This Invitation to Bid document is issued by Coffee County Schools in Douglas, Georgia, for a wall replacement project at Coffee Middle School. The project involves removing and replacing masonry walls, hollow metal frames and doors, aluminum windows, flooring, and ceiling components at the school located at 901 Connector 206 N., Douglas, Georgia 31533. The Owner's Representative is Michael Spikes (912-850-5018), and the project architect is Altman + Barrett Architects. A mandatory prebid conference will be held on November 19, 2026, at 10:00 a.m. at the school site, with attendance required for all prospective bidders. Sealed bids must be submitted by December 8, 2026, at 2:00 p.m. local time at Coffee County Schools, 211 Gaskin Avenue S., Douglas, Georgia 31533. The successful bidder shall begin work upon receipt of Notice to Proceed, with a projected start date of May 27, 2027, and completion date of July 26, 2027.

Bidders must submit bid security equal to 5 percent of the bid amount, and bids may not be withdrawn for 60 days after opening. Procurement and contracting documents are available for purchase from Print Life Printing and Supplies, Inc., for $150.00 (plus shipping) after November 5, 2026, or may be viewed online at www.altmanbarrettarchitects.com. The contract is structured as a General Contract covering all trades. Qualified bidders must be properly licensed in their respective trades and must provide a Performance Bond, separate Labor and Material Payment Bond, and acceptable insurance upon award. The Owner reserves the right to reject any and all bids and to waive informalities and irregularities.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

26037 Wall Replacement CMS Altman + Barrett Architects 001116-1

SECTION 001116

INVITATION TO BID

1.01 PROJECT INFORMATION

A. Notice to Bidders: Qualified bidders are invited to submit bids for Project as de-scribed in this Document according to the Instructions to Bidders.

B. Project Identification: Wall Replacement Coffee Middle School.

C. Project Location: Coffee Middle School: 901 Connector 206 N., Douglas, GA

31533.

D. Owner: Coffee County Schools, 271 Trojan Way. Douglas, GA 31533.

E. Owner's Representative: Michael Spikes, 912-850-5018 F. Architect: Altman + Barrett Architects, P.O. Box 665 Hahira, GA 31632.

G. Project Description: Project consists of removing masonry wall, hollow metal frames, aluminum windows, flooring, ceiling tile, ceiling grid, install new masonry wall, hollow metal doors and frames, hardware install new ceiling tile, ceiling grid, new flooring, and removing debris from site.

H. Construction Contract: Bids will be received for the following Work:

1. General Contract (all trades).

1.02 BID SUBMITTAL AND OPENING

A. Owner will receive sealed bids until the bid time and date at the location indicated below. Owner will consider bids prepared in compliance with the Instructions to Bidders issued by Owner, and delivered as follows:

1. Bid Date: December 8, 2026

2. Bid Time: 2:00 p.m. local time.

B. Location: Coffee County Schools, 211 Gaskin Avenue S. Douglas, GA 31533 C. Bids will be thereafter publicly opened and read aloud.

1.03 BID SECURITY

A. Bid security shall be submitted with each bid in the amount of [5] percent of the bid amount. No bids may be withdrawn for a period of [60] days after opening of bids. Owner reserves the right to reject any and all bids and to waive informalities and irregularities.

1.04 PREBID CONFERENCE

A. A mandatory prebid conference for all bidders will be held at Coffee Middle

School: 901 Connector 206 N., Douglas, GA 31533. on November 19th, 2026, at 10:00 A.M. local time. Prospective bidders are required to attend.

1.05 DOCUMENTS

A. Printed Procurement and Contracting Documents: Obtain after November 5, 2026, by contacting Print Life Printing and Supplies, Inc., 1006 Williams St. Val-dosta, GA 31601 or by calling (229)244-5598. Documents will be provided to prime bidders only; only complete sets of documents will be issued.

1. Payment: $150.00 [made payable to Print Life Printing and Supplies].

2. Shipping: Additional shipping charges will apply.

B. Viewing Procurement and Contracting Documents: Examine after November 5, 2026, at the locations below:

1. www.altmanbarrettarchitects.com

1.06 TIME OF COMPLETION

A. Successful bidder shall begin the Work on receipt of the Notice to Proceed and shall complete the Work within the Contract Time. Start May 27, 2027 and pro-ject completed July 26, 2027.

http://www.altmanbarrettarchitects.com/

26037 Wall Replacement CMS Altman + Barrett Architects 001116-2

1.07 BIDDER'S QUALIFICATIONS

A. Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the Work. A Per-formance Bond, a separate Labor and Material Payment Bond, and Insur-ance in a form acceptable to Owner will be required of the successful Bid-der.

END OF DOCUMENT 001116