This is an Intent to Award document issued by the Oregon Department of Transportation (ODOT) for the demolition of office and storage buildings located on Hayden Island. The bid was closed on August 18, 2025, at 2:00 PM, with the Intent to Award issued on August 19, 2025. The project encompasses the complete demolition of the ODOT Hayden Island Storage Building, including all materials, labor, tools, and miscellaneous equipment required to complete the work as a single lump sum contract item. Six contractors submitted bids for the project, and ODOT intends to award the contract to O'Malley Brothers Corporation. Aggrieved bidders have seven calendar days from the issued date to file a protest against the intent to award.
The winning bid submitted by O'Malley Brothers Corporation totaled $89,400.00, representing the lowest cost among all six bidders. The competing bids ranged from $109,743.50 to $249,999.00, with the second-lowest bid submitted by NW Construction General Contracting Inc. at $109,743.50. The bid tabulation includes pricing from five additional contractors: Konell Construction & Demolition Corp ($138,470.00), 3 Kings Environmental ($147,687.00), Sutherland Construction LLC ($151,500.00), and Willamette Construction Services LLC ($249,999.00). No information regarding set-asides, incumbent contractors, or renewal options is specified in this award notice.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NOI Structured Juniper April 2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 8/19/25 | |||||||
| ITB No. | S-7300000000013575 | BIDDER | ||||||
| NAME: | O'malley Brothers Corportation | NW Construction General Contracting Inc | Konell Construction & Demolition Corp | 3 Kings Envioronmental | Sutherland Construction LLC | Willamette Construction Services LLC | ||
| Bid Closing: | 8/18/2025 @ 2:00 PM | |||||||
| Description: | ODOT Hayden Island Office and Storage Buildings Demolition | |||||||
| This bid tabulation shall serve as ODOT's notice of intent to award a contract to (O'Malley Brothers Corporation). Aggrieved Bidders have 7 calendar days from the issued date shown above to protest the intent to award. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Total Project Bid: ODOT Hayden Island Storage Bulding Demolition including all materials, labor, tools and misc. equipment | 1 | Lump Sum | $ 89,400.00 | $ 89,400.00 | $ 109,743.50 | $ 109,743.50 | $ 138,470.00 | $ 138,470.00 | $ 147,687.00 | $ 147,687.00 | $ 151,500.00 | $ 151,500.00 | $ 249,999.00 | $ 249,999.00 |
| TOTAL | $ 89,400.00 | $ 109,743.50 | $ 138,470.00 | $ 147,687.00 | $ 151,500.00 | $ 249,999.00 |