00014729 Preliminary Results.xlsx
XLSX spreadsheet 24 KB Posted
- Attached to
- Rowena Fire Tree Removal
- Solicitation number
- S-73000-00014729
- Issued by
- Wasco County, Oregon
About this file
This document is a bid tabulation spreadsheet for Invitation to Bid (ITB) No. S-73000-00014729, issued by the Oregon Department of Transportation (ODOT) for the Rowena Fire Tree Removal project in Wasco County. The procurement involves cutting and removing recently burned dead trees along Interstate 84 and Oregon State Highway 30 right of way west of The Dalles, with three bidders submitting quotes: Ash Tree Enterprises LLC, Pomeroy Tree Care LLC, and O'Malley Brothers Corporation. The project requires specialized services including traffic control, flagging, tree cutting, and equipment operations such as bucket trucks, brush chippers, self-loading log trucks, and excavators. The bid closing date is September 9, 2025, at 1:00 PM, with a substantial completion date of October 15, 2025, and a final completion date of October 30, 2025.
The bid tabulation shows varying unit prices for different project components, with total bid amounts ranging from $42,500 (Ash Tree Enterprises) to $103,200 (O'Malley Brothers Corporation). The contract will be awarded to the lowest responsible offeror, with work to be paid hourly and ODOT providing on-site guidance. Contractors must comply with Bureau of Labor and Industries (BOLI) prevailing wage rates and provide comprehensive insurance coverage, including Workers' Compensation and Commercial General Liability. No specific contract value is listed, but the bid includes estimated quantities for traffic control, tree cutting, and equipment services. Bidders must be authorized to do business in Oregon and submit additional documentation, including references, tax ID numbers, and potential conflict of interest disclosures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00014729 RFCQ.docx | DOCX document | |
| COBID Notice S-10700-00014730.docx | DOCX document | |
| 00014282 PreBid Sign In.pdf | ||
| 00014729 RFCQ_AttABCD.docx | DOCX document | |
| 00014729 Bid Pricing Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 9/9/25 | ||||
| ITB No. | S-73000-00014729 | BIDDER | |||
| NAME: | Ash Tree Enterprises LLC | Pomeroy Tree Care LLC | O'Malley Brothers Corporation | ||
| Bid Closing: | 9/9/2025 @ 1:00 PM | ||||
| Description: | Rowena Fire Tree Removal | ||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Standard Traffic Control and Materials | 5 | DAY | 0.00 | $ - 0 | $ 300.00 | $ 1,500.00 | $ 250.00 | $ 1,250.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 2 | Flagger - Prevailing Wage | 120 | HOUR | $ 50.00 | $ 6,000.00 | $ 75.00 | $ 9,000.00 | $ 95.00 | $ 11,400.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Three Tree Cutting and Removal Workers - Prevailing Wage | |||||||||||||||||||
| 3 | Mobilization | 1 | CREW | $ 2,500.00 | $ 2,500.00 | $ 500.00 | $ 500.00 | $ 1,950.00 | $ 1,950.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 4 | Equipment/Crew | 120 | HOUR | $ 250.00 | $ 30,000.00 | $ 300.00 | $ 36,000.00 | $ 345.00 | $ 41,400.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Bucket Truck | |||||||||||||||||||
| 5 | Mobilization | 1 | CREW | 0.00 | $ - 0 | $ 500.00 | $ 500.00 | $ 1,950.00 | $ 1,950.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 6 | Equipment | 16 | HOUR | 0.00 | $ - 0 | $ 300.00 | $ 4,800.00 | $ 175.00 | $ 2,800.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Brush Chipper | |||||||||||||||||||
| 7 | Mobilization | 1 | CREW | 0.00 | $ - 0 | $ 500.00 | $ 500.00 | $ 1,950.00 | $ 1,950.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 8 | Equipment | 80 | HOUR | $ 50.00 | $ 4,000.00 | $ 135.00 | $ 10,800.00 | $ 175.00 | $ 14,000.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Self loading log truck and Operator - Prevailing Wage | |||||||||||||||||||
| 9 | Mobilization | 1 | CREW | 0.00 | $ - 0 | $ 500.00 | $ 500.00 | $ 1,950.00 | $ 1,950.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 10 | Equipment and Operator | 80 | HOUR | 0.00 | $ - 0 | $ 175.00 | $ 14,000.00 | $ 195.00 | $ 15,600.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Excavator (under 10,000 lb) and Operator - Prevailing Wage | |||||||||||||||||||
| 11 | Mobilization | 1 | CREW | 0.00 | $ - 0 | $ 550.00 | $ 550.00 | $ 1,950.00 | $ 1,950.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 12 | Equipment and Operator | 40 | HOUR | 0.00 | $ - 0 | $ 275.00 | $ 11,000.00 | $ 175.00 | $ 7,000.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| TOTAL | $ 42,500.00 | $ 89,650.00 | $ 103,200.00 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |