00111 _ Ashburn Manhole Repair Advertisement .pdf

PDF 141 KB Posted

Attached to
Sanitary Sewer Manhole Repair
Solicitation number
PE-74250-NONST-2024-000000006
Issued by
Upson County, Georgia

About this file

This document is an Advertisement for Bids from the City of Ashburn, Georgia for a Sanitary Sewer Manhole Repair project funded by a State Fiscal Recovery Fund (SFRF) grant. The work involves raising 4 manholes above a flood-prone area and installing bolt-down ring and covers, as well as clearing 2,000 linear feet of sanitary sewer easement. Sealed bids are due by 11:00 AM on Friday, November 1, 2024, with a 60-day bid validity period. Bidders must be licensed utility contractors, and the successful bidder will be required to provide performance and payment bonds. The project is expected to be completed within 60 consecutive calendar days, with an additional 14 days for contract closeout.

The contract will be awarded using funds from the SFRF grant, GEFA funds, or local City funds. Contractors must meet the provisions of the funding agency, and the City reserves the right to reject any or all bids. Prequalification of bidders may be required prior to award, and the City has the right to waive informalities and re-advertise the project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Advertisement for Bids Section 00111

City of Ashburn, Georgia W&A Project No.: W0119-044-01 Sanitary Sewer Manhole Repair SFRF Grant No.: GA-0010824 01200-1

CITY OF ASHBURN

SANITARY SEWER MANHOLE REPAIR

STATE FISCAL RECOVERY FUND

SFRF GRANT NO. GA-0010824

ADVERTISEMENT FOR BIDS

PART 1 GENERAL

1.01. COMPETITIVE COST SEALED BIDS

Sealed Bids for the construction of the Sanitary Sewer Manhole Repair will be received, by City of Ashburn, at City Hall of Ashburn, 259 East Washington Avenue, Ashburn, GA 31714, until 11:00 A.M., Friday, November 1, 2024, local time, at which time the Bids received will be publicly opened and read. No bid may be withdrawn after the closing time for receipt of bids for a period of sixty (60) days.

1.02. CONTRACTOR LICENSE

Any Contractor submitting a bid must be a licensed utility contractor. License information must be written on the face of the bid envelope. No bid will be opened unless the license information is clearly shown. See Instructions to Bidders for additional bidding requirements.

1.03. SCOPE OF WORK

The work to be done shall consist of furnishing all labor, materials and equipment necessary to perform the proposed Sanitary Sewer Manhole Repair as shown on the construction drawings. In general, construction consists of raising 4 manholes above flood prone area and installing bolt down ring & covers. Work will involve clearing of 2000 liner linear feet of sanitary sewer easement (20 feet width), and dewatering area above beaver pond and all associated measures for the complete project. Time allotted for completion of work is 60 consecutive calendar days to substantial completion. Work shall be complete and ready for contract closeout with 74 consecutive calendar days. All work shall be completed in accordance with the plans and specifications. The work will be awarded in one (1) Contract.

1.04. PLANS AND BIDDING DOCUMENTS

Copies of Bidding Documents for bidding purposes can be obtained from Watkins & Associates, L.L.C., 1606 Whiddon Mill Road, Tifton, Georgia 31793, Phone: (229) 388- 8823, (Office of the Engineer) upon payment of $300.00 for each set (non-refundable).

Prospective Bidders may examine the Bidding Documents at the City Hall of Ashburn, 259 East Washington Avenue, Ashburn, GA 31714 or at Watkins & Associates, LLC on Mondays through Fridays between the hours of 8 A.M. and 5 P.M. Upon request and receipt of the document payment indicated above, Watkins & Associates, LLC will transmit the Bidding Documents via delivery service. The date that the Bidding Documents are transmitted will be considered the prospective Bidder’s date of receipt of

SFRF Grant No.: GA-0010824 01200-2 the Bidding Documents. Partial sets of Bidding Documents will not be available from the Engineer. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including Addenda if any, obtained from sources other than the Office of the Engineer.

1.05. REQUESTS FOR INFORMATION

Plan holders list, addenda and bid results are available at www.watkinseng.com.

1.06. PREQUALIFICATION OF BIDDERS

Prequalification may be required of Bidders prior to the award of contract. At the Owner’s request, detailed written evidence such as financial data, bonding capacity, previous experience, present commitments, and other such data may be necessary to assist Owner in determining Contractor’s qualifications shall be provided per the Instructions to Bidders contained in the contract documents.

1.07. BONDS

All bid forms must be accompanied by a Bid Bond or a certified cashier’s check in an amount not less than ten percent (10%) of the amount bid. All bonds shall be by a surety company licensed in Georgia with “A” minimum rating performance and financial strength of at least five (5) times the contract price as listed in the most current publication of “Best’s Key Rating Guide Property Liability”. The successful bidder, if awarded the Contract, will be required to furnish a Performance Bond and Payment Bond, each in the amount of one hundred percent (100%) of the Contract amount. All bonds must appear on the Treasury Department's most current Circular 570 Listing. Each Bond shall be accompanied by a “Power of Attorney” authorizing the attorney-in-fact to bind the surety and certified to include the date of the bond.

1.08. PERMITS

All anticipated federal, state, or local permits required for the project have been applied for and are expected to be approved prior to issuance of the Notice to Proceed.

1.09. GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT

All qualifying Contractors and Subcontractors performing work with the City of Ashburn must register and participate in the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, to verify the work eligibility information of new employees. In order for a Bid to be considered, it is mandatory that the Bidder’s Affidavit of Compliance with O.C.G.A. §13-10-91 be completed and submitted with the Bid.

1.10. FUNDING SOURCES

Any Contract or Contracts awarded under this Advertisement for Bids will be funded by a grant from the State Fiscal Recovery fund, GEFA funds or local City funds. Contractor will be required to meet and provisions of the funding agency.

SFRF Grant No.: GA-0010824 01200-3

1.11. RESERVATION OF RIGHTS

Owner reserves the right to reject any or all Bids, including without limitation, the rights to reject any or all nonconforming, nonresponsive, unbalanced, or conditional Bids and to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by the Owner. Owner reserves the right to waive informalities and to re-advertise.

Owner: City of Ashburn By: Mrs. Sandra Lumpkin Title: Mayor Date: October 2, 2024 October 16, 2024

END OF SECTION

PART 1 GENERAL
1.01. COMPETITIVE COST SEALED BIDS
1.02. Contractor license
1.03. SCOPE of work
The work to be done shall consist of furnishing all labor, materials and equipment necessary to perform the proposed Sanitary Sewer Manhole Repair as shown on the construction drawings. In general, construction consists of raising 4 manholes above fl...
1.04. plans and bidding documents
1.05. requests for information
1.06. Prequalification of bidders
1.07. Bonds
1.08. Permits
1.09. georgia security and immigration compliance act affidavit
1.10. funding sources
Any Contract or Contracts awarded under this Advertisement for Bids will be funded by a grant from the State Fiscal Recovery fund, GEFA funds or local City funds. Contractor will be required to meet and provisions of the funding agency.

1.11. reservation of rights

File details come from the government source that posted it. Updated .