00018352 Exhibit 5 Specifications~2.docx
DOCX document 54 KB Posted
- Attached to
- ESB - District 14 Stockpile Fencing Project
- Solicitation number
- S-73000-00018352
- Issued by
- Linn County, Oregon
About this file
This is an exhibit of specifications for the ESB District 14 Stockpile Fencing Project issued by the Oregon Department of Transportation (ODOT). The project involves the installation of Type 1 5W perimeter fencing at six ODOT stockpile sites located along various Oregon highways, including Hills Stockpile (Highway 205 MP 32.71), Yapaa Creek Stockpile (Highway 20 MP 216.76), Mascall (Highway 26 MP 126), Silvies Stockpile Site (Highway 395C MP 38), Hwy 30 Stockpile Site (Highway 30 MP 2.9), and an unnamed site (North MP 6). The total fence installation includes approximately 7,045 linear feet of fencing and 11 gates across all locations. All materials, labor, and equipment must be furnished by the contractor in accordance with 2024 Oregon Standard Specifications and Standard Drawings RD810 and RD820. The project must be completed by June 15, 2027, with the note that bid item quantities may be scaled back to match budget constraints. Work must remain on ODOT property, with all equipment and staging conducted off paved shoulders.
The specifications require adherence to environmental protection measures, including erosion control, stormwater management, pollution prevention, and hazardous waste management per Section 00290 of the Standard Specifications. Archaeological monitoring is mandatory during ground-disturbing activities at Hill Top Quarry and Silvies Stockpile Site, with monitoring reports required within 21 to 60 calendar days of completion. No separate payment will be made for mobilization or work zone traffic control, which are considered incidental costs. Contractors must comply with the Migratory Bird Treaty Act and obtain written approval from the Project Manager before implementing any fence design modifications. Prior to construction, contractors must request underground utility locates and coordinate with the Project Manager for any necessary fence location adjustments to avoid utilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00018352 Exhibit 6 Plans.pdf | ||
| 00018352 Exhibit 7 Standard Drawings.pdf | ||
| 00018352 ESB Sample Contract.docx | DOCX document | |
| 00018352 ESB_RFCQ_279C.docx | DOCX document | |
| 00018352 Att A Form A2 Bid Pricing Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit 5 – Specifications
ESB District 14 Stockpile Fencing Project
OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION. The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed specifications in Part 00200 and beyond (“technical specifications”) that apply to this Project. Some sections of the technical specifications may be identified and modified in the Contract Documents. Sections of the technical specifications not identified in the Contract Documents remain applicable to the Contract according to their original terms.
Sections 00120-00199 in Part 00100 of the Standard Specifications are not applicable to the Contract unless they are specifically identified in a Contract Document as being applicable. However, if a section in Part 00100, Section 00120—00199, that has been identified as being applicable references another section in Part 00100, or if a technical specification references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Abbreviations, definitions, and conventions in Part 00100, Section 00110, apply to the RFCQ and any resulting Contract as required for context within the Contract Document. The Standard Specifications can be accessed online at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
Contract work shall also comply with ODOT Standard Drawings RD810 and RD820, as applicable:
Oregon Department of Transportation : Standard Drawings | Roadway : Engineering : State of Oregon
WORK SCOPE: This ESB Contract is to provide all material, labor and equipment necessary to Construct Type 1 5W Fencing at locations as Follows and designated in the bid schedule.
This project is for the installation of a property perimeter fence surrounding All fence construction will adhere to Oregon Standard Drawings RD 810 Type 1‐5W consisting of all metal components.
All gates and gateways will consist of metal components conforming to standard drawings RD820. All work equipment and materials must remain and be performed on ODOT property.
site name
| inset |
| # gates |
| gate width |
| type 1 5W fence |
LF
| No name |
| 201 N MP 6 |
| Yes |
| 2 |
| 24 |
| 2000 |
| Hills Stockpile |
| Hwy205 MP32.71 |
| none |
| 2 |
| 16 |
| 2640 |
| Yapaa Creek Stockpile |
| Hwy 20 MP216.76 |
| none |
| 1 |
| 24 |
| 625 |
| Mascall |
| Hwy 26 MP 126 |
| yes |
| 2 |
| 16 |
| 280 |
| Silvies Stockpile Site |
| Hwy 395C MP 38 |
| none |
| 1 |
| 32 |
| 1600 |
| Hwy 30 stockpile site |
| Hwy 30 mp 2.9 |
| Yes |
| 2 |
| 16 |
| 900 |
The Bidder shall furnish all material, labor, and equipment necessary to perform all tasks in accordance with the 2024 Standard Specifications, 2024 Standard Drawings, the current version of the Routine Road Maintenance “Blue Book” and these Special Provisions to include the terms and conditions in the contract documents.
This ESB Project must be completed by June 15, 2027. Due to the limited budget the project Bid Item Quantities may be scaled back or adjusted as needed to match the budget.
Parking and Staging of Equipment should take place off the paved shoulder. Erosion control maybe be required were ground is disturbed. This may include wattles, bio-bags, straw mulch, and seeding. All work must take place within ODOT property.
Stormwater management will apply to this project. The goal would be to reduce or eliminate pollutants of concerns, to the maximum extent practicable, from entering the waters of the state.
This is a Type 1 5W fencing project with no modifications permitted without the approval of the Project Manager.
Minimization Measures, Avoidance Measures, and BMPs:
1. Use best professional judgment on installing erosion control and implementing good housekeeping practices for this fence maintenance project.
2. Minimize ground disturbance.
3. There are no known wetlands along this project. Should a wetlands be determine during construction it should be avoided.
4. Install erosion control devices where appropriate to prevent work from possibly impacting wetlands, storm drains, etc.
5. Should concrete be delivered by truck, truck chute cleanout with proper containment of green clean out will be required at a location approved by the Project Manager.
6. All inlets, catchments, wetlands and waterways will be protected from green concrete.
7. All matter, debris, vegetation and wire shall be removed and disposed of in accordance to Standard Specification 00290.20. No separate or additional payment will be made.
LOCATES: Contractor shall seek underground utility locates prior to installing any portion of the new fence. If adjustment to the fence location is needed to avoid underground utilities, the project manager will accommodate reasonable alternate locations.
Applicable Standard Specifications: “2024 Oregon Standard Specifications for Construction”, 2024 Oregon Standard Drawings, the current version of the Routine Road Maintenance “Blue Book” and these Special Provisions.
The Contractor shall not incorporate Materials into the Project prior to submitting Materials Conformance Documents acceptable to the Engineer. Contractor shall not incorporate any rejected or none approved Materials.
SECTION 00180 – PROSECUTION AND PROGRESS
Comply with Section 00180 of the Standard Specifications modified as follows:
00180.50(h) Contract Time – The Contractor shall complete all work to be done under the contract no later than June 15, 2021.
SECTION 00210 – MOBILIZATION
Comply with Section 00210 of the Standard Specifications modified as follows:
00210.90 Payment – No separate payment for mobilization will be made.
Section 00221 - Common Provisions for Work Zone Traffic Control Description
00221.00 Scope - In addition to the requirements of Section 00220, this Work consists of providing temporary Traffic Control Measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing Traffic Control Devices throughout the Project area according to the Standard Drawings, the Traffic Control Plan for the Project, the Specifications, and as directed.
Replace 00221.06 Traffic Control Plan -with the following: Provide Temporary Traffic Control in accordance with the “ODOT Temporary Traffic Control Handbook for Operations of Three Days or Less”.
Measurement
00221.80 Measurement, Method “A” - Under this method, Work covered under this Section will be measured as follows:
00221.89 Measurement, Method “C” - Under this method, no measurement of quantities will be made.
Payment
00221.99 Payment, Method "C" - Incidental Basis - When the Contract Schedule of Items does not indicate payment for Work Zone traffic control, all Work Zone traffic control will be considered Incidental, and no separate payment will be made.
This Work includes Work specified in the following Sections: 00222, 00223, 00224, 00225, 00226, 00227, and 00228.
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications modified as follows:
00290.00 Scope ‑ Replace the paragraph that begins “If any provision of the Specifications …” with the following paragraph:
If any provision of the Specifications appears to conflict with one or more Laws, the more stringent requirement applies, unless the Engineer directs otherwise in situations where the Specifications are more stringent.
00290.10 Staging and Disposal Sites ‑ Replace the paragraph that begins “Locate staging areas…” with the following paragraph:
Locate staging areas and disposal sites in previously improved or disturbed sites, including existing Roadways, pullouts, turnouts, parking lots, and storage yards that have been compacted, and graveled or paved, unless otherwise specified in Section 00236 or Section 00237 or approved, in writing, by the Engineer.
00290.20(c)(3)d. Concrete and Masonry ‑ Replace the paragraph that begins "If the Engineer provides written …" with the following paragraph:
If the Engineer provides written approval, concrete may be reused as Aggregate as directed.
00290.20(c)(3)f. Off-Site Disposal ‑ Replace the paragraph that begins "Subject to local zoning codes …" with the following paragraph:
Subject to local zoning codes and the requirements of 00280.05, materials that meet the definition of clean fill may be placed on other properties in a manner consistent with environmental requirements, and with the written permission of the property owner. Provide the Engineer a copy of the signed agreement with the owner before placing the clean fill material. Do not place the clean fill material at locations that are visible from a public Highway, road, or street unless the site is zoned and licensed for landfill.
00290.20(d) Hazardous Waste Management ‑ Replace the bullet that begins "Fill in the Comments section with …" with the following bullet:
Fill in the Comments section with the following statement:
"[Contractor name] is responsible for the following: All hazardous waste management on‑site for the duration of this construction Project, for delivery of the waste to a permitted recycling or disposal facility, and for all forms and fees associated with the hazardous waste management including cancellation of the RCRA site identification number at the end of the Project. ODOT is the owner of the waste and maintains long‑term responsibility for the waste as required by RCRA, excluding all wastes generated solely from materials brought to the site by the Contractor that remain the property of the Contractor."
Replace the bullet that begins "All employees involved in the handling …" with the following bullet:
The Contractor is responsible to ensure that all employees involved in the handling and waste management of CEG hazardous waste comply with the federal and State Laws for hazardous waste management. Train all employees involved in the handling of SQG and LQG hazardous waste according to federal and State Laws. For LQG hazardous waste projects, keep employee training records on-site and readily available.
Replace the bullet that begins "If hazardous waste is treated on-site …" with the following bullet:
If hazardous waste is treated on-site, obtain approval from DEQ and the Engineer for each specific treatment or recycling process, treat wastes within accumulation tanks or closed containers that meet RCRA requirements, conduct treatment within the storage time for the applicable generator category, maintain current copies of all required notifications and waste analysis plans readily available on-site and request DEQ technical assistance prior to starting any on-site recycling or treatment.
00290.20(f) Unexpected Contamination ‑ Replace the paragraph that begins "The Engineer will attempt to resolve …" with the following paragraph:
The Engineer will attempt to resolve the unanticipated situation expeditiously according to 00140.40. Delays to Work due to the discovery of unexpected contamination may be considered for exclusion from Contract Time according to 00180.50(e).
00290.20(g) Spills and Releases ‑ Replace the bullet that begins "Provide a written report to the Engineer …" with the following bullet:
Provide a written report to the Engineer, using the DEQ Spill/Release Report form, within 10 Calendar Days of completing spill response, but no more than 30 Calendar Days after the initial event. If the spill was reported to DEQ, submit the report to DEQ concurrently. Include a description of how to prevent future releases.
00290.30 Pollution Control ‑ Replace the paragraph that begins "Prevent, control, and abate…" with the following paragraph:
Prevent, control, and abate pollution of the environment.
00290.30(a)(1) General - Replace this subsection, except for the subsection number and title, with the following:
Do not allow any foreign substances or objects to enter waters of the State and U.S. that exceed regulated or permit limits.
Do not cause turbidity in waters of the State and U.S. that exceeds regulated or permit limits.
00290.36(a) Migratory Birds ‑ Replace the paragraph that begins "Comply with the Migratory Bird Treaty Act …" with the following paragraph:
Comply with the Migratory Bird Treaty Act (16 U.S.C. 703-712) that protects most species of birds in Oregon and prohibits the removal of nests containing eggs or dependent young (i.e., active nest) without a permit. Migratory birds include most birds in Oregon; the few exceptions include rock pigeons, house sparrows, and European starlings.
Replace the paragraph that begins "Except where allowed by the Contract …" with the following paragraph:
Except where allowed by the Contract and by permit, do not disturb an active migratory bird nest, do not inhibit the ability of adult birds to care for eggs or dependent young, and do not impact the supporting structure where an active nest is built.
Add the following to the end of this subsection:
Do not disturb migratory bird nesting habitat (shrubs, trees, and structures), or clear vegetation from March 1 to September 1 of each year without prior written approval from the Engineer. Notify the Engineer, in writing, a minimum of 10 Calendar Days prior to starting activities that could harm nesting birds.
(1) Bird Management - Bird management activities to comply with the Migratory Bird Treaty Act (16 U.S.C. 703 712) will be performed by the Agency. Ensure that the Agency and its permitted agents have access to the project area, as needed to prevent migratory bird nesting. Nesting prevention may include daily bird harassment and the installation and maintenance of devices that exclude birds.
Do not disturb migratory bird nesting habitats (shrubs, trees, and structures), or clear vegetation from March 1 to September 1 of each calendar year without prior written approval from the Engineer. Notify the Engineer, in writing, a minimum of 10 Calendar Days prior to starting activities that could harm nesting birds.
00290.38 Protection of Plants ‑ Replace this subsection, except for the subsection number and title, with the following:
Plant habitats to be protected are shown with the plant habitat boundaries flagged by the Engineer. Avoid destruction of plant habitats by ensuring construction personnel, Equipment, and associated pollutants, including sediment, chemical contaminants, discharge water, non-native grass and weed seed, do not enter the habitat.
00290.50 Protection of Cultural Resources ‑ Replace the paragraph that begins “Comply with all Laws…” with the following paragraph:
Comply with all Laws governing preservation of cultural resources. Cultural resources include, but are not limited to:
Historic buildings (i.e. typically 50 years of age and older) Historic structures (i.e. bridges) Sites (i.e. sites with artifacts) Objects (i.e. monuments) Districts (i.e. historic districts, or linear historic districts like historic roads).
Replace the paragraph that begins “If cultural resources are…” with the following paragraph:
If cultural resources not previously identified in preconstruction are encountered on the Project area or in material sources, and their disposition is not addressed in the Special Provisions, do the following:
00290.51 Protection of Sensitive Cultural Sites - Add the following to the end of this subsection:
There are sensitive cultural sites or areas of high probability for cultural resources on this Project. At the time of preparation of the Plans, two sites were identified.
The Region Environmental Coordinator for this Project is Tayton Duby.
The Agency Archaeology Representative for this Project is Emma Vance.
The Engineer will coordinate all contact with the Agency Archaeology Representative and the Region Environmental Coordinator.
An Inadvertent Discovery Plan (IDP) has been developed for this project. The IDP is available from the Engineer.
Archaeological and Tribal Monitors are required to be on-site during ground‑disturbing activities associated with the excavation and installation of the gates at Hill Top Quarry (OR205 MP 32.71) and Silvies Stockpile site (US 395C MP 36.79), unless otherwise notified. Notify the Engineer 10 Calendar Days before beginning ground-disturbing activities, or 14 Calendar Days if ground-disturbing activities are anticipated to occur simultaneously in more than two locations.
Provide archaeological monitoring during construction by a professional archaeologist who meets the Secretary of the Interior's professional standards for archaeology (36 CFR 61, Appendix A) and who has completed the ODOT Cultural Resources Consultant Qualification Training Program.
Submit the following reports according to 00150.37. Within 21 Calendar Days after receipt of the reports, the Engineer will review the submittal and accept or return for correction.
Use monitoring reports to document activities and discoveries from the Project according to the State of Oregon Guidelines for Reporting on Archaeological Investigations for monitoring from the Oregon State Historic Preservation Office website at:
https://www.oregon.gov/oprd/OH/Documents/Reporting_Guidelines.pdf
Draft Monitoring Report ‑ Submit the draft monitoring report completed by a professional archaeologist, not later than 21 Calendar Days following completion of the archaeological monitoring.
Final Monitoring Report ‑ Submit the final monitoring report completed by a professional archaeologist, not later than 60 Calendar Days following completion of the archaeological monitoring.
00290.51(b) Disturbing Unknown Sensitive Cultural Sites ‑ Replace the paragraph that begins "If the Contractor finds a previously undiscovered…" with the following paragraph:
If the Contractor finds a previously undiscovered sensitive cultural site, immediately cease all activities at that site, follow procedures listed in 00290.50, and notify the Engineer. If the Contractor inadvertently disturbs unknown sensitive cultural sites, but immediately ceases all activities and follows the procedures listed in 00290.50, the Agency, to the extent permitted by Article XI, section 7 of the Oregon Constitution and by the Oregon Tort Claims Act, will indemnify, within the limits of the Tort Claims Act, the Contractor for costs associated with monitoring, recovery, site restoration or other required archaeological Work, provided neither the Agency nor the State are required to indemnify the Contractor for such costs resulting from, arising out of or relating to the willful misconduct, negligence or other wrongful acts attributable to the Contractor or other persons on the Project site.
Replace the paragraph that begins "Delays to Work due to new …" with the following paragraph:
The Engineer may consider for exclusion from Contract Time according to 00180.50(e) delays to Work due to new cultural resource finds.
00290.90 Payment - Add the following paragraph(s) to the end of this subsection:
The accepted quantities of archaeological monitoring report will be paid for at the Contract lump sum amount for the item “Monitoring and Reporting”.
Payment for archaeological monitoring will be payment in full for providing a professional archaeologist to monitor the Work and for preparing, submitting correcting, and resubmitting the monitoring reports.
Section 01050 - Fences
Comply with section 01050 of the Standard Specifications.
Comply with section 01050 of the Standard Specifications modified as follows:
Modify Section 01050.42 as follows:
01050.42 Optional Posts –
Use Option 1: Steel posts entirely in all types of Fence.
Rev 1/4/2019