00011006 Preliminary Results.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Axon Notice of Intent
- Solicitation number
- S-C01010-00011005
- Issued by
- Clackamas County, Oregon
About this file
This file contains preliminary bid results for a pavement removal and asphalt overlay project (Contract S-73000-00011006) dated August 6, 2024. The bid results show LTM, Incorporated dba Knife River Materials as the apparent bidder. The project encompasses mobilization, work zone traffic control, bridge end panel cold plane pavement removal at 2 inches deep (70 square yards), general cold plane pavement removal at 2 inches deep (20,300 square yards), and Level 3, 1/2 inch asphalt concrete pavement (ACP) mixture placement (2,400 tons). The estimated quantities and scope indicate a significant roadway resurfacing project involving approximately 20,370 square yards of pavement removal and 2,400 tons of new asphalt placement.
The total bid amount from Knife River Materials is $345,945.00, with mobilization costs at $21,785.00, traffic control at $19,000.00, bridge end panel removal at $840.00, general pavement removal at $48,720.00, and asphalt mixture placement at $255,600.00. The unit prices range from $2.40 per square yard for general cold plane removal to $12.00 per square yard for bridge end panel removal and $106.50 per ton for asphalt mixture. The document explicitly notes that these preliminary results do not constitute an award notification and are subject to final review and approval.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AXON NOI -RR.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| S-73000-00011006 | August 06, 2024 2:00 PM | |||
| PRELIMINARY RESULTS* | LTM, Incorporated dba Knife River Materials | |||
| Bid Item # | Description | Est | ||
| QTY | UNIT | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | $21,785.00 | $21,785.00 |
| 2 | WORK ZONE TRAFFIC CONTROL, COMPLETE | 1 | LS | $19,000.00 | $19,000.00 |
| 3 | BRIDGE END PANEL COLD PLANE PAVEMENT REMOVAL, 2 INCH DEEP | 70 | SQYD | $12.00 | $840.00 |
| 4 | COLD PLANE PAVEMENT REMOVAL, 2 INCH DEEP | 20300 | SQYD | $2.40 | $48,720.00 |
| 5 | LEVEL 3, 1/2 INCH ACP MIXTURE | 2400 | TON | $106.50 | $255,600.00 |
| TOTAL | $ 345,945.00 | ||||
| *Preliminary Results are not an indicator of Award |