This is an Advertisement for Bids issued by the Decatur County Board of Commissioners in Georgia for Generator & Transfer Switch Installations. The project involves furnishing all labor, materials, and equipment necessary to install six generators with transfer switches and associated equipment at multiple locations within the Decatur County Industrial Air Park and County Public Works Site. Sealed bids will be received until 11:00 AM on Tuesday, July 1, 2025, at the Decatur County Board of Commissioners office located at 203 West Broughton Street, Bainbridge, Georgia 39817. The contract will be awarded as a single contract, and the contractor must complete the work within 180 consecutive calendar days to substantial completion, with full contract closeout required within 194 consecutive calendar days. Bidding documents are available for purchase from Watkins & Associates, LLC for $300.00 per set (non-refundable) and can be examined at either the County Commissioners office or the engineer's office during business hours, Monday through Friday, 8:00 AM to 5:00 PM. Plan holders list, addenda, and bid results are available at www.watkinseng.com.

All bidders must be licensed Electrical Contractors with license numbers clearly displayed on the bid envelope. Bids must be accompanied by a Bid Bond or certified cashier's check equal to ten percent (10%) of the bid amount from a Georgia-licensed surety company with minimum "A" rating. The successful bidder will be required to furnish Performance and Payment Bonds each equal to 100 percent of the contract amount. Prequalification of bidders may be required, and all bidders must complete an Affidavit of Compliance with Georgia's Security and Immigration Compliance Act and register with E-Verify. The project is funded through a GEMA Grant. No bid may be withdrawn after the closing time for a period of 60 days. The Owner reserves the right to reject any or all bids and to waive informalities or re-advertise as deemed in the best interest of the project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Advertisement for Bids Section 00111

Decatur County Board of Commissioners W&A Project No.: W0405-037-01 Generator & Transfer Switch Installations 01200-1

DECATUR COUNTY BOARD OF COMMISSIONERS

GENERATOR & TRANSFER SWITCH INSTALLATIONS

ADVERTISEMENT FOR BIDS

PART 1 GENERAL

1.01. COMPETITIVE COST SEALED BIDS

Sealed Bids for the construction of the Generator & Transfer Switch Installations will be received, by Decatur County Board of Commissioners at 203 West Broughton Street, Bainbridge, GA 39817, until 11:00 AM, Tuesday, July 1, 2025, local time, at which time the Bids received will be publicly opened and read. No bid may be withdrawn after the closing time for receipt of bids for a period of sixty (60) days.

1.02. CONTRACTOR LICENSE

Any Contractor submitting a bid must be a licensed Electrical Contractor. License numbers must be written on the face of the bid envelope. No bid will be opened unless the license number is clearly shown. See Instructions to Bidders for additional bidding requirements.

1.03. SCOPE OF WORK

The work to be done shall consist of furnishing all labor, materials and equipment necessary to construct the proposed Generator & Transfer Switch Installations as shown on the construction drawings. In general, construction consists of installing (6) generators transfer switch and associated equipment required for a complete project. Locations vary within the Decatur County Industrial Air Park and County Public Works Site. Time allotted for completion of work is 180 consecutive calendar days to substantial completion. Work shall be complete and ready for contract close-out with 194 consecutive calendar days. All work shall be completed in accordance with the plans and specifications. The work will be awarded in one (1) Contract.

1.04. PLANS AND BIDDING DOCUMENTS

Copies of Bidding Documents for bidding purposes can be obtained from Watkins & Associates, L.L.C., 1606 Whiddon Mill Road, Tifton, Georgia 31793, Phone: (229) 388- 8823, (Office of the Engineer) upon payment of $300.00 for each set (non-refundable).

Prospective Bidders may examine the Bidding Documents at the Decatur County Board of Commissioners, located at 203 West Broughton Street, Bainbridge, GA 39817 or at Watkins & Associates, LLC on Mondays through Fridays between the hours of 8 A.M. and 5 P.M. Upon request and receipt of the document payment indicated above, Watkins & Associates, LLC will transmit the Bidding Documents via delivery service. The date that the Bidding Documents are transmitted will be considered the prospective Bidder’s date of receipt of the Bidding Documents. Partial sets of Bidding Documents will not be available from the Engineer. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including Addenda if any, obtained from sources other than the Office of the Engineer.

Generator & Transfer Switch Installations 01200-2

1.05. REQUESTS FOR INFORMATION

Plan holders list, addenda and bid results are available at www.watkinseng.com.

1.06. PREQUALIFICATION OF BIDDERS

Prequalification may be required of Bidders prior to the award of contract. At the Owner’s request, detailed written evidence such as financial data, bonding capacity, previous experience, present commitments, and other such data may be necessary to assist Owner in determining Contractor’s qualifications shall be provided per the Instructions to Bidders contained in the contract documents.

1.07. BONDS

All bid forms must be accompanied by a Bid Bond or a certified cashier’s check in an amount not less than ten percent (10%) of the amount bid. All bonds shall be by a surety company licensed in Georgia with “A” minimum rating performance and financial strength of at least five (5) times the contract price as listed in the most current publication of “Best’s Key Rating Guide Property Liability”. The successful bidder, if awarded the Contract, will be required to furnish a Performance Bond and Payment Bond, each in the amount of one hundred percent (100%) of the Contract amount. All bonds must appear on the Treasury Department's most current Circular 570 Listing. Each Bond shall be accompanied by a “Power of Attorney” authorizing the attorney-in-fact to bind the surety and certified to include the date of the bond.

1.08. PERMITS

All anticipated federal, state, or local permits required for the project have been applied for and are expected to be approved prior to issuance of the Notice to Proceed.

1.09. GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT

All qualifying Contractors and Subcontractors performing work with the Decatur County Board of Commissioners must register and participate in the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, to verify the work eligibility information of new employees. In order for a Bid to be considered, it is mandatory that the Bidder’s Affidavit of Compliance with O.C.G.A. §13-10-91 be completed and submitted with the Bid.

1.10. FUNDING SOURCES

Any Contract or Contracts awarded under this Advertisement for Bids will be funded by a grant from the GEMA Grant.

1.11. RESERVATION OF RIGHTS

Owner reserves the right to reject any or all Bids, including without limitation, the rights to reject any or all nonconforming, nonresponsive, unbalanced, or conditional Bids and to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent

Generator & Transfer Switch Installations 01200-3 standard or criteria established by the Owner. Owner reserves the right to waive informalities and to re-advertise.

Owner: Decatur County Board of Commissioners By: Alan Thomas Title: County Administrator Date: May 28, 2025 June 11, 2025 June 25, 2025

END OF SECTION

PART 1 GENERAL
1.01. COMPETITIVE COST SEALED BIDS
1.02. Contractor license
1.03. SCOPE of work
The work to be done shall consist of furnishing all labor, materials and equipment necessary to construct the proposed Generator & Transfer Switch Installations as shown on the construction drawings. In general, construction consists of installing (6...
1.04. plans and bidding documents
1.05. requests for information
1.06. Prequalification of bidders
1.07. Bonds
1.08. Permits
1.09. georgia security and immigration compliance act affidavit
1.10. funding sources
Any Contract or Contracts awarded under this Advertisement for Bids will be funded by a grant from the GEMA Grant.

1.11. reservation of rights