way to Interior D-Marc in or at the Venue.
DOCK #1581746Insert Field Map
Insert Exterior & Interior Pictures
Include Rack or Wall Mount Pictures

insert pic here insert pic here

Tie point in bldg 465, room 009, Comms ClosetEnter existing conduit and back feed coax to the wall
Dig up and expose the existing conduit and install a pull box.Asphalt bore coax to the S side of bldg 465
insert pic hereinsert pic here

Insert Exterior & Interior Pictures insert pic here insert pic here

Concrete bore and cut next to the bldgInstall coax in EMT conduit and attach to the bldg
Coax in EMT on the E end of the fenced in area.Bore coax E, the S to an existing pull box
insert pic hereinsert pic here

Insert Exterior & Interior Pictures insert pic here insert pic here

Enter coax in customer pull box.Pull coax in customer conduit and enter mech room
Enter into the bsmt mechanical roomMount equipment on the W wall. Coax end point
insert pic hereinsert pic here

image1.jpeg image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.png image2.jpeg image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg