00014726 Bid Results.xlsx
XLSX spreadsheet 27 KB Posted
- Solicitation number
- S-580501-00014725
- Issued by
- Oregon
About this file
Bid Results Summary
This is a Bid Results tabulation for an Invitation to Bid (ITB No. S-73000-00014726) issued by the State of Oregon for an Emergency Repair Project on US Route 101 at mileposts 314.7 and 344.5 near Brookings, Oregon. The project is a rebid emergency repair initiative that encompasses traffic control, erosion management, contaminated soil handling, and roadway reconstruction work. The bid closing date was September 8, 2025, at 11:00 AM, with four contractors submitting bids: Tidewater Contractors, Inc. (located in Brookings, OR), LTM, Incorporated dba Knife River Materials (Coos Bay, OR), LaDuke Construction, LLC (Central Point, OR), and Granite Construction Company (Vancouver, WA). The scope includes 44 line items ranging from mobilization and temporary traffic control to asbestos removal, excavation, storm sewer installation, and asphalt paving work.
The total bid amounts submitted were $1,753,948.00 (Tidewater Contractors), $2,333,333.00 (LTM, Incorporated), $3,461,940.00 (LaDuke Construction), and $3,604,492.50 (Granite Construction Company). Significant cost variations exist across bidders, particularly for items such as stone embankment ($277,400 to $1,080,400), contaminated soil disposal ($455 to $127,400), and general excavation ($214,400 to $502,500), indicating different interpretations of project scope and risk assessment among contractors. The tabulation explicitly notes that it is not an indicator of award but rather a compilation of submitted bids for consideration, meaning the final contract award determination would be made following bid evaluation and approval by state procurement officials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Procurement Information~49.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 9/8/25 | |||||||
| ITB No. | S-73000-00014726 | BIDDER | ||||||
| NAME: | Tidewater Contractors, Inc. | LTM, Incorporated dba Knife River Materials | LaDuke Construction, LLC | Granite Construction Company | ||||
| Bid Closing: | 9/8/2025 at 11:00 AM | CITY/STATE: | Brookings, OR | Coos Bay, OR | Central Point, OR | Vancouver, WA | ||
| Description: | ER US101: MP314.7 and MP344.5 Emergency Repair Project REBID | CCB# | 29995 | 56603 | 193168 | 101195 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $175,000.00 | $175,000.00 | $99,879.00 | $99,879.00 | $400,000.00 | $400,000.00 | $ 350,000.00 | $350,000.00 |
| 2 | Temporary Protection & Direction of Traffic | 1 | LS | $65,000.00 | $65,000.00 | $207,000.00 | $207,000.00 | $45,000.00 | $45,000.00 | $ 155,000.00 | $155,000.00 |
| 3 | Temporary Signs | 325 | SQFT | $35.00 | $11,375.00 | $30.00 | $9,750.00 | $42.00 | $13,650.00 | $ 12.50 | $4,062.50 |
| 4 | Portable Changeable Message Signs | 2 | EA | $6,000.00 | $12,000.00 | $1,500.00 | $3,000.00 | $9,000.00 | $18,000.00 | $ 2,500.00 | $5,000.00 |
| 5 | Flagger | 2020 | HR | $88.00 | $177,760.00 | $88.50 | $178,770.00 | $83.00 | $167,660.00 | $ 100.00 | $202,000.00 |
| 6 | Flagger Station Lighting | 2 | EA | $5,000.00 | $10,000.00 | $1,600.00 | $3,200.00 | $5,500.00 | $11,000.00 | $ 1,500.00 | $3,000.00 |
| 7 | Pilot Cars | 1000 | HR | $97.00 | $97,000.00 | $100.50 | $100,500.00 | $125.00 | $125,000.00 | $ 100.00 | $100,000.00 |
| 8 | Automated Flagger Assistance Device | 2 | EA | $4,000.00 | $8,000.00 | $2500.00 | $5,000.00 | $9,000.00 | $18,000.00 | $ 5,000.00 | $10,000.00 |
| 9 | Temporary Barricades, Type II | 4 | EA | $75.00 | $300.00 | $125.00 | $500.00 | $125.00 | $500.00 | $ 40.00 | $160.00 |
| 10 | Temporary Barricades, Type III | 2 | EA | $200.00 | $400.00 | $150.00 | $300.00 | $210.00 | $420.00 | $ 200.00 | $400.00 |
| 11 | Temporary Plastic Drums | 157 | EA | $40.00 | $6,280.00 | $100.00 | $15,700.00 | $130.00 | $20,410.00 | $ 20.00 | $3,140.00 |
| 12 | Temporary Pavement Bars | 24 | SQFT | $12.00 | $288.00 | $35.00 | $840.00 | $24.00 | $576.00 | $ 75.00 | $1,800.00 |
| 13 | Erosion Control | 1 | LS | $500.00 | $500.00 | $100.00 | $100.00 | $14,000.00 | $14,000.00 | $ 39,000.00 | $39,000.00 |
| 14 | Plastic Sheeting | 500 | SQYD | $2.00 | $1,000.00 | $2.00 | $1,000.00 | $8.00 | $4,000.00 | $ 6.00 | $3,000.00 |
| 15 | Check Dam, Type 1 | 7 | EA | $250.00 | $1,750.00 | $750.00 | $5,250.00 | $185.00 | $1,295.00 | $ 350.00 | $2,450.00 |
| 16 | Inlet Protection, Type 3 | 2 | EA | $50.00 | $100.00 | $50.00 | $100.00 | $240.00 | $480.00 | $ 250.00 | $500.00 |
| 17 | Inlet Protection, Type 4 | 2 | EA | $200.00 | $400.00 | $80.00 | $160.00 | $240.00 | $480.00 | $ 250.00 | $500.00 |
| 18 | Straw Bale | 30 | EA | $35.00 | $1,050.00 | $31.00 | $930.00 | $21.00 | $630.00 | $ 125.00 | $3,750.00 |
| 19 | Pollution Control Plan | 1 | LS | $100.00 | $100.00 | $100.00 | $100.00 | $1,200.00 | $1,200.00 | $ 2,000.00 | $2,000.00 |
| 20 | Contaminated Soil Disposal | 455 | TONS | $1.00 | $455.00 | $1.00 | $455.00 | $280.00 | $127,400.00 | $ 300.00 | $136,500.00 |
| 21 | Lead Compliance Plan | 1 | LS | $2,000.00 | $2,000.00 | $100.00 | $100.00 | $8,000.00 | $8,000.00 | $ 5,000.00 | $5,000.00 |
| 22 | Segregate and Stockpile Contaminated Soil | 1 | LS | $10,000.00 | $10,000.00 | $100.00 | $100.00 | $60,000.00 | $60,000.00 | $ 25,000.00 | $25,000.00 |
| 23 | Soil Sample Collection and Analytical Testing | 4 | EA | $400.00 | $1,600.00 | $1.00 | $4.00 | $2,000.00 | $8,000.00 | $ 700.00 | $2,800.00 |
| 24 | Remove Asbestos Material, Non-Friable | 20 | FT | $450.00 | $9,000.00 | $112.00 | $2,240.00 | $200.00 | $4,000.00 | $ 125.00 | $2,500.00 |
| 25 | Construction Survey Work | 1 | LS | $25,000.00 | $25,000.00 | $20000.00 | $20,000.00 | $65,000.00 | $65,000.00 | $ 10,000.00 | $10,000.00 |
| 26 | Removal of Structures and Obstructions | 1 | LS | $12,000.00 | $12,000.00 | $20,000.00 | $20,000.00 | $60,000.00 | $60,000.00 | $ 17,000.00 | $17,000.00 |
| 27 | Clearing and Grubbing | 1 | LS | $10,000.00 | $10,000.00 | $1,500.00 | $1,500.00 | $190,000.00 | $190,000.00 | $ 10,000.00 | $10,000.00 |
| 28 | General Excavation | 6700 | CUYD | $32.50 | $217,750.00 | $42.00 | $281,400.00 | $32.00 | $214,400.00 | $ 75.00 | $502,500.00 |
| 29 | Stone Embankment | 7300 | TONS | $38.00 | $277,400.00 | $55.00 | $401,500.00 | $148.00 | $1,080,400.00 | $ 140.00 | $1,022,000.00 |
| 30 | 24 Inch Subgrade Stabilization | 150 | SQYD | $70.00 | $10,500.00 | $125.00 | $18,750.00 | $38.00 | $5,700.00 | $ 165.00 | $24,750.00 |
| 31 | Subgrade Geotextile | 9500 | SQYD | $1.20 | $11,400.00 | $1.50 | $14,250.00 | $3.00 | $28,500.00 | $ 3.00 | $28,500.00 |
| 32 | Riprap Basins | 1 | EA | $5,000.00 | $5,000.00 | $4,000.00 | $4,000.00 | $1,400.00 | $1,400.00 | $ 8,000.00 | $8,000.00 |
| 33 | 24 Inch Storm Sewer Pipe, 10 ft Depth | 76 | FT | $440.00 | $33,440.00 | $860.00 | $65,360.00 | $280.00 | $21,280.00 | $ 400.00 | $30,400.00 |
| 34 | 24 Inch Storm Sewer Pipe, 20 ft Depth | 126 | FT | $545.00 | $68,670.00 | $1,000.00 | $126,000.00 | $410.00 | $51,660.00 | $ 450.00 | $56,700.00 |
| 35 | Concrete Inlets, Type G-2MA | 2 | EA | $6,100.00 | $12,200.00 | $8,500.00 | $17,000.00 | $3,800.00 | $7,600.00 | $ 16,000.00 | $32,000.00 |
| 36 | Adjusting Catch Basins | 1 | EA | $750.00 | $750.00 | $3400.00 | $3,400.00 | $1,400.00 | $1,400.00 | $ 2,000.00 | $2,000.00 |
| 37 | Filling Abandon Structure | 2 | EA | $3,000.00 | $6,000.00 | $7500.00 | $15,000.00 | $6,000.00 | $12,000.00 | $ 1,500.00 | $3,000.00 |
| 38 | Aggregate Base and Shoulders | 2400 | TONS | $44.00 | $105,600.00 | $103.00 | $247,200.00 | $38.00 | $91,200.00 | $ 125.00 | $300,000.00 |
| 39 | Level 3, 1/2 Inch ACP Mixture (64-22 oil) | 2400 | TONS | $130.00 | $312,000.00 | $172.00 | $412,800.00 | $203.00 | $487,200.00 | $ 185.00 | $444,000.00 |
| 40 | Guardrail, Type 2A | 875 | FT | $26.00 | $22,750.00 | $25.00 | $21,875.00 | $65.00 | $56,875.00 | $ 40.00 | $35,000.00 |
| 41 | Guardrail Terminals, Flared | 3 | EA | $6,000.00 | $18,000.00 | $5,200.00 | $15,600.00 | $4,000.00 | $12,000.00 | $ 4,000.00 | $12,000.00 |
| 42 | Delineators, Type 1 | 10 | EA | $105.00 | $1,050.00 | $100.00 | $1,000.00 | $40.00 | $400.00 | $ 10.00 | $100.00 |
| 43 | Bi-Directional Yellow Type IAR Markers | 26 | EA | $30.00 | $780.00 | $25.00 | $650.00 | $24.00 | $624.00 | $ 30.00 | $780.00 |
| 44 | Thermoplastic, Sprayed, Surface, Non-Profiled | 4100 | FT | $3.00 | $12,300.00 | $2.70 | $11,070.00 | $6.00 | $24,600.00 | $ 2.00 | $8,200.00 |
| TOTAL | $ 1,753,948.00 | $ 2,333,333.00 | $ 3,461,940.00 | $ 3,604,492.50 |
File details come from the government source that posted it. Updated .